CN103669902B - 现浇梁支撑桁架整体降落拆除工装及其施工方法 - Google Patents

现浇梁支撑桁架整体降落拆除工装及其施工方法 Download PDF

Info

Publication number
CN103669902B
CN103669902B CN201310749204.0A CN201310749204A CN103669902B CN 103669902 B CN103669902 B CN 103669902B CN 201310749204 A CN201310749204 A CN 201310749204A CN 103669902 B CN103669902 B CN 103669902B
Authority
CN
China
Prior art keywords
set bolt
dismounting
truss
bolster
jack
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310749204.0A
Other languages
English (en)
Other versions
CN103669902A (zh
Inventor
张书国
李拴虎
刘歆泽
袁伟
曾建国
高涛
歧志强
宋志国
张鹏
朱建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China State Railway Investment Construction Group Co Ltd
Original Assignee
China Construction Railway Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Railway Construction Co Ltd filed Critical China Construction Railway Construction Co Ltd
Priority to CN201310749204.0A priority Critical patent/CN103669902B/zh
Publication of CN103669902A publication Critical patent/CN103669902A/zh
Application granted granted Critical
Publication of CN103669902B publication Critical patent/CN103669902B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

一种现浇梁支撑桁架整体降落拆除工装及其施工方法,梁体支撑桁架整体由四套拆除工装吊于箱梁下方;拆除工装包括吊杆、上垫枕、下垫枕、扁担梁、上固定螺栓I、上固定螺栓II、下固定螺栓和两个千斤顶。本发明能够在施工场地狭窄、征地拆迁困难、地形复杂、工期紧、作业高度受限、吊车不能就位的情况下,将整个支撑底桁架同步降落,达到适合吊机作业的高度或直接下落至地面进行拆除,避免了高空吊装带来的安全风险,同时提高了支撑桁架拆除效率。本发明拆除一孔梁支撑桁架仅需3小时,大大缩短了拆模速度,而且节约吊车及人工费用,减少了施工用地,达到节能减排、绿色环保的效果。

Description

现浇梁支撑桁架整体降落拆除工装及其施工方法
技术领域
本发明涉及一种客运专线支架现浇箱梁支撑桁架整体降落拆除工装及其施工方法。
背景技术
在客运专线现浇梁的施工中,现浇梁支架拆除是关键工序,也是影响梁体施工时间的主要因素。传统的拆除方式是采用手动葫芦将梁底桁架拖拉至梁体两侧(满足吊车吊装高度),然后用吊车吊装拆除,但在施工场地狭窄、地形复杂、工期紧、作业高度受限、吊车不能就位的情况下,采用传统拆除设备不能满足工期和安全的要求。
发明内容
本发明提供一种现浇梁支撑桁架整体降落拆除工装及其施工方法,要解决传统拆除设备拆除效率低,存在较大安全隐患的技术问题。
本发明解决其技术问题所采用的技术方案是:
这种现浇梁支撑桁架整体降落拆除工装,包括四套安装于箱梁上部两侧的拆除工装,梁体支撑桁架整体由四套拆除工装吊于箱梁下方;
所述拆除工装包括吊杆、上垫枕、下垫枕、扁担梁、上固定螺栓I、上固定螺栓II、下固定螺栓和两个千斤顶;所述上垫枕坐落于箱梁上,两个千斤顶置于上垫枕上,千斤顶的油缸上顶扁担梁,下垫枕置于梁体支撑桁架底面;所述吊杆上端依次穿过箱梁上的预留孔、上垫枕和扁担梁,上固定螺栓I在扁担梁顶面与吊杆锁紧,上固定螺栓II在上垫枕顶面与吊杆锁紧,吊杆下端穿过梁体支撑桁架和下垫枕,下固定螺栓在下垫枕底面与吊杆锁紧。
所述吊杆为精轧螺纹钢。
所述上固定螺栓I与上固定螺栓II的底面均设有垫板,下固定螺栓的顶面设有垫板。
这种现浇梁支撑桁架整体降落拆除工装的施工方法,施工步骤如下:
步骤一,箱梁张拉压浆完成后,在箱梁上部两侧安装拆除工装;
步骤二,调紧所有拆除工装的上固定螺栓II和下固定螺栓,将上固定螺栓I向上旋转至距扁担梁的距离大于千斤顶油缸行程;
步骤三,同步空顶所有拆除工装的千斤顶;
步骤四,千斤顶油缸向上伸出一个行程后,锁紧上固定螺栓I,同时将上固定螺栓II向上旋转至距上垫枕的距离大于千斤顶油缸行程;
步骤五,所有千斤顶同时同步回油,使整个梁体支撑桁架同步下降,当千斤顶回油至最底位置后锁紧上固定螺栓II;
步骤六,重复上述步骤二到步骤五,直至梁体支撑桁架整体降落至地面。
本发明的有益效果如下:
本发明将支撑底桁架用四根精轧螺纹钢穿过梁体预留孔固定在千斤顶的扁担梁上,先拆除支撑桁架以下的钢管立柱,然后将支撑桁架采用千斤顶整体同步降落,直到降落到地面即可拆除。
本发明能够在施工场地狭窄、征地拆迁困难、地形复杂、工期紧、作业高度受限、吊车不能就位的情况下,将整个支撑桁架同步降落,达到适合吊机作业的高度或直接下落至地面进行拆除,避免了高空吊装带来的安全风险,同时提高了支撑桁架拆除效率。本发明拆除一孔梁支撑桁架仅需3小时,大大缩短了拆模速度,而且节约吊车及人工费用,减少了施工用地,达到节能减排、绿色环保的效果。
附图说明
下面结合附图和实施例对本发明进一步说明。
图1是本发明的结构示意图。
图2是本发明施工方法步骤二的示意图。
图3是本发明施工方法步骤三的示意图。
图4是本发明施工方法步骤四的示意图。
图5是本发明施工方法步骤五的示意图。
附图标记:1-吊杆、2-上垫枕、3-下垫枕、4-扁担梁、5-上固定螺栓I、6-上固定螺栓II、7-下固定螺栓、8-千斤顶、9-箱梁、10-梁体支撑桁架。
具体实施方式
实施例参见图1所示,这种现浇梁支撑桁架整体降落拆除工装,包括四套安装于箱梁9上部两侧的拆除工装,梁体支撑桁架10整体由四套拆除工装吊于箱梁9下方。
所述拆除工装包括吊杆1、上垫枕2、下垫枕3、扁担梁4、上固定螺栓I5、上固定螺栓II6、下固定螺栓7和两个千斤顶8。上垫枕2坐落于箱梁9上,两个千斤顶8置于上垫枕2上,千斤顶8的油缸上顶扁担梁4,下垫枕3置于梁体支撑桁架10底面。所述吊杆1采用精轧螺纹钢。吊杆1上端依次穿过箱梁9上的预留孔、上垫枕2和扁担梁4。上固定螺栓I5在扁担梁4顶面与吊杆1锁紧,上固定螺栓II6在上垫枕2顶面与吊杆1锁紧。所述上固定螺栓I5与上固定螺栓II6的底面均设有垫板。吊杆1下端穿过梁体支撑桁架10和下垫枕3。下固定螺栓7在下垫枕3底面与吊杆1锁紧。下固定螺栓7的顶面设有垫板。
参见图1~5所示,这种现浇梁支撑桁架整体降落拆除工装的施工方法,施工步骤如下:
步骤一,箱梁9张拉压浆完成后,在箱梁上部两侧安装拆除工装;
步骤二,调紧所有拆除工装的上固定螺栓II6和下固定螺栓7,将上固定螺栓I5向上旋转至距扁担梁4的距离大于千斤顶油缸行程;
步骤三,同步空顶所有拆除工装的千斤顶8;
步骤四,千斤顶油缸向上伸出一个行程后,锁紧上固定螺栓I5,同时将上固定螺栓II6向上旋转至距上垫枕2的距离大于千斤顶油缸行程;
步骤五,所有千斤顶8同时同步回油,使整个梁体支撑桁架10同步下降,当千斤顶回油至最底位置后锁紧上固定螺栓II6;
步骤六,重复上述步骤二到步骤五,直至梁体支撑桁架10整体降落至地面。

Claims (2)

1.一种现浇梁支撑桁架整体降落拆除工装,其特征在于:包括四套安装于箱梁(9)上部两侧的拆除工装,梁体支撑桁架(10)整体由四套拆除工装吊于箱梁(9)下方;
所述拆除工装包括吊杆(1)、上垫枕(2)、下垫枕(3)、扁担梁(4)、上固定螺栓I(5)、上固定螺栓II(6)、下固定螺栓(7)和两个千斤顶(8);所述上垫枕(2)坐落于箱梁(9)上,两个千斤顶(8)置于上垫枕(2)上,千斤顶(8)的油缸上顶扁担梁(4),下垫枕(3)置于梁体支撑桁架(10)底面;所述吊杆(1)上端依次穿过箱梁(9)上的预留孔、上垫枕(2)和扁担梁(4),上固定螺栓I(5)在扁担梁(4)顶面与吊杆(1)锁紧,上固定螺栓II(6)在上垫枕(2)顶面与吊杆(1)锁紧,吊杆(1)下端穿过梁体支撑桁架(10)和下垫枕(3),下固定螺栓(7)在下垫枕(3)底面与吊杆(1)锁紧;所述吊杆(1)为精轧螺纹钢;所述上固定螺栓I(5)与上固定螺栓II(6)的底面均设有垫板,下固定螺栓(7)的顶面设有垫板。
2.一种如权利要求1所述现浇梁支撑桁架整体降落拆除工装的施工方法,其特征在于施工步骤如下:
步骤一,箱梁(9)张拉压浆完成后,在箱梁上部两侧安装拆除工装;
步骤二,调紧所有拆除工装的上固定螺栓II(6)和下固定螺栓(7),将上固定螺栓I(5)向上旋转至距扁担梁(4)的距离大于千斤顶油缸行程;
步骤三,同步空顶所有拆除工装的千斤顶(8);
步骤四,千斤顶油缸向上伸出一个行程后,锁紧上固定螺栓I(5),同时将上固定螺栓II(6)向上旋转至距上垫枕(2)的距离大于千斤顶油缸行程;
步骤五,所有千斤顶(8)同时同步回油,使整个梁体支撑桁架(10)同步下降,当千斤顶回油至最底位置后锁紧上固定螺栓II(6);
步骤六,重复上述步骤二到步骤五,直至梁体支撑桁架(10)整体降落至地面。
CN201310749204.0A 2013-12-31 2013-12-31 现浇梁支撑桁架整体降落拆除工装及其施工方法 Expired - Fee Related CN103669902B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310749204.0A CN103669902B (zh) 2013-12-31 2013-12-31 现浇梁支撑桁架整体降落拆除工装及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310749204.0A CN103669902B (zh) 2013-12-31 2013-12-31 现浇梁支撑桁架整体降落拆除工装及其施工方法

Publications (2)

Publication Number Publication Date
CN103669902A CN103669902A (zh) 2014-03-26
CN103669902B true CN103669902B (zh) 2015-07-15

Family

ID=50308611

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310749204.0A Expired - Fee Related CN103669902B (zh) 2013-12-31 2013-12-31 现浇梁支撑桁架整体降落拆除工装及其施工方法

Country Status (1)

Country Link
CN (1) CN103669902B (zh)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104404968B (zh) * 2014-12-10 2016-05-25 中建三局第一建设工程有限责任公司 基坑内支撑梁拆除装置及基坑内支撑梁拆除方法
CN107116674A (zh) * 2017-06-30 2017-09-01 中交第航务工程局有限公司 一种t型梁整体式模板的千斤顶拆模法
CN110747761B (zh) * 2019-10-21 2021-03-23 宁波市政工程建设集团股份有限公司 路桥预制小箱梁式隐盖梁临时支承体系的拆除施工方法
CN111042576A (zh) * 2019-12-18 2020-04-21 中建科工集团有限公司 一种倒三角桁架的拆除方法
CN111535448A (zh) * 2020-05-13 2020-08-14 中国二十二冶集团有限公司 屋架吊装方法
CN112502476B (zh) * 2020-11-27 2022-07-19 上海建工五建集团有限公司 一种钢绞绳承载力转换装置及其使用方法
CN113202027A (zh) * 2021-04-07 2021-08-03 中交路桥建设有限公司 一种现浇梁钢管桩支架快速拆除方法
CN113184744B (zh) * 2021-04-16 2024-05-14 中铁大桥局集团第六工程有限公司 一种适用于穿心千斤顶的辅助装置及其使用方法

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0649810A (ja) * 1992-07-27 1994-02-22 Teruo Takatsu 橋梁の撤去方法
JP5038964B2 (ja) * 2008-04-11 2012-10-03 大成建設株式会社 箱桁の構築方法、コンクリート構造物の構築方法および足場構造
CN101929130B (zh) * 2010-09-19 2012-01-04 中铁十二局集团有限公司 连续箱梁合拢段施工的挂篮装置
CN203669407U (zh) * 2013-12-31 2014-06-25 中建铁路建设有限公司 现浇梁支撑桁架整体降落拆除工装

Also Published As

Publication number Publication date
CN103669902A (zh) 2014-03-26

Similar Documents

Publication Publication Date Title
CN103669902B (zh) 现浇梁支撑桁架整体降落拆除工装及其施工方法
CN104963301B (zh) 用于墩顶梁段与桥墩拆除的拖拉平移下放装置及方法
CN103669885B (zh) 超大跨度钢桁架分段吊装工艺
CN101922243B (zh) 建筑物拆除内顶升方法及其设备
CN102251483B (zh) 自提升附着式吊机吊装钢管混凝土格构桥墩的施工方法
CN201907630U (zh) 一种用于船舶分段支撑的自升式支撑装置
CN106759845A (zh) 一种钢结构连廊的施工方法
CN203669407U (zh) 现浇梁支撑桁架整体降落拆除工装
CN102049335B (zh) 大型球磨机安装施工方法
CN104179121B (zh) 一种移动模架托架四提升自拼装方法
CN104989111A (zh) 钢结构高层吊装施工方法
CN111350523B (zh) 用于有限空间内负环拆除的施工方法及装置
CN206308702U (zh) 一种塔式起重机移动式基础
CN104404888A (zh) 一种大型空中坡度调整吊装系统及应用
CN109531802B (zh) 一种t梁组合钢模板安拆结构及方法
CN202482772U (zh) 铁路桥梁防落梁挡块安装系统
CN204173887U (zh) 液压型检查井盖的开启装置
CN215164726U (zh) 一种用于现浇梁钢管桩支架快速拆除的整体卸落结构
CN204125840U (zh) 模架横梁系统置于主箱梁顶面的双导梁移动模架造桥机
CN101768925A (zh) 防落梁挡块的安装设备及其施工方法
CN201325363Y (zh) 用于整体搬迁石油钻机底座的垂直升降平板拖车
CN101774516B (zh) 更换耙式吊车桥架的顶升装置及施工方法
CN113735015A (zh) 一种单轨道拆装辅助设备及其工作方法
CN203452362U (zh) 一种升降料台
CN113202027A (zh) 一种现浇梁钢管桩支架快速拆除方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20181207

Address after: 100000 room 905, 3 building, 10 Gua Xiang Road, Pang Zhuang Town, Daxing District, Beijing.

Patentee after: China Construction Railway Investment and Construction Group Co., Ltd.

Address before: 100053 Guanganmen South Street, Xicheng District, Beijing 4

Patentee before: China Construction Railway Building Co., Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150715

Termination date: 20181231

CF01 Termination of patent right due to non-payment of annual fee