CN103573274B - 软土地基盾构隧道沉降控制钢套管注浆加固装置 - Google Patents

软土地基盾构隧道沉降控制钢套管注浆加固装置 Download PDF

Info

Publication number
CN103573274B
CN103573274B CN201310554187.5A CN201310554187A CN103573274B CN 103573274 B CN103573274 B CN 103573274B CN 201310554187 A CN201310554187 A CN 201310554187A CN 103573274 B CN103573274 B CN 103573274B
Authority
CN
China
Prior art keywords
grouting
shield tunnel
steel casing
steel
casing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310554187.5A
Other languages
English (en)
Other versions
CN103573274A (zh
Inventor
陈仁朋
尹鑫晟
李忠超
孟凡衍
冯建波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University ZJU
Original Assignee
Zhejiang University ZJU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University ZJU filed Critical Zhejiang University ZJU
Priority to CN201310554187.5A priority Critical patent/CN103573274B/zh
Publication of CN103573274A publication Critical patent/CN103573274A/zh
Application granted granted Critical
Publication of CN103573274B publication Critical patent/CN103573274B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种软土地基盾构隧道沉降控制钢套管注浆加固装置。将盾构隧道管片埋于土内,注浆设备放在盾构隧道管片内,由多个TAM单元串接成的钢套管的一端垂直埋设在土内,所述钢套管底端安装有桩尖,钢套管的上端穿过盾构隧道管片上的注浆孔与连接件连接,连接件固定在盾构隧道管片内壁上;注浆管的一端与注浆设备连接,注浆管的另一端插入所述钢套管内。本发明通过盾构隧道管片上的注浆孔将钢管套压入隧道下的土体,并利用钢管套上的TAM可以在任意埋深向周围土体进行注浆,进而在钢管套周边形成注浆区,此时钢管套与注浆区可以共同视为一个微型桩,通过连接件与隧道管片连接,达到加固盾构隧道,控制隧道管片沉降的目的。

Description

软土地基盾构隧道沉降控制钢套管注浆加固装置
技术领域
本发明涉及一种盾构隧道的加固装置,尤其是涉及一种软土地基盾构隧道沉降控制钢套管注浆加固装置。
背景技术
对于饱和软弱粘土中的隧道,由于隧道底部土体反力总是小于未修建隧道前该处土层自重应力,隧道下土层压缩模量比修建隧前有所降低,加之隧道下受扰动土层的长期次固结在地表加载时仍在缓慢继续,因此长期沉降的发展往往不可忽视。在上海、杭州等地建成的地铁隧道运营到目前均发生了较大的累积沉降和不均匀沉降,影响到了隧道的正常使用和安全运营。因此找到一种能够有效控制地铁隧道长期沉降的施工方法非常有必要。
目前,国内一些地铁施工单位提出了一些控制隧道长期沉降的方法,比如采用注浆改善下卧地层的特性来控制隧道的变形。这种注浆方法需要的注浆范围较大,注浆深度有限,注浆压力不易控制,经济性有待改善。因此需要能够发明找出一种更经济有效的方法来控制地铁隧道的长期沉降。
发明内容
本发明的目的在于提供一种软土地基盾构隧道沉降控制钢套管注浆加固装置,通过在盾构隧道管片下建设微型桩来控制隧道长期沉降。
本发明采用的技术方案如下:
本发明包括盾构隧道管片,连接件,由多个TAM单元串接成的钢套管,桩尖,注浆管,注浆设备;盾构隧道管片埋于土内,注浆设备放在盾构隧道管片内,由多个TAM单元串接成的钢套管的一端垂直埋设在土内,所述钢套管底端安装有桩尖,钢套管的上端穿过盾构隧道管片上的注浆孔与连接件连接,连接件固定在盾构隧道管片内壁上;注浆管的一端与注浆设备连接,注浆管的另一端插入所述钢套管内。
所述多个TAM单元串接成的钢套管,每个TAM单元结构相同,均包括一段钢套管和环形橡胶膜,一段钢套管中部套有环形橡胶膜,在套有环形橡胶膜的钢套管的同一个截面上等分开有四个出浆孔,四个出浆孔对应的环形橡胶膜上分别开有V形裂缝。
所述插入所述钢套管内的另一端注浆管上分别串接两个膨胀式止浆塞,两个膨胀式止浆塞间的注浆管的同一个截面上等分开有四个出浆开口。
本发明具有的有益效果是:
本发明通过盾构隧道管片上的注浆孔将钢管套压入隧道下的土体,并利用钢管套上的TAM可以在任意埋深向周围土体进行注浆,进而在钢管套周边形成注浆区,此时钢管套与注浆区可以共同视为一个微型桩,通过连接件与隧道管片连接,达到加固盾构隧道,控制隧道管片沉降的目的。
附图说明
图1是加固设施结构原理示意图。
图2是图1的TAM和注浆管注浆部分的结构示意图。
图中:1、盾构隧道管片,2、连接件,3、多个TAM单元串接成的钢套管,4-12、环形橡胶膜,13、注浆区,14、注浆孔,15、土,16、注浆设备,17、注浆管,18、膨胀式止浆塞,19、出浆孔,20、出浆开口,21、V形裂缝,22、桩尖。
具体实施方式
下面结合附图和实施例对本发明作进一步说明。
如图1、图2所示,本发明包括盾构隧道管片1,连接件2,由多个TAM单元串接成的钢套管3,桩尖22,注浆管17,注浆设备16;盾构隧道管片1埋于土15内,注浆设备16放在盾构隧道管片1内,由多个TAM单元串接成的钢套管3的一端垂直埋设在土15内,所述钢套管3底端安装有桩尖22,钢套管3的上端穿过盾构隧道管片1上的注浆孔14与连接件2连接,连接件2固定在盾构隧道管片1内壁上;注浆管17的一端与注浆设备16连接,注浆管17的另一端插入所述钢套管3内。
多个TAM单元串接成的钢套管3,每个TAM单元结构相同,均包括一段钢套管和环形橡胶膜,一段钢套管中部套有环形橡胶膜,在套有环形橡胶膜的钢套管的同一个截面上等分开有四个出浆孔,四个出浆孔19对应的环形橡胶膜上分别开有V形裂缝21。如图1中由六段钢套管用螺纹串接而成,六段钢套管外分别套有环形橡胶膜4、5、6、7、8、9、10、11和12。出浆孔19在钢套管3上,每个出浆孔19附近的环形橡胶膜4-12上均有1个V形裂缝21时浆液能在压力作用下流向土体,并不会倒流进钢套管3内。
所述插入所述钢套管3内的另一端注浆管17上分别串接两个膨胀式止浆塞18,两个膨胀式止浆塞18间的注浆管17的同一个截面上等分开有四个出浆开口20,用以膨胀后限制浆液的流动方向,并在TAM附近形成高压区。
本发明的工作过程如下:
在地铁隧道沉降较大处的盾构隧道管片1注浆孔14上实施本发明,施工时,先通过电动锤击碎注浆孔14的混凝土;之后将连接件2安装在注浆孔14上并与盾构隧道管片1固定,然后将多个TAM单元串接成的钢套管3预定位置,并将多个TAM单元串接成的钢套管3与连接件2固定;准备好注浆设备16、注浆管17和浆液,将注浆管放入多个TAM单元串接成的钢套管3,先在多个TAM单元串接成的钢套管3最底部的TAM处,打开2个膨胀式止浆塞18,从四个出浆开口20开始注浆,当浆液压力大于一定值后会撑开环形橡胶膜上的V形裂缝21,涌向钢套管附近周边土体15形成注浆区13,之后关闭膨胀式止浆塞18;然后,由下向上提高注浆管17,逐一在其他TAM处,打开2个膨胀式止浆塞18,并进行注浆;注浆时要求相邻的两个TAM的注浆区13相互搭接,最后在多个TAM单元串接成的钢套管3内注浆,最终形成如图1所示的桩;待注浆完成后撤出注浆管17,并用快干水泥封堵注浆孔14。

Claims (2)

1.一种软土地基盾构隧道沉降控制钢套管注浆加固装置,其特征在于:包括盾构隧道管片(1),连接件(2),由多个TAM单元串接成的钢套管(3),桩尖(22),注浆管(17),注浆设备(16);盾构隧道管片(1)埋于土(15)内,注浆设备(16)放在盾构隧道管片(1)内,由多个TAM单元串接成的钢套管(3)的一端垂直埋设在土(15)内,所述钢套管(3)底端安装有桩尖(22),钢套管(3)的上端穿过盾构隧道管片(1)上的注浆孔(14)与连接件(2)连接,连接件(2)固定在盾构隧道管片(1)内壁上;注浆管(17)的一端与注浆设备(16)连接,注浆管(17)的另一端插入所述钢套管(3)内,注浆完成后,此时,钢管套(3)与注浆区共同形成一个微型桩;
所述多个TAM单元串接成的钢套管(3),每个TAM单元结构相同,均包括一段钢套管和环形橡胶膜,一段钢套管中部套有环形橡胶膜,在套有环形橡胶膜的钢套管的同一个截面上等分开有四个出浆孔,四个出浆孔对应的环形橡胶膜上分别开有V形裂缝(21)。
2.根据权利要求1所述的一种软土地基盾构隧道沉降控制钢套管注浆加固装置,其特征在于:所述插入所述钢套管(3)内的另一端注浆管(17)上分别串接两个膨胀式止浆塞(18),两个膨胀式止浆塞(18)间的注浆管(17)的同一个截面上等分开有四个出浆开口。
CN201310554187.5A 2013-11-11 2013-11-11 软土地基盾构隧道沉降控制钢套管注浆加固装置 Expired - Fee Related CN103573274B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310554187.5A CN103573274B (zh) 2013-11-11 2013-11-11 软土地基盾构隧道沉降控制钢套管注浆加固装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310554187.5A CN103573274B (zh) 2013-11-11 2013-11-11 软土地基盾构隧道沉降控制钢套管注浆加固装置

Publications (2)

Publication Number Publication Date
CN103573274A CN103573274A (zh) 2014-02-12
CN103573274B true CN103573274B (zh) 2016-01-20

Family

ID=50045915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310554187.5A Expired - Fee Related CN103573274B (zh) 2013-11-11 2013-11-11 软土地基盾构隧道沉降控制钢套管注浆加固装置

Country Status (1)

Country Link
CN (1) CN103573274B (zh)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018856B (zh) * 2014-06-27 2015-11-11 上海隧道工程股份有限公司 衬砌构件及其偏心注浆结构
CN104120731B (zh) * 2014-07-24 2016-02-24 黄俊文 一种隧道沉降防护装置及其施工方法
CN105178322B (zh) * 2015-08-28 2017-09-26 上海市政工程设计研究总院(集团)有限公司 一种注浆施工方法
CN105370290B (zh) * 2015-11-03 2018-03-13 中铁工程设计咨询集团有限公司 一种盾构隧道的纠偏加固方法
CN106812536A (zh) * 2017-03-31 2017-06-09 华东建筑设计研究院有限公司 地铁隧道减沉减振装置及其施工方法
CN107060824B (zh) * 2017-04-12 2019-01-04 浙江科技学院(浙江中德科技促进中心) 防止软土中地铁盾构隧道长期沉降的水泥加固装置及方法
CN110344843A (zh) * 2019-06-27 2019-10-18 国网浙江省电力有限公司经济技术研究院 基于可调节注浆容器的盾构隧道位置精确调整装置和方法
CN111287763B (zh) * 2020-02-20 2021-04-23 海南大学 一种防止地铁盾构隧道长期沉降的控制方法
CN111764926B (zh) * 2020-08-03 2024-10-29 中铁二院工程集团有限责任公司 一种盾构或顶管隧道长期沉降的控制结构及控制方法
CN112901203A (zh) * 2020-09-09 2021-06-04 中铁二院工程集团有限责任公司 一种盾构和顶管隧道周边地层加固结构与加固方法
CN113309108A (zh) * 2021-04-14 2021-08-27 武汉市市政建设集团有限公司 一种兼顾伺服注浆功能的隔离桩及其施工方法
CN113699968B (zh) * 2021-09-02 2023-02-14 华侨大学 一种控制地铁运营盾构隧道沉降的自膨胀桩施工方法
CN114776309B (zh) * 2021-11-15 2024-09-27 中铁二院华东勘察设计有限责任公司 软土体区深埋盾构隧道横向受力改善方法
CN114542116A (zh) * 2022-01-19 2022-05-27 上海勘察设计研究院(集团)有限公司 一种嚢袋注浆修复盾构隧道服役姿态的方法
CN115680673A (zh) * 2022-10-20 2023-02-03 北京市政建设集团有限责任公司 一种盾构隧道深孔注浆加固设备
CN119145883B (zh) * 2024-11-11 2025-02-18 中国建筑第六工程局有限公司 一种富水砂卵石地层盾构施工注浆方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1587544A (zh) * 2004-07-30 2005-03-02 于来喜 多用途可控劈裂后注浆装置及应用工艺
CN101126238A (zh) * 2007-09-10 2008-02-20 铁道第四勘察设计院 布袋注浆成桩方法
CN201801861U (zh) * 2010-06-02 2011-04-20 中国京冶工程技术有限公司 重复自适应注浆系统
CN201826315U (zh) * 2010-10-15 2011-05-11 中铁五局(集团)有限公司 注浆袖阀管
CN202559368U (zh) * 2012-05-17 2012-11-28 中交公路规划设计院有限公司 一种沉管隧道带帽钢管减沉桩结构
CN202577307U (zh) * 2012-04-11 2012-12-05 沈阳中建东设岩土工程有限公司 桩底后注浆装置
CN203603927U (zh) * 2013-11-11 2014-05-21 浙江大学 一种软土地基盾构隧道沉降控制钢套管注浆加固装置

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7090435B2 (en) * 2004-09-24 2006-08-15 Leroy Mitchell Method and apparatus for raising, leveling, and supporting displaced foundation allowing for readjustment after installation

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1587544A (zh) * 2004-07-30 2005-03-02 于来喜 多用途可控劈裂后注浆装置及应用工艺
CN101126238A (zh) * 2007-09-10 2008-02-20 铁道第四勘察设计院 布袋注浆成桩方法
CN201801861U (zh) * 2010-06-02 2011-04-20 中国京冶工程技术有限公司 重复自适应注浆系统
CN201826315U (zh) * 2010-10-15 2011-05-11 中铁五局(集团)有限公司 注浆袖阀管
CN202577307U (zh) * 2012-04-11 2012-12-05 沈阳中建东设岩土工程有限公司 桩底后注浆装置
CN202559368U (zh) * 2012-05-17 2012-11-28 中交公路规划设计院有限公司 一种沉管隧道带帽钢管减沉桩结构
CN203603927U (zh) * 2013-11-11 2014-05-21 浙江大学 一种软土地基盾构隧道沉降控制钢套管注浆加固装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
上海软土地层中运营地铁隧道不均匀沉降的治理方法;汪小兵等;《上海交通大学学报》;20120128;第46卷(第1期);第1-2节,附图1-5 *

Also Published As

Publication number Publication date
CN103573274A (zh) 2014-02-12

Similar Documents

Publication Publication Date Title
CN103573274B (zh) 软土地基盾构隧道沉降控制钢套管注浆加固装置
CN102493822B (zh) 一种通过富水断层影响带的隧道的帷幕注浆施工方法
CN204901197U (zh) 一种直径为300-600mm的排水管道用局部注浆修复装置
CN104695963B (zh) 碎裂岩层中地铁隧道穿越建筑物的施工方法
CN105350519A (zh) 一种适用于砂土层浅埋隧道超前预注浆装置及施工工艺
CN205314107U (zh) 一种地基加固用的分段式注浆管装置
CN102839691B (zh) 无砂水泥管深井降水井口快速封堵方法及其装置
CN114542116A (zh) 一种嚢袋注浆修复盾构隧道服役姿态的方法
CN205296175U (zh) 高承压水深基坑支护锚杆结构
CN104594919A (zh) 软岩巷道可缓冲渐变式双强壳体支护体系及其施工方法
CN203603927U (zh) 一种软土地基盾构隧道沉降控制钢套管注浆加固装置
CN202644538U (zh) 一种在富水流砂地层中使用的注浆装置
CN207176686U (zh) 全封堵地下洞室回填、固结灌浆管路布置结构
CN113339064B (zh) 一种通过柔体膨胀调控隧道矢量变形的多维主动控制方法
CN204457810U (zh) 软岩巷道可缓冲渐变式双强壳体支护体系
CN107956484B (zh) 既有盾构隧道变形控制的加固结构及施工方法
CN204326061U (zh) 一种易拔出的管桩
CN205822207U (zh) 一种防护边坡的钢管桩桁架
CN102220764A (zh) 深基坑支护体系及其施工方法
CN204609897U (zh) 一种管幕冻结法支护结构
CN201649082U (zh) 一种防止锚索钻孔施工孔口涌砂的装置
CN205171501U (zh) 一种工字钢接头式地下连续墙绕流处理装置
CN103911988A (zh) 一种用于基坑支护的新型护壁桩
CN104533448A (zh) 一种岩石地层中盾构隧道端头止水加固的施工方法
CN204510861U (zh) 建筑物整体移动路径地基抗沉降结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160120