CN103791733B - The installation method of the cooling tower with coil pipe heat-exchange system and this coil heat exchange system - Google Patents

The installation method of the cooling tower with coil pipe heat-exchange system and this coil heat exchange system Download PDF

Info

Publication number
CN103791733B
CN103791733B CN201410033465.7A CN201410033465A CN103791733B CN 103791733 B CN103791733 B CN 103791733B CN 201410033465 A CN201410033465 A CN 201410033465A CN 103791733 B CN103791733 B CN 103791733B
Authority
CN
China
Prior art keywords
coil
pipe
water inlet
exchange system
fixed mount
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410033465.7A
Other languages
Chinese (zh)
Other versions
CN103791733A (en
Inventor
贺颂钧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Langxun Technology Development Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410033465.7A priority Critical patent/CN103791733B/en
Publication of CN103791733A publication Critical patent/CN103791733A/en
Application granted granted Critical
Publication of CN103791733B publication Critical patent/CN103791733B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P80/00Climate change mitigation technologies for sector-wide applications
    • Y02P80/10Efficient use of energy, e.g. using compressed air or pressurized fluid as energy carrier

Landscapes

  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

<b> is with the cooling tower of coil pipe heat-exchange system and the installation method of this coil heat exchange system, and it comprises tower body, some brace summers, some guide rails and coil heat exchange system.Coil heat exchange system comprises fixed mount, water inlet pipe, outlet pipe and some coil pipes.Fixed mount is provided with some convex sliding parts bottom it.Water inlet pipe and outlet pipe are arranged at fixed mount opposite end along being parallel to fixed mount bearing of trend, and the water inlet end of each coil pipe is connected with water inlet pipe and its water side is connected with outlet pipe; Each guide rail is provided with chute, and each sliding part removably slides and is contained in corresponding chute.In the present invention, coil pack is for assemble formation in advance, so can leak hunting to coil pipe in advance when dispatching from the factory, and stops to leak to occur.When mounted, the coil pack assembled in advance can be hung in by hanging device and be slidably connected on guide rail, saves the position of cooling tower set-up time, the conveniently each coil pack of adjustment and is easy to change and scale removal.</b>

Description

The installation method of the cooling tower with coil pipe heat-exchange system and this coil heat exchange system
Technical field
The present invention relates to a kind of closed cooling tower with coil pipe heat-exchange system, be particularly with the cooling tower of coil pipe heat-exchange system and the installation method of this coil heat exchange system.
Background technology
In traditional open cooling tower, recirculated cooling water directly contacts with air, cooling water is easily by the contaminating impurity in air, such as use in the environment that the dust such as wind sandy land, chemical plant, smeltery are large, cooling water contaminated rear operational efficiency and service life directly having influence on unit.Therefore in this type of area, water cooling equipment widely uses closed cooling tower.
The installation of existing close type cooling tower coil pipe mostly is building-site assembling, the wherein loose mail such as water inlet pipe and water outlet pipe, coil pipe shipment.When mounted, first water inlet pipe and water outlet pipe is fixedly mounted on tower body support frame, the installation position then coil pipe of single-piece being fixedly mounted on one by one successively water inlet pipe and water outlet pipe side is communicated with water inlet pipe and water outlet pipe.But owing to limiting by conditions such as field apparatus shortcomings, installation effectiveness is low, coil pipe easily and other object collision deformation or scratch leakage etc.And when occur can not Timeliness coverage when leaking, just can pinpoint the problems when tower be waited to run.When there is the phenomenons such as leakage, fouling, replacing and scale removal will be taken out coil pipe usually, can only dismantle coil pipe in the tower body confined space.
Summary of the invention
For the deficiencies in the prior art, object one of the present invention is intended to provide a kind of closed cooling tower installing simple band coil pipe heat-exchange system.
Object two of the present invention is intended to there is a need to provide a kind of installation method being applied to the cooling tower of band coil pipe heat-exchange system.
For achieving the above object one, the present invention adopts following technical scheme:
With the cooling tower of coil pipe heat-exchange system, it is characterized in that: comprise with the tower body of inner chamber, the some brace summers be set up in tower body, the coil heat exchange system that is arranged at the some guide rails on some brace summers and is slidably connected on some guide rails; This coil heat exchange system comprises fixed mount, water inlet pipe, outlet pipe and some coil pipes, and water inlet pipe, outlet pipe and some coil pipes are all arranged in fixed mount; Fixed mount is provided with some sliding parts protruded from bottom it; Water inlet pipe and outlet pipe are arranged at fixed mount opposite end along being parallel to fixed mount bearing of trend, and the water inlet end of each coil pipe is connected with water inlet pipe and its water side is connected with outlet pipe; Each guide rail is provided with chute, and each sliding part removably slides and is contained in corresponding chute; This coil heat exchange system comprises some installed parts, and some installed parts are set in turn in the relative two ends of fixed mount and each installed part is arranged at intervals with some installing holes; The water inlet end of each coil pipe is connected with water inlet pipe, and its water side is connected with outlet pipe through corresponding installing hole.
For achieving the above object two, the present invention adopts following technical scheme:
Be applied to the installation method of the cooling tower of band coil pipe heat-exchange system, it is characterized in that: comprise the following steps:
A, some guide rails are fixed on some brace summers successively;
B, water inlet pipe, outlet pipe, some coil pipes, fixed mount and some installed parts are assembled formation coil pack entirety in advance;
Coil pack entirety is hung in inner chamber from tower body top for C, use hanging device and correspondence is positioned over guide rail;
D, by along slide coil pack to adjust the position that each coil pack is positioned at tower body.
In the present invention, coil pack is for assemble formation in advance, so can leak hunting to coil pipe in advance when dispatching from the factory, and stops to leak to occur.When mounted, the coil pack assembled in advance can be hung in by hanging device and be slidably connected on guide rail, saves the position of cooling tower set-up time, the conveniently each coil pack of adjustment and is easy to change and scale removal.
Accompanying drawing explanation
Fig. 1 is the schematic perspective view of cooling tower of the present invention.
Fig. 2 is the structure chart of coil pipe heat-exchange system in cooling tower shown in Fig. 1.
The sections fit design sketch that Fig. 3 is cooling tower shown in Fig. 1.
Wherein: 10, tower body; 11, inner chamber; 30, brace summer; 40, guide rail; 41, chute; 50, coil heat exchange system; 51, water inlet pipe; 52, outlet pipe; 53, coil pipe; 54, fixed mount; 55, installed part; 550, installing hole; 56, sliding part.
Detailed description of the invention
Below in conjunction with accompanying drawing and detailed description of the invention, the present invention is described further:
Refer to Fig. 1, the cooling tower of this better embodiment comprises with the tower body 10 of an inner chamber 11, the some brace summers 30 be set up in tower body 10, the coil heat exchange system 50 that is arranged at the some guide rails 40 on some brace summers 30 and is slidably connected on some guide rails 40.
Please in the lump referring to Fig. 2, tower body 10 is substantially square-shaped.Some brace summers 30 are set up in inner chamber 11 along perpendicular to tower body 10 bearing of trend.Coil heat exchange system 50 comprises water inlet pipe 51, outlet pipe 52, is connected to some coil pipes 53, fixed mount 54 and some installed parts 55 between water inlet pipe 51 and outlet pipe 52.Fixed mount 54, substantially in hollow rectangular frame-shaped, its width is provided with the some sliding parts 56 protruding its bottom surface.Some installed parts 55 are juxtaposed on the both sides of fixed mount 54 length direction successively, and each installed part 55 are provided with some installing holes 550.Water inlet pipe 51 and outlet pipe 52 are arranged at the two ends of fixed mount 54 length direction along the direction perpendicular to some installed parts 55, and between some installed parts 55 of relative both sides.The water inlet of each coil pipe 53 is connected with water inlet pipe 51, and delivery port is connected with outlet pipe 52 through the installing hole 550 on corresponding installed part 55 successively.So, common assembling formation coil pack entirety of water inlet pipe 51, outlet pipe 52, some coil pipes 53, fixed mount 54 and some installed parts 55.
Some guide rails 40 to be arranged at intervals at along the direction perpendicular to some brace summers 30 on some brace summers 30 and with some sliding part 56 one_to_one corresponding.Each guide rail 40 is provided with the chute 41 for accommodating corresponding sliding part 56.In the present embodiment, the end of each sliding part 56 slides and is contained in corresponding chute 41, and can slide relative to guide rail 40 under external force.Understandably, in some other embodiment, sliding part 56 can be one-body molded with fixed mount 54, and the end of sliding part 56 can arrange other structures of easily sliding such as castor, does not limit at this.
Please in the lump referring to Fig. 3, when cooling tower is installed, some guide rails 40 are fixed on some brace summers 30 successively.Water inlet pipe 51, outlet pipe 52, some coil pipes 53, fixed mount 54 and some installed parts 55 assembling formation in advance coil pack entirety.Coil pack hanging device is hung in Ta Nei along arrow A direction by the top of tower body 10 and is placed on guide rail 40.In the present embodiment, guide rail 40 is provided with three groups of coil packs, operator regulates the position of three groups of coil packs by the slip along arrow B direction on guide rail 40.Adopt coil pipe 53 in this way and can save the cooling tower set-up time, and coil heat exchange system 50 is leaked hunting when dispatching from the factory, stop to leak appearance.In like manner, when coil pipe 53 needs replacing, scale removal, available hanging device hangs out a whole set of coil pipe heat-exchange system 50 outside tower body 10, conveniently replaced, scale removal.
Operationally, the High-temperature cooling medium flowed out from machine set outlet end enters in the water inlet of coil pipe 53 from water inlet pipe 51, and cooling medium convoluted flow from top to bottom in coil pipe 53, coil pipe 53 wraps up by Sprayer Circulation water.Absorbed the heat of cooling medium by tube wall heat trnasfer, the recirculated cooling water after heat absorption is subsequently by Air flow, and heat is discharged in air by tower body 10 top, and last cooled low-temperature cooling media is back in unit by outlet pipe 52 and carries out heat exchange.
In the present invention, by water inlet pipe 51, outlet pipe 52, some coil pipes 53, fixed mount 54 and some installed parts 55 assembling formation in advance coil pack entirety.So, can leak hunting to coil pipe 53 when coil heat exchange system 50 is dispatched from the factory, stop to leak appearance, and save the cooling tower set-up time.Meanwhile, when mounted, the coil pack assembled in advance can be hung in by hanging device and be slidably connected on guide rail 40, thus the position of each coil pack of convenient adjustment, and conveniently replaced, scale removal.
For a person skilled in the art, according to technical scheme described above and design, other various corresponding change and distortion can be made, and all these change and distortion all should belong within the protection domain of the claims in the present invention.

Claims (2)

1. be with the cooling tower of coil pipe heat-exchange system, it is characterized in that: comprise with the tower body of inner chamber, the some brace summers be set up in tower body, the coil heat exchange system that is arranged at the some guide rails on some brace summers and is slidably connected on some guide rails; This coil heat exchange system comprises fixed mount, water inlet pipe, outlet pipe and some coil pipes, and water inlet pipe, outlet pipe and some coil pipes are all arranged in fixed mount; Fixed mount is provided with some sliding parts protruded from bottom it; Water inlet pipe and outlet pipe are arranged at fixed mount opposite end along being parallel to fixed mount bearing of trend, and the water inlet end of each coil pipe is connected with water inlet pipe and its water side is connected with outlet pipe; Each guide rail is provided with chute, and each sliding part removably slides and is contained in corresponding chute; This coil heat exchange system comprises some installed parts, and some installed parts are set in turn in the relative two ends of fixed mount and each installed part is arranged at intervals with some installing holes; The water inlet end of each coil pipe is connected with water inlet pipe, and its water side is connected with outlet pipe through corresponding installing hole.
2. be applied to the installation method of the cooling tower of band coil pipe heat-exchange system according to claim 1, it is characterized in that: comprise the following steps:
A, some guide rails are fixed on some brace summers successively;
B, water inlet pipe, outlet pipe, some coil pipes, fixed mount and some installed parts are assembled formation coil pack entirety in advance;
Coil pack entirety is hung in inner chamber from tower body top for C, use hanging device and correspondence is positioned over guide rail;
D, by along slide coil pack to adjust the position that each coil pack is positioned at tower body.
CN201410033465.7A 2014-01-23 2014-01-23 The installation method of the cooling tower with coil pipe heat-exchange system and this coil heat exchange system Active CN103791733B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410033465.7A CN103791733B (en) 2014-01-23 2014-01-23 The installation method of the cooling tower with coil pipe heat-exchange system and this coil heat exchange system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410033465.7A CN103791733B (en) 2014-01-23 2014-01-23 The installation method of the cooling tower with coil pipe heat-exchange system and this coil heat exchange system

Publications (2)

Publication Number Publication Date
CN103791733A CN103791733A (en) 2014-05-14
CN103791733B true CN103791733B (en) 2016-04-20

Family

ID=50667632

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410033465.7A Active CN103791733B (en) 2014-01-23 2014-01-23 The installation method of the cooling tower with coil pipe heat-exchange system and this coil heat exchange system

Country Status (1)

Country Link
CN (1) CN103791733B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113831932A (en) * 2020-06-08 2021-12-24 中国石化工程建设有限公司 Installation device and installation method for cracking furnace radiation coil
CN111721140A (en) * 2020-06-13 2020-09-29 中国化学工程第十一建设有限公司 Construction method of glass fiber reinforced plastic cooling tower and glass fiber reinforced plastic cooling tower
CN111895806A (en) * 2020-09-07 2020-11-06 广东览讯科技开发有限公司 EC fan convulsions crossing current closed side entry air-out cooling tower

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1963369A (en) * 2005-11-10 2007-05-16 矿昱科技股份有限公司 Evaporative closed cooling tower
CN102997715A (en) * 2011-09-15 2013-03-27 上海良机冷却设备有限公司 Countercurrent closed cooling tower of novel device with coil group quick disassembly structure
CN102997722A (en) * 2011-09-15 2013-03-27 上海良机冷却设备有限公司 Countercurrent closed cooling tower of novel device with coil layer structure
CN203216328U (en) * 2013-03-02 2013-09-25 浙江天鼎机械制造有限公司 Mobile evaporation cooling coil structure
CN203216340U (en) * 2013-04-22 2013-09-25 江苏中烟工业有限责任公司徐州卷烟厂 Split type shell and tube heat exchanger
CN203758300U (en) * 2014-01-23 2014-08-06 贺颂钧 Cooling tower with coil-pipe heat exchanging system

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004076972A (en) * 2002-08-12 2004-03-11 Sanki Eng Co Ltd Cover device for sprinkling tank of cooling tower

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1963369A (en) * 2005-11-10 2007-05-16 矿昱科技股份有限公司 Evaporative closed cooling tower
CN102997715A (en) * 2011-09-15 2013-03-27 上海良机冷却设备有限公司 Countercurrent closed cooling tower of novel device with coil group quick disassembly structure
CN102997722A (en) * 2011-09-15 2013-03-27 上海良机冷却设备有限公司 Countercurrent closed cooling tower of novel device with coil layer structure
CN203216328U (en) * 2013-03-02 2013-09-25 浙江天鼎机械制造有限公司 Mobile evaporation cooling coil structure
CN203216340U (en) * 2013-04-22 2013-09-25 江苏中烟工业有限责任公司徐州卷烟厂 Split type shell and tube heat exchanger
CN203758300U (en) * 2014-01-23 2014-08-06 贺颂钧 Cooling tower with coil-pipe heat exchanging system

Also Published As

Publication number Publication date
CN103791733A (en) 2014-05-14

Similar Documents

Publication Publication Date Title
CN103791733B (en) The installation method of the cooling tower with coil pipe heat-exchange system and this coil heat exchange system
CN210874511U (en) Contain high caloric industrial waste gas processing apparatus
RU2018131248A (en) ELECTRIC COOLING COOLER
GB2610706B (en) Filter kit, assembly, and method for installation within a support surface associated with a heat exchanger unit not limited to such as an air cooled liquid
CN213214217U (en) Liquid-cooled heat dissipation regulator cubicle
CN203758300U (en) Cooling tower with coil-pipe heat exchanging system
CN202121227U (en) High voltage electrical equipment cabinet body
CN103231877B (en) Horizontal cold box system
CN202928217U (en) Condensing device of high temperature heat pump
CN215186314U (en) Water cooling system
CN102840644A (en) Automatic temperature control communication base station
CN205481740U (en) Full frequency conversion air source heat pump unit
CN210666637U (en) Computer machine case with dynamic refrigeration mechanism
CN205121462U (en) Cloud calculates host computer heat dissipation frame
CN209806291U (en) Cooling device of outdoor communication cabinet
CN202361603U (en) Fan coil surface cooler
CN203785524U (en) Novel cooler support structure of closed cooling tower
CN222255484U (en) Long-life rotary joint
CN213515166U (en) Combined falling film heat exchanger
CN214507133U (en) Inside cooling device for mobile phone projection device
CN205864901U (en) Communication cabinet outside a kind of oil SAPMAC method heat dissipation chamber
CN220771957U (en) Mining closed cooling tower
CN204240646U (en) A kind of coverboard full-liquid type heat exchanger
CN222029493U (en) Mobile box type switch station
CN222806311U (en) Supporting table with cooling function for laser cutting of steel plate

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190214

Address after: 526000 Spinning Workshop of Zhaoqing Yongwang Textile Co., Ltd. Shali Industrial Park, Zhaoqing High-tech Zone, Zhaoqing City, Guangdong Province

Patentee after: Guangdong Langxun Technology Development Co., Ltd.