CN103669901A - Method used for reforming pile in underground space into pillar - Google Patents
Method used for reforming pile in underground space into pillar Download PDFInfo
- Publication number
- CN103669901A CN103669901A CN201310646576.0A CN201310646576A CN103669901A CN 103669901 A CN103669901 A CN 103669901A CN 201310646576 A CN201310646576 A CN 201310646576A CN 103669901 A CN103669901 A CN 103669901A
- Authority
- CN
- China
- Prior art keywords
- stake
- shaped steel
- post
- underground space
- ring shaped
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Abstract
The invention relates to a method used for reforming a pile in an underground space into a pillar and aims to provide the method which enables the purposes of being high in reforming speed, easy to construct, fast in forming and good in effect to be achieved. According to the technical scheme, the method includes the following steps that firstly, the upper surface of the pile is cleaned up; secondly, two semicircular-ring-shaped steel cylinders matched with the diameter of the pile are selected, and the steel cylinders are wrapped on the upper surface of the pile so that the pile can be located in the center of the two semicircular-ring-shaped steel cylinders; thirdly, electric welding is carried out on the combined portions between the two semicircular-ring-shaped steel cylinders so that the two semicircular-ring-shaped steel cylinders are mutually welded into a whole and firmly wrap the pile; fourthly, after the welded portions are cooled, the gaps between the pile and the two semicircular-ring-shaped steel cylinders are filled with concrete or grouting materials, and then the pillar is formed.
Description
Technical field
The present invention relates to building field, specifically a kind of method that stake in the underground space is transform as to post.
Background technology
In conventional building field, the definition of post is mainly to bear axial compression, is used for supporting superstructure and load is reached to basic vertical straight-bar; The definition of stake is to bear pile top load by frictional resistance and end resistance, and the load bearing is delivered to the vertical straight-bar in foundation soil (or basement rock).Because stake and post have two diverse function settings, be difficult to change and transformation always.
Yet in the process of the following newly-built underground space of existed building, the needs due to design and bearing capacity, be transformed into post by stake, to reach the design standard of the underground space.
Summary of the invention
The object of the invention is to overcome the deficiency in above-mentioned background technology, a kind of method that stake is transform as to the post in support underground space is provided, the method should have that transformation speed is fast, construction is simple, fast, the effective feature of moulding.
Technical scheme provided by the invention is: a kind of method that stake in the underground space is transform as to post, according to following steps, carry out:
1) first the upper face of stake is cleared up;
2) choose two semicircular ring shaped steel cylinders of adapting of diameter with stake, be wrapped in the upper face of stake, make stake in two semicircular ring shaped steel Tong centers;
3) binding site between two semicircular ring shaped steel cylinders carries out electric welding field, makes two semicircular ring shaped steel cylinders be welded to each other into an integral body and stake is wrapped in wherein firmly;
4) place to be welded cooling after, the gap between stake and semicircular ring shaped steel cylinder is filled up with concrete or grouting material, become post.
The inside diameter of described semicircular ring shaped steel cylinder is larger than the outer dia of stake.
Stake in the underground space is transform as to a method for post, according to following steps, carries out:
1) first the exposed surface of stake is cleared up;
2) at the peripheral assembling reinforcement cage of clearing up position, and set up template;
3) concreting or grouting material in template, make it to be solidified as securely one with reinforcing cage and stake;
4) when concrete curing moulding reaches due intensity, stripping; Become post.
Described cleaning is that loosening float stone and the dust of the upper face of stake is removed clean.
Operating principle of the present invention is: stake is mainly at axis direction pressurized, and is embedded in the soil body; In being exposed to space, when post is used, be mainly whole stressed, shearing resistance etc.; Therefore need to carry out overstriking reinforcing, increase shearing resistance and whole stress-bearing capability, enable to bear the Integral Loading of beam slab,
The invention has the beneficial effects as follows:
The present invention by the exposed position of stake is around made steel cylinder or stake around assembling reinforcement cage set up template concreting, make stake there is the bearing capacity of post, thereby stake be transformed into post.Can when building is built the underground space below, gather materials on the spot, the stake originally just with certain bearing capacity is transformed into post, reduced the quantity of newly-built post, guaranteed that the underground space do not cave in, and underground space bearing capacity meets the requirements; The method has reduced material consumption, has saved artificial input, has also accelerated project construction progress.
Accompanying drawing explanation
Fig. 1 is the main TV structure schematic diagram of one of embodiment of the present invention.
Fig. 2 is the attached TV structure schematic diagram of one of embodiment of the present invention.
The specific embodiment
Below in conjunction with embodiment shown in the drawings, further illustrate.
In the digging process carrying out for the following newly-built underground space (as underground parking, basement etc.) of existed building, the stake being embedded in the soil body 5 reveals gradually, according to conventional way, these exposed part all need to be removed.Yet building the underground space needs again many posts to support.For Accelerating The Construction progress, reduction construction cost, inventor determines to transform the stake in the underground space as post; Specifically can be divided into following two kinds of methods;
In embodiment shown in Fig. 1, adaptation step is as follows:
1) first the exposed surface of stake 1 is cleared up, the loosening float stone of the exposed surface of stake and dust are removed clean.
2) choose two semicircular ring shaped steel cylinders 2 mutually suitable with the diameter of stake, be wrapped in the position after cleaning, make stake in two semicircular ring shaped steel Tong centers; The inside diameter of semicircular ring shaped steel cylinder is larger than the outer dia of stake, conventionally should be greater than 2-5cm, is beneficial to concreting or grouting material.The length (axial length) of semicircular ring shaped steel cylinder is according to the height at exposed position (or determining as required).
3) binding site between two semicircular ring shaped steel cylinders 3 carries out electric welding field, makes two semicircular ring shaped steel cylinders be welded to each other into an integral body and stake is wrapped in wherein firmly;
4) place to be welded cooling after, gap 4 use concrete or grouting material between stake and semicircular ring shaped steel cylinder are filled up.
Another kind of by the method for the stake change post in the underground space, according to following steps, carry out (view omission):
1) first the exposed surface of stake is cleared up;
2) according to the size of stake, and the requirement of load bearing capacity, the peripheral assembling reinforcement cage at cleaning position, and set up template;
3) in template, concreting or grouting material make it to be solidified as securely one with reinforcing cage;
4) when concrete curing moulding reaches due intensity, stripping; Stake becomes post.After above-mentioned transformation task is complete, the post that these transformations form just can have been born support task.
Claims (5)
1. the stake in the underground space is transform as to a method for post, according to following steps, carries out:
1) first the upper face of stake (1) is cleared up;
2) choose two semicircular ring shaped steel cylinders (2) of adapting of diameter with stake, be wrapped in the upper face of stake, make stake in two semicircular ring shaped steel Tong centers;
3) binding site (3) between two semicircular ring shaped steel cylinders carries out electric welding field, makes two semicircular ring shaped steel cylinders be welded to each other into an integral body and stake is wrapped in wherein firmly;
4) place to be welded cooling after, the gap (4) between stake and semicircular ring shaped steel cylinder is filled up with concrete or grouting material, become post.
2. a kind of method that stake in the underground space is transform as to post according to claim 1, is characterized in that: the inside diameter of described semicircular ring shaped steel cylinder is larger than the outer dia of stake.
3. a kind of method that stake in the underground space is transform as to post according to claim 2, is characterized in that: described cleaning is that loosening float stone and the dust of the upper face of stake is removed clean.
4. the stake in the underground space is transform as to a method for post, according to following steps, carries out:
1) first the exposed surface of stake is cleared up;
2) at the peripheral assembling reinforcement cage of clearing up position, and set up template;
3) concreting or grouting material in template, make it to be solidified as securely one with reinforcing cage and stake;
4) when concrete curing moulding reaches due intensity, stripping; Become post.
5. a kind of method that stake in the underground space is transform as to post according to claim 4, is characterized in that: described cleaning is that loosening float stone and the dust of the upper face of stake is removed clean.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310646576.0A CN103669901A (en) | 2013-12-04 | 2013-12-04 | Method used for reforming pile in underground space into pillar |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310646576.0A CN103669901A (en) | 2013-12-04 | 2013-12-04 | Method used for reforming pile in underground space into pillar |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103669901A true CN103669901A (en) | 2014-03-26 |
Family
ID=50308610
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310646576.0A Pending CN103669901A (en) | 2013-12-04 | 2013-12-04 | Method used for reforming pile in underground space into pillar |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103669901A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107269019A (en) * | 2017-07-10 | 2017-10-20 | 浙江大学 | The device and method of very-high performance fiber concrete prefabricated pipe section hoop constraint reinforced concrete column |
CN113399929A (en) * | 2021-07-20 | 2021-09-17 | 上海市机械施工集团有限公司 | Welding reinforcement method and welding reinforcement structure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101117801A (en) * | 2007-09-05 | 2008-02-06 | 哈尔滨工业大学 | Superposition pile for engineering reconstruction and pile forming method |
CN101343871A (en) * | 2008-08-22 | 2009-01-14 | 北京航空航天大学 | Composite pile with high permanent stability protection layer and its production and construction method |
JP2009138478A (en) * | 2007-12-10 | 2009-06-25 | Daichi Koei Kk | Rc column reinforcing method |
CN102444142A (en) * | 2011-09-20 | 2012-05-09 | 新世纪建设集团有限公司 | Pile group column replacement expanded basement and construction method of same |
JP2012107445A (en) * | 2010-11-18 | 2012-06-07 | Takenaka Komuten Co Ltd | Earthquake strengthening member, earthquake strengthening structure and earthquake strengthening method |
-
2013
- 2013-12-04 CN CN201310646576.0A patent/CN103669901A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101117801A (en) * | 2007-09-05 | 2008-02-06 | 哈尔滨工业大学 | Superposition pile for engineering reconstruction and pile forming method |
JP2009138478A (en) * | 2007-12-10 | 2009-06-25 | Daichi Koei Kk | Rc column reinforcing method |
CN101343871A (en) * | 2008-08-22 | 2009-01-14 | 北京航空航天大学 | Composite pile with high permanent stability protection layer and its production and construction method |
JP2012107445A (en) * | 2010-11-18 | 2012-06-07 | Takenaka Komuten Co Ltd | Earthquake strengthening member, earthquake strengthening structure and earthquake strengthening method |
CN102444142A (en) * | 2011-09-20 | 2012-05-09 | 新世纪建设集团有限公司 | Pile group column replacement expanded basement and construction method of same |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107269019A (en) * | 2017-07-10 | 2017-10-20 | 浙江大学 | The device and method of very-high performance fiber concrete prefabricated pipe section hoop constraint reinforced concrete column |
CN113399929A (en) * | 2021-07-20 | 2021-09-17 | 上海市机械施工集团有限公司 | Welding reinforcement method and welding reinforcement structure |
CN113399929B (en) * | 2021-07-20 | 2022-11-22 | 上海市机械施工集团有限公司 | Welding reinforcement method and welding reinforcement structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102720206A (en) | Novel connecting structure of prestressed concrete pile and cushion cap | |
CN103114585A (en) | Prestressed prefabricated pile tip structure | |
CN203782684U (en) | Anti-skid pile provided with crossbeam | |
CN102493602A (en) | Ductile concrete column capable of delaying local buckling of steel bars and manufacturing method thereof | |
CN204060020U (en) | A kind of Reinforced Concrete Reinforcement structure | |
CN105568963A (en) | Concrete pile and manufacturing method thereof | |
CN105386454B (en) | A kind of joint assembling type base for power transmission tower | |
CN203229943U (en) | Steel reinforcement laying structure of squeezed bearing plate of pile foundation well | |
CN106223359A (en) | A kind of wind power foundation damping energy-dissipating device and construction technique thereof | |
CN103669901A (en) | Method used for reforming pile in underground space into pillar | |
CN102864796B (en) | Construction spreading foundation adaptive to filled ground settlement and construction method | |
CN102102456B (en) | Powdery material repository | |
CN103806451B (en) | A kind of anchorage type foundation ditch strengthening structure and construction method thereof | |
CN1740457A (en) | Vibration process of eliminating wet foundation falling for CFG pile | |
CN202148523U (en) | Jet grouting soil-cement-pile strengthened pile | |
CN204530685U (en) | A kind of cement-soil stiff composite pile | |
CN204112858U (en) | The prefabricated enclosure wall of a kind of prestressed concrete | |
CN203668926U (en) | Foundation for tapered concrete piles | |
CN204000841U (en) | Combination rectangular pile | |
CN107700516B (en) | A kind of power transmission line iron tower foundation and method of construction | |
CN202509521U (en) | Roadbed side slope retaining protection structure | |
CN206562613U (en) | A kind of mini pile suspension roof support structure | |
CN105971196B (en) | The embedded Concrete-Filled Square Steel Tube ring beam and construction column method of construction of masonry structure | |
CN105064359A (en) | Unbonded prestressed construction anchor rod | |
CN103806450A (en) | Double-row pile foundation pit reinforcement structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20140326 |