CN103600185A - Temporary construction platform for high-altitude welding of steel structure - Google Patents

Temporary construction platform for high-altitude welding of steel structure Download PDF

Info

Publication number
CN103600185A
CN103600185A CN201310530866.9A CN201310530866A CN103600185A CN 103600185 A CN103600185 A CN 103600185A CN 201310530866 A CN201310530866 A CN 201310530866A CN 103600185 A CN103600185 A CN 103600185A
Authority
CN
China
Prior art keywords
clamping bar
construction platform
temporary construction
lower clamping
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310530866.9A
Other languages
Chinese (zh)
Other versions
CN103600185B (en
Inventor
高雷雷
刘明路
罗建
王志福
王馥琴
贾文彬
徐宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
MCC Tiangong Group Corp Ltd
CMTCC Shanghai Shisanye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Tiangong Group Corp Ltd, CMTCC Shanghai Shisanye Construction Co Ltd filed Critical MCC Tiangong Group Corp Ltd
Priority to CN201310530866.9A priority Critical patent/CN103600185B/en
Publication of CN103600185A publication Critical patent/CN103600185A/en
Application granted granted Critical
Publication of CN103600185B publication Critical patent/CN103600185B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B23MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
    • B23KSOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
    • B23K37/00Auxiliary devices or processes, not specially adapted for a procedure covered by only one of the other main groups of this subclass
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B25HAND TOOLS; PORTABLE POWER-DRIVEN TOOLS; MANIPULATORS
    • B25HWORKSHOP EQUIPMENT, e.g. FOR MARKING-OUT WORK; STORAGE MEANS FOR WORKSHOPS
    • B25H5/00Tool, instrument or work supports or storage means used in association with vehicles; Workers' supports, e.g. mechanics' creepers
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Optics & Photonics (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention relates to a temporary construction platform for high-altitude welding of a steel structure. The temporary construction platform comprises rods, a plurality of vertical columns (4), safety ropes (5) and bolts, an upper clamping rod (1) penetrates the upper surface of a lower flange of a steel beam and is fixedly connected with a lower clamping rod (2) correspondingly positioned on the lower surface of the lower flange of the steel beam, cross rods (3) are vertically and crossly fixed to two ends of the lower surface of the lower clamping rod (2) respectively, floor plates (6) are mounted on a frame formed by the lower clamping rod (2) and the cross rods (3), the vertical columns (4) are equidistantly mounted along the lower clamping rod (2), the upper clamping rod (1) and the cross rods (3), and one safety rope (5) is connected between every two adjacent vertical columns (4). The temporary construction platform overcomes the shortcomings that an existing high-altitude welding platform cannot be disassembled or repeatedly used, the bolts of the bidirectional clamping rods can be adjusted according to the size of the lower flange of the welded steel beam, welding requirements of steel beams with different sections are met, and the temporary construction platform is reasonable in structure, convenient to operate, high in practicability and suitable for popularization and application, and can be repeatedly used.

Description

A kind of temporary construction platform for steel structural overhead welding
Technical field
The invention belongs to field of engineering technology, particularly relate to a kind of temporary construction platform for steel structural overhead welding.
Background technology
The middle and later periods nineties 20th century, along with continuing to bring out of China's skyscraper, the high level of disjunctor moulding and high-rise building also obtain certain development.For different version, construction technology, there is more practical technology measure.For the installation method of large span or spatial steel structure, meeting under the prerequisite of the key elements such as quality, safety, progress especially, in conjunction with construction, in work high above the ground environment, for workmen provides, job platform is most important safely and effectively.The present invention has overcome the defect that traditional operation platform is non-dismountable, can not reuse, and can, according to the sectional dimension of installation component, upper and lower clamping bar be adjusted, to meet job requirements.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of temporary construction platform for steel structural overhead welding, to solve the defect that platform in prior art is non-dismountable, can not reuse.
The technical solution adopted for the present invention to solve the technical problems is: a kind of temporary construction platform for steel structural overhead welding is provided, comprise clamping bar, lower clamping bar, cross bar, column, safety rope, bed board, puller bolt, hold-down bolt, shearing bolt, described upper clamping bar through above girder steel lower flange and the corresponding lower clamping bar being positioned at below girder steel lower flange by puller bolt and hold-down bolt, be fixedly connected, below lower clamping bar two ends respectively square crossing be fixed with cross bar, on the framework of lower clamping bar and cross bar formation, bed board is installed, along lower clamping bar, upper clamping bar and cross bar are equidistantly provided with some columns, between adjacent upright posts, be connected with safety rope.
Described girder steel is i-shape steel beam.
Below described lower clamping bar, two ends are fixed with cross bar by shearing bolt square crossing respectively.
On the framework that described lower clamping bar and cross bar form, by tied silk, be installed with bed board.
Described upper clamping bar, lower clamping bar and cross bar are angle steel.
Described column is pipe.
Described safety rope is steel wire rope.
Beneficial effect
The present invention has overcome the defect that temporary platform in prior art is non-dismountable, can not reuse, can be when installing the concrete section form of member, the gap between upper and lower clamping bar is adjusted, guaranteed carrying out smoothly of overhead welding.Apparatus structure is reasonable, easy to operate, practical, is applicable to applying.
Accompanying drawing explanation
Fig. 1 is schematic diagram of the present invention.
Fig. 2 is A-A cutaway view of the present invention.
Fig. 3 is B-B cutaway view of the present invention.
The specific embodiment
Below in conjunction with specific embodiment, further set forth the present invention.Should be understood that these embodiment are only not used in and limit the scope of the invention for the present invention is described.In addition should be understood that those skilled in the art can make various changes or modifications the present invention after having read the content of the present invention's instruction, these equivalent form of values fall within the application's appended claims limited range equally.
Embodiment 1
As shown in FIG. 1 to 3, a kind of temporary construction platform for steel structural overhead welding, comprise clamping bar 1, lower clamping bar 2, cross bar 3, column 4, safety rope 5, bed board 6, puller bolt 7, hold-down bolt 8, shearing bolt 9, described upper clamping bar 1 through above girder steel lower flange and the corresponding lower clamping bar 2 being positioned at below girder steel lower flange by puller bolt 7 and hold-down bolt 8, be fixedly connected, lower clamping bar 2 below two ends respectively square crossing be fixed with cross bar 3, on the framework of lower clamping bar 2 and cross bar 3 formation, bed board 6 is installed, along lower clamping bar 2, upper clamping bar 1 and cross bar 3 are equidistantly provided with some columns 4, between adjacent upright posts 4, be connected with safety rope 5.
Described girder steel is i-shape steel beam.
Described lower clamping bar 2 is fixed with cross bar 3 by shearing bolt 9 square crossings respectively in two ends below.
On the framework that described lower clamping bar 2 and cross bar 3 form, by tied silk, be installed with bed board 6.
Described upper clamping bar 1, lower clamping bar 2 and cross bar 3 are angle steel.
Described column 4 is pipe.
Described safety rope 5 is steel wire rope.
In the invention process, according to the following step, carry out:
1) at upper 1 circular hole and the 1 platoon leader's circular hole opened;
2) upper clamping bar 1 and lower clamping bar 2 are stuck on pre-installation member lower flange, adjust puller bolt 7 and hold-down bolt 8, to guarantee that between two groups of clamping bars, distance is adjustable;
3) cross bar 3 is installed between two groups of clamping bars by shearing bolt 9;
4) column 4 is installed on upper clamping bar 1, lower clamping bar 2 and cross bar 3;
5) column 4 use safety ropes 5 are connected;
6) by bed board 6 colligations on lower clamping bar 2.
Above construction procedure is simple, can complete fast assembling at Steel Structure Installation scene, after platform forms, just can carry out weld job.The present invention is convenient and practical, be easy to grasp, and is widely used in high-altitude steel structure weld job.

Claims (7)

1. the temporary construction platform for steel structural overhead welding, comprise clamping bar (1), lower clamping bar (2), cross bar (3), column (4), safety rope (5), bed board (6), puller bolt (7), hold-down bolt (8), shearing bolt (9), it is characterized in that: described upper clamping bar (1) through above girder steel lower flange and the corresponding lower clamping bar (2) being positioned at below girder steel lower flange by puller bolt (7) and hold-down bolt (8), be fixedly connected, lower clamping bar (2) below two ends respectively square crossing be fixed with cross bar (3), on the framework of lower clamping bar (2) and cross bar (3) formation, bed board (6) is installed, along lower clamping bar (2), upper clamping bar (1) and cross bar (3) are equidistantly provided with some columns (4), between adjacent upright posts (4), be connected with safety rope (5).
2. a kind of temporary construction platform for steel structural overhead welding according to claim 1, is characterized in that: described girder steel is i-shape steel beam.
3. a kind of temporary construction platform for steel structural overhead welding according to claim 1, is characterized in that: described lower clamping bar (2) below two ends is fixed with cross bar (3) by shearing bolt (9) square crossing respectively.
4. a kind of temporary construction platform for steel structural overhead welding according to claim 1, is characterized in that: on the framework that described lower clamping bar (2) and cross bar (3) form, by tied silk, be installed with bed board (6).
5. a kind of temporary construction platform for steel structural overhead welding according to claim 1, is characterized in that: described upper clamping bar (1), lower clamping bar (2) and cross bar (3) are angle steel.
6. a kind of temporary construction platform for steel structural overhead welding according to claim 1, is characterized in that: described column (4) is pipe.
7. a kind of temporary construction platform for steel structural overhead welding according to claim 1, is characterized in that: described safety rope (5) is steel wire rope.
CN201310530866.9A 2013-10-30 2013-10-30 Temporary construction platform for high-altitude welding of steel structure Active CN103600185B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310530866.9A CN103600185B (en) 2013-10-30 2013-10-30 Temporary construction platform for high-altitude welding of steel structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310530866.9A CN103600185B (en) 2013-10-30 2013-10-30 Temporary construction platform for high-altitude welding of steel structure

Publications (2)

Publication Number Publication Date
CN103600185A true CN103600185A (en) 2014-02-26
CN103600185B CN103600185B (en) 2015-06-24

Family

ID=50118481

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310530866.9A Active CN103600185B (en) 2013-10-30 2013-10-30 Temporary construction platform for high-altitude welding of steel structure

Country Status (1)

Country Link
CN (1) CN103600185B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118407514A (en) * 2024-07-02 2024-07-30 中铁城建集团第一工程有限公司 Steel beam and installation method thereof

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2898184Y (en) * 2006-05-25 2007-05-09 上海振华港口机械(集团)股份有限公司 Easily-installed and detachable temporary platform
CN101025045A (en) * 2006-02-22 2007-08-29 香港理工大学 Quick Detachable Platform
CN201268938Y (en) * 2008-09-05 2009-07-08 高智鹏 Corner hanging cradle for working aloft
CN202416823U (en) * 2011-12-22 2012-09-05 上海宝钢化工有限公司 Aerial work platform
CN202509754U (en) * 2012-04-18 2012-10-31 中建二局第三建筑工程有限公司 High-altitude steel structure node construction working platform
CN202559701U (en) * 2012-05-11 2012-11-28 中建新疆建工(集团)有限公司 Operating platform for installing roof trusses and steel structural beams
CN202745352U (en) * 2012-05-24 2013-02-20 浙江精工钢结构有限公司 Combined-type high-altitude operation platform easy for assembly and disassembly
CN102966235A (en) * 2012-11-09 2013-03-13 南通华凯重工有限公司 Carrying tool
CN202829511U (en) * 2012-09-27 2013-03-27 徐州天地重型机械制造有限公司 Overload-proof working platform of hydraulic aerial cage
CN103086162A (en) * 2011-10-28 2013-05-08 五冶集团上海有限公司 Temporary online transportation platform supporting structure and using method thereof

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101025045A (en) * 2006-02-22 2007-08-29 香港理工大学 Quick Detachable Platform
CN2898184Y (en) * 2006-05-25 2007-05-09 上海振华港口机械(集团)股份有限公司 Easily-installed and detachable temporary platform
CN201268938Y (en) * 2008-09-05 2009-07-08 高智鹏 Corner hanging cradle for working aloft
CN103086162A (en) * 2011-10-28 2013-05-08 五冶集团上海有限公司 Temporary online transportation platform supporting structure and using method thereof
CN202416823U (en) * 2011-12-22 2012-09-05 上海宝钢化工有限公司 Aerial work platform
CN202509754U (en) * 2012-04-18 2012-10-31 中建二局第三建筑工程有限公司 High-altitude steel structure node construction working platform
CN202559701U (en) * 2012-05-11 2012-11-28 中建新疆建工(集团)有限公司 Operating platform for installing roof trusses and steel structural beams
CN202745352U (en) * 2012-05-24 2013-02-20 浙江精工钢结构有限公司 Combined-type high-altitude operation platform easy for assembly and disassembly
CN202829511U (en) * 2012-09-27 2013-03-27 徐州天地重型机械制造有限公司 Overload-proof working platform of hydraulic aerial cage
CN102966235A (en) * 2012-11-09 2013-03-13 南通华凯重工有限公司 Carrying tool

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118407514A (en) * 2024-07-02 2024-07-30 中铁城建集团第一工程有限公司 Steel beam and installation method thereof

Also Published As

Publication number Publication date
CN103600185B (en) 2015-06-24

Similar Documents

Publication Publication Date Title
CN106939707B (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN104358207A (en) Rapid steel trestle construction structure and construction method
CN208122371U (en) On across the high-speed rail safe guarding shed fast dismounting device of operation line
CN203756015U (en) Aerial work platform for power transmission iron tower
CN206873307U (en) Movable type bridge justifies pier stud work high above the ground operating platform
CN208009863U (en) A kind of tool-type pier stud construction operation platform device
CN103334584B (en) Template regulating system for sliding form system
CN103600185B (en) Temporary construction platform for high-altitude welding of steel structure
CN103147401B (en) Construction method of self-climbing portal frame
CN204662929U (en) A kind of cross-line walking fence operation device
CN211689948U (en) A suspension operation platform device for the construction of a cable-stayed bridge tower
CN205857026U (en) A kind of movable type bridge anticollision barrier construction operation chassis
CN205575534U (en) Lattice formula groined type support body lifting means
CN208618838U (en) A kind of safety device
CN102587649A (en) Template profiled bar supporting system of high and large cantilever structure
CN211818054U (en) Fixing structure of safety protection device for cast-in-place part on periphery of assembly type shear wall
CN209703977U (en) Steel structure column overhead connection operating platform
CN211285306U (en) A bridge hanging basket front upper operating platform
CN209323390U (en) Absolute altitude iron box beam catenary mast and the bracing wire pre-cast bolt positioning device that casts anchor
CN212176590U (en) Outer frame safety protection structure is exempted from to assembled building
CN209874434U (en) Simple and easy scaffold frame of encorbelmenting of building high latitude
CN210713741U (en) Overhanging type scaffold structure
CN203361596U (en) Auxiliary support of integrated lifting operation platform
CN102277999A (en) Large-section portal steel structure holding pole
CN208604976U (en) A kind of mould plate supporting device of hanging concrete straining beam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Co-patentee after: MCC TIANGONG GROUP Corp.,Ltd.

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Co-patentee before: MCC TIANGONG GROUP Corp.,Ltd.

Patentee before: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address after: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Co-patentee after: MCC TIANGONG GROUP Corp.,Ltd.

Patentee after: SHANGHAI MCC13 CONSTRUCTION Co.,Ltd.

Address before: 201999 room A, room 1325, Mudanjiang Road, Shanghai, Baoshan District, 403

Co-patentee before: MCC TIANGONG GROUP Corp.,Ltd.

Patentee before: CMTCC Shanghai 13th Construction Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190701

Address after: Room A, Room 403, 1325 Mudanjiang Road, Baoshan District, Shanghai, 20199

Co-patentee after: CHINA MCC20 GROUP Corp.,Ltd.

Patentee after: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.

Address before: Room A, Room 403, 1325 Mudanjiang Road, Baoshan District, Shanghai, 20199

Co-patentee before: MCC TIANGONG GROUP Corp.,Ltd.

Patentee before: SHANGHAI ERSHIYE CONSTRUCTION Co.,Ltd.