CN103615043A - Surface directly-buried drain pipe assembly bearing large equipment or dynamic load, and construction method thereof - Google Patents

Surface directly-buried drain pipe assembly bearing large equipment or dynamic load, and construction method thereof Download PDF

Info

Publication number
CN103615043A
CN103615043A CN201310544684.7A CN201310544684A CN103615043A CN 103615043 A CN103615043 A CN 103615043A CN 201310544684 A CN201310544684 A CN 201310544684A CN 103615043 A CN103615043 A CN 103615043A
Authority
CN
China
Prior art keywords
pipe
cast iron
steel
wall
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310544684.7A
Other languages
Chinese (zh)
Other versions
CN103615043B (en
Inventor
李学军
张发祥
朱冠生
李长江
魏磊
蒙悟
陈兵章
胥俊德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Original Assignee
Second Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd filed Critical Second Engineering Co Ltd of China Railway 21st Bureau Group Co Ltd
Priority to CN201310544684.7A priority Critical patent/CN103615043B/en
Publication of CN103615043A publication Critical patent/CN103615043A/en
Application granted granted Critical
Publication of CN103615043B publication Critical patent/CN103615043B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Protection Of Pipes Against Damage, Friction, And Corrosion (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to a surface directly-buried drain pipe assembly bearing large equipment or a dynamic load, and a construction method thereof. The directly-buried drain pipe assembly comprises a surface drain, a drain pipe and a tee. The drain pipe comprises a cast iron drain pipe and a steel pipe. The cast iron drain pipe is sleeved with the steel pipe. The inner wall of the steel pipe is provided with an inner anticorrosion layer, and the outer wall of the steel pipe is provided with an outer anticorrosion layer. The inner wall of the cast iron drain pipe is provided with a cast iron internal anticorrosion layer. The tee comprises a cast iron three-way pipe sleeved with a steel three-way pipe. The upper end of a connection, connected with the butt end of the surface drain, of the steel three-way pipe is provided with a circular steel plate. The inner wall of the steel three-way pipe is provided with an inner anticorrosion layer. The outer wall of the steel three-way pipe is provided with an outer anticorrosion layer. The inner wall of the cast iron three-way pipe is provided with a cast iron internal anticorrosion layer. The cast iron pipe is sleeved with the steel pipe, namely in a pipe-in-pipe manner, the steel pipe is mainly functional in bearing pressure and draining a small amount of water, the cast iron pipe is mainly functional in draining water, the advantages of the two pipes are given to full play, and advantages and disadvantages are implemented. Through the application of the surface directly-buried drain pipe assembly bearing large equipment or the dynamic load and the construction method thereof, the problem that a surface dynamic load easily crushes a pipeline is solved effectively.

Description

Direct-burried gutter and the construction method thereof on carrying main equipment or dynamic load ground
Technical field
The invention belongs to room and build water supply and sewage work technical field, be specifically related to a kind of direct-burried gutter that carries main equipment or dynamic load ground, the invention still further relates to the construction method of the direct-burried gutter on carrying main equipment or dynamic load ground.
Background technology
Lanzhou heavy ion medical research center magnet power supply test and debugging central steel structure belongs to industrial premises, because equipment in use can be at land drainage, again because the heavy ion experimental facilities of 30 tons (ground design is 300kpa/m) left and right is installed on ground, and its be as dynamic loading on ground, do draining trench and will increase high cost, consider that in addition dynamic load also should not arrange draining trench to the impact of structure, and open drain more there is considerable influence to equipment Foundations.In the buried cast iron pipe pipeline configuration of the building < < Water and Waste Water Engineering specification > > that China Engineering Construction Standardization Association formulates, clearly state buried iron drain-pipe construction method and be not suitable for the ground that has large load in industrial enterprise, therefore can only be by gutter direct-burried.Due to direct-burried, cast iron pipe is clamp connection on the one hand, once leak, maintenance will be very difficult; In addition dynamic load, the stronger weakness of its fragility of cast iron pipe will be more outstanding.Owing to also not having at present the relevant construction technology can be for reference, so the selection of pipe and construction technology be large technical barriers.
Summary of the invention
The technical problem to be solved in the present invention is to provide carrying main equipment that a kind of simple in structure, long service life, cost are low or the direct-burried drainage system on dynamic load ground; Another technical problem that the present invention will solve is to provide a kind of construction method of carrying the direct-burried gutter on main equipment or dynamic load ground.
It is as follows that the present invention solves the problems of the technologies described above the technical scheme of taking: a kind of direct-burried gutter that carries main equipment or dynamic load ground, comprise floor drain, gutter and threeway, it is characterized in that: gutter comprises iron drain-pipe and steel pipe iron drain-pipe outside suit steel pipe; Steel pipe inner wall is provided with interior anticorrosive coat, and outer wall of steel pipe is provided with external anti-corrosion layer, and iron drain-pipe inwall is provided with anticorrosive coat in cast iron pipe.
Threeway comprises cast iron tee piece, and cast iron tee piece outside is set with steel tee piece, is provided with doughnut-shaped steel plate with the steel tee piece interface upper surface of floor drain butt end; Steel tee piece inwall is provided with interior anticorrosive coat, and steel tee piece outer wall is provided with external anti-corrosion layer; Cast iron tee piece inwall is provided with anticorrosive coat in cast iron pipe.
The present invention carries the direct-burried gutter on main equipment or dynamic load ground, from run into technical barrier analysis, adopts single cast iron pipe or steel pipe obviously all cannot solve this difficulty, if adopt special material cost too high again; So inventor is from using the prerequisite of conventional material, by stack, use two kinds of tubing, adopt steel pipe and cast iron pipe simultaneously, at cast iron pipe outside suit steel pipe, Guan Zhongyou pipe, a small amount of draining of holding concurrently of the main pressure-bearing of steel pipe, cast iron pipe arterial drainage, give full play to the advantage of two kinds of tubing, realize advantage and weakness complementary.
It is as follows that the present invention solves the technical scheme that above-mentioned another technical problem takes: a kind of construction method of carrying the direct-burried gutter on main equipment or dynamic load ground, comprises the steps:
A, channel excavation: cutting depth is 64~74cm below absolute altitude at the bottom of pipeline, at least 1 meter of excavation width, guarantor can be in groove constructing operation; Having dug both sides, Hou Gou slope will have 10% the gradient, prevents slump;
B, be backfilling and compacted: sand horsestone backfill twice for channel bottom, the each 28~35cm of sand horsestone backfill thickness, needs watering after compacting leveling after each backfill, and the water yield is for slightly making sand horsestone surface slightly moistening; Residue 8~10cm is not more than the sand head backfill of 3mm and pours water and roll, tamp with particle diameter; Pipe laying after three~five days; Sand head refer in wall plaster construction, sift out, particle diameter is less than 3mm waste material;
C, making cement buttress: according to conduit slope, calculate in advance the absolute altitude of corresponding buttress, make cement buttress, buttress is fixing to be wanted firmly, and repetition measurement absolute altitude while placing pipeline, to control the gradient well;
D, cast iron pipe pipeline corrosion protection and be connected: cast iron pipe is carried out to interior preservative treatment, and with antirust painting brush twice, the Sudan one time, accomplishes even thickness during brush, can not leak brush; Pipeline connects the zinc-plated clamp connection of employing stainless steel;
E, cast iron pipe water filling test: adopt existing conventional method to pour water to the cast iron pipe after connecting, guarantee that the cast iron pipe after connecting is water-tight;
F, steel pipe corrosion-proof: steel pipe inner wall brushes one times corrosion resistant coating, outer wall of steel pipe brushes one times with pitch, then obtains anti-corrosive steel tube twice with cement mortar brush;
G, pipeline suit: cast iron pipe integral body that do not leak through water filling test, after connecting is coated with anti-corrosive steel tube, obtains suit pipeline; The connected mode of anti-corrosive steel tube is welding;
H, pipeline are installed: suit pipeline is installed to cement buttress, and after installation, outer wall of steel pipe is coated with three oily two felts; Then use again sand head backfill 4cm, then use the backfill of sand horsestone layered rolling, when rolling backfill, add water compacting to the foundation pad absolute altitude of ground.
The way of pipeline foundation of the present invention is compared with common way, and innovation has proposed to roll the way that adds water compacting in compacting, i.e. and " watertight method ", basis, ground is sand horsestone, layering flattens and tamps, and due to intrinsic spacing between the grains of sand, follow-uply may cause foundation settlement.By pouring water, drive on the one hand the tiny grains of sand to fill space, during on the other hand for follow-up vibrating, lubrication is played in grains of sand motion, has reduced greatly the existence in space, has then avoided foundation settlement.
The construction method of the direct-burried gutter on carrying main equipment provided by the invention or dynamic load ground, effectively avoided the adverse effect that direct-buried pipe is leaked and material corrosion phenomenon causes, solved the severe phenomenon that pipeline that ground dynamic load easily causes crushes, with by the method comparison of reinforcing pipes measure, greatly reduce financial cost, and sand head has also obtained the application of maximum function as waste material.For there being the present situation of gutter way on the ground of dynamic load to be improved without industrial premises, filled up in building construction the blank without this way.
As calculated, with respect to the construction method that strengthens trench arrangement of reinforcement and reduce the impact that dynamic load causes, this construction method is reduced expenses more than 30,000 yuan; Save construction cost more than 50%.
Accompanying drawing explanation
Fig. 1 is the surface drainage system schematic diagram of direct-burried gutter of the present invention,
Fig. 2 is A-A sectional drawing of Fig. 1,
Fig. 3 is that a large figure is put in the B portion of Fig. 1,
Fig. 4 is the process chart of construction method of the present invention,
Fig. 5 is the preceding pipeline base state schematic diagram of pouring water,
Fig. 6 is each componental movement schematic diagram of pipeline foundation while rolling of pouring water,
Fig. 7 pours water to roll rear pipeline foundation view.
In figure: 1-floor drain, 2-sand head, 3-sand horsestone, 4-gutter, 5-threeway, 501-cast iron tee piece, 502-steel tee piece, 6-doughnut-shaped steel plate, 7-external anti-corrosion layer, 8-steel pipe, 9-interior anticorrosive coat, 10-iron drain-pipe, anticorrosive coat in 11-cast iron pipe, 12-sand grains movement locus, F-cal rolling active force.
The specific embodiment
Product embodiments is as shown in Figures 1 and 2: a kind of direct-burried gutter that carries main equipment or dynamic load ground, comprise floor drain 1, gutter 4 and threeway 5, and gutter 2 comprises iron drain-pipe 10 and steel pipe 8, iron drain-pipe 10 outsides suit steel pipes 8; Steel pipe 8 inwalls are provided with interior anticorrosive coat 9, and steel pipe 8 outer walls are provided with external anti-corrosion layer 7, and iron drain-pipe 10 inwalls are provided with anticorrosive coat 11 in cast iron pipe.
Referring to Fig. 3: threeway 5 comprises cast iron tee piece 501, and cast iron tee piece 501 outsides are set with steel tee piece 502, is provided with doughnut-shaped steel plate 6 with the steel tee piece interface upper surface of floor drain butt end; Steel tee piece 502 inwalls are provided with interior anticorrosive coat 9, and steel tee piece 502 outer walls are provided with external anti-corrosion layer 7; Cast iron tee piece 501 inwalls are provided with anticorrosive coat 11 in cast iron pipe.
Embodiment of the method 1 is referring to Fig. 4: a kind of construction method of carrying the direct-burried gutter on main equipment or dynamic load ground provided by the invention, comprises the steps:
A, channel excavation: excavation is front according to working drawing unwrapping wire, select the method that mechanical equivalent of light excavation is combined with manual amendment to carry out channel excavation, the following 70cm of cutting depth absolute altitude at the bottom of pipeline, can guarantee that like this backfill layered is at 30~35cm, sand head backfill for remaining space, excavation width is more than 1 meter, and guarantor can construct in groove; Having dug both sides, Hou Gou slope will have 10% the gradient, prevents slump;
B, be backfilling and compacted: during backfill, use the compacting of backfill limit, mechanical limit, sand horsestone backfill twice for channel bottom, each 30 cm of sand horsestone backfill thickness, need slightly watering after compacting leveling after each backfill, and the water yield is for slightly making sand horsestone surface slightly moistening; Residue 8cm is not more than the sand head backfill of 3mm and pours water and roll, tamp with particle diameter; Pipe laying after three days; Sand head be in wall plaster construction, sift out, particle diameter is less than 3mm waste material; Pour water preceding pipeline base state as shown in Figure 5: between the Shi Yushi of sand horsestone 3, Sha Yushi, hole is larger, pour water roll front need to be at the sand head 2 of sand horsestone 3 upper berth 3~5cm; Pour water each componental movement state while rolling as shown in Figure 6: under the effect of cal rolling directed force F, the tiny grains of sand start filling pore, sand head makes up vacancy, sand grains between sand horsestone 3, stone, sand head 2 distribute and move along sand grains movement locus 12, and each component starts to tend towards stability; Each component state of pouring water after rolling is as shown in Figure 7: the tiny grains of sand have been filled hole, and sand head has made up vacancy, and component distributes stable;
C, making cement buttress: according to conduit slope, calculate in advance the absolute altitude of corresponding buttress, make cement buttress;
D, cast iron pipe pipeline corrosion protection and be connected: cast iron pipe is carried out to interior preservative treatment, and with antirust painting brush twice, the Sudan one time, accomplishes even thickness during brush, can not leak brush; Pipeline connects the zinc-plated clamp connection of employing stainless steel;
E, cast iron pipe water filling test: adopt existing conventional method to pour water to the cast iron pipe after connecting, guarantee that the cast iron pipe after connecting is water-tight;
F, steel pipe corrosion-proof: steel pipe inner wall brushes one times corrosion resistant coating, outer wall of steel pipe brushes one times with pitch, then obtains anti-corrosive steel tube twice with cement mortar brush;
G, pipeline suit: cast iron pipe integral body that do not leak through water filling test, after connecting is coated with anti-corrosive steel tube, obtains suit pipeline; The connected mode of anti-corrosive steel tube is welding;
H, pipeline are installed: suit pipeline is installed to cement buttress, and after installation, outer wall of steel pipe is coated with three oily two felts; Then use again sand head backfill 4cm, then use the backfill of sand horsestone layered rolling, when rolling backfill, add water compacting to foundation pad absolute altitude place, ground.
Embodiment of the method 2
The following 75cm of a, cutting depth absolute altitude at the bottom of pipeline, all the other are with embodiment 1;
B, be backfilling and compacted: sand horsestone backfill thickness is 35cm, 30 cm for the second time for the first time; Remaining space 10cm is not more than the sand head backfill of 3mm and pours water and roll, tamp with particle diameter; Pipe laying after five days; All the other are with embodiment 1;
C, making cement buttress: with embodiment 1;
D, cast iron pipe pipeline corrosion protection and be connected same embodiment 1;
E, cast iron pipe water filling test: with embodiment 1;
F, steel pipe corrosion-proof: with embodiment 1;
G, pipeline suit: with embodiment 1;
H, pipeline are installed: with embodiment 1.

Claims (4)

1. a direct-burried gutter that carries main equipment or dynamic load ground, comprises floor drain, gutter and threeway, and its spy is: gutter (2) comprises iron drain-pipe (10) and steel pipe (8), iron drain-pipe (10) outside suit steel pipe (8); Steel pipe (8) inwall is provided with interior anticorrosive coat (9), and steel pipe (8) outer wall is provided with external anti-corrosion layer (7), and iron drain-pipe (10) inwall is provided with anticorrosive coat (11) in cast iron pipe.
2. a kind of direct-burried gutter that carries main equipment or dynamic load ground as claimed in claim 1, its spy is: threeway (5) comprises cast iron tee piece (501), cast iron tee piece (501) outside is set with steel tee piece (502), is provided with doughnut-shaped steel plate (6) with the steel tee piece interface upper surface of floor drain butt end; Steel tee piece (502) inwall is provided with interior anticorrosive coat (9), and steel tee piece (502) outer wall is provided with external anti-corrosion layer (7); Cast iron tee piece (501) inwall is provided with anticorrosive coat (11) in cast iron pipe.
3. a construction method of carrying the direct-burried gutter on main equipment or dynamic load ground, is characterized in that comprising the steps:
A, channel excavation: cutting depth is 64~74cm below absolute altitude at the bottom of pipeline, at least 1 meter of excavation width, guarantor can be in groove constructing operation; Having dug both sides, Hou Gou slope will have 10% the gradient, prevents slump;
B, be backfilling and compacted: sand horsestone backfill twice for channel bottom, the each 28~35cm of sand horsestone backfill thickness, needing watering compacting leveling watering after each backfill, make sand horsestone surface slightly moistening; Residue 8~10cm is not more than the sand head backfill of 3mm and pours water and roll, tamp with particle diameter; Pipe laying after three~five days;
C, making cement buttress: according to conduit slope, calculate in advance the absolute altitude of corresponding buttress, make cement buttress;
D, cast iron pipe pipeline corrosion protection and be connected: cast iron pipe is carried out to interior preservative treatment, and with antirust painting brush twice, the Sudan one time, accomplishes even thickness during brush, can not leak brush; Pipeline connects the zinc-plated clamp connection of employing stainless steel;
E, cast iron pipe water filling test: adopt existing conventional method to pour water to the cast iron pipe after connecting, guarantee that the cast iron pipe after connecting is water-tight;
F, steel pipe corrosion-proof: steel pipe inner wall brushes one times corrosion resistant coating, outer wall of steel pipe brushes one times with pitch, then obtains anti-corrosive steel tube twice with cement mortar brush;
G, pipeline suit: cast iron pipe integral body that do not leak through water filling test, after connecting is coated with anti-corrosive steel tube, obtains suit pipeline; The connected mode of anti-corrosive steel tube is welding;
H, pipeline are installed: suit pipeline is installed to cement buttress, and after installation, outer wall of steel pipe is coated with three oily two felts; Then use again sand head backfill 4cm, then use the backfill of sand horsestone layered rolling, when rolling backfill, add water compacting to foundation pad absolute altitude place, ground.
4. a kind of construction method of carrying the direct-burried gutter on main equipment or dynamic load ground as claimed in claim 3, it is characterized in that sand head described in step b refer in wall plaster construction, sift out, particle diameter is less than 3mm waste material.
CN201310544684.7A 2013-11-06 2013-11-06 Direct-burried drainpipe and the construction method thereof on carrying main equipment or dynamic load ground Active CN103615043B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310544684.7A CN103615043B (en) 2013-11-06 2013-11-06 Direct-burried drainpipe and the construction method thereof on carrying main equipment or dynamic load ground

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310544684.7A CN103615043B (en) 2013-11-06 2013-11-06 Direct-burried drainpipe and the construction method thereof on carrying main equipment or dynamic load ground

Publications (2)

Publication Number Publication Date
CN103615043A true CN103615043A (en) 2014-03-05
CN103615043B CN103615043B (en) 2016-05-25

Family

ID=50165758

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310544684.7A Active CN103615043B (en) 2013-11-06 2013-11-06 Direct-burried drainpipe and the construction method thereof on carrying main equipment or dynamic load ground

Country Status (1)

Country Link
CN (1) CN103615043B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104405027A (en) * 2014-11-05 2015-03-11 扬州大学 Rain sewage diversion reforming system for old residential area
CN107606306A (en) * 2017-09-18 2018-01-19 金丹 Road rain water pipeline construction method
CN113836763A (en) * 2021-09-02 2021-12-24 中国石化工程建设有限公司 Self-balancing system and verification method for buried pressure-bearing large-diameter socket connecting pipeline

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0184743A2 (en) * 1984-12-12 1986-06-18 MENGERING Sanitär-Haustechnik GmbH Device for sealed connection of two smooth cylindrical pipe ends
CN2431459Y (en) * 1999-12-03 2001-05-23 陶英树 Synthetic pipe
CN1904456A (en) * 2005-07-25 2007-01-31 李寿山 Anti corrosion pressure resistant pipe material
CN101205751A (en) * 2007-12-04 2008-06-25 张发亮 Construction method of roof anti-leak protection layer
CN201605650U (en) * 2010-03-06 2010-10-13 吉林新源牧业有限公司 Waste water discharge device used for food production workshop
CN102182866A (en) * 2011-03-25 2011-09-14 浙江省火电建设公司 Backfilling process for large ultra-deep circulating water pipe
CN202228806U (en) * 2011-08-29 2012-05-23 成都智利达科技有限公司 Double compression resistant composite tube
CN202418944U (en) * 2012-01-19 2012-09-05 莱芜市凤凰新能源科技集团有限公司 Double-layer flow dividing pipe
CN102936886A (en) * 2012-11-30 2013-02-20 中水北方勘测设计研究有限责任公司 Embedded fixing structure for diversion steel penstock of hydropower station
CN203594092U (en) * 2013-11-06 2014-05-14 中铁二十一局集团第二工程有限公司 Directly buried drainage pipe bearing large equipment or movable load ground

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0184743A2 (en) * 1984-12-12 1986-06-18 MENGERING Sanitär-Haustechnik GmbH Device for sealed connection of two smooth cylindrical pipe ends
CN2431459Y (en) * 1999-12-03 2001-05-23 陶英树 Synthetic pipe
CN1904456A (en) * 2005-07-25 2007-01-31 李寿山 Anti corrosion pressure resistant pipe material
CN101205751A (en) * 2007-12-04 2008-06-25 张发亮 Construction method of roof anti-leak protection layer
CN201605650U (en) * 2010-03-06 2010-10-13 吉林新源牧业有限公司 Waste water discharge device used for food production workshop
CN102182866A (en) * 2011-03-25 2011-09-14 浙江省火电建设公司 Backfilling process for large ultra-deep circulating water pipe
CN202228806U (en) * 2011-08-29 2012-05-23 成都智利达科技有限公司 Double compression resistant composite tube
CN202418944U (en) * 2012-01-19 2012-09-05 莱芜市凤凰新能源科技集团有限公司 Double-layer flow dividing pipe
CN102936886A (en) * 2012-11-30 2013-02-20 中水北方勘测设计研究有限责任公司 Embedded fixing structure for diversion steel penstock of hydropower station
CN203594092U (en) * 2013-11-06 2014-05-14 中铁二十一局集团第二工程有限公司 Directly buried drainage pipe bearing large equipment or movable load ground

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
冯光仁: "浅谈排水管道主要的施工方法", 《水利工程》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104405027A (en) * 2014-11-05 2015-03-11 扬州大学 Rain sewage diversion reforming system for old residential area
CN107606306A (en) * 2017-09-18 2018-01-19 金丹 Road rain water pipeline construction method
CN107606306B (en) * 2017-09-18 2019-07-12 金丹 Construction method of road rainwater pipeline
CN113836763A (en) * 2021-09-02 2021-12-24 中国石化工程建设有限公司 Self-balancing system and verification method for buried pressure-bearing large-diameter socket connecting pipeline
CN113836763B (en) * 2021-09-02 2024-08-16 中国石化工程建设有限公司 Self-balancing system and verification method for buried pressure-bearing large-diameter socket connection pipeline

Also Published As

Publication number Publication date
CN103615043B (en) 2016-05-25

Similar Documents

Publication Publication Date Title
CN101435198B (en) Deep pit support reinforcing anti-seepage water stop composite structure
CN103526770B (en) A kind of construction method of high antiseepage anti-floating pile raft structure
CN103074891B (en) Double-layer plastic sleeve bulk material and concrete stiffness core composite pile and construction method thereof
CN101936032A (en) Method for mounting and constructing polyethylene double-wall corrugated water discharge pipe
CN104264688A (en) Manual hole digging non-uniform pile support construction technology
CN103669374A (en) Combined supporting construction method of steel sheet pile used in silt soil slope
CN113373962B (en) Combined leakage stoppage construction method for deep foundation pit
CN105089081A (en) Anti-floating anchor rod construction method
CN100510281C (en) Semi-inverted construction method for storage tanks with super large diameter and super buried depth
CN107100179B (en) Light combined retaining structure and method for treating large-range high-fill slope engineering
CN206467695U (en) A kind of joint for sinking type empty stomach diaphram wall
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN101575859B (en) Anti-seepage Joint of Underground Diaphragm Wall and Its Construction Method
CN107700521B (en) A building foundation reinforcement underpinning pier and its construction method
CN201538975U (en) Underground Diaphragm Wall Anti-seepage Joint
CN103615043B (en) Direct-burried drainpipe and the construction method thereof on carrying main equipment or dynamic load ground
CN112038980A (en) Direct-buried cable laying method
CN203594092U (en) Directly buried drainage pipe bearing large equipment or movable load ground
CN206529795U (en) A kind of municipal comprehensive pipeline passage of assembled
CN212641685U (en) Underground garage drainage open ditch and blind ditch combine antiseep system
CN109235439B (en) A pressure-maintaining pouring method for outsourcing large-volume concrete below the waistline of a volute of a hydropower project
CN107152034A (en) A kind of pipe gallery and its construction method
CN105673933A (en) Waterproof sealing device for post-through-wall pipeline and construction method
CN204080861U (en) Inspection-pit between a kind of Novel top pipeline section
CN116290076A (en) Pipe gallery and construction method using permanent support and basement exterior wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant