CN103812053B - Be exclusively used in the repair method to electrical lead degree of speeding - Google Patents
Be exclusively used in the repair method to electrical lead degree of speeding Download PDFInfo
- Publication number
- CN103812053B CN103812053B CN201410099725.0A CN201410099725A CN103812053B CN 103812053 B CN103812053 B CN 103812053B CN 201410099725 A CN201410099725 A CN 201410099725A CN 103812053 B CN103812053 B CN 103812053B
- Authority
- CN
- China
- Prior art keywords
- sag
- slack
- wire
- value
- tension
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Electric Cable Installation (AREA)
Abstract
本发明公开了一种专用于对电力导线驰度的检修方法,将手扳葫芦一端固定在横担上,另一端通过铝合金紧线夹头连接在导线上,收紧手板葫芦拆除弯头挂板与耐张线夹处的销钉和耐张线夹,利用手扳葫芦的收紧或放松将计算得到的导线的驰度值f输送到手扳葫芦中进行调整;在两侧直线杆的导线悬挂点,垂直向下量出与弛度值相等的距离处,各绑上一块弛度板,从一侧电杆上的弛度板瞄准对侧电杆上的弛度板,调整导线张力,此时的弛度,即为所要求的弛度。该检修方法通过采用严格的测量和公式计算,得到准确的数值,能够将电力线的调整到最佳的状态,解决了现有电力线的驰度调整都是通过检修人员根据经验调整出现误差很大的问题。The invention discloses a method for overhauling the tension of electric wires. One end of the hand hoist is fixed on the cross arm, the other end is connected to the wire through an aluminum alloy clamp, and the hand hoist is tightened to remove the elbow hanger. The pins at the plate and the tension clamps and the tension clamps are used to tighten or loosen the lever block to transfer the calculated slack value f of the conductor to the lever block for adjustment; the conductors on the straight rods on both sides are suspended point, measure the distance equal to the sag value vertically downwards, tie a slack plate on each, aim at the sag plate on the opposite pole from the sag plate on one pole, and adjust the wire tension. The sag at that time is the required sag. This maintenance method obtains accurate values by adopting strict measurement and formula calculation, which can adjust the power line to the best state, and solves the problem that the existing power line slack adjustment is adjusted by the maintenance personnel according to experience. question.
Description
技术领域technical field
本发明涉及一种检修方法,尤其是涉及一种专用于对电力导线驰度的检修方法,属于电力检修领域。The invention relates to a maintenance method, in particular to a maintenance method dedicated to the slack of electric power conductors, which belongs to the field of electric power maintenance.
背景技术Background technique
电力是以电能作为动力的能源。发明于19世纪70年代,电力的发明和应用掀起了第二次工业化高潮。成为人类历史18世纪以来,世界发生的三次科技革命之一,从此科技改变了人们的生活。即使是当今的互联网时代我们仍然对电力有着持续增长的需求,因为我们发明了电脑、家电等更多使用电力的产品。不可否认新技术的不断出现使得电力成为人们的必需品。20世纪出现的大规模电力系统是人类工程科学史上最重要的成就之一,是由发电、输电、变电、配电和用电等环节组成的电力生产与消费系统。当今是互联网的时代,我们仍然对电力有着持续增长的需求,因为我们发明了电脑、家电等更多使用电力的产品。电力的输送都是通过电力线来传递,电力线都是暴露在外界环境中,由于自然环境的作用,电力线的自身重力等因素,电力线在使用一段时间后,容易出现松弛或者紧绷的情况,而这样情况容易对电力线的使用寿命造成影响,以往人们对此都是通过检修人员依据经验进行调整,这个就存在着很大的误差,常常造成调整不到位,电力线的使用寿命得不到保证,影响输电效率,造成经济损失。Electricity is an energy source powered by electrical energy. Invented in the 1870s, the invention and application of electricity set off the second industrialization climax. It has become one of the three scientific and technological revolutions in the world since the 18th century in human history. Since then, technology has changed people's lives. Even in today's Internet age we still have a growing demand for electricity, as we have invented more products that use electricity, such as computers and home appliances. It is undeniable that the continuous emergence of new technologies has made electricity a necessity for people. The large-scale power system that appeared in the 20th century is one of the most important achievements in the history of human engineering science. It is a power production and consumption system composed of power generation, power transmission, power transformation, power distribution and power consumption. Today is the age of the Internet, and we still have a growing demand for electricity because we have invented more products that use electricity, such as computers and home appliances. The power transmission is transmitted through the power line, and the power line is exposed to the external environment. Due to the effect of the natural environment, the gravity of the power line and other factors, the power line is prone to looseness or tension after a period of use. The situation is easy to affect the service life of the power line. In the past, people adjusted it through the maintenance personnel based on experience. This has a large error, which often results in improper adjustment, and the service life of the power line cannot be guaranteed, which affects power transmission. efficiency and cause economic loss.
发明内容Contents of the invention
本发明的目的在于克服上述现有电力线的驰度调整都是通过检修人员根据经验调整出现误差很大的问题,设计了一种专用于对电力导线驰度的检修方法,该检修方法通过采用严格的测量和公式计算,得到准确的数值,能够将电力线的调整到最佳的状态,解决了现有电力线的驰度调整都是通过检修人员根据经验调整出现误差很大的问题。The purpose of the present invention is to overcome the above-mentioned problem that the adjustment of the slack of the existing electric power line is made by the maintenance personnel according to the experience adjustment, and a large error occurs. Accurate values can be obtained through accurate measurement and formula calculation, and the power line can be adjusted to the best state, which solves the problem that the existing power line slack adjustment is adjusted by the maintenance personnel according to experience, and there is a large error.
本发明的目的通过下述技术方案实现:专用于对电力导线驰度的检修方法,包括以下步骤:The purpose of the present invention is achieved through the following technical solutions: a method for overhauling the slack of the power conductors, comprising the following steps:
(a)通过下式计算出驰度值f,(a) Calculate the laxity value f by the following formula,
f——在温度为t时的弛度值(m);f——sag value at temperature t (m);
f1——与t1相应的弛度值(m);f1——the relaxation value corresponding to t1 (m);
f2——与t2相应的弛度值(m);f2——sag value corresponding to t2 (m);
t——所测实际温度(℃);t - the measured actual temperature (°C);
t1——与实际温度相邻近的一个较大温度值(℃);t1——a larger temperature value adjacent to the actual temperature (°C);
t2——与实际温度相邻近的一个较小温度值(℃);t2——a smaller temperature value adjacent to the actual temperature (°C);
(b)将手扳葫芦一端固定在横担上,另一端通过铝合金紧线夹头连接在导线上,收紧手板葫芦拆除弯头挂板与耐张线夹处的销钉和耐张线夹,利用手扳葫芦的收紧或放松将计算得到的导线的驰度值f输送到手扳葫芦中进行调整;(b) Fix one end of the hand hoist on the cross arm, and connect the other end to the wire through the aluminum alloy clamp, tighten the hand hoist and remove the pins and tension clamps at the elbow hanging plate and the tension clamp , use the tightening or loosening of the lever block to transfer the calculated slack value f of the wire to the lever block for adjustment;
(c)在两侧直线杆的导线悬挂点,垂直向下量出与弛度值相等的距离处,各绑上一块弛度板,观测人员在杆上,从一侧电杆上的弛度板瞄准对侧电杆上的弛度板,调整导线张力,使导线正好切于瞄准直线上,此时的弛度,即为所要求的弛度;(c) At the wire suspension points of the straight poles on both sides, measure the distance equal to the sag value vertically downward, and tie a sag board to each, and observe the sag from the pole on one side by the observer. Aim at the slack plate on the pole on the opposite side, adjust the tension of the wire so that the wire is just cut on the aiming line, and the sag at this time is the required sag;
(d)检修人员利用驰度板观察导线驰度符合要求且三相驰度一致,合格后重新选取位置固定好耐张线夹,并与弯头挂板连接。(d) Maintenance personnel use the slack plate to observe that the slack of the conductor meets the requirements and the three-phase slack is consistent. After passing the test, re-select the position to fix the strain clamp and connect it to the elbow hanging plate.
调整时需要将该耐张段内的瓷瓶绑扎线全部解开,便于调整,导线弛度的大小与导线的张力及对地绝缘距离等有直接关系。一般在耐张段内高差较小的平坦地带选出弛度观测档。耐张段内有6档时,可选择中部一档观测弛度;7~15档时,应选择两档观测弛度,并尽量选靠耐张段两端;15档以上时,应选择三档观测弛度,即在耐张段两端及中间各选择一档来观测弛度。When adjusting, it is necessary to untie all the binding wires of the porcelain bottle in the tension section to facilitate adjustment. The slack of the wire is directly related to the tension of the wire and the insulation distance to the ground. Generally, the sag observation file is selected in the flat area with small height difference in the tension section. When there are 6 levels in the tension section, you can choose the first level to observe the sag in the middle; Observe the sag in one file, that is, select one file at both ends and the middle of the tensile section to observe the sag.
观测导线的弛度,通常与紧线工作配合进行,通过观测使安装后的导线弛度,符合设计弛度。导线弧垂的误差,不应超过设计弧垂的±5%。导线紧好后,同档内各相导线弧垂力求一致,水平排列的导线弧垂相差不应大于50mm。同一横担上的架设截面不同的导线时,导线垂弧应以垂弧最大的导线为主。Observe the sag of the conductor, usually in conjunction with the tightening work, and make the sag of the installed conductor conform to the design sag through observation. The error of wire sag should not exceed ±5% of the design sag. After the wires are tightened, the sag of the wires of each phase in the same gear should be consistent, and the sag difference of the wires arranged horizontally should not be greater than 50mm. When erecting wires with different cross-sections on the same cross arm, the wire with the largest vertical arc should be the main wire.
通过上述方法,能够准确地得出导线的驰度具体值,检修人员根据得到的具体值而控制导线进行调整,克服了传统检修方式仅仅依靠检修人员的经验进行判断,其误差大,常常出现返工的现象。Through the above method, the specific value of the slack of the wire can be accurately obtained, and the maintenance personnel can control the wire to adjust according to the obtained specific value, which overcomes the traditional maintenance method that only relies on the experience of the maintenance personnel to judge, the error is large, and rework often occurs The phenomenon.
综上所述,本发明的有益效果是:该检修方法通过采用严格的测量和公式计算,得到准确的数值,能够将电力线的调整到最佳的状态,解决了现有电力线的驰度调整都是通过检修人员根据经验调整出现误差很大的问题。To sum up, the beneficial effects of the present invention are: the overhaul method obtains accurate values by adopting strict measurement and formula calculation, and can adjust the power line to the best state, which solves the problem of the existing power line slack adjustment. It is the problem that the error is very large after the maintenance personnel adjust according to experience.
具体实施方式detailed description
下面结合实施例,对本发明作进一步的详细说明,但本发明的实施方式不仅限于此。The present invention will be further described in detail below in conjunction with the examples, but the embodiments of the present invention are not limited thereto.
实施例1:Example 1:
专用于对电力导线驰度的检修方法,预先测得当时环境的温度为20℃,设定t1为25℃,t2为15℃,通过查表得出f1为8m,f2为4m,利用公式It is specially used for the maintenance method of the slack of the power conductor. The ambient temperature at that time is measured in advance as 20°C, and t1 is set as 25°C, and t2 is set as 15°C. It is obtained by looking up the table that f1 is 8m, and f2 is 4m. Use the formula
计算得出f为6m,将手扳葫芦一端固定在横担上,另一端通过铝合金紧线夹头连接在导线上,收紧手板葫芦拆除弯头挂板与耐张线夹处的销钉和耐张线夹,利用手扳葫芦的收紧将计算得到的导线的驰度值6m输送到手扳葫芦中进行调整;It is calculated that f is 6m. Fix one end of the lever hoist on the cross arm, and connect the other end to the wire through an aluminum alloy clamp. Tighten the hand hoist to remove the pins and Tension-resistant wire clamp, use the tightening of the lever block to transfer the calculated slack value of the wire 6m to the lever block for adjustment;
在两侧直线杆的导线悬挂点,垂直向下量出与弛度值相等的距离处,各绑上一块弛度板,观测人员在杆上,从一侧电杆上的弛度板瞄准对侧电杆上的弛度板,调整导线张力,使导线正好切于瞄准直线上,此时的弛度,即为所要求的弛度;At the wire suspension points of the straight rods on both sides, measure the distance equal to the sag value vertically downwards, and tie a sag board to each. The sag plate on the side pole adjusts the tension of the wire so that the wire is just cut on the aiming line, and the sag at this time is the required sag;
检修人员利用驰度板观察导线驰度符合要求且与三相驰度一致,合格后重新选取位置固定好耐张线夹,并与弯头挂板连接。Maintenance personnel use the slack plate to observe that the slack of the conductor meets the requirements and is consistent with the three-phase slack. After passing the test, re-select the position to fix the tension clamp and connect it to the elbow hanging plate.
利用上述方法,将电力导线的驰度调整到合适的驰度,数值准确,电力线能够进行最大化的输电效率,保证其使用寿命,解决了现有电力线的驰度调整都是通过检修人员根据经验调整出现误差很大的问题。Using the above method, adjust the slack of the power wire to a suitable slack, the value is accurate, the power line can maximize the transmission efficiency, and ensure its service life, and solve the problem that the slack adjustment of the existing power line is all based on the experience of maintenance personnel There is a big error in the adjustment.
实施例2:Example 2:
专用于对电力导线驰度的检修方法,预先测得当时环境的温度为12℃,设定t1为15℃,t2为6℃,通过查表得出f1为4m,f2为1.8m,利用公式It is specially used for the maintenance method of the slack of the power conductor. The ambient temperature at that time is measured in advance as 12°C, and the t1 is set to 15°C, and the t2 is set to 6°C. It is obtained by looking up the table that f1 is 4m, and f2 is 1.8m. Use the formula
计算得出f为2.9m,将手扳葫芦一端固定在横担上,另一端通过铝合金紧线夹头连接在导线上,收紧手板葫芦拆除弯头挂板与耐张线夹处的销钉和耐张线夹,利用手扳葫芦的收紧将计算得到的导线的驰度值2.9m输送到手扳葫芦中进行调整;It is calculated that f is 2.9m. Fix one end of the lever hoist on the cross arm, and connect the other end to the wire through an aluminum alloy clamp. Tighten the hand hoist to remove the pins at the elbow hanging plate and the tension clamp. and tension clamp, use the tightening of the lever block to transfer the calculated slack value of the wire 2.9m to the lever block for adjustment;
在两侧直线杆的导线悬挂点,垂直向下量出与弛度值相等的距离处,各绑上一块弛度板,观测人员在杆上,从一侧电杆上的弛度板瞄准对侧电杆上的弛度板,调整导线张力,使导线正好切于瞄准直线上,此时的弛度,即为所要求的弛度;At the wire suspension points of the straight rods on both sides, measure the distance equal to the sag value vertically downwards, and tie a sag board to each. The sag plate on the side pole adjusts the tension of the wire so that the wire is just cut on the aiming line, and the sag at this time is the required sag;
检修人员利用驰度板观察导线驰度符合要求且与三相驰度一致,合格后重新选取位置固定好耐张线夹,并与弯头挂板连接。Maintenance personnel use the slack plate to observe that the slack of the conductor meets the requirements and is consistent with the three-phase slack. After passing the test, re-select the position to fix the tension clamp and connect it to the elbow hanging plate.
以上所述,仅是本发明的较佳实施例,并非对本发明做任何形式上的限制,凡是依据本发明的技术、方法实质上对以上实施例所作的任何简单修改、等同变化,均落入本发明的保护范围之内。The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention in any form. Any simple modification or equivalent change made to the above embodiments in essence according to the technology and method of the present invention shall fall within the scope of the present invention. within the protection scope of the present invention.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410099725.0A CN103812053B (en) | 2014-03-18 | 2014-03-18 | Be exclusively used in the repair method to electrical lead degree of speeding |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410099725.0A CN103812053B (en) | 2014-03-18 | 2014-03-18 | Be exclusively used in the repair method to electrical lead degree of speeding |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103812053A CN103812053A (en) | 2014-05-21 |
| CN103812053B true CN103812053B (en) | 2016-04-13 |
Family
ID=50708446
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201410099725.0A Active CN103812053B (en) | 2014-03-18 | 2014-03-18 | Be exclusively used in the repair method to electrical lead degree of speeding |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103812053B (en) |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH08182134A (en) * | 1994-12-22 | 1996-07-12 | Asahi Tec Corp | Sag adjusting device for multiconductor power-transmission line |
| CN101859988A (en) * | 2010-03-12 | 2010-10-13 | 湖北省输变电工程公司 | Prefabricated stringing construction technology |
| CN202550405U (en) * | 2012-04-21 | 2012-11-21 | 石家庄供电公司 | Special ladder for maintenance of strain insulator |
-
2014
- 2014-03-18 CN CN201410099725.0A patent/CN103812053B/en active Active
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH08182134A (en) * | 1994-12-22 | 1996-07-12 | Asahi Tec Corp | Sag adjusting device for multiconductor power-transmission line |
| CN101859988A (en) * | 2010-03-12 | 2010-10-13 | 湖北省输变电工程公司 | Prefabricated stringing construction technology |
| CN202550405U (en) * | 2012-04-21 | 2012-11-21 | 石家庄供电公司 | Special ladder for maintenance of strain insulator |
Also Published As
| Publication number | Publication date |
|---|---|
| CN103812053A (en) | 2014-05-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN204645808U (en) | Bar stepped on by cement pole cable | |
| CN105606858A (en) | A polycarbonate electric meter box fixing frame | |
| CN203481420U (en) | Grounding wire device used for power transmission line overhauling | |
| CN102620846A (en) | Method of calculating steady-state heat capacity of power circuit | |
| CN103887735A (en) | Linear charged wire lifting device of electric transmission line | |
| CN203871745U (en) | Double-hoisting-point rod head fixture for live changing of linear insulator on steel pipe pole of 220kV line | |
| CN103812053A (en) | Special maintenance method for sag adjustment of electric conductors | |
| CN103178468A (en) | Wire clamp for being connected with live wire during live working | |
| CN203352104U (en) | Multifunctional insulating cross arm | |
| CN205159053U (en) | Phase -shifting transformer | |
| CN104993394A (en) | Power equipment power distribution box convenient to maintain and repair | |
| CN204030448U (en) | A kind of electrified fastening pin type insulator nut tool | |
| CN104332897A (en) | Two-end wire fastening device for construction of power lines | |
| CN204651789U (en) | The special hanger of hot-line insulator string replacement | |
| CN203850744U (en) | Live working special tool for pluggable cable terminal | |
| CN203758645U (en) | Transformer post head temperature measurer | |
| CN209822060U (en) | Multifunctional combined training facility for simulation low-voltage distribution line | |
| CN205178049U (en) | Diversion type meets ground wire device | |
| CN223729038U (en) | A lead clamp for electrical installation | |
| CN204720829U (en) | A kind of distribution box of power equipment being convenient to keep in repair | |
| CN204304322U (en) | A kind of reserve protection for changing 110kV strain insulator list insulator string | |
| CN203895279U (en) | Line connector rod | |
| CN202888720U (en) | Wire lifting tool of 10kV same-tower multi-circuit intermediate phase conductor | |
| CN206562906U (en) | A kind of construction ladder of power construction | |
| CN203891558U (en) | Live lead wire fixing insulation cross arm |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |