CN103742154A - 一种盾构隧道通风井施工方法 - Google Patents

一种盾构隧道通风井施工方法 Download PDF

Info

Publication number
CN103742154A
CN103742154A CN201310752435.7A CN201310752435A CN103742154A CN 103742154 A CN103742154 A CN 103742154A CN 201310752435 A CN201310752435 A CN 201310752435A CN 103742154 A CN103742154 A CN 103742154A
Authority
CN
China
Prior art keywords
tunnel
caisson structure
shield
ventilating shaft
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310752435.7A
Other languages
English (en)
Other versions
CN103742154B (zh
Inventor
翟世鸿
杨钊
刘毅
罗卫
杨擎
陈培帅
姬付全
唐炫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201310752435.7A priority Critical patent/CN103742154B/zh
Publication of CN103742154A publication Critical patent/CN103742154A/zh
Application granted granted Critical
Publication of CN103742154B publication Critical patent/CN103742154B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明公开了一种盾构隧道通风井施工方法,它将预制的沉井结构作为隧道通风井,沉井结构定位下沉与隧道盾构同步进行,沉井结构底口与隧道顶部采用现浇钢筋混凝土连成整体,并在隧道顶部开口,形成通风井。该施工方法规避了传统地下连续墙深基坑施工的风险,减小了风井施工的深度,不影响盾构掘进施工并规避了盾构机进出风井的风险,加快了盾构区间施工工期,对需设置通风井的盾构公路或地铁隧道有较好的经济效益。

Description

一种盾构隧道通风井施工方法
技术领域
本发明涉及土木建筑领域,具体地指一种盾构隧道通风井施工方法。
背景技术
长距离公路或地铁盾构隧道一般需要设置通风井,以满足通风、排烟的要求。目前通风井一般先采用地下连续墙体形成围护的深基坑,水下混凝土结构封底,并在墙体上预留盾构机进、出的孔洞,盾构机进出洞掘进通过风井后,再拆除风井内多余的隧道管片,最后施工洞门、完成风井结构。该施工方法需要施作超过盾构隧道底部一定深度的地下连续墙结构,基坑较深,基坑在开挖过程中会导致周边地面沉降,极端的情况下甚至会产生基坑失稳、渗流等巨大安全事故。在盾构到达时,需要凿除洞门位置连续墙。对盾构机进、出洞而言,破除洞门时面临着高水土压力的巨大施工风险。盾构机到达风井和通过风井均会影响正常的掘进,致使掘进停顿,从而影响掘进效率。
发明内容
本发明的目的就是要解决上述背景技术的不足,提供一种盾构隧道通风井施工方法。
本发明的技术方案为:一种盾构隧道通风井施工方法,其特征在于,它包括以下步骤:
1)、盾构隧道掘进并穿过通风井预设位置;同步在地面预制并定位沉井结构;
2)、沉井结构沿内壁开挖土方,使沉井结构下沉至隧道顶部;
3)、将沉井结构底口与隧道顶部之间的土体形成止水的密封结构;
4)、开挖沉井结构底口与隧道顶部之间的土体,并切割隧道顶部,将沉井结构底口与隧道连接成整体,形成通风井结构。
上述方案中:
步骤2)中,沉井结构内按设定高度多次开挖土方,其中一段土方与上段土方接高并养护至强度达到要求后再进行下一段土方的开挖。
所述沉井结构内开挖土方下沉至离隧道顶部0.5至2米。
优选地,步骤3)中,先通过在沉井结构井口外围设置锁口结构以防止沉井结构下沉,再沿锁口结构竖向即沉井结构外侧约0.5米位置及沉井结构井壁内预留的孔洞中打设冷冻管至隧道顶部,并采用冻结法将沉井结构底口与隧道顶部之间的土体形成止水的密封结构。
优选地,步骤3)中,采用深井降水的方法,将地下水降至隧道顶部之下,沉井结构底口与隧道顶部之间的土体形成止水的密封结构。
所述通风井位置对应的盾构隧道采用能切割形成与沉井结构贯通开口的管片进行衬砌。
所述沉井结构底口与隧道通过现浇钢筋混凝土连成整体。
本发明所示的施工方法,与现有的施工方法相比,不需要施工风险较大的地下连续墙深基坑,能减少通风井的深度。采用沉井结构大大降低了通风井围护结构的施工风险,避免了盾构机掘进通过风井时的进、出洞工序和风险,能保证盾构机连续掘进而不受通风井施工的影响,能加快施工进度,并能降低工程造价。
附图说明
图1为本发明实施例的隧道通风井结构立面图;
图2为本发明实施例的隧道通风井结构俯视图;
图3为图1中1-1剖面示意图;
图4为本发明实施例的隧道通风井结构冻结法大样图;
图5为本发明实施例中沉井结构定位示意图;
图6、图7为本发明实施例中沉井结构沿内壁开挖土方结构示意图;
图8为将沉井结构底口与隧道顶部之间的土体冻结示意图;
图9为将沉井结构底口与隧道管片连接成整体结构示意图。
具体实施方式
下面结合附图和具体实施例对本发明作进一步的详细说明。
本实施例所描述的一种盾构隧道通风井施工方法,它包括以下步骤:
1)、参考图5,盾构隧道掘进并穿过通风井预设位置;同步在地面预制并定位沉井结构1,将沉井结构1作为通风井井筒;其中通风井预设位置对应的盾构隧道采用能切割形成与沉井结构1贯通开口的管片3进行衬砌,而在沉井结构1的井壁预留孔洞4;
2)、参考图6、图7,沉井结构1沿内壁开挖土方,使沉井结构1下沉至隧道顶部0.5至2米范围停止下沉;具体为:沉井结构1内按设定高度多次开挖土方,其中一段土方与上段土方接高并养护至强度达到要求后再进行下一段土方的开挖,在下沉过程中,可采用纠偏设备-千斤顶对沉井结构1跟踪纠偏;
3)、参考图4及图8,先通过在沉井结构1井口外围设置锁口结构5以防止沉井结构1下沉,锁口结构5为施工中常见的锁口环;再沿锁口结构5竖向即沉井结构1外侧约0.5米位置及沉井结构1井壁内预留的孔洞4中打设冷冻管2至隧道顶部约0.5米范围,采用冻结法将沉井结构1底口与隧道顶部之间的土体形成止水的密封结构,起到防止外侧水、土压力的作用,在冷冻土体和沉井结构井筒的保护下,内部可以进行干施工;
当地面具备降水条件时,也可以采用深井降水,将地下水降至隧道顶部之下,使沉井底口与隧道顶部管片之间能干施工,从而省略土体冷冻工艺;
4)、参考图9,将沉井结构1底口与隧道顶部之间的土体冻结完成后,开挖二者之间的土体,同时采取固定措施,防止沉井结构1下沉;随后切割隧道顶部管片3,并在管片3内设置支撑保护,并拔出沉井结构1井壁内的冷冻管,现浇钢筋混凝土,将沉井结构1底口与隧道管片3连接成整体,形成通风井结构,其结构示意图如图1、图2及图3所示;在接口位置做好防水措施,最后拔出锁口结构5内的冷冻管。
本发明所示的盾构隧道通风井施工方法,规避了传统地下连续墙深基坑施工的风险,减小了风井施工的深度,不影响盾构掘进施工并规避了盾构机进出风井的风险,加快了盾构区间施工工期,对需设置通风井的盾构公路或地铁隧道有较好的经济效益。
本发明所示的盾构隧道通风井施工方法,具有以下优点:
1、适应性好:适用于各种不同地质,特别是地质条件差,深基坑开挖风险较大的场地;
2、施工安全风险小:采用盾构先掘进,再通过沉井结构下沉明挖施工,避免了深基坑围护开挖的施工风险,以及盾构机通过通风井进洞和出洞面临的高水土压力的风险;
3、经济性好:采用沉井结构作为通风井井筒结构,一方面沉井结构较地连墙围护深基坑造价低,基坑深度小(只需要到隧道顶部),另一方面,盾构能连续掘进而不受风井施工影响,提高掘进效率,降低工程造价;
4、运用前景好:该种方法可以避开其他因素对盾构掘进的影响,降低盾构掘进的风险,减少掘进的时间。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明技术原理的前提下,还可以做出若干改进和变形,如沉井可改为地下连续墙围护结构,沉井可以是圆形或矩形,也可以采取打设钢圆筒下沉作为通风井井筒,沉井底口与隧道顶部也可以不采用冷冻而采取降水或加固等其它措施,这些改进和变形也应视为本发明的保护范围。

Claims (7)

1.一种盾构隧道通风井施工方法,其特征在于,它包括以下步骤:
1)、盾构隧道掘进并穿过通风井预设位置;同步在地面预制并定位沉井结构(1);
2)、沉井结构(1)沿内壁开挖土方,使沉井结构(1)下沉至隧道顶部;
3)、将沉井结构(1)底口与隧道顶部之间的土体形成止水的密封结构;
4)、开挖沉井结构(1)底口与隧道顶部之间的土体,并切割隧道顶部,将沉井结构(1)底口与隧道连接成整体,形成通风井结构。
2.根据权利要求1所述的一种盾构隧道通风井施工方法,其特征在于:步骤2)中,沉井结构(1)内按设定高度多次开挖土方,其中一段土方与上段土方接高并养护至强度达到要求后再进行下一段土方的开挖。
3.根据权利要求1或2所述的一种盾构隧道通风井施工方法,其特征在于:所述沉井结构(1)内开挖土方下沉至离隧道顶部0.5至2米。
4.根据权利要求1所述的一种盾构隧道通风井施工方法,其特征在于:步骤3)中,先通过在沉井结构(1)井口外围设置锁口结构(5)以防止沉井结构1下沉,再沿锁口结构(5)竖向即沉井结构(1)外侧约0.5米位置及沉井结构(1)井壁内预留的孔洞(4)中打设冷冻管(2)至隧道顶部,采用冻结法将沉井结构(1)底口与隧道顶部之间的土体形成止水的密封结构。
5.根据权利要求1所述的一种盾构隧道通风井施工方法,其特征在于:步骤3)中,采用深井降水的方法,将地下水降至隧道顶部之下,沉井结构(1)底口与隧道顶部之间的土体形成止水的密封结构。
6.根据权利要求1所述的一种盾构隧道通风井施工方法,其特征在于:所述通风井位置对应的盾构隧道采用能切割形成与沉井结构(1)贯通开口的管片(3)进行衬砌。
7.根据权利要求1所述的一种盾构隧道通风井施工方法,其特征在于:所述沉井结构(1)底口与隧道通过现浇钢筋混凝土连成整体。
CN201310752435.7A 2013-12-31 2013-12-31 一种盾构隧道通风井施工方法 Active CN103742154B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310752435.7A CN103742154B (zh) 2013-12-31 2013-12-31 一种盾构隧道通风井施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310752435.7A CN103742154B (zh) 2013-12-31 2013-12-31 一种盾构隧道通风井施工方法

Publications (2)

Publication Number Publication Date
CN103742154A true CN103742154A (zh) 2014-04-23
CN103742154B CN103742154B (zh) 2015-08-12

Family

ID=50499208

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310752435.7A Active CN103742154B (zh) 2013-12-31 2013-12-31 一种盾构隧道通风井施工方法

Country Status (1)

Country Link
CN (1) CN103742154B (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104389608A (zh) * 2014-11-19 2015-03-04 中交隧道工程局有限公司 盾构穿越风井的施工方法
CN105240018A (zh) * 2015-10-30 2016-01-13 中铁上海工程局集团有限公司 竖井施工装置及方法
CN110541722A (zh) * 2019-09-30 2019-12-06 中铁第四勘察设计院集团有限公司 中间风井内盾构隧道管片局部拆除方法及止水结构
CN110566212A (zh) * 2019-09-19 2019-12-13 中铁六局集团石家庄铁路建设有限公司 一种先隧后井暗挖风道施工方法
CN112302700A (zh) * 2020-11-22 2021-02-02 青岛市市政工程设计研究院有限责任公司 用于地铁区间隧道的风井及其施工方法
CN112593948A (zh) * 2020-12-18 2021-04-02 中国能源建设集团浙江省电力设计院有限公司 一种盾构电力隧道区间内逃生通风井的施工方法
CN112727466A (zh) * 2021-01-29 2021-04-30 绍兴市柯桥区轨道交通集团有限公司 一种无支护预制拼装式盾构隧道风井结构施工方法
CN114352288A (zh) * 2021-12-30 2022-04-15 南京工大交通科学研究院(滁州)有限公司 一种盾构近距离上穿既有盾构隧道施工结构及施工方法
CN114382486A (zh) * 2021-12-10 2022-04-22 上海市基础工程集团有限公司 垂直顶升与套管法结合的骑马井施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3117147A1 (de) * 1981-04-30 1982-11-18 Daimler-Benz Ag, 7000 Stuttgart "strassentunnel mit zwangslueftung"
SU1260527A1 (ru) * 1982-04-28 1986-09-30 Свердловский Ордена Трудового Красного Знамени Горный Институт Им.В.В.Вахрушева Способ проходки вентил ционного ствола
JPH08246468A (ja) * 1995-03-09 1996-09-24 Kenji Kasuga 立坑の施工方法
CN102146679A (zh) * 2010-02-09 2011-08-10 中铁十一局集团有限公司 复杂地质地段土压平衡盾构通过中间风井施工方法
CN103161471A (zh) * 2011-12-19 2013-06-19 上海市基础工程有限公司 大直径盾构长距离穿越风井推进施工方法
CN103352704A (zh) * 2013-07-29 2013-10-16 北京住总集团有限责任公司 一种盾构通过竖井结构的施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3117147A1 (de) * 1981-04-30 1982-11-18 Daimler-Benz Ag, 7000 Stuttgart "strassentunnel mit zwangslueftung"
SU1260527A1 (ru) * 1982-04-28 1986-09-30 Свердловский Ордена Трудового Красного Знамени Горный Институт Им.В.В.Вахрушева Способ проходки вентил ционного ствола
JPH08246468A (ja) * 1995-03-09 1996-09-24 Kenji Kasuga 立坑の施工方法
CN102146679A (zh) * 2010-02-09 2011-08-10 中铁十一局集团有限公司 复杂地质地段土压平衡盾构通过中间风井施工方法
CN103161471A (zh) * 2011-12-19 2013-06-19 上海市基础工程有限公司 大直径盾构长距离穿越风井推进施工方法
CN103352704A (zh) * 2013-07-29 2013-10-16 北京住总集团有限责任公司 一种盾构通过竖井结构的施工方法

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张红伟等: "高深埋小曲线段盾构过中间风井施工技术", 《隧道建设》 *
张鹏等: "西安地铁二号线钟鼓楼站通风空调系统设计", 《隧道建设》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104389608A (zh) * 2014-11-19 2015-03-04 中交隧道工程局有限公司 盾构穿越风井的施工方法
CN105240018A (zh) * 2015-10-30 2016-01-13 中铁上海工程局集团有限公司 竖井施工装置及方法
CN105240018B (zh) * 2015-10-30 2018-09-18 中铁上海工程局集团有限公司 竖井施工装置及方法
CN110566212A (zh) * 2019-09-19 2019-12-13 中铁六局集团石家庄铁路建设有限公司 一种先隧后井暗挖风道施工方法
CN110566212B (zh) * 2019-09-19 2021-08-06 中铁六局集团石家庄铁路建设有限公司 一种先隧后井暗挖风道施工方法
CN110541722B (zh) * 2019-09-30 2024-07-23 中铁第四勘察设计院集团有限公司 中间风井内盾构隧道管片局部拆除方法及止水结构
CN110541722A (zh) * 2019-09-30 2019-12-06 中铁第四勘察设计院集团有限公司 中间风井内盾构隧道管片局部拆除方法及止水结构
CN112302700A (zh) * 2020-11-22 2021-02-02 青岛市市政工程设计研究院有限责任公司 用于地铁区间隧道的风井及其施工方法
CN112302700B (zh) * 2020-11-22 2025-04-04 青岛市市政工程设计研究院有限责任公司 用于地铁区间隧道的风井及其施工方法
CN112593948A (zh) * 2020-12-18 2021-04-02 中国能源建设集团浙江省电力设计院有限公司 一种盾构电力隧道区间内逃生通风井的施工方法
CN112727466A (zh) * 2021-01-29 2021-04-30 绍兴市柯桥区轨道交通集团有限公司 一种无支护预制拼装式盾构隧道风井结构施工方法
CN114382486A (zh) * 2021-12-10 2022-04-22 上海市基础工程集团有限公司 垂直顶升与套管法结合的骑马井施工方法
CN114352288B (zh) * 2021-12-30 2024-04-16 南京工大交通科学研究院(滁州)有限公司 一种盾构近距离上穿既有盾构隧道施工结构及施工方法
CN114352288A (zh) * 2021-12-30 2022-04-15 南京工大交通科学研究院(滁州)有限公司 一种盾构近距离上穿既有盾构隧道施工结构及施工方法

Also Published As

Publication number Publication date
CN103742154B (zh) 2015-08-12

Similar Documents

Publication Publication Date Title
CN103742154B (zh) 一种盾构隧道通风井施工方法
CN106567717B (zh) 一种利用地铁出入口兼作施工斜通道结构及施工方法
CN105257301B (zh) 一种浅埋暗挖隧道软弱围岩塌方加固处理方法
CN108194102B (zh) 隧道初期支护变形侵限段拆除及安全受力转换施工方法
CN101781889B (zh) 一种h型止水帷幕施工工艺
CN105003270B (zh) 适用于超浅覆土条件下的水下隧道施工方法
CN105863648B (zh) 一种暗挖浅覆大断面隧道施工方法
CN108442943A (zh) 一种渡线段隧道双侧壁导坑法施工方法
CN202117686U (zh) 铁路隧道深埋富水软弱带围岩超前支护构造
CN103628887A (zh) 大断面富水饱和粉细砂铁路隧道开挖方法
CN104675405B (zh) 一种矩形顶管机进洞的辅助结构及施工方法
CN103114857A (zh) 一种盾构隧道施工方法
CN107524459A (zh) 一种地铁暗挖车站竖井和横通道的冻结止水结构和方法
CN105041327B (zh) 暗挖隧道反挖盾构接收方法
CN103133007A (zh) 盾构地面开仓方法
CN103993885A (zh) 一种暗挖隧道侧向开洞支撑体系构建方法
CN102182464A (zh) 通道结构的施工结构及施工方法
CN110905536A (zh) 复杂地层土压盾构在暗挖隧道内接收的施工方法
CN110685709A (zh) 一种叠线隧道联络通道施工方法及其结构
CN105019913A (zh) 基岩隆起区盾构换刀原位加固方法
CN112963168A (zh) 扰动敏感地层超小净距大断面群洞隧道马头门施工方法
CN102913249B (zh) 斜井横向贯通正洞单喇叭挑高施工方法
CN214062960U (zh) 一种盾构穿越运营车站下方不规则障碍物的施工系统
CN204099720U (zh) 土石组合地质条件下人工顶管施工方法所用的防护罩
CN106437749B (zh) 一种隧道双支洞挑顶施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant