CN103693528B - Combined hanging equipment - Google Patents

Combined hanging equipment Download PDF

Info

Publication number
CN103693528B
CN103693528B CN201310723229.3A CN201310723229A CN103693528B CN 103693528 B CN103693528 B CN 103693528B CN 201310723229 A CN201310723229 A CN 201310723229A CN 103693528 B CN103693528 B CN 103693528B
Authority
CN
China
Prior art keywords
cage
scientific investigation
equipment
well lid
cable wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310723229.3A
Other languages
Chinese (zh)
Other versions
CN103693528A (en
Inventor
张国强
初向英
谢康
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGDAO SHIPYARD CO Ltd
Original Assignee
QINGDAO SHIPYARD CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO SHIPYARD CO Ltd filed Critical QINGDAO SHIPYARD CO Ltd
Priority to CN201310723229.3A priority Critical patent/CN103693528B/en
Publication of CN103693528A publication Critical patent/CN103693528A/en
Application granted granted Critical
Publication of CN103693528B publication Critical patent/CN103693528B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Artificial Fish Reefs (AREA)

Abstract

The invention provides a kind of combined hanging equipment, comprise guide rail, electric bicycle installed by described guide rail, described electric bicycle connects cable wire, described cable wire connects cage, scientific investigation equipment is placed in cage, utilizes guide rail and electric bicycle to carry out moving and promoting cable wire, thus control hoisting of cage.The present invention proposes a whole set of handling for the scientific investigation equipment of marine survey, the combined hanging equipment with protection be installed, have make simply, cost is low, installation difficulty is little, easy to use, can effectively protect scientific investigation equipment.

Description

Combined hanging equipment
Technical field
The invention belongs to rig a ship equipment technical field, specifically, relate to a kind of be suitable for scientific investigation equipment installation, protection and handling combined hanging equipment.
Background technology
A lot of for the kind of the scientific investigation equipment of marine survey at present; install and occupation mode varied; the scientific investigation equipment of use is fixed for the need be installed at present in hull interior vertical shaft; as: multi-beam, ADCP, Sub-bottom profiler etc.; this kind equipment had both needed to stretch out hull; need again to maintain static; boats and ships are when navigating by water; the obstacles such as fishing net can be run into; easily cause the damage of equipment; cause huge economic loss, therefore how to install and protect this type of scientific investigation equipment to be then problem to be solved by this invention.
Summary of the invention
The object of the invention is to solve the easy impaired problem of the above-mentioned scientific investigation equipment be installed in vertical shaft and a kind of combined hanging equipment is provided; have make structure simple, cost is low, easy to use; energy available protecting scientific investigation equipment, is applicable to the handling of scientific investigation equipment, installation and protection.
For solving the problems of the technologies described above, the present invention is achieved by the following technical solutions:
A kind of combined hanging equipment, comprises guide rail, electric bicycle is installed by described guide rail, and described electric bicycle connects cable wire, and described cable wire connects cage.Be placed in cage by scientific investigation equipment, electric bicycle is arranged on guide rail, utilizes guide rail and electric bicycle to carry out moving and promoting cable wire, thus controls hoisting of cage.
Combined hanging equipment described above, described cage is positioned at hull vertical shaft inner bottom part, adopts angle steel to be made into tower structure, and cage inside is provided with the supporting seat installing scientific investigation equipment, to be convenient for changing different scientific investigation equipment.
Combined hanging equipment described above, described vertical shaft inner bottom part is welded with rectangular frame-cage supporting seat, and described cage top peripheral is provided with the support panel be connected with cage supporting seat, and described cage is supported on cage supporting seat.Cage adopts angle steel to be made into tower structure, and effectively reduce the buoyancy that the weight of cage and seawater produce it, inside is provided with installation and the replacing that supporting seat is convenient to scientific investigation equipment.
Combined hanging equipment described above, the top seal of described cage, end face is provided with the eye thimble be connected with cable wire.
Combined hanging equipment described above, the upper opening place of described vertical shaft is provided with well lid, and well lid is secured by bolts in deck plane top, is provided with strut bar between described well lid and cage.
Combined hanging equipment described above, described strut bar is threaded connection by some sections of connecting rods to form, and described connecting rod one end has bolt shank, and the other end has tapped bore, be convenient to the strut bar be connected to each other as a whole, between two often adjacent connecting rods, be provided with locating plate.
Combined hanging equipment described above, the central authorities of described locating plate have adjustable knock hole, namely can pass through bolt adjusting size and degree of tightness, and locating plate four limit is symmetrically arranged four supports.
Combined hanging equipment described above,
When needs use scientific investigation equipment, scientific investigation equipment is arranged on described cage inner, the bottom of described cage arranges streamlined reefer housing, and described strut bar is installed between cage and well lid, is connected between electric bicycle with cage with cable wire; Streamlined reefer housing is installed on bottom cage, by streamlined reefer housing, scientific investigation equipment is protected, to prevent the object in water such as fishing net, damage is caused to scientific investigation equipment;
When not using scientific investigation equipment, for reducing vertical shaft to the impact of the speed of a ship or plane, described streamlined reefer housing being pulled down, cage bottom panel is installed bottom described cage.Cage bottom panel is installed on bottom cage, is reduced the opening of vertical shaft by cage bottom panel, to reduce the impact of big uncork on ship speed of vertical shaft.
Combined hanging equipment described above, described streamlined reefer housing comprises two schistose textures, is symmetricly set on the two bottom sides of cage, along the navigation direction of boats and ships, the front bottom end of every a slice streamlined reefer housing is circular arc, and the design energy actv. of circular arc plays directional tagging to the such as obstacle such as fishing net.
Combined hanging equipment described above, described well lid central authorities are provided with the first through hole passed for cable wire, and the first bore periphery is provided with to be convenient to connecting rod and to pass the second fixing through hole, and well lid periphery is provided with some fixed orifices.
Because cage can be subject to the impact of seawater under sail, thus output movement upwards, this moves the test results that can affect scientific investigation equipment, so adopt strut bar to be connected between cage and well lid, play the effect of fixing cage, cage utilizes locating plate position cage and lead in decentralization process.
Compared with prior art, advantage of the present invention and good effect are:
The present invention proposes a whole set of handling for the scientific investigation equipment of marine survey, the combined hanging equipment with protection be installed, have make simply, cost is low, installation difficulty is little, easy to use, can effectively protect scientific investigation equipment.
Accompanying drawing explanation
Fig. 1 is the combination schematic diagram one (when installing scientific investigation equipment) of combined hanging equipment specific embodiment of the present invention;
Fig. 2 is the combination schematic diagram two (when not installing scientific investigation equipment) of combined hanging equipment specific embodiment of the present invention;
Fig. 3 is manhole cover structure figure of the present invention;
Fig. 4 is supporting bar structure figure of the present invention;
Fig. 5 is positioning plate structure figure of the present invention;
Fig. 6-1 is cage birds-eye view of the present invention;
Fig. 6-2 is cage lateral plans of the present invention;
Fig. 7-1 is cage supporting seat birds-eye view of the present invention;
Fig. 7-2 is cage supporting seat lateral plans of the present invention;
Fig. 8-1 is streamlined reefer housing birds-eye view of the present invention;
Fig. 8-2 is streamlined reefer housing lateral plans of the present invention;
Fig. 9 is cage bottom panel constructional drawing of the present invention.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the present invention is further detailed explanation.
Shown in figure 1, combined hanging equipment is made up of electric bicycle 1, guide rail 2, well lid 3, cable wire 4, strut bar 5, locating plate 6, cage 7, cage supporting seat 71, streamlined reefer housing 8.
Electric bicycle 1 is arranged on guide rail 2, electric bicycle 1 has eye thimble, and cable wire 4 upper end is connected on the eye thimble of electric bicycle 1, and cable wire 4 lower end connects cage 7, cage 7 is positioned at hull vertical shaft inner bottom part, and vertical shaft inner bottom part is welded with cage supporting seat 71 to support cage 7.
The upper opening place of vertical shaft is provided with well lid 3, and well lid 3 bolt is installed on deck plane top, and connected by strut bar 5 between cage 7 and well lid 3 and support, strut bar 5 is threaded connection by some sections of connecting rods 51 to form.
Because cage 7 can be subject to the impact of seawater under sail, thus output movement upwards, this moves the test results that can affect scientific investigation equipment, so adopt strut bar 5 to be connected between cage 7 and well lid 3, play the effect of fixing cage 7, cage 7 utilizes locating plate 6 pairs of cages 7 position and lead in decentralization process.
When needs use scientific investigation equipment, scientific investigation equipment is arranged on cage 7 inner, the bottom of cage 7 connects two panels streamlined reefer housing 8, and strut bar 5 is installed between cage 7 and well lid 3, is connected between electric bicycle 1 with cage 7 with cable wire 4; Utilize guide rail 2 and electric bicycle 1 to carry out moving and promote cable wire 4, thus control hoisting of cage 7.Electric bicycle 1 is adopted to control the handling of scientific investigation equipment, installation and protection, more convenient than manpower.Streamlined reefer housing 8 is installed on bottom cage 7, protects scientific investigation equipment, causes damage to prevent the object in water such as fishing net to scientific investigation equipment.
As shown in Fig. 6-1 and 6-2, cage 7 adopts angle steel to be made into tower structure, cage 7 top peripheral is provided with the support panel 72 be connected with cage supporting seat 71, the top seal of cage 7, end face is provided with the eye thimble 73 be connected with cable wire 4, the hanging basket of a similar top seal, and cage 7 adopts angle steel to be made into tower structure, effectively reduce the buoyancy that the weight of cage and seawater produce it, cage 7 inside is provided with installation and the replacing that supporting seat is convenient to scientific investigation equipment.
As shown in Fig. 7-1,7-2, cage supporting seat 71 is rectangular frame-structure, and for coordinating to support cage 7 with the support panel 72 of cage 7 top peripheral, the bottom of cage supporting seat 71 arranges some brace rods 711.
As shown in Figure 4, strut bar 5 comprises some sections of connecting rods 51, is threaded connection and forms between adjacent links 51, connecting rod 51 one end has bolt shank 511, the other end has tapped bore 512, is convenient to the strut bar 5 be connected to each other as a whole, between two often adjacent connecting rods 51, be provided with locating plate 6.
As shown in Figure 5, the central authorities of locating plate 6 have adjustable knock hole 61, namely can pass through bolt adjusting size and degree of tightness, and locating plate 6 four limit is symmetrically arranged four supports 62.
As shown in Figure 3, the well lid 3 at vertical shaft upper opening place, well lid 3 central authorities are provided with the first through hole 31, first through hole 31 periphery passed for cable wire 4 and are provided with and are convenient to connecting rod 51 and pass the second fixing through hole 32, and well lid 3 periphery is provided with some fixed orifices 33.
As shown in Fig. 8-1,8-2, streamlined reefer housing 8 comprises two schistose textures, be symmetricly set on the two bottom sides of cage 7, the top of each schistose texture is provided with some fixed orifices, streamlined reefer housing 8 installs the navigation direction along boats and ships, the front bottom end of every a slice streamlined reefer housing is circular arc, and the design energy actv. of circular arc plays directional tagging to the such as obstacle such as fishing net.
The hull vertical shaft clinical practice that combined hanging equipment of the present invention is mainly used in marine research ship is investigated handling, the installation of equipment and protects.This combined hanging equipment is for scientific investigation exploration ship, when needs do scientific investigation test, scientific investigation equipment is installed on cage 7 inner, streamlined reefer housing 8 is installed on bottom cage 7, strut bar 5 is installed between cage 7 and well lid 3, is connected between electric bicycle 1 with cage 7 with cable wire 4; When not doing scientific investigation test, scientific investigation equipment and streamlined reefer housing 8 are unloaded, install cage bottom panel 9 bottom cage 7, have structure simple, handling and replacing scientific investigation equipment convenience, to features such as scientific investigation equipment play a protective role.
Setting-up procedure (when installing scientific investigation equipment):
A cage supporting seat 71 is first welded in vertical shaft inner bottom part by ();
When () installs scientific investigation equipment b, two panels streamlined reefer housing 8 is installed on bottom cage 7;
C cable wire 4 one end is connected on the eye thimble at cage 7 top by (), the other end is connected on the eye thimble of electric bicycle 1;
What d cage 7 was moved to vertical shaft by () transfers mouth place, wherein one section of connecting rod 51 of strut bar 5 is installed, then electric bicycle 1 is used to be transferred by cage 7, when connecting rod 51 top is transferred to soon parallel with vertical shaft upper opening, locating plate 6 and next section of connecting rod 51 are installed, continue to transfer cage 7, until locating plate 6 and strut bar 5 install, then transfer cage 7 to silo bottom, finally strut bar 5 upper end is fixedly connected with well lid 3.
The using method of combinations thereof hanging device:
First scientific investigation equipment is installed on the device support seat of cage 7 inside, then according to above-mentioned setting-up procedure assembly hanging device, utilizes electric bicycle 1 to control the lifting of cage 7 and to change scientific investigation equipment.
As shown in Figure 2, when not using scientific investigation equipment, for reducing vertical shaft to the impact of the speed of a ship or plane, streamlined reefer housing 8 being pulled down, cage bottom panel 9 is installed bottom cage 7.Cage bottom panel 9 is installed on bottom cage 7, is reduced the opening of vertical shaft by cage bottom panel 9, to reduce the impact of big uncork on ship speed of vertical shaft.
As shown in Figure 9, cage bottom panel 9 is the rectangular panel closed, and periphery is provided with some fixed orifices.
The above is only preferred embodiment of the present invention, and be not restriction the present invention being made to other form, any those skilled in the art may utilize the technology contents of above-mentioned announcement to be changed or be modified as the Equivalent embodiments of equivalent variations.But everyly do not depart from technical solution of the present invention content, any simple modification, equivalent variations and the remodeling done above embodiment according to technical spirit of the present invention, still belong to the protection domain of technical solution of the present invention.

Claims (1)

1. a combined hanging equipment, is characterized in that: comprise guide rail, and electric bicycle installed by described guide rail, and described electric bicycle connects cable wire, and described cable wire connects cage;
Described cage is positioned at hull vertical shaft inner bottom part, adopts angle steel to be made into tower structure, and cage inside is provided with the supporting seat installing scientific investigation equipment;
The upper opening place of described vertical shaft is provided with well lid, and well lid is secured by bolts in deck plane top, is provided with strut bar between described well lid and cage;
Described strut bar is threaded connection by some sections of connecting rods to form, and described connecting rod one end has bolt shank, and the other end has tapped bore, between two often adjacent connecting rods, be provided with locating plate;
The central authorities of described locating plate have adjustable knock hole, and four limits have symmetrically arranged four supports;
When needs use scientific investigation equipment, scientific investigation equipment is arranged on described cage inner, the bottom of described cage arranges streamlined reefer housing, and described strut bar is installed between cage and well lid, is connected between electric bicycle with cage with cable wire;
When not using scientific investigation equipment, scientific investigation equipment and streamlined reefer housing are unloaded, cage bottom panel is installed bottom described cage;
Described streamlined reefer housing comprises two schistose textures, is symmetricly set on the two bottom sides of cage, and the front bottom end of every a slice streamlined reefer housing is circular arc;
Described well lid central authorities are provided with the first through hole passed for cable wire, and the first bore periphery is provided with to be convenient to connecting rod and to pass the second fixing through hole, and well lid periphery is provided with some fixed orifices.
CN201310723229.3A 2013-12-25 2013-12-25 Combined hanging equipment Expired - Fee Related CN103693528B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310723229.3A CN103693528B (en) 2013-12-25 2013-12-25 Combined hanging equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310723229.3A CN103693528B (en) 2013-12-25 2013-12-25 Combined hanging equipment

Publications (2)

Publication Number Publication Date
CN103693528A CN103693528A (en) 2014-04-02
CN103693528B true CN103693528B (en) 2016-01-13

Family

ID=50355231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310723229.3A Expired - Fee Related CN103693528B (en) 2013-12-25 2013-12-25 Combined hanging equipment

Country Status (1)

Country Link
CN (1) CN103693528B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105735624A (en) * 2016-02-17 2016-07-06 浙江远大钢构实业有限公司 Cage for installing roof ceiling sheet
CN111824362A (en) * 2020-07-09 2020-10-27 交通运输部北海航海保障中心天津海事测绘中心 A hull-based work equipment mounting system and a vessel with the mounting system
CN113213315B (en) * 2021-06-17 2024-04-26 江苏阿尔法电梯制造有限公司 Transfer method for building partition plate

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB312393A (en) * 1928-02-25 1929-05-27 Marryat & Scott Ltd Improvements in lifts, hoists and the like
UA15799U (en) * 2006-01-24 2006-07-17 Yurii Viktorovych Berezovskyi Pneumatic elevator
CN201433031Y (en) * 2009-07-13 2010-03-31 李贤明 Shaft overhead operation lifting basket
CN101734552A (en) * 2010-01-01 2010-06-16 江苏能建机电实业集团有限公司 Maintenance trolley for vacuum chamber
CN101891010A (en) * 2009-05-18 2010-11-24 张楚 Mobile operation platform device for ship
CN102001428A (en) * 2010-11-12 2011-04-06 武汉理工大学 Fin lifting system of comprehensive marine science research ship
CN201980831U (en) * 2011-04-11 2011-09-21 博宇(无锡)科技有限公司 Lifting maintenance platform of wind generating set
CN202164003U (en) * 2011-05-25 2012-03-14 浙江工业职业技术学院 Construction freight elevator
CN203740809U (en) * 2013-12-25 2014-07-30 青岛造船厂有限公司 Combined hoisting device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB312393A (en) * 1928-02-25 1929-05-27 Marryat & Scott Ltd Improvements in lifts, hoists and the like
UA15799U (en) * 2006-01-24 2006-07-17 Yurii Viktorovych Berezovskyi Pneumatic elevator
CN101891010A (en) * 2009-05-18 2010-11-24 张楚 Mobile operation platform device for ship
CN201433031Y (en) * 2009-07-13 2010-03-31 李贤明 Shaft overhead operation lifting basket
CN101734552A (en) * 2010-01-01 2010-06-16 江苏能建机电实业集团有限公司 Maintenance trolley for vacuum chamber
CN102001428A (en) * 2010-11-12 2011-04-06 武汉理工大学 Fin lifting system of comprehensive marine science research ship
CN201980831U (en) * 2011-04-11 2011-09-21 博宇(无锡)科技有限公司 Lifting maintenance platform of wind generating set
CN202164003U (en) * 2011-05-25 2012-03-14 浙江工业职业技术学院 Construction freight elevator
CN203740809U (en) * 2013-12-25 2014-07-30 青岛造船厂有限公司 Combined hoisting device

Also Published As

Publication number Publication date
CN103693528A (en) 2014-04-02

Similar Documents

Publication Publication Date Title
JP5860976B2 (en) Floating wind power generator and method of conveying parts of the device
CN103693528B (en) Combined hanging equipment
CN102616340B (en) A kind of a kind of method of transport installation ship, by sea defeated installation Wind turbines
CN103407552A (en) Counterweight anchor chain of single point mooring system
JP2013519568A (en) Device for reducing flow resistance in moon pools
CN104908910A (en) Automatic underwater detection equipment extending-retracting device
CN103168755B (en) Electricity-net composite fish blocking system and method
CN206141776U (en) Large -scale component transportation of self -navigation formula installs integrative ship
CN106394837A (en) Submarine pipeline transporting and loading boat
CN204737648U (en) Marine supplementary loop wheel machine
KR20130047241A (en) Lift-type launching device for ship
CN203740809U (en) Combined hoisting device
CN202686698U (en) Large-scale marine meteorological monitoring buoy
RU2549250C1 (en) Measurement system for research of small-scale turbulence in near-surface layer of sea
CN215669289U (en) Ecological bank protection electricity-proof fish device
CN1924614B (en) Ocean towing linear array two wings self-balance unfolded device
CN202272163U (en) Auxiliary lifting mechanism for launching of deep-water submersible
CN202686681U (en) Watertight penetrating device of exposed deck
CN209290614U (en) A kind of hull based on sea typhoon protection
CN203544339U (en) Assisting float for improving wave resistance of exploring ship
CN203242966U (en) Guide device for fan base submarine cable protection and laying
CN203545555U (en) Hand winch for survey vessels
CN203032885U (en) Rail water working table for land-based barricading test
CN203684191U (en) Fan construction system of offshore intertidal zone
CN207553036U (en) A kind of net formula water surface safety barrage system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160113