CN103643795B - Fastening type cylindrical timber formwork concrete casting construction method - Google Patents
Fastening type cylindrical timber formwork concrete casting construction method Download PDFInfo
- Publication number
- CN103643795B CN103643795B CN201310721707.7A CN201310721707A CN103643795B CN 103643795 B CN103643795 B CN 103643795B CN 201310721707 A CN201310721707 A CN 201310721707A CN 103643795 B CN103643795 B CN 103643795B
- Authority
- CN
- China
- Prior art keywords
- template
- steel band
- steel
- construction
- column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The invention belongs to technical field of buildings, particularly to a kind of fastening type cylindrical timber formwork concrete casting construction method, comprise the following steps: 1) the main muscle of colligation pillar;2) location;3) template construct;4) model sheetinstallat;5) template is in the cutting process of beam-column intersection position;6) formwork reinforcement;7) template system entirety is fixed;8) concreting;9) form removal.The plank sheathing light weight of the present invention, using birch poplar is raw material, and intensity is big, template general weight 40 45Kg of good toughness, highly 3m, and two people cooperate can complete to install operation, compared with traditional steel form construction, shortens the construction period of 70%;Use sizing column-form, use unique convex groove design at template interface, make piece combine closely, prevent running pulp, spillage, make concrete demoulding the fastest but also attractive in appearance;Solve the difficult problem that steel form cannot arbitrarily cut, can arbitrarily cut according to actual size, reduce difficulty of construction for construction party.
Description
Technical field
The present invention relates to a kind of fastening type cylindrical timber formwork concrete casting construction method, belong to technical field of buildings.
Background technology
Along with the development of skyscraper, various special-shaped buildings progressively increase, and cylinder is more and more applied in architectural design,
Cylinder construction uses template mainly to have cylindrical steel template, PVC plastic template, and steel shutterings pretends to be stupid heavily, needs bigger lifting to set
Standby lifting, wastes time and energy, though PVC template quality is light, but due to template threading defects, is easily caused circle arc error, gets
Cylinder qualification rate low, particularly interface position, it is generally required to secondary repair.For solve an above difficult problem, when cylinder is constructed I
Company uses buckle-type cylindrical wooden template, uses this template concrete formation surface to can reach the apparent mass of clear-water concrete, no
Need to carry out secondary again to plaster, and handle simple and easy to control, the most cost-effective but also decrease one working procedure, accelerate
Construction speed.
Summary of the invention
The technical problem to be solved in the present invention is: provide a kind of convenient construction, can guarantee that construction safety and raising pour after coagulation
Soil property amount, and the fastening type cylindrical timber formwork concrete casting construction method of easily form removal.
Fastening type cylindrical timber formwork concrete casting construction method of the present invention, comprises the following steps:
1) colligation cylinder framework of steel reinforcement;
2) location: surveying column-form outer edge unwrapping wire, a diameter of needs of column-form outer edge pours the straight of cylinder outer edge
Footpath adds the template thickness of twice, is then respectively provided with spacer bar in cylinder framework of steel reinforcement upper, middle and lower, by spacer bar and circle
Post framework of steel reinforcement is with tying up a colligation together, and spacer bar uses two horizontal strokes two to erect reinforcement welding together;
3) template construct: template is wooden template, and template is made up of two semicircular template, one end of each half circle template all processes
Going out groove, the other end all processes the projection that matches with groove;
4) model sheetinstallat: when model sheetinstallat height is within 3m, uses the semicircle template assembly of monoblock, and by two semicircular mould
Together with plate and groove fasten to projection;When model sheetinstallat height is more than 3m, carry out dislocation lap joint installation;
5) template is in the cutting process of beam-column intersection position: in beam-column intersection position, cut template;
6) formwork reinforcement: every piece of template assembly all first passes through iron wire after completing carries out closing up Guan Bi, then reinforces with steel band, steel band
Being provided with an opening, opening part two ends are respectively provided with bolt block, when installing steel band, first follow closely on the circumference of the sustained height of template
Nail, steel band is placed on nail, and template is encased from its opening part, is tightened by the bolt block at opening part two ends with bolt;
7) template system entirety is fixed: add the lumps of wood in template periphery, and the lumps of wood is fixed by steel pipe, and steel pipe is fixed on scaffold,
Steel pipe distance between the upper and lower is 500~1500mm;
8) concreting: before concreting, builds platform with mortar bottom template, and height is 10~20mm, and template pours
Can primary concreting time within concrete seven m;Time highly more than 7m, pour at twice, pour latter 30~60 points for the first time
Clock carries out second time and pours;
9) form removal.
Wherein, in step 2 during location, total powerstation method of polar coordinates can be used to be accurately positioned;The length of spacer bar is can guarantee that steel
Tendon protective layer thickness is advisable, position, the accuracy of cover to reinforcement during to ensure that cylinder pours;
In step 6 install steel band time bolt time, each bolt degree of tightening to keep consistent, such guarantee steel band elasticity
Concordance and construction safety;
The lumps of wood in step 7 can use cross section to be foursquare cuboid wood, a length of 100mm, width and be highly 50mm,
By the lumps of wood, template system entirety is fixed, be possible not only to make template carry out perpendicular positioning, and being forced into of template can be made
One entirety, reaches the effect of second consolidation;
Spacer bar in described step 2 is set to 3 roads;Nail in step 5 uses 3~4, steel band between the upper and lower away from
From 200~300mm, can increase steel band and fix between neighbouring template, steel band level covers reinforces at interface position.
Wooden template in described step 3 is inside and outside uses epoxy resin overlay film.Smooth, waterproof and have certain breathability, beat
The concrete cylindrical gone out is the most smooth but also forming, vision and feel are splendid, and general effect is better than similar plain form.
It addition, template of the present invention can use high-quality birch poplar template.
The invention has the beneficial effects as follows:
1) plank sheathing light weight, using birch poplar is raw material, and intensity is big, general weight 40-45Kg of template of good toughness, highly 3m,
Two people cooperate can complete to install operation, compared with traditional steel form construction, shorten the construction period of 70%;
2) plank sheathing uses sizing column-form, uses unique convex groove design, make piece combine closely at template interface, anti-
Only running pulp, spillage, makes concrete demoulding the fastest but also attractive in appearance;
3) the inside and outside epoxy resin overlay film that uses of this typified form, smooth, waterproof and have certain breathability, the concrete circular got
Post is the most smooth but also forming, vision and feel are splendid, and general effect is better than similar plain form;
4) plank sheathing solves the difficult problem that steel form cannot arbitrarily cut, and arbitrarily can cut according to actual size, drops for construction party
Low difficulty of construction:
5) plank sheathing solve punching block, PVC template etc. because of self-defect cannot a lintel difficult problem.
Accompanying drawing explanation
Fig. 1 is the structural representation of the present invention.
Fig. 2 is the structural representation of spacer bar in the present invention.
Fig. 3 is the structural representation of template in the present invention.
Fig. 4 is the structural representation that in the present invention, template system entirety is fixing.
In figure: 1, template 2, column-form outer edge 3, cylinder framework of steel reinforcement 4, perpendicular reinforcing bar 5, cross reinforcement 6,
Protruding 7, groove 8, steel pipe 9, the lumps of wood 10, need to pour cylinder outer edge.
Detailed description of the invention
Below in conjunction with the accompanying drawings the present invention is described further:
As shown in Figure 1 to 4, fastening type cylindrical timber formwork concrete casting construction method of the present invention, including following step
Rapid:
1) colligation cylinder framework of steel reinforcement 3;
2) location: surveying column-form outer edge 2 unwrapping wire, a diameter of needs of column-form outer edge 2 pours cylinder outer edge
The diameter of 10 adds the thickness of the template 1 of twice, is then respectively provided with spacer bar in cylinder framework of steel reinforcement 3 upper, middle and lower, will
Spacer bar and cylinder framework of steel reinforcement 3 are with together with tying up a colligation, and spacer bar uses two cross reinforcements 5 and two to erect reinforcing bar 4 and welds
Together;
3) template construct: template 1 is wooden template, and template 1 is made up of two semicircular template, one end of each half circle template is equal
Processing groove 7, the other end all processes the projection 6 that matches with groove 7;
4) model sheetinstallat: when model sheetinstallat height is within 3m, uses the semicircle template assembly of monoblock, and by two semicircular mould
Plate and groove 7 are together with protruding 6 fasten to;When template 1 setting height(from bottom) is more than 3m, carry out dislocation lap joint installation;
5) template is in the cutting process of beam-column intersection position: in beam-column intersection position, cut template 1;
6) formwork reinforcement: the assembly of every piece of template 1 all first passes through iron wire and carries out closing up Guan Bi after completing, then reinforces with steel band, steel
Band is provided with an opening, and opening part two ends are respectively provided with bolt block, when installing steel band, first on the circumference of the sustained height of template
Nailing, steel band is placed on nail, and template is encased from its opening part, is tightened by the bolt block at opening part two ends with bolt;
7) template system entirety is fixed: add the lumps of wood 9 in template 1 periphery, and the lumps of wood 9 is fixed by steel pipe 8, and steel pipe 8 is fixed
On scaffold, steel pipe 8 distance between the upper and lower is 500~1500mm;
8) concreting: before concreting, builds platform with mortar bottom template, and height is 10~20mm, and template pours
Can primary concreting time within concrete seven m;Time highly more than 7m, pour at twice, pour latter 30~60 points for the first time
Clock carries out second time and pours;
9) form removal.
Wherein the spacer bar in step 2 is set to 3 roads;Nail in step 6 uses 3~4, steel band distance between the upper and lower
200~300mm, steel band can be increased between neighbouring template and fix, steel band level covers reinforces at interface position.Step 3
In wooden template inside and outside use epoxy resin overlay film.
Claims (1)
1. a fastening type cylindrical timber formwork concrete casting construction method, it is characterised in that comprise the following steps:
1) colligation cylinder framework of steel reinforcement (3);
2) location: surveying column-form outer edge (2) unwrapping wire, a diameter of needs of column-form outer edge (2) pours cylinder
The diameter of outer edge (10) adds the thickness of the template (1) of twice, then in cylinder framework of steel reinforcement (3) upper, middle and lower respectively
Arranging spacer bar, by spacer bar and cylinder framework of steel reinforcement (3) with together with tying up a colligation, spacer bar uses two cross reinforcements
(5) and two erect reinforcing bar (4) welds together;
3) template construct: template (1) is wooden template, and template (1) is made up of two semicircular template, each half circle template
One end all processes groove (7), and the other end all processes the projection (6) that matches with groove (7);
4) model sheetinstallat: when model sheetinstallat height is within 3m, uses the semicircle template assembly of monoblock, and by two semicircular mould
Together with plate and groove (7) fasten to protruding (6);When template (1) setting height(from bottom) is more than 3m, carries out dislocation and take
Connect installation;
5) template is in the cutting process of beam-column intersection position: in beam-column intersection position, cuts template (1);
6) formwork reinforcement: the assembly of every piece of template (1) all first passes through iron wire after completing and carries out closing up Guan Bi, then reinforces with steel band,
Steel band is provided with an opening, and opening part two ends are respectively provided with bolt block, when steel band is installed, and the circumference of the first sustained height in template
On nail, steel band is placed on nail, and template is encased from its opening part, is tightened by the bolt block at opening part two ends with bolt;
7) template system entirety is fixed: add the lumps of wood (9) in template (1) periphery, and the lumps of wood (9) is fixed by steel pipe (8),
Steel pipe (8) is fixed on scaffold, and steel pipe (8) distance between the upper and lower is 500~1500mm;
8) concreting: before concreting, builds platform with mortar bottom template, and height is 10~20mm, and template pours
Primary concreting time within concrete seven m;Time highly more than 7m, pour at twice, pour for the first time latter 30~60 minutes
Carry out second time to pour;
9) form removal;
Spacer bar in step 2 is set to 3 roads;Nail in step 6 uses 3~4, steel band distance 200 between the upper and lower~
300mm, increases steel band and fixes between neighbouring template, steel band level covers reinforces at interface position;
Wooden template in step 3 is inside and outside uses epoxy resin overlay film.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310721707.7A CN103643795B (en) | 2013-12-24 | 2013-12-24 | Fastening type cylindrical timber formwork concrete casting construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310721707.7A CN103643795B (en) | 2013-12-24 | 2013-12-24 | Fastening type cylindrical timber formwork concrete casting construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103643795A CN103643795A (en) | 2014-03-19 |
CN103643795B true CN103643795B (en) | 2016-09-14 |
Family
ID=50249072
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310721707.7A Active CN103643795B (en) | 2013-12-24 | 2013-12-24 | Fastening type cylindrical timber formwork concrete casting construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103643795B (en) |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104060829A (en) * | 2014-05-22 | 2014-09-24 | 中国建筑第四工程局有限公司 | Construction method and construction device for house beam pillar |
CN104153573B (en) * | 2014-08-22 | 2016-08-31 | 中冶建工集团有限公司 | V-type cylinder concrete pour mould and construction method |
CN105649327A (en) * | 2015-03-16 | 2016-06-08 | 中国建筑第四工程局有限公司 | Method for pouring concrete outside steel pipe columns by using semicircular templates |
CN105649328A (en) * | 2015-03-16 | 2016-06-08 | 中国建筑第四工程局有限公司 | Fixing method and structure for columnar mould |
CN106567540A (en) * | 2016-09-26 | 2017-04-19 | 浙江大华建设集团有限公司 | Template supporting system of cylindrical butt-joint template and construction method for template supporting system |
CN108466351B (en) * | 2018-04-12 | 2024-03-22 | 杭州汽轮铸锻股份有限公司 | Barrel structure wood die |
CN108979137A (en) * | 2018-06-29 | 2018-12-11 | 浙江展诚建设集团股份有限公司 | The assembling and disassembling construction method of Round Concrete column composite wooden template |
CN111472543A (en) * | 2020-04-17 | 2020-07-31 | 安徽省第二建筑工程有限公司 | Concrete pouring construction method for cylindrical wood formwork |
CN113172748B (en) * | 2021-04-27 | 2022-12-30 | 平凉市新世纪建筑工程有限责任公司 | Construction method of concrete cylindrical formwork |
CN115788024A (en) * | 2022-11-23 | 2023-03-14 | 中国建筑第四工程局有限公司 | Inclined cylinder high formwork construction process |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20110132789A (en) * | 2010-06-03 | 2011-12-09 | 이피아이주식회사 | Hybrid paper formwork |
CN202577963U (en) * | 2012-01-12 | 2012-12-05 | 中国建筑土木建设有限公司 | Novel cylindrical pier formwork |
CN103184794A (en) * | 2013-03-12 | 2013-07-03 | 杭州二建建设有限公司 | Quick formwork construction method for cylindrical strap type butt splicing wooden template |
CN203201145U (en) * | 2013-03-18 | 2013-09-18 | 山河建设集团有限公司 | Concrete film-covered building round template |
-
2013
- 2013-12-24 CN CN201310721707.7A patent/CN103643795B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20110132789A (en) * | 2010-06-03 | 2011-12-09 | 이피아이주식회사 | Hybrid paper formwork |
CN202577963U (en) * | 2012-01-12 | 2012-12-05 | 中国建筑土木建设有限公司 | Novel cylindrical pier formwork |
CN103184794A (en) * | 2013-03-12 | 2013-07-03 | 杭州二建建设有限公司 | Quick formwork construction method for cylindrical strap type butt splicing wooden template |
CN203201145U (en) * | 2013-03-18 | 2013-09-18 | 山河建设集团有限公司 | Concrete film-covered building round template |
Also Published As
Publication number | Publication date |
---|---|
CN103643795A (en) | 2014-03-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103643795B (en) | Fastening type cylindrical timber formwork concrete casting construction method | |
CN104453093B (en) | Prefabricated steel reinforced concrete beam with transversal high-strength concrete clapboard, and construction method | |
CN105804395B (en) | Stair continuously poured in one molding construction method based on monoblock type typified form | |
CN105714684A (en) | Prestressed concrete variable cross-section fish-bellied type continuous box girder construction method | |
CN106760502A (en) | Shear wall end cylinder construction method | |
CN104153573B (en) | V-type cylinder concrete pour mould and construction method | |
CN206888506U (en) | The cast-in-place system of formwork structure and shear wall of shear wall angle node | |
CN209817167U (en) | Section steel concrete superimposed shear wall | |
CN106337530B (en) | A kind of construction of frame beam seams stifled construction method | |
CN103806593A (en) | Precast concrete member | |
CN105275087B (en) | The attachment structure of prefabricated assembled concrete beam column | |
CN105178256B (en) | One kind is used for the deep nonmetallic horizontal slip-form system of narrow gutter wall continuous placing | |
CN208763208U (en) | Additional closure connection reinforcing bar without support assembled integral beam-column node structure | |
CN105908883A (en) | Construction method for preventing upward floating of composite floor system lightweight core formwork | |
CN204001212U (en) | Band ring-type rebar connector | |
CN207934055U (en) | A kind of prefabricated cushion cap template and prefabricated cushion cap loose tool | |
CN206928426U (en) | A kind of prefabricated composite wallboard formula underground installation | |
CN207348280U (en) | A kind of novel precast floor slab | |
CN108979137A (en) | The assembling and disassembling construction method of Round Concrete column composite wooden template | |
CN208415925U (en) | A kind of PVC column-form | |
CN204001714U (en) | The concrete mould of building of V-type cylinder | |
CN204001713U (en) | V-type cylinder oblique line section concrete is built mould | |
CN209163443U (en) | A kind of tool type yin-yang Angle formwork | |
CN208486550U (en) | A kind of assembled architecture floor support plate bracket mould | |
CN206752707U (en) | Steel construction track vestibule expansion gap device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |