CN103669432A - Jacking device for deviation rectification of steel pylon in mining area of coal mine - Google Patents

Jacking device for deviation rectification of steel pylon in mining area of coal mine Download PDF

Info

Publication number
CN103669432A
CN103669432A CN201310575656.1A CN201310575656A CN103669432A CN 103669432 A CN103669432 A CN 103669432A CN 201310575656 A CN201310575656 A CN 201310575656A CN 103669432 A CN103669432 A CN 103669432A
Authority
CN
China
Prior art keywords
pylon
plate
electric power
base plate
deviation rectification
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310575656.1A
Other languages
Chinese (zh)
Other versions
CN103669432B (en
Inventor
舒前进
袁广林
王丽彬
任秀生
李庆涛
王玮
宋巍
王文龙
李青
徐支松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Shanxi Electric Power Co Ltd
Original Assignee
China University of Mining and Technology CUMT
State Grid Corp of China SGCC
Economic and Technological Research Institute of State Grid Shanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT, State Grid Corp of China SGCC, Economic and Technological Research Institute of State Grid Shanxi Electric Power Co Ltd filed Critical China University of Mining and Technology CUMT
Priority to CN201310575656.1A priority Critical patent/CN103669432B/en
Publication of CN103669432A publication Critical patent/CN103669432A/en
Application granted granted Critical
Publication of CN103669432B publication Critical patent/CN103669432B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a deviation rectification device for a steel pylon, and particularly relates to a jacking device for deviation rectification of the steel pylon in a mining area of a coal mine. The jacking device for deviation rectification of the steel pylon in the mining area of the coal mine comprises an independent long-column concrete foundation (1), foundation bolts (3) and a pylon leg plate (4) capable of being jacked, wherein the pylon leg plate capable of being jacked (4) comprises a base plate (6) and a steel pylon principle material connecting plate (8) welded to the base plate (6), the steel pylon principle material connecting plate (8) is welded to a steel pylon principle material (5) along the edge, the base plate (6) of the pylon leg plate capable of being jacked (4) is connected with the independent long-column concrete foundation (1) through the foundation bolts (3), loading holes (7) used for installation of jacks (2) are formed in the independent long-column concrete foundation (1), and the length of exposed screw threads of each foundation bolt (3) is no smaller than 150mm. According to the structural system, the jacking device for deviation rectification of the steel pylon in the mining area of the coal mine is simple in structure, when the steel pylon inclines, the foundation bolts (3) are loosened, the jacks can be used for directly jacking the pylon leg plate capable of being jacked, and deviation rectification can be carried out.

Description

A kind of colliery minery electric power pylon correction lift-up device
Technical field
The present invention relates to a kind of electric power pylon deviation correcting device, relate in particular to a kind of colliery minery electric power pylon correction lift-up device.
Background technology
Due to the variation of colliery minery geologic structure, easily there is sinking and inclination in various degree in the electric power pylon of building at minery, causes serious threat to the safe operation of transmission line of electricity.The way addressing this problem is at present after electric power pylon tilts, and adopts iron tower structure or the basic mode of transforming are rectified a deviation.Adopt in this way, Work tool consumption is large, site layout project is more complicated, workload and labor strength all larger.
Summary of the invention
The problem existing for above-mentioned prior art, the invention provides a kind of colliery minery electric power pylon correction lift-up device, in easy construction, use Work tool few in the situation that, the electric power pylon tilting is rectified a deviation, and guarantees the safety of transmission line of electricity.
To achieve these goals, the technical solution used in the present invention is: a kind of colliery minery electric power pylon correction lift-up device, comprises concrete long column independent footing, stone bolt and can jacking column foot plate; Can jacking column foot plate comprise base plate and be welded on the iron tower main material junction plate on base plate, iron tower main material junction plate and iron tower main material weld along edge, and base plate that can jacking column foot plate is connected with concrete long column independent footing by stone bolt; Concrete long column independent footing is provided with the loading hole that can lay jack; Described stone bolt exposes screw thread length and is not shorter than 150mm.
Preferably, on base plate, be welded with stiffener, stiffener and iron tower main material junction plate vertical welding.
Preferably, loading hole is rectangular structure.
Preferably, the size in described loading hole wide * length * height is not less than 150mm * 200mm * 300mm.
Preferably, to expose screw thread length be 150mm-300mm to described stone bolt.
The present invention, when carrying out foundation construction, reserves the loading hole that can lay jack, and installation can jacking column foot plate when steel tower is installed.During steel tower run-off the straight, unclamp stone bolt, jack is placed on and is loaded in hole, adopt jack jacking column foot plate, just can be safely, accurately, reliably the electric power pylon of run-off the straight is rectified a deviation; The present invention, when electric power pylon run-off the straight, unclamps stone bolt, uses the direct jacking column foot of jack plate just can rectify a deviation, can to the steel tower tilting, carry out continuous setup easily, effectively reduce the angle of inclination of steel tower, easy construction, the Work tool using is few, and reliability is high; Can significantly reduce the subsidiary stress that earth's surface distortion produces on electric power pylon, make electric power pylon can stand the moving impact of Coal Exploitation, and then guarantee the safety of transmission line of electricity.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is the A-A generalized section of Fig. 1;
Fig. 3 is the top view of concrete long column independent footing;
Fig. 4 is the left view of concrete long column independent footing.
In figure: 1, concrete long column independent footing, 2, jack, 3, stone bolt, 4, can jacking column foot plate, 5, iron tower main material, 6, base plate, 7, load hole, 8, iron tower main material junction plate, 9, stiffener.
The specific embodiment
Below in conjunction with accompanying drawing, the invention will be further described.
As shown in Figures 1 to 4: the present invention includes concrete long column independent footing 1, stone bolt 3 and can jacking column foot plate 4; Can jacking column foot plate 4 comprise base plate 6 and be welded on the iron tower main material junction plate 8 on base plate 6, iron tower main material junction plate 8 is with iron tower main material 5 along edge welding, and base plate 6 that can jacking column foot plate 4 is connected with concrete long column independent footing 1 by stone bolt 3; Concrete long column independent footing 1 is provided with the reserved loading hole 7 that can lay jack 2; Described stone bolt 3 exposes screw thread length and is not shorter than 150mm.
On base plate 6, be welded with stiffener 9, stiffener 9 and iron tower main material junction plate 8 vertical weldings, due to the setting of stiffener 9, can effectively improve the bearing capacity of this device.
For the ease of holding jack 2, loading hole 7 is rectangular structure.
In order to hold jack 2, the size in described loading hole 7 is wide * and length * height is not less than 150mm * 200mm * 300mm.
It is 150mm-300mm that described stone bolt 3 exposes screw thread length, in this length range, and convenient installation and removal that can jacking column foot plate 4.
In the present invention, by the reserved loading hole 7 that can lay jack 2 on concrete long column independent footing 1, and construction can jacking column foot plate 4 when steel tower is installed, i.e. iron tower main material junction plate 8 and iron tower main material 5 welding, and be welded on base plate 6 with stiffener 9 simultaneously.When steel tower run-off the straight, only need to unclamp stone bolt 3, jack 2 is placed in the reserved loading hole 7 of concrete long column independent footing 1, use jack 2 jackings can jacking column foot plate 4, just can rectify a deviation to the electric power pylon tilting, after correction work completes, fastening foundation bolt 3.The present invention can reduce the angle of inclination of steel tower at easy construction, Work tool the in the situation that of few effectively, and can carry out continuous setup, reduce the subsidiary stress that earth's surface distortion produces on electric power pylon, make steel tower can stand the moving impact of Coal Exploitation, and then guarantee the safety of transmission line of electricity.

Claims (5)

1. a colliery minery electric power pylon correction lift-up device, comprises concrete long column independent footing (1) and stone bolt (3); Characterized by further comprising can jacking column foot plate (4), can comprise base plate (6) and be welded on the iron tower main material junction plate (8) on base plate (6) by jacking column foot plate (4), and iron tower main material junction plate (8) welds along edge with iron tower main material (5); Base plate (6) that can jacking column foot plate (4) is connected with concrete long column independent footing (1) by stone bolt (3); Concrete long column independent footing (1) is provided with for laying the loading hole (7) of jack (2); Described stone bolt (3) exposes screw thread length and is not shorter than 150mm.
2. a kind of colliery according to claim 1 minery electric power pylon correction lift-up device, is characterized in that, is welded with stiffener (9) on base plate (6), stiffener (9) and iron tower main material junction plate (8) vertical welding.
3. a kind of colliery according to claim 1 minery electric power pylon correction lift-up device, is characterized in that, described loading hole (7) is rectangular structure.
4. a kind of colliery according to claim 3 minery electric power pylon correction lift-up device, is characterized in that, and the size in described loading hole (7) is wide * and length * height is not less than 150mm * 200mm * 300mm.
5. a kind of colliery according to claim 1 minery electric power pylon correction lift-up device, is characterized in that, it is 150mm-300mm that described stone bolt (3) exposes screw thread length.
CN201310575656.1A 2013-11-18 2013-11-18 A kind of jacking device for deviation rectification of steel pylon in mining area of coal mine Expired - Fee Related CN103669432B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310575656.1A CN103669432B (en) 2013-11-18 2013-11-18 A kind of jacking device for deviation rectification of steel pylon in mining area of coal mine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310575656.1A CN103669432B (en) 2013-11-18 2013-11-18 A kind of jacking device for deviation rectification of steel pylon in mining area of coal mine

Publications (2)

Publication Number Publication Date
CN103669432A true CN103669432A (en) 2014-03-26
CN103669432B CN103669432B (en) 2016-11-02

Family

ID=50308146

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310575656.1A Expired - Fee Related CN103669432B (en) 2013-11-18 2013-11-18 A kind of jacking device for deviation rectification of steel pylon in mining area of coal mine

Country Status (1)

Country Link
CN (1) CN103669432B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104563172A (en) * 2015-01-13 2015-04-29 浙江湖州市建工集团有限公司 Sinking restoration structure for steel structure room and restoration method thereof
CN104763005A (en) * 2015-03-18 2015-07-08 山东省水利科学研究院 Large steel spherical tank inclination rectification method
CN106759556A (en) * 2016-12-26 2017-05-31 中国化学工程第三建设有限公司 One kind correction inclined method of tower body
CN113482034A (en) * 2021-06-23 2021-10-08 国网山西省电力公司阳泉供电公司 Deviation rectifying method for uneven settlement of power transmission iron tower
CN114278141A (en) * 2021-11-26 2022-04-05 内蒙古电力(集团)有限责任公司鄂尔多斯电业局 Deviation-correctable power transmission tower and using method thereof
CN114278139A (en) * 2021-11-26 2022-04-05 内蒙古电力(集团)有限责任公司鄂尔多斯电业局 Mining-correcting cooperative power transmission tower maintenance method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10280427A (en) * 1997-03-31 1998-10-20 Fujio Itagaki Correction device and method for correcting settlement of building
CN102080382A (en) * 2010-11-30 2011-06-01 济南大学 Building foundation adaptable to goaf foundation deformation
CN102864795A (en) * 2012-10-19 2013-01-09 重庆大学 Light steel factory post foundation suitable for sedimentation of filled-in ground and construction method
CN203284791U (en) * 2013-06-06 2013-11-13 中鼎国际工程有限责任公司 Independent column basis below column and capable of conducting jacking rectification
CN203960919U (en) * 2013-11-18 2014-11-26 国家电网公司 Colliery minery electric power pylon correction lift-up device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10280427A (en) * 1997-03-31 1998-10-20 Fujio Itagaki Correction device and method for correcting settlement of building
CN102080382A (en) * 2010-11-30 2011-06-01 济南大学 Building foundation adaptable to goaf foundation deformation
CN102864795A (en) * 2012-10-19 2013-01-09 重庆大学 Light steel factory post foundation suitable for sedimentation of filled-in ground and construction method
CN203284791U (en) * 2013-06-06 2013-11-13 中鼎国际工程有限责任公司 Independent column basis below column and capable of conducting jacking rectification
CN203960919U (en) * 2013-11-18 2014-11-26 国家电网公司 Colliery minery electric power pylon correction lift-up device

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104563172A (en) * 2015-01-13 2015-04-29 浙江湖州市建工集团有限公司 Sinking restoration structure for steel structure room and restoration method thereof
CN104763005A (en) * 2015-03-18 2015-07-08 山东省水利科学研究院 Large steel spherical tank inclination rectification method
CN106759556A (en) * 2016-12-26 2017-05-31 中国化学工程第三建设有限公司 One kind correction inclined method of tower body
CN113482034A (en) * 2021-06-23 2021-10-08 国网山西省电力公司阳泉供电公司 Deviation rectifying method for uneven settlement of power transmission iron tower
CN114278141A (en) * 2021-11-26 2022-04-05 内蒙古电力(集团)有限责任公司鄂尔多斯电业局 Deviation-correctable power transmission tower and using method thereof
CN114278139A (en) * 2021-11-26 2022-04-05 内蒙古电力(集团)有限责任公司鄂尔多斯电业局 Mining-correcting cooperative power transmission tower maintenance method

Also Published As

Publication number Publication date
CN103669432B (en) 2016-11-02

Similar Documents

Publication Publication Date Title
CN203960919U (en) Colliery minery electric power pylon correction lift-up device
CN103669432A (en) Jacking device for deviation rectification of steel pylon in mining area of coal mine
CN103669431A (en) Device for adjusting inclined steel pylon in mining area of coal mine
CN103938663A (en) Correction device of inclined power transmission tower made of signal-splicing steel angle principal material
CN210460706U (en) Underground roadway supporting device for coal mining
CN108999225B (en) Inclination correcting method for rotary shifting brick-concrete structure building
CN205024600U (en) A work platform that is used for bridge aquatic pile foundation to be under construction
CN203960920U (en) Colliery minery electric power pylon inclination adjusting device
CN203594058U (en) Inclined transmission tower rectification device with single-spliced angle steel as main material
CN102817617B (en) Novel inhaul cable type shield originating backrest substrate system
CN203594263U (en) Inclined steel pylon deviation correcting device for two-sort angle steel main material
CN215858944U (en) Platform structure for steel structure construction operation
CN203594264U (en) Clamp special for angle steel iron tower rectification and tool for angle steel iron tower rectification
CN203361170U (en) Supporting upright column pile for building foundation pit support
CN203322513U (en) Double-supporting-leg type petroleum pipeline protective device
CN106759557B (en) Mining area power transmission tower horizontal deformation recovery device
CN204174980U (en) A kind of grinding machine inspection platform
CN204570707U (en) For the steel structure support assembly of pattern foundation pit supporting structure
CN216077144U (en) Concrete filled steel tube support and anchor rod supporting device in coordination
CN216381404U (en) Top bracing frame for tunnel drilling
CN204591280U (en) A kind of mobile platform structure for pipe curtain jacking construction
CN213709566U (en) Inner supporting device for foundation pit
CN204060727U (en) For steel pipe truss grouting and reinforcing and the supporting and protection structure of heavily stressed weak broken wall rock
CN201714414U (en) Quick supporting device for preventing roofs from falling in stope
CN211950595U (en) Device for burying tunnel roof at mine measurement control point

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20161102

Termination date: 20211118

CF01 Termination of patent right due to non-payment of annual fee