CN103631921B - A kind of configuration information of transformer substation detection method and device - Google Patents

A kind of configuration information of transformer substation detection method and device Download PDF

Info

Publication number
CN103631921B
CN103631921B CN201310642196.XA CN201310642196A CN103631921B CN 103631921 B CN103631921 B CN 103631921B CN 201310642196 A CN201310642196 A CN 201310642196A CN 103631921 B CN103631921 B CN 103631921B
Authority
CN
China
Prior art keywords
configuration information
configuration
information
file
substation
Prior art date
Application number
CN201310642196.XA
Other languages
Chinese (zh)
Other versions
CN103631921A (en
Inventor
张沛超
杨漪俊
姜健宁
高翔
吴振杰
盛海华
郑杨
方天宇
潘武略
王悦
Original Assignee
国家电网公司
国网浙江省电力公司
国网浙江省电力公司杭州供电公司
上海交通大学
上海毅昊自动化有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 国家电网公司, 国网浙江省电力公司, 国网浙江省电力公司杭州供电公司, 上海交通大学, 上海毅昊自动化有限公司 filed Critical 国家电网公司
Priority to CN201310642196.XA priority Critical patent/CN103631921B/en
Publication of CN103631921A publication Critical patent/CN103631921A/en
Application granted granted Critical
Publication of CN103631921B publication Critical patent/CN103631921B/en

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING; COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/24Querying
    • G06F16/248Presentation of query results
    • GPHYSICS
    • G06COMPUTING; CALCULATING; COUNTING
    • G06QDATA PROCESSING SYSTEMS OR METHODS, SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL, SUPERVISORY OR FORECASTING PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply

Abstract

This application discloses a kind of configuration information of transformer substation detection method and device, methods described is by setting the SCD file configured containing transformer station's whole station engineering, the standard configuration information that the IED equipment for needing to detect is obtained from the SCD file is used as the first configuration information, and the actual disposition information by the use of the detected equipment I ED equipment in MMS service acquisition intelligent substations is used as the second configuration information, first configuration information and second configuration information are contrasted, export corresponding comparing result, realize the on-line checking of detected equipment I ED equipment, improve operating efficiency, effectively prevent because configuration information is inconsistent and to the hidden trouble that is brought of safe and reliable operation of intelligent substation, improve the reliability of power system power supply.

Description

A kind of configuration information of transformer substation detection method and device
Technical field
The application is related to intelligent testing technology field, more specifically to a kind of configuration information of transformer substation detection method And device.
Background technology
More and more high with grid automation level, the mankind more come to the economy, the feature of environmental protection, security reliability of power network Higher requirement, set up the intelligent power supply system of a new generation turns into the common recognition of countries in the world.It is different from traditional electric power system It is that intelligent grid of new generation can make full use of modern information technologies, the communication technology and control technology, realizes that energy basis is set Apply comprehensive fusion with information infrastructure.Protection observing and controlling is carried out due to most primary equipment in power network and to primary equipment Secondary device and sensor, executing agency etc. be all arranged in transformer station, so the intellectuality of transformer station is to power network intelligence The important support of energyization.
China has put into operation a large amount of intelligent substation equipment, with the update of equipment, the constantly improve of technological means, These intelligent substation equipment will enter the equipment operation maintenance cycle successively, will occur such as increase and decrease interval, change IED equipment (Intelligent Electronic Device, intelligent electronic device), IED DFUs, change IED functions of the equipments/ Model and IED overhauls of the equipments etc. are operated.In this process, SCD file (Substation Configuration Description, substation configuration description) it is dynamic change.In the process, in order to ensure intelligent substation equipment just Often, safe operation, then be necessarily always ensured that the empty terminal and empty loop configuration information and whole station SCD texts of each IED device interiors Configuration information in part is completely the same.But because ICD files (IED Capability change privately in part producer Configuration, device capability description) or CID files (Configured IED Description, device instantiation matches somebody with somebody Put) or the reason such as lower wrong configuration information, still it is difficult to ensure that actual disposition information and matching somebody with somebody in SCD file in In-situ FTIR spectra D equipment The uniformity of confidence breath, thus for the intelligent substation equipment in intelligent substation safe and reliable operation bring it is serious hidden Suffer from.
Generally judge in the prior art using man-made chamber by the way of in the detected IED equipment actual disposition information and Whether the configuration information in SCD file is consistent, causes inefficiency.
The content of the invention
In view of this, the application provides a kind of configuration information of transformer substation detection method and device, to realize automatic decision It is detected actual disposition information in IED equipment whether consistent with the configuration information in SCD file.
To achieve these goals, it is proposed that scheme it is as follows:
A kind of configuration information of transformer substation detection method, methods described includes:
According to transformer station's whole station engineering configuration, substation configuration description file is formed;
The configuration information file for being detected intelligent electronic device is extracted in substation configuration description file;
The first configuration information is obtained according to the configuration information in configuration information file;
It is detected using MMS (Manufacturing Message Specification manufacture message specification) service acquisition The configuration information for surveying intelligent electronic device is used as the second configuration information;
First configuration information and the second configuration information are contrasted and comparing result is exported.
It is preferred that, in above-mentioned configuration information of transformer substation detection method, the first quasi- configuration information includes:Equipment identification information With standard configuration information;
Second configuration information includes:Equipment identification information and actual disposition information.
It is preferred that, in above-mentioned configuration information of transformer substation detection method, intelligence is extracted in the file by substation configuration description The configuration information file of energy electronic equipment, including:
According to the equipment identification information for being detected intelligent electronic device, extract corresponding by the substation configuration description file Intelligent electronic device configuration information block, obtain the power transformation towards general object in the intelligent electronic device configuration information block Event control block, sampled value control block and the empty terminal block of information of input stand as configuration information file.
It is preferred that, in above-mentioned configuration information of transformer substation detection method, by first configuration information and the second configuration information Contrast and export comparing result, including:
Judge whether first configuration information is identical with second configuration information, if it is different, output equipment is identified Information and alarm signal.
It is preferred that, in above-mentioned configuration information of transformer substation detection method, extracting tested in substation configuration description file Before the configuration information file for surveying intelligent electronic device, in addition to:
The configuration information related to detected intelligent electronic device is extracted in the substation configuration description file, and is protected Save as device instantiation configuration file;
The detected intelligent electronic device reads described device instantiation configuration file, sets up empty terminal, empty loop Object oriented programming model.
A kind of configuration information of transformer substation detection means, described device includes:
Substation configuration description document data bank, for storing transformer station's whole station configuration, forms substation configuration description text Part.
First configuration information extraction unit, extracts in substation configuration description file and is detected matching somebody with somebody for intelligent electronic device Message file is put, standard configuration information is obtained according to the configuration information in configuration information file;
Second configuration information acquiring unit, for obtaining the configuration information of detected intelligent electronic device as the second configuration Information;
Comparing unit:First configuration information and second configuration information are contrasted, comparing result is exported.
It is preferred that, in above-mentioned configuration information of transformer substation detection means, first configuration information includes:Equipment identification information With standard configuration information;
Second configuration information includes:Equipment identification information and actual disposition information.
It is preferred that, in above-mentioned configuration information of transformer substation detection means, the first configuration information extraction unit, including:
Device identification acquiring unit, the equipment identification information for obtaining detected intelligent electronic device;
Configuration information extraction unit, for according to the equipment identification information, being carried by the substation configuration description file Take corresponding intelligent electronic device configuration information block, obtain in the intelligent electronic device configuration information block towards general object Transformer substation case control block, sampled value control block and the empty terminal block of information of input be used as configuration information file.
It is preferred that, above-mentioned configuration information of transformer substation detection means, in addition to:
Object oriented programming model creating unit, extracts in the substation configuration description file and is set with detected smart electronicses Standby related configuration information, and device instantiation configuration file is saved as, the detected intelligent electronic device reads the dress Instantiation configuration file is put, empty terminal, the object oriented programming model in empty loop is set up.
It is preferred that, in above-mentioned configuration information of transformer substation detection means, the comparing unit, including:
Judging unit, for judging whether first configuration information and second configuration information are identical, if it is different, The corresponding equipment identification information of the actual disposition information is obtained, and sends alarm command;
Alarm, for sending alarm signal according to the alarm command, and shows the equipment identification information.
It can be seen from above-mentioned technical scheme that, configuration information of transformer substation detection method disclosed in the present application and device pass through Substation configuration description file containing transformer station's whole station engineering configuration is set, obtained from the substation configuration description file The standard configuration information of intelligent electronic device of detection is needed as the first configuration information, and utilizes MMS service acquisitions intelligence Intelligent electronic device actual disposition information in transformer station is as the second configuration information, by first configuration information and described Two configuration informations are contrasted, and are exported corresponding comparing result, are realized the on-line checking of intelligent electronic device, improve work Efficiency, effectively prevent because configuration information is inconsistent and to the hidden trouble that is brought of safe and reliable operation of intelligent substation, Improve the reliability of power system power supply.
Brief description of the drawings
, below will be to embodiment or existing in order to illustrate more clearly of the embodiment of the present application or technical scheme of the prior art There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, drawings in the following description are only this Some embodiments of application, for those of ordinary skill in the art, on the premise of not paying creative work, can be with Other accompanying drawings are obtained according to these accompanying drawings.
The flow chart for the configuration information of transformer substation detection method that Fig. 1 provides for the present embodiment;
Fig. 2 is the detected IED device configuration informations mapping relations schematic diagram that the present embodiment is set up;
The configuration information of transformer substation structure of the detecting device figure that Fig. 3 provides for the application.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present application, the technical scheme in the embodiment of the present application is carried out clear, complete Site preparation is described, it is clear that described embodiment is only some embodiments of the present application, rather than whole embodiments.It is based on Embodiment in the application, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made Embodiment, belongs to the scope of the application protection.
It is right against and is difficult to ensure that in In-situ FTIR spectra D equipment that actual disposition information is matched somebody with somebody with the standard in SCD file in the prior art The uniformity of confidence breath, so that the safe and reliable operation for the intelligent substation equipment in intelligent substation brings hidden trouble The problem of, this application provides a kind of configuration information of transformer substation detection method.
The flow chart for the configuration information of transformer substation detection method that Fig. 1 provides for the present embodiment.
Referring to Fig. 1, this method includes:
Step S101:According to transformer station's whole station engineering configuration, SCD file is formed;
Step S102:The configuration information file for being detected IED equipment is extracted in SCD file;
Step S103:The first configuration information is obtained according to the configuration information in configuration information file;
The configuration informations such as the empty terminal of each detected IED equipment, empty loop are parsed from SCD file, first is formed and matches somebody with somebody Confidence ceases.
Step S104:The configuration information for obtaining detected IED equipment is used as the second configuration information;
Wherein described step S104 can simultaneously be carried out with the step S102/ steps S103.
MMS server can be provided with by being detected IED equipment, and the MMS server is by transformer station's Ethernet to outside MMS services are provided, the MMS services include but is not limited to the service of reading and report services;By MMS server, from transformer station with Service or report services are read by MMS in netting very much and obtain the configuration informations such as the empty terminal for being detected IED equipment, empty loop online, Form the second configuration information.Wherein using the MMS services in the standards of IEC 61850, loaded very to the additional networks that system is brought It is small, realize lightweight.
The empty terminal arrangement information of described IED uses State Grid Corporation of China's company standard《The works of Q/GDW-396-IEC 61850 Journey relay protection application model》In regulation, be divided into the empty terminal arrangement information of input and the empty terminal arrangement information of output;It is described The empty loop configuration information of IED equipment, refers to the annexation between the empty terminal of IED equipment;The empty terminal arrangement letter of above-mentioned input Cease and described in the INPUTS parts of IED equipment, the empty terminal arrangement information of above-mentioned output IED equipment GOOSE (to general object Transformer substation case) defined in control block and SV control blocks (sampled value control block), above-mentioned INPUTS, GOOSE control block, SV controls Clamp dog is all configuration information block defined in IEC 61850-6 standards.
Step S105:First configuration information and the second configuration information are contrasted and comparing result is exported.
First configuration information and the second configuration information are contrasted, if fruit finds that both are inconsistent, report is sent Alert information.
It can be seen that the technical scheme that the above embodiments of the present application are provided is by setting the SCD configured containing transformer station's whole station engineering File, obtains the standard configuration information for the IED equipment for needing to detect as the first configuration information from the SCD file, and By the use of the IED equipment actual disposition information in MMS service acquisition intelligent substations as the second configuration information, described first is matched somebody with somebody Confidence is ceased and second configuration information is contrasted, and is exported corresponding comparing result, is realized the on-line checking of IED equipment, Operating efficiency is improved, be effectively prevent because configuration information is inconsistent and is brought to the safe and reliable operation of intelligent substation Hidden trouble, improves the reliability of power system power supply.
It is understood that one IED equipment of each configuration information correspondence, so described first in the embodiment of the present application Configuration information can include equipment identification information and standard configuration information, and second configuration information can include device identification letter Breath and actual disposition information.
It is appreciated that step S102 described in above-described embodiment can specifically include:According to detected IED equipment Equipment identification information, corresponding IED device configuration informations block is extracted by the SCD file, the IED configuration information blocks are obtained In GOOSE control blocks, SV control blocks and INPUTS information (the empty terminal of input) block be used as configuration information file.
It is understood that being that the configuration information of that IED equipment has problem, the application in order to point out user Step S105 can include in above-described embodiment:Judge whether first configuration information is identical with second configuration information, If it is different, output equipment identification information and alarm signal.
It is understood that the configuration information in order to obtain the detected IED equipment according to default rule, this Application can also include between the step S101 and the step S102:Object oriented programming model is set up, can be included:By institute State in SCD file and extract and the device-dependent configuration informations of detected IED, and save as CID files;The detected IED is set It is standby to read the CID files, set up empty terminal, the object oriented programming model in empty loop.
Detected IED device configuration informations are specifically extracted from SCD file, CID files are set up, are detected by described IED equipment is according to configuration information ExtRef1, ExtRef2 ... ExtRefn in the INPUTS in the CID files, described It is detected input InRef (reference) example for creating that data type is ORG in the LN0 logical nodes of IED equipment, the InRef Example can be named according to InRef1, InRef2 ... InRefn modes, the empty terminal of each one input of lnRef examples correspondence, this Sample just creates the empty terminal of the detected IED equipment and the object oriented programming model in empty loop in the detected IED equipment, In plant running, communicated according to the object oriented programming model by MMS services with each detected IED equipment.Its Described in LN0 logical nodes, be the special LN nodes of a class defined in IEC 61850-7-2 standards, be detected each of IED LN0 example can only be corresponded in LD (Logical Device, logical device).
As shown in Fig. 2 the detected IED device configuration informations mapping relations set up for the present embodiment.
Including:
Configuration information 201 described in CID files, its descriptor format follows IEC 61850-6 standards;
The object oriented programming model 202 created according to the configuration information in the CID in detected IED equipment, the face The configuration information of measurement equipment is detected into object model 202.
Of course, it should be understood that after the object oriented programming model is set up, the step S105 can include:According to figure Mapping method shown in 2, by the INPUTS information in the first configuration information of detected IED equipment and the second configuration information Object model information is compared item by item.
Corresponding to the above method, present invention also provides a kind of configuration information of transformer substation detection means.
The configuration information of transformer substation structure of the detecting device figure that Fig. 3 provides for the application.
Referring to Fig. 2, described device includes:
SCD file database 1, for storing transformer station's whole station configuration, forms SCD file.
First configuration information extraction unit 2, extracts the configuration information file for being detected IED equipment 0 in SCD file, according to Standard configuration information is obtained according to the configuration information in configuration information file;
Second configuration information acquiring unit 3, matches somebody with somebody confidence for obtaining the configuration information of detected IED equipment 0 as second Breath;
Comparing unit 4:First configuration information and second configuration information are contrasted, comparing result is exported.
Wherein described first configuration information extraction unit, including:
Device identification acquiring unit 201, the equipment identification information for obtaining detected IED equipment;
Configuration information extraction unit 202, for according to the equipment identification information, extracting corresponding by the SCD file IED device configuration information blocks, obtain GOOSE control blocks, SV control blocks and the INPUTS block of informations in the IED configuration information blocks It is used as configuration information file.
It is understood that said apparatus can also include:Object oriented programming model creating unit, for by SCD texts Extracted and the device-dependent configuration informations of detected IED in part, and save as CID files, the detected IED equipment reads institute CID files are stated, empty terminal, the object oriented programming model in empty loop is set up.
The comparing unit 4 can include:Judging unit 401, for judging first configuration information and described second Whether configuration information is identical, if it is different, obtaining the corresponding IED equipment identification informations of the actual disposition information, and sends report Alert instruction;
Alarm 402, for sending alarm signal according to the alarm command, and shows the equipment identification information.
Finally, in addition it is also necessary to explanation, herein, such as first and second or the like relational terms be used merely to by One entity or operation make a distinction with another entity or operation, and not necessarily require or imply these entities or operation Between there is any this actual relation or order.Moreover, term " comprising ", "comprising" or its any other variant meaning Covering including for nonexcludability, so that process, method, article or equipment including a series of key elements not only include that A little key elements, but also other key elements including being not expressly set out, or also include be this process, method, article or The intrinsic key element of equipment.In the absence of more restrictions, the key element limited by sentence "including a ...", is not arranged Except also there is other identical element in the process including the key element, method, article or equipment.
The embodiment of each in this specification is described by the way of progressive, and what each embodiment was stressed is and other Between the difference of embodiment, each embodiment identical similar portion mutually referring to.
The foregoing description of the disclosed embodiments, enables professional and technical personnel in the field to realize or use the application. A variety of modifications to these embodiments will be apparent for those skilled in the art, as defined herein General Principle can in other embodiments be realized in the case where not departing from spirit herein or scope.Therefore, the application The embodiments shown herein is not intended to be limited to, and is to fit to and principles disclosed herein and features of novelty phase one The most wide scope caused.

Claims (6)

1. a kind of configuration information of transformer substation detection method, it is characterised in that methods described includes:
According to transformer station's whole station engineering configuration, substation configuration description file is formed;
The configuration information file for being detected intelligent electronic device is extracted in substation configuration description file;
The first configuration information is obtained according to the configuration information in configuration information file;
The configuration information for being detected intelligent electronic device by the use of MMS service acquisitions is used as the second configuration information;
First configuration information and the second configuration information are contrasted and comparing result is exported;
First configuration information includes:Equipment identification information and standard configuration information;
Second configuration information includes:Equipment identification information and actual disposition information;
The configuration information file of intelligent electronic device is extracted in the file by substation configuration description, including:
According to the equipment identification information for being detected intelligent electronic device, corresponding intelligence is extracted by the substation configuration description file Energy electronic equipment block of information, obtains transformer station's thing towards general object in the intelligent electronic device configuration information block Part control block, sampled value control block and the empty terminal block of information of input are used as configuration information file.
2. configuration information of transformer substation detection method according to claim 1, it is characterised in that by first configuration information Contrasted with the second configuration information and export comparing result, including:
Judge whether first configuration information is identical with second configuration information, if it is different, output equipment identification information And alarm signal.
3. configuration information of transformer substation detection method according to claim 1, it is characterised in that by substation configuration description Extracted in file before being detected the configuration information file of intelligent electronic device, in addition to:
The configuration information related to detected intelligent electronic device is extracted in the substation configuration description file, and is saved as Device instantiates configuration file;
The detected intelligent electronic device reads described device instantiation configuration file, set up empty terminal, empty loop towards Object model.
4. a kind of configuration information of transformer substation detection means, it is characterised in that described device includes:
Substation configuration description document data bank, for storing transformer station's whole station configuration, forms substation configuration description file;
First configuration information extraction unit, detected intelligent electronic device is extracted in substation configuration description file matches somebody with somebody confidence File is ceased, standard configuration information is obtained according to the configuration information in configuration information file;
Second configuration information acquiring unit, for obtaining the configuration information of detected intelligent electronic device as the second configuration information
Comparing unit:First configuration information and second configuration information are contrasted, comparing result is exported;
First configuration information includes:Equipment identification information and standard configuration information;
Second configuration information includes:Equipment identification information and actual disposition information;
The first configuration information extraction unit, including:
Device identification acquiring unit, the equipment identification information for obtaining detected intelligent electronic device;
Configuration information extraction unit, for according to the equipment identification information, phase to be extracted by the substation configuration description file The intelligent electronic device configuration information block answered, obtains the change towards general object in the intelligent electronic device configuration information block Power station event control block, sampled value control block and the empty terminal block of information of input are used as configuration information file.
5. configuration information of transformer substation detection means according to claim 4, it is characterised in that also include:
Object oriented programming model creating unit, is extracted and detected intelligent electronic device phase in the substation configuration description file The configuration information of pass, and device instantiation configuration file is saved as, it is real that the detected intelligent electronic device reads described device Exampleization configuration file, sets up empty terminal, the object oriented programming model in empty loop.
6. configuration information of transformer substation detection means according to claim 5, it is characterised in that the comparing unit, including:
Judging unit, for judging whether first configuration information and second configuration information are identical, if it is different, obtaining The corresponding equipment identification information of the actual disposition information, and send alarm command;
Alarm, for sending alarm signal according to the alarm command, and shows the equipment identification information.
CN201310642196.XA 2013-12-03 2013-12-03 A kind of configuration information of transformer substation detection method and device CN103631921B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310642196.XA CN103631921B (en) 2013-12-03 2013-12-03 A kind of configuration information of transformer substation detection method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310642196.XA CN103631921B (en) 2013-12-03 2013-12-03 A kind of configuration information of transformer substation detection method and device

Publications (2)

Publication Number Publication Date
CN103631921A CN103631921A (en) 2014-03-12
CN103631921B true CN103631921B (en) 2017-11-07

Family

ID=50212962

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310642196.XA CN103631921B (en) 2013-12-03 2013-12-03 A kind of configuration information of transformer substation detection method and device

Country Status (1)

Country Link
CN (1) CN103631921B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104486132A (en) * 2014-12-26 2015-04-01 武汉中元华电科技股份有限公司 Feedback detection method for network topology in electric system
CN104734364B (en) * 2015-04-15 2017-03-01 国家电网公司 The method and system of relay protection device of intelligent substation SV, GOOSE input test
CN105048632B (en) * 2015-07-09 2017-08-25 国网新疆电力公司 The consistency detection system and method for intelligent substation IED configuration informations and SCD file
CN105140810B (en) * 2015-08-13 2017-07-11 国网安徽省电力公司 The soft pressing plate of intelligent substation whole station, which is thrown, moves back status check system and method
CN106815001B (en) * 2015-11-30 2020-03-03 北京国双科技有限公司 Method and device for detecting configuration file information
CN106156373A (en) * 2016-09-09 2016-11-23 黑龙江省电力科学研究院 A kind of intelligent substation SCD file Explore of Unified Management Ideas and system
CN106528722A (en) * 2016-10-26 2017-03-22 南京能云电力科技有限公司 Method and system for consistency testing of equipment data models of intelligent electronic device
CN107578345A (en) * 2017-09-08 2018-01-12 南方电网科学研究院有限责任公司 Power system security detection method, device, storage medium and computer equipment
CN108551394A (en) * 2018-02-09 2018-09-18 国电南瑞科技股份有限公司 A kind of intelligent substation station level device parameter configuration method of calibration
CN109240755A (en) * 2018-06-28 2019-01-18 平安科技(深圳)有限公司 A kind of configuration file comparison method and configuration file Compare System

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101706816A (en) * 2009-12-22 2010-05-12 广东电网公司电力科学研究院 Method for detecting digitized transformer station model

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1976177B1 (en) * 2007-03-30 2014-07-02 ABB Technology AG Substation automation system with increased availability

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101706816A (en) * 2009-12-22 2010-05-12 广东电网公司电力科学研究院 Method for detecting digitized transformer station model

Also Published As

Publication number Publication date
CN103631921A (en) 2014-03-12

Similar Documents

Publication Publication Date Title
Wang et al. Power system transient stability assessment based on big data and the core vector machine
US10833532B2 (en) Method and system for managing a power grid
CN106253486B (en) A kind of power supply system intelligent fault Computer Aided Analysis System
CN102368634B (en) Unified information platform system for state monitoring of intelligent transformer substation
CN103105550B (en) A kind of intelligent relay protection device detection method and system
JP5452613B2 (en) Power grid supply interruption and failure status management
CN101272051B (en) Information system integration method of electric network production control region and management information region
CN103544352B (en) Empty terminal based on SCD file connects graphic method
US8451753B2 (en) Systems and methods for the configuration of substation remote terminals with a central controller
CN102005818B (en) Method for detecting consistency of SCD (System Configuration Document) and IED (Intelligent Electronic Device) model on line
CN104865837A (en) Novel smart home monitoring system based on Internet of things
Zhao et al. Development of an energy monitoring system for large public buildings
CN106019039B (en) Standardize protective relaying device assembly line automatic checkout system and method
CN103972981B (en) A kind of intelligent monitor system of the low-tension switch cabinet based on cloud
CN102142716B (en) Power grid online fault diagnosis method based on three-state data multidimensional cooperative processing
CN100385874C (en) Integrative intelligent system of digitization community
CN104483842B (en) One kind regulation and control one automation main website comparison method
CN104135069B (en) Method for configuring operating parameters of secondary equipment of intelligent substation
CN103441572B (en) Substation equipment method for supervising
CN102222982B (en) Method and device for realizing programmed operation of transformer station based on SVG (Scalable Vector Graphics) technology
CN103200051B (en) Intelligent substation message emulating is tested and is associated message analysis system and method
CN103366311B (en) A kind of Data Fusion method based on transformer station's multisystem
CN106980071B (en) Visual first-aid repair system based on power grid GIS and working method thereof
CN106093652A (en) A kind of non-intrusive electrical load monitoring System and method for possessing self-learning function
CN103823433A (en) Method for realizing relay protection equipment on-line monitoring by use of communication process analysis

Legal Events

Date Code Title Description
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171107

Termination date: 20181203

CF01 Termination of patent right due to non-payment of annual fee