CN103774766B - Intelligent building thunder and lightning pre-control construction method - Google Patents

Intelligent building thunder and lightning pre-control construction method Download PDF

Info

Publication number
CN103774766B
CN103774766B CN201410010852.9A CN201410010852A CN103774766B CN 103774766 B CN103774766 B CN 103774766B CN 201410010852 A CN201410010852 A CN 201410010852A CN 103774766 B CN103774766 B CN 103774766B
Authority
CN
China
Prior art keywords
construction
surge protector
equipment
building
thunder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410010852.9A
Other languages
Chinese (zh)
Other versions
CN103774766A (en
Inventor
葛加君
葛小敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xuzhou Yukun Water Conservancy Engineering Construction Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201410010852.9A priority Critical patent/CN103774766B/en
Publication of CN103774766A publication Critical patent/CN103774766A/en
Application granted granted Critical
Publication of CN103774766B publication Critical patent/CN103774766B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Elimination Of Static Electricity (AREA)

Abstract

The invention discloses a kind of intelligent building thunder and lightning pre-control construction method, comprise shielding construction, all press construction, clamping protection construction.Easy construction of the present invention, reaches more than 90% to intelligent building thunder and lightning pre-control degree of safety, improves more than 42% on year-on-year basis, and transient overvoltage compression resistance improves more than 60%, and electromagnetic interference degree reduces by less than 35%, available protecting Method of Intelligent Building Performance product facility.

Description

Intelligent building thunder and lightning pre-control construction method
Technical field
The present invention relates to a kind of intelligent building thunder and lightning pre-control construction method.
Background technology
The development of recent domestic intelligent building is very fast, becomes other theme of Building class.So-called intelligent building is actually the application of high-end technology on building such as network technology, intellectual technology, visualization technique, intellectualized technology, wireless local area network technology, data communication technology, two-way television transmission technology.And the electronic equipment applying these high-end technologies is very low to Lightning Transient overvoltage tolerance, very responsive to thunder and lightning electromagnetic interference, after suffering the infringement of thunderbolt electromagnetism, very easily damage.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, effective intelligent building thunder and lightning pre-control construction method.
Technical solution of the present invention is:
A kind of intelligent building thunder and lightning pre-control construction method, is characterized in that: comprise the following steps:
(1) shielding construction
(1) structure body shielding construction: first when designing, fabric structure is designed to frame structure, its inherent reinforcing bar adopts welding method to connect, and is formed netted, and network is even.And outer lattice tie point is set by spacing 2m, adopt diameter 3mm reinforcing bar to be vertically welded on inherent steel grid, each aspect arranges 2-3 internally electric and electronic smart machine tie point, and the same diameter 3mm reinforcing bar that adopts carries out vertical welding; Carry out cover when wall toft face forms covering one deck eyelet 1cm*1cm gauze wire cloth comprehensively, its gauze wire cloth cover is connected with outer lattice tie point, then carries out wall roofing and whitewashes; When after interior of building smart machine, electronic equipment, installation of electrical equipment, be connected with inherent tie point, form the structure body shielding thunder and lightning pre-control network system;
(2) circuit shielding construction: the H cable selecting band metal on cable is selected; To the cable not having function of shielding, adopt the metallic conduit of wall thickness >=2mm, cable is passed from metallic conduit, at building entrance place, the reinforcing bar down lead of metal pipe-wall and building or grounding wire carry out colligation and are connected; Concentric wiring region in building, arranges wiring well, and in the borehole wall, reinforcing bar carries out a circle connection every 50cm spacing, forms grid; In building on branch's wiring and house wiring path, erection iron and steel wiring groove, and carry out colligation with grounding wire and be connected, and press 100cm spacing screw fastening, formation circuit shields the thunder and lightning pre-control network system;
(3) device mask construction: when equipment choice, select bulk metal shielding device housing, housing is also welded to connect with down lead contact, simultaneously get lines crossed hole, insert hole, heat elimination hole of giving vent to anger of apparatus casing is adopting eyelet to be the close guard face of metal of below 2mm, housing gap adopts conductive fiber pad, the forming device shielding thunder and lightning pre-control network system;
(2) all construction is pressed
Construction is all pressed to comprise to adopt the construction of busbar formula and female ring formula to construct two aspects;
Busbar is constructed: compare concentrated area at multiple metalwork and arrange a connection busbar, its sectional area is 25-95mm 2, busbar adopts metal sheet to make, and is fixed on metope, by multiple hardware, plate, line, pipe, cable shield, equipment metal shell wire bonds on busbar, forms balanced pressure system;
Female ring is constructed: in order to make multiple equipment or system carry out equipotential link, and arrange a circle in indoor along body of wall surrounding and connect female ring, female ring is closed, adopts sectional area>=50mm 2metal sheet, is embeddingly attached on body of wall, and apart from ground 5-10mm, by multiple component, line equipment wire bonds is in female ring; Female ring, by spacing 5m, connects ground connector and forms annular balanced pressure system;
(3) construct with clamping protection
Mainly comprise surge protector selection, surge protector power inleting terminal lays, surge protector dress position is determined, surge protector is installed;
Surge protector select: according to maximum working voltage, maximum protection level, maximum thunderbolt impingement flow, the corresponding protection power of maximum beautiful electric current four selecting factors surge protector '
Surge protector power inleting terminal lays: two ends cable is straight, and plain conductor is radian smoothed version in corner;
Surge protector dress position is determined: be arranged on and move into thing entrance, near protected equipment;
Surge protector is installed: surge protector installation is carried out after determining in dress position; Surge protector is arranged on switchboard, selects identical SPD module to discharge lightning current over the ground and keeps proterctive equipment equipotential.
Easy construction of the present invention, reaches more than 90% to intelligent building thunder and lightning pre-control degree of safety, improves more than 42% on year-on-year basis, and transient overvoltage compression resistance improves more than 60%, and electromagnetic interference degree reduces by less than 35%, available protecting Method of Intelligent Building Performance product facility.
Below in conjunction with embodiment, the invention will be further described.
Detailed description of the invention
A kind of intelligent building thunder and lightning pre-control construction method, comprises the following steps:
(1) shielding construction
(1) structure body shielding construction: first when designing, fabric structure is designed to frame structure, its inherent reinforcing bar adopts welding method to connect, and is formed netted, and network is even.And outer lattice tie point is set by spacing 2m, adopt diameter 3mm reinforcing bar to be vertically welded on inherent steel grid, each aspect arranges 2-3 internally electric and electronic smart machine tie point, and the same diameter 3mm reinforcing bar that adopts carries out vertical welding; Carry out cover when wall toft face forms covering one deck eyelet 1cm*1cm gauze wire cloth comprehensively, its gauze wire cloth cover is connected with outer lattice tie point, then carries out wall roofing and whitewashes; When after interior of building smart machine, electronic equipment, installation of electrical equipment, be connected with inherent tie point, form the structure body shielding thunder and lightning pre-control network system;
(2) circuit shielding construction: the H cable selecting band metal on cable is selected; To the cable not having function of shielding, adopt the metallic conduit of wall thickness >=2mm, cable is passed from metallic conduit, at building entrance place, the reinforcing bar down lead of metal pipe-wall and building or grounding wire carry out colligation and are connected; Concentric wiring region in building, arranges wiring well, and in the borehole wall, reinforcing bar carries out a circle connection every 50cm spacing, forms grid; In building on branch's wiring and house wiring path, erection iron and steel wiring groove, and carry out colligation with grounding wire and be connected, and press 100cm spacing screw fastening, formation circuit shields the thunder and lightning pre-control network system;
(3) device mask construction: when equipment choice, select bulk metal shielding device housing, housing is also welded to connect with down lead contact, simultaneously get lines crossed hole, insert hole, heat elimination hole of giving vent to anger of apparatus casing is adopting eyelet to be the close guard face of metal of below 2mm, housing gap adopts conductive fiber pad, the forming device shielding thunder and lightning pre-control network system;
(2) all construction is pressed
Construction is all pressed to comprise to adopt the construction of busbar formula and female ring formula to construct two aspects;
Busbar is constructed: compare concentrated area at multiple metalwork and arrange a connection busbar, its sectional area is 25-95mm 2, busbar adopts metal sheet to make, and is fixed on metope, by multiple hardware, plate, line, pipe, cable shield, equipment metal shell wire bonds on busbar, forms balanced pressure system;
Female ring is constructed: in order to make multiple equipment or system carry out equipotential link, and arrange a circle in indoor along body of wall surrounding and connect female ring, female ring is closed, adopts sectional area>=50mm 2metal sheet, is embeddingly attached on body of wall, and apart from ground 5-10mm, by multiple component, line equipment wire bonds is in female ring; Female ring, by spacing 5m, connects ground connector and forms annular balanced pressure system;
(3) clamping protection construction
Mainly comprise surge protector selection, surge protector power inleting terminal lays, surge protector dress position is determined, surge protector is installed;
Surge protector is selected: according to the surge protector of maximum working voltage, maximum protection level, maximum thunderbolt impingement flow, the corresponding protection power of maximum beautiful electric current four selecting factors;
Surge protector power inleting terminal lays: two ends cable is straight, and plain conductor is radian smoothed version in corner;
Surge protector dress position is determined: be arranged on and move into thing entrance, near protected equipment;
Surge protector is installed: surge protector installation is carried out after determining in dress position; Surge protector is arranged on switchboard, selects identical SPD module to discharge lightning current over the ground and keeps proterctive equipment equipotential.

Claims (1)

1. an intelligent building thunder and lightning pre-control construction method, is characterized in that: comprise the following steps:
(1) shielding construction
(1) structure body shielding construction: first when designing, fabric structure is designed to frame structure, its inherent reinforcing bar adopts welding method to connect, formed netted, and network is even, and outer lattice tie point is set by spacing 2m, adopt diameter 3mm reinforcing bar to be vertically welded on inherent steel grid, each aspect arranges 2-3 internally electric and electronic smart machine tie point, and the same diameter 3mm reinforcing bar that adopts carries out vertical welding; When wall toft face is formed, the gauze wire cloth comprehensively covering one deck eyelet 1cm*1cm carries out cover, and its gauze wire cloth cover is connected with outer lattice tie point, then carries out wall roofing and whitewashes; When after interior of building smart machine, electronic equipment, installation of electrical equipment, be connected with interior electric and electronic smart machine tie point, form the structure body shielding thunder and lightning pre-control network system;
(2) circuit shielding construction: the H cable selecting band metal on cable is selected; To the cable not having function of shielding, adopt the metallic conduit of wall thickness >=2mm, cable is passed from metallic conduit, at building entrance place, the reinforcing bar down lead of metal pipe-wall and building or grounding wire carry out colligation and are connected; Concentric wiring region in building, arranges wiring well, and in the borehole wall, reinforcing bar carries out a circle connection every 50cm spacing, forms grid; In building on branch's wiring and house wiring path, erection iron and steel wiring groove, and carry out colligation with grounding wire and be connected, and press 100cm spacing screw fastening, formation circuit shields the thunder and lightning pre-control network system;
(3) device mask construction: when equipment choice, select bulk metal shielding device housing, housing is also welded to connect with reinforcing bar down lead contact, simultaneously get lines crossed hole, insert hole, heat elimination hole of giving vent to anger of apparatus casing is adopting eyelet to be the close guard face of metal of below 2mm, housing gap adopts conductive fiber pad, the forming device shielding thunder and lightning pre-control network system;
(2) all construction is pressed
All press construction to comprise and adopt busbar construction to construct two aspects with female ring;
Busbar is constructed: compare concentrated area at multiple metalwork and arrange a connection busbar, its sectional area is 25-95mm 2, busbar adopts metal sheet to make, and is fixed on metope, by multiple hardware, plate, line, pipe, cable shield, equipment metal shell wire bonds on busbar, forms balanced pressure system;
Female ring is constructed: in order to make multiple equipment or system carry out equipotential link, and arrange a circle in indoor along body of wall surrounding and connect female ring, female ring is closed, adopts sectional area>=50mm 2metal sheet, is embeddingly attached on body of wall, and apart from ground 5-10mm, by multiple component, line equipment wire bonds is in female ring; Female ring, by spacing 5m, connects ground connector and forms annular balanced pressure system;
(3) clamping protection construction
Mainly comprise surge protector selection, surge protector power inleting terminal lays, surge protector dress position is determined, surge protector is installed;
Surge protector is selected: according to the surge protector of maximum working voltage, maximum protection level, maximum thunderbolt impingement flow, the corresponding protection power of maximum beautiful electric current four selecting factors;
Surge protector power inleting terminal lays: two ends cable is straight, and plain conductor is radian smoothed version in corner;
Surge protector dress position is determined: be arranged on and move into thing entrance, near protected equipment; Surge protector is installed: surge protector installation is carried out after determining in dress position; Surge protector is arranged on switchboard, selects identical SPD module to discharge lightning current over the ground and keeps proterctive equipment equipotential.
CN201410010852.9A 2014-01-10 2014-01-10 Intelligent building thunder and lightning pre-control construction method Active CN103774766B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410010852.9A CN103774766B (en) 2014-01-10 2014-01-10 Intelligent building thunder and lightning pre-control construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410010852.9A CN103774766B (en) 2014-01-10 2014-01-10 Intelligent building thunder and lightning pre-control construction method

Publications (2)

Publication Number Publication Date
CN103774766A CN103774766A (en) 2014-05-07
CN103774766B true CN103774766B (en) 2015-12-09

Family

ID=50567473

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410010852.9A Active CN103774766B (en) 2014-01-10 2014-01-10 Intelligent building thunder and lightning pre-control construction method

Country Status (1)

Country Link
CN (1) CN103774766B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105633923A (en) * 2014-10-28 2016-06-01 安徽铁创新材料科技有限公司 Protective grounding system of workshop electrical device
CN106251911B (en) * 2016-07-22 2018-07-27 葛加君 The method of building intelligence system multidigit pre-control electromagnetism Leibo interference
CN107552991A (en) * 2017-10-16 2018-01-09 上海建科检验有限公司 The welding method of cable jacket iron pipe in a kind of earth work

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11141185A (en) * 1997-11-14 1999-05-25 Tomoe Corp Electromagnetic shield building using seismic isolation method
CN201075650Y (en) * 2007-08-09 2008-06-18 江苏新源建筑工程有限公司 Lightning protection system of building constructive engineering
CN102345331A (en) * 2011-07-13 2012-02-08 葛加君 Construction method of solar energy lightning protection facility on building roof
CN103151767A (en) * 2013-02-16 2013-06-12 中讯邮电咨询设计院有限公司 Method for connecting transient equipotential of grounding grid in case of dangerous influence to small-sized communication station caused by strong currents
CN203367747U (en) * 2013-05-31 2013-12-25 嘉兴永明石化有限公司 High-efficient safe lightning protection system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11141185A (en) * 1997-11-14 1999-05-25 Tomoe Corp Electromagnetic shield building using seismic isolation method
CN201075650Y (en) * 2007-08-09 2008-06-18 江苏新源建筑工程有限公司 Lightning protection system of building constructive engineering
CN102345331A (en) * 2011-07-13 2012-02-08 葛加君 Construction method of solar energy lightning protection facility on building roof
CN103151767A (en) * 2013-02-16 2013-06-12 中讯邮电咨询设计院有限公司 Method for connecting transient equipotential of grounding grid in case of dangerous influence to small-sized communication station caused by strong currents
CN203367747U (en) * 2013-05-31 2013-12-25 嘉兴永明石化有限公司 High-efficient safe lightning protection system

Also Published As

Publication number Publication date
CN103774766A (en) 2014-05-07

Similar Documents

Publication Publication Date Title
CN103534894B (en) Lightning protection radio remote unit, distributed base station and lightning protection system and method thereof
CN103774766A (en) Thunder and lightning pro-control construction method for intelligent building
CN102751713A (en) Transient protection system of mobile communication base station based on thunder-and-lightning import port
CN204597473U (en) The indoor 7 grades of lightning-protection systems of a kind of network center machine room
CN102956997A (en) Equipotential lightning protection auxiliary device for small-scale industrial control room
CN202339977U (en) Grounding structure for lightning protection direct current feeder cable of distributed base station
KR101748170B1 (en) Insulation stick for blocking water movement
CN103779806B (en) The method and system of the anti-down power supply of electrical network
CN211670613U (en) Lightning protection system for roof electrical equipment
CN216312650U (en) Protection grounding box from both sides inlet wire
CN105429034A (en) Grounding device of transformer substation containing inlet and outlet cables and mounting method thereof
JP5258454B2 (en) Grounding system
CN206401542U (en) A Lightning Protection Grounding System Based on Indoor Wireless Communication System
CN208571558U (en) The lightning protection device of tower crane before hydroelectric dam
KR101044447B1 (en) Smart bonding method of control panel with metal enclosure
CN205666097U (en) Copper -core polyvinyl chloride sheath steel strip armoring power cable
CN104393426B (en) A kind of method reducing potential difference between earth conductor and device thereof
CN203787850U (en) Anti-reverse power supply system of power grid
CN202957351U (en) Equipotential lightning protection assisting device for small industrial control room
CN107181247A (en) A kind of transformer station's communication system lightening arresting method
CN103151767B (en) Method for connecting transient equipotential of grounding grid in case of dangerous influence to small-sized communication station caused by strong currents
CN203521645U (en) Earthing device of secondary electrical equipment and earthing system
JP7457301B2 (en) Lightning protection methods for electrical facilities
CN204391643U (en) Equipotential terminal link box
CN203445609U (en) Electrical Equipment Protection System for Adjacent Houses When Communication Base Stations Are Struck by Lightning

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20191129

Address after: 221000 No.9 Xingye Road, Lingang Industrial Park, Pizhou City, Xuzhou City, Jiangsu Province

Patentee after: Jiangsu Sanzhou Machinery Technology Co., Ltd

Address before: 226400, Development Building, east side of Taishan Road, digging Town, Rudong County, Jiangsu, Nantong 1002

Patentee before: Ge Jiajun

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200910

Address after: Room 301, office building, No. 11, Zhujiang East Road, Xuzhou high tech Industrial Development Zone, Xuzhou City, Jiangsu Province

Patentee after: Xuzhou Yukun Water Conservancy Engineering Construction Co., Ltd

Address before: 221000 No.9 Xingye Road, Lingang Industrial Park, Pizhou City, Xuzhou City, Jiangsu Province

Patentee before: Jiangsu Sanzhou Machinery Technology Co.,Ltd.

TR01 Transfer of patent right