CN103541517B CN201310224491.3A CN201310224491A CN103541517B CN 103541517 B CN103541517 B CN 103541517B CN 201310224491 A CN201310224491 A CN 201310224491A CN 103541517 B CN103541517 B CN 103541517B
Authority
CN
China
Prior art keywords
tile batten
overhang
slabstone
receiving portion
erecting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310224491.3A
Other languages
Chinese (zh)
Other versions
CN103541517A (en
Inventor
爱德华·李·麦克林蒂克
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Building Materials Investment Corp
Original Assignee
Building Materials Investment Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from US11/686,791 external-priority patent/US8033072B2/en
Application filed by Building Materials Investment Corp filed Critical Building Materials Investment Corp
Publication of CN103541517A publication Critical patent/CN103541517A/en
Application granted granted Critical
Publication of CN103541517B publication Critical patent/CN103541517B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention relates to Roof system and method.Describe the system for the roofing element assembled and give support to a roof in structure.Exemplary system includes at least one tile batten extended along a part for described roof structure.Described tile batten includes receiving portion, and described receiving portion is for being detachably secured erecting by overhang along described tile batten.Also describe for supporting and the correlation technique of assembling.

Description

Roof system and method
The application is the Application No. 200710090141.7 submitted on April 16th, 2007, invention entitled " Roof system And method " the divisional application of application for a patent for invention.
Technical field
The invention of applicant relates to the roofing (roofing) of building, and more particularly, to slabstone (slate) Roof system and installation method.
Background technology
Slate roofs is liked by masses due to their attractive in appearance and durable quality.Slabstone is the most exquisite available roofing One in material, and for comparing asphalt shingle (asphalt shingle) roof, there is several advantage.Such as, Slate roof is prevented fires, opposing hail damage, and is generally of 100 years or longer service life.But, slabstone is firm Property lithotome goods, regrettably, described rigidity lithotome goods can be by stress damage.Stress can pass through Several ways is introduced in slabstone, but causes the modal reason of the stress of slabstone to be used to slabstone is attached to room The nail of top board (roof deck).Using nail to install, described nail needs to be fastened and makes slabstone hanging nail on.If nail quilt Insert the most tightly, then nail can extrude (pinch) slabstone.On the other hand, if nail is not inserted into the deepest, then slabstone Bonding jumper (overlapping piece) may rupture from hiding pressure spot.Environment is to wood decking (wood decking) Impact with nail is likely to cause stress.The environmental change of the lifting of such as temperature and humidity can cause slab to expand and receive Contracting.If in this case, nail is in crunch, then slabstone may rupture or fall.
Further, slate roofs fairly expensive (generally than synthetic asphalts roofing expensive two to three times), and compare synthesis roof boarding, The weight of slabstone is quite big (described slabstone may need the extra support for roof, increases cost further).Stone slab Material itself is expensive, so any minimizing of slabstone quantity will cause cost and the weight on roof necessary to effective roofing Reduction.
About slate roof and its installation method abundant background can in NRCA roofing and waterproof handbook fourth edition, Page 1179 finds in page 1227, and described file is included herein here by quoting.Typical slate roofs Being so to build, so that first wooden roof covers with substrate (underlayment) layer, described substrate layer is usual For asphalt felt paper.Subsequently, in addition to the position at overlap joint, overlap joint slabstone layer (course) is in order to the side of two-layer (ply) Formula covers slate and applies, and wherein, there are three layers of slabstone in the position of described overlap joint.From slate roofs surface to felt not Through seam (through joint) should occur.So, using conventional slate roof technology, roofing slate must be by enough Ground extends and allows three layers of overlap joint (with the two-layer slabstone on roof expose portion), to guarantee that water can not seam between roofing slate Between through roof.Accordingly, because the double-deck covering needed for waterproof ability and three layers of overlap joint, conventional slate roof Technology needs to use a large amount of slate material, is greatly increased cost and the weight of slate roofs.
Slate roofs can be by reducing the amount being used for creating the slabstone on water-proof roofing surface and solid by eliminating roofing slate The nail of the appropriate location being scheduled on roof (or needing any other penetrator or the system in hole in slabstone) and be modified. This can allow more robust, but relatively inexpensive and lighter slate roofs.Further, if there is resisting by wind at roofing slate Some means of the uplift force of upper generation, then slate roofs can be more durable.High wind may be stopped under the leading edge of roofing slate Gear (catch), puts on slabstone by lifting force.By this way, wind can increase the stress on roofing slate.It addition, wind is real Roofing slate can be lifted on border, following roof is exposed to natural agent (element).Therefore, the slate roof system of improvement Unite and will use some that roofing slate is attached to roofing board by the device to windproof uplift force, it is provided that more durable and gasproof The roof waited.
Summary of the invention
The embodiment of the disclosure includes having the slabstone component being attached by tile batten (batten) and suspender member (hanger) Roof.Roofing slate is typically attached to roof in the way of the row (row) of overlap joint.Substrate can be attached to roof, It is positioned under tile batten.In some embodiments, tile batten is attached to roof, crosses the length extending on roof, And it is spaced apart in vertical direction at regular intervals on roof.Suspender member may then attach to tile batten to support stone Pan tile, thus attaches to roof by roofing slate.Generally, suspender member can be removably secured to tile hanging Bar, and/or so that tile batten can be fixed in the way of relocating along the length of tile batten.In some embodiments, Suspender member is usually (the tension sprung) of elastic tension, lifts so that opposing is upper.Therefore, suspender member helps them to be supported Roofing slate resist the uplift force that produced by wind.It addition, suspender member can be by crossing (in lap segment) roofing slate Tip portion is pressed downward against helping the upper act of roofing slate opposing of relatively low row.Substantially, the overlap joint essence of slabstone row allows suspender member Maximize the resistivity to upper act.
Roof can also include that roofing carpet veneer (interlayment) material below slabstone (is commonly called " slate liner (liner)”).Generally, the slate liner being associated with every calculus pan tile is under the roofing slate of this row.Logical Often, slate liner for a row of tile is by the top being positioned in the suspender member being associated with this row, and roofing slate subsequently will be Position on the top of slate liner is placed in suspender member.It addition, roof can include the gutter being placed on roofing board (valley) hardware, gable (gable)/cornice (rake) edge metal component and drip (drip) edge metal Component.Generally, slate roofs can be installed by being disposed and be attached to roofing board by tile batten.Suspender member with After will be fixed to tile batten, be positioned on tile batten, suitably support roofing slate crossing roof.An embodiment party In case, tile batten will have, along their length, the hanger holder or slot that are regularly spaced apart, and described suspender member is solid The shapes and sizes determining device or slot are provided to accommodate suspender member.It is solid that suspender member is operable to be reliably mounted on suspender member Determine in device, so that suspender member reliably can be attached as required along the length of tile batten, to be added by roofing slate (affix) on roof.By providing the suspender member that can be removably secured to tile batten, no matter in roof Edge or gutter at, suspender member can by suitably dispose (positioned).Interchangeable embodiment can have edge The suspender member that the length of tile batten can relocate, from regardless of whether at edge or gutter, suspender member can suitably be pacified Put.Once suspender member has been appropriately placed on tile batten, and before putting down slabstone, slate liner will be positioned in and hang On the top of suspension member.It addition, substrate can be placed under tile batten, wherein it is placed under substrate from adhesive film.
By laying roofing felt material layer under each slabstone layer, roofing felt layer material serves as the substrate of through seam, resistance Sealing penetrates into following roof by the seam in roofing slate.This can make the amount being used to form the slabstone of waterproof roof reduce Substantially 40% to 50% (because roofing felt layer material stops the water seepage (seepage) by the seam between roofing slate, institute Waterproof roof is provided with needs less slabstone overlap joint.The present embodiment only uses monolayer to expose at slabstone and overlapping regions Two-layer slabstone rather than two-layer expose three layers of slabstone at slabstone and overlapping regions).Generally, will use reinforced (heavy-duty), weather proof roofing felt material layer, it is common that thickness is 20 to 60 mils (mil) Plastics.Further, in the case of avris is met conjunction (through seam) by slabstone avris, roofing felt layer material below carries Roof is protected for sufficient waterproof ability.Comparing its substituted slabstone, roofing felt layer material is the most relatively inexpensive, and weight is relatively Gently.Therefore, disclosed embodiment has significantly improved weather barrier, lighter in weight and more cost effective by offer Slate roofs, improves prior art slate roofs.
Disclosed suspender member embodiment need not nail and is arranged on roof by slabstone, improves roofing slate by reducing stress Ruggedness.Disclosed embodiment allows the multiple suspender member of once mounting.Because also being able to cause damage during roof construction, So the multiple suspender member of once mounting allows to install slabstone from top down.It addition, the essence of suspender member makes the roof can be by gently Change places repairing, and without instrument.The hardware used in some embodiments of suspender member can also be that roofing slate is attached Receive the more durable device on roof, because the shape of suspender member provides firm, durable attachment.Suspender member is the most usual Being spring temper, this point helps they elastic releases relative to roofing board.By elastic tension, suspender member can carry For lifting protection on preferable wind.
The present invention provides the system of a kind of roofing element in the structure that gives support to a roof, and described system includes: along described room At least one tile batten that the part of roof construction extends, described tile batten has and is limited at receiving portion therein;And it is many Individual erecting by overhang, described erecting by overhang has head, and described head is removably secured to described receiving portion; Erecting by overhang described at least one of which includes the projection that the described head from it extends out, and described projection can be grasped Make to engage described receiving portion.
Wherein, at least one in described receiving portion is the lattice-shaped structure limited in described tile batten, described protuberance Divide and may operate to engage described lattice-shaped structure removably.
Wherein, at least one in described receiving portion is socket piece, and described projection may operate to removably Engage described socket piece.
Wherein, described projection can move to the second position from primary importance at least partially.
The present invention also provides for the system of a kind of roofing element in the structure that gives support to a roof, and described system includes: along described At least one tile batten that the part of roof structure extends, described tile batten has and is limited at receiving portion therein;And Multiple erectings by overhang, described erecting by overhang has head, and described head is removably secured to described receiving portion; Wherein said receiving portion and head have the shape of correspondence.
Wherein, described head is substantially annular, and described receiving portion is formed in a corresponding manner.
Wherein, described head is the most hexagonal, and described receiving portion is formed in a corresponding manner.
Wherein, described receiving portion includes that the opening of its apex, a part for described erecting by overhang extend through described top Point.
Wherein, described erecting by overhang also includes short component and long component, described short component and the long component extended from described head Cooperate, to allow described head to be inserted in described receiving portion.
Wherein, described short component is spaced apart with described long component, and is arranged essentially parallel to described long component.
The present invention also provides for a kind of method of roofing element for assembling on roof structure, and described method includes: by tile batten Being fixed to roof, described tile batten has and is limited at receiving portion therein;Thering is provided multiple erecting by overhang, described hanging fills Put and there is head, and the component extended out from described head, wherein said head and receiving portion have the shape of correspondence; Described erecting by overhang is inserted in described receiving portion, thus removably described erecting by overhang is fixed to described Tile batten;And described roofing structure is set on described tile batten and in the way of engaging with described erecting by overhang component Part.
Wherein, described method is additionally included in before arranging described roofing element on described tile batten, on described tile batten And in the way of engaging with described erecting by overhang, lining component is set.
Wherein, described method also includes dismantling described erecting by overhang from described receiving portion, and is inserted by described erecting by overhang In another receiving portion.
Although the embodiment in the application specifically quotes slabstone and slabstone is installed, but the invention here provided and technology are also Be applied to no matter which kind of material watt and watt installation, and any kind of roof boarding.
Accompanying drawing explanation
Fig. 1 is the top view of roofing board.
Fig. 2 is the top view of the roofing board of the installation of the diagram preparation of gutter and drip edge.
Fig. 3 is the top view of the roofing board that diagram substrate is placed.
Fig. 4 is the top view of the roofing board of diagram valley and rake edge metal placement.
Fig. 5 be illustrate all gutters, berm ridge (hip), ridge (ridge), body of wall (wall) pass through partly (roof mutually with roof The top view of the roofing board of preparation penetrations).
Fig. 6 is the top view of the roofing board that diagram slabstone is installed.
Fig. 7 is the perspective view of the roofing board that diagram slabstone is installed.
Fig. 8 is the perspective view being shown in the roofing board that the slabstone at gutter is installed.
Fig. 9 A is the top view of the tile batten with the exemplary suspender member according to disclosure use.
Fig. 9 B is the top view of the tile batten with the exemplary suspender member according to disclosure use.
Fig. 9 C is the top view of the tile batten with the exemplary suspender member according to disclosure use.
Fig. 9 D is the perspective view of the tile batten with the exemplary suspender member according to disclosure use.
Fig. 9 E is the perspective view of the tile batten with the exemplary suspender member according to disclosure use.
Figure 10 is the front view of the roofing board that diagram slabstone berm ridge is installed.
Figure 11 is the top view of the roofing board of diagram ridge.
Figure 12 is the side view of the roofing board that diagram slabstone ridge is installed.
Figure 13 is the detailed view of slate installation step 1.
Figure 14 is the detailed view of slate installation step 2.
Figure 15 is the detailed view of slate installation step 3.
Figure 16 is the perspective view of the roofing board of the flashing member (flashing) at diagram exterior wall (siding) place.
Figure 17 is the perspective view of the roofing board of the flashing member at diagram sidewall (sidewall)/chimney.
Figure 18 is the perspective view of the roofing board of the installation details of the air vent (plumbing vent) of diagram tubing.
Figure 19 A is the side view of the suspender member according to an aspect of this disclosure.
Figure 19 B is the plane graph of the suspender member of Figure 19 A.
Detailed description of the invention
In FIG, the top view of roofing board 102 is illustrated.In context of methods, initial step is to check and prepare room Top board 102.In one embodiment, roofing board 102 has gutter 104, eaves (eave) 114, gable/cornice 116 and ridge 118.Check in step at this exemplary roof plate 102, check existing roof for structural intergrity Cover plate (sheathing).Roofing board 102 shall preferably be the plywood (plywood) of minimum 15/32 inch, or The directional fiber plate (OSB) of regulator approval.The nail of all of roofing board 102 should be advanced and flush with roofing board 102. Should check roofing board 102 for thrust, described thrust may damage 110 (see Fig. 3) at the bottom of packing felt.
Fig. 2 is the top view of the roofing board 102 of the installation of the diagram preparation of gutter 104 and drip edge 108.Herein Method the step in, user is installed in gutter 104 and is i.e. shelled i.e. patch (peel and stick) film 106, simultaneously with 6 The seam of the preferred minimum overlap joint film 106 of inch.The film 106 used preferably is from adhering to poly-(styrene-butadiene-benzene Ethylene) (SBS) type.Such as, the film 106 used in preferred embodiments is Tarco TM Leak Barrier Ice With Water Armor.However, it will be understood that the film of any equivalent can be utilized.Film 106 is preferably 36 inches wide.With After, all of drip edge 108 is mounted.It is zinc-plated that drip edge 108 is preferably No. 26 specifications (gauge) of D type Or the hardware of 16 ounces of copper.In new building, if fascia (fascia board) is not the most painted, then Drip edge 108 can be delayed by, and installs after installing substrate 110 (see Fig. 3).Substrate 110 (see Fig. 3) Should extend on drip edge 108 hardware.
In figure 3 it is shown that the top view of the roofing board 102 of diagram substrate 110 placement.Context of methods the step in, User installs substrate 110, and described substrate 110 the most poly-(s-B-S) (SBS) is multiplex Way or the Type30 according to ASTM D226.The step for during, user will at gable/cornice edge 112 it On spread (roll) substrate 110 with the preferred minimum of an inch.For substrate 110, headlap (headlap) Preferred minimum be 2 inches.In moist or snowy region, this can be added to the minimum of four inches.For this The purpose of application, headlap is defined as by the stone overlapped from two neighbouring row's two-layer slabstones 130 (see Fig. 6) The part of plate 130 (see Fig. 6).Headlap assists to make roof watertight.It practice, do not observe the overlap joint recommended Overlapping portion branch causes internal water to be damaged.For substrate 110, the preferred minimum of avris overlap joint is 6 inches.In order to The purpose of the application, avris overlap joint (sidelap) is defined as the lateral edges of adjacent (adjoining) sheet of substrate.Nail (not shown) can be used to fixing substrate 110, and have preferably at headlap 12 inches in the heart Away from, and preferably in 36 inches of OC general layouts of the center of substrate coiled material.
Fig. 4 is the top view of the roofing board 102 of diagram valley 120 and rake edge metal 154 placement. In context of methods, user can install valley 120 on film 106 (see Fig. 2).This gutter metal It is zinc-plated that component 120 is preferably 26 specifications, 24 inches " W ", or 16 ounces of copper hardwares.It preferably with one inch Water dividing component (splash diverter) (not shown) be mounted together, and preferably follow closely with the roof of 1.25 inches or The copper slabstone nail of person 1.25 inches is fastened on the position of isolated edge 1 inch.User can also be gable/cornice edge Gable/rake edge metal 154 is installed at 112.It is zinc-plated that gable/rake edge metal 154 is preferably 26 specifications Or 16 ounces of copper hardwares.Then, user can install vertical body of wall flashing member (see Figure 16 and 17) and pipe The vertical tube (stack) of road system and air vent flashing member (see Figure 18).Vertical body of wall flashing member (see Figure 16 and 17) It is preferably that 26 specifications are zinc-plated or 16 ounce copper.At next step, user can be installed on ridge 118 and i.e. shell I.e. pad pasting 106.The film 106 used preferably is from poly-(s-B-S) (SBS) type adhered to. Film 106 is preferably 12 inches wide, has end overlap joint (endlap) of 3 inches.
In Figure 5, it is illustrated that all gutters 104, berm ridge 156, ridge 118, body of wall pass through the roofing board of part mutually with roof The top view of 102 is illustrated.Peel and stick membrane 106 is applied on valley 120 (see Fig. 4), preferably Reserve the region of the centrage 3 inches from gutter 104 without covering.Film 106 should on every side of centrage with The preferred minimum of 11 inches covers valley 120, and with the preferred minimum covering nail of 3 inches.Utilize U.S. Work cutter (utility knife), user can cut preferably 10 feet wide bands (strip) from peel and stick membrane 106 coiled material. User can install peel and stick membrane 106 on gable/rake edge metal 154, to guarantee to cover all fastenings Part.Film 106 should extend beyond the gable/rake edge metal on substrate 110 with the preferred minimum of 6 inches 154.The film 106 of this gable/rake edge metal 154 can also extend on the film 106 of gutter 104.Gutter Film 106 on hardware 120 and gable/rake edge metal 154 can be from adhering to rather than following closely fixing. Film 106 also should be installed in every other flashing member and room with the preferred minimum beyond all flashing members 6 inches Top is passed through on part mutually.Then, user can be preferably used the roofing nail of 1.5 inches or the faceplate screw peace of coating Dress hip spacer 126 and ridge spacer 122.These securing members are preferably provided in 24 English of every side of nailer At very little center distance.Distance piece flashing member 124 cuts from slate liner 140 (see Fig. 6), and is placed on On ridge spacer 122, and preferably should overlap 12 inches in avris lap-joint.
Fig. 6 is the top view of the roofing board 102 of the installation of diagram slabstone 130.In slate installation step, roofing board 102 Slabstone 130 is used to spread out profile.First berm ridge 156, ridge 118 and gutter 104 are spread out profile.Then, user To position at drip edge 108 and tile batten row 172 bottom labelling.The bottom row of suspender member 134 (see Fig. 7) 174 (see Fig. 7) should extend to drip edge 108.User can use chalk line (chalk line) and volume subsequently Chi is positioned for the remaining row of tile batten 132.Tile batten 132 should preferably be mounted with the interval of 10 inches. Tile batten 132 is preferably zinc-plated or stainless steel beam column.In the region paying close attention to coastal brine corrosion problem, generally use Rustless steel.It would be recognized that tile batten 132 spacing can increase or reduce to adapt to portion pitch (fraction spacing). User can start at berm ridge 156 and gutter 104, and progressively constructs roofing board 102, is often arranging installation Complete tile batten 132, slate liner 140 and 2-3 slabstone 130, makes place walking accessible.Then, use Person can position and install the tile batten 132 of top row, slate liner 140 and the slabstone 130 (ridge row 178) of top row, It is subsequently mounted ridge slabstone 150.Ridge slabstone 150 should overlap and lock in the slabstone 130 of ridge row 178.Make User can use cutter to cut the slate liner 140 of any exposure.
In one embodiment, four rows before the ridge row 178 of slabstone 130 starts down, user can install extension Watt bar 132.Suspender member 134 may or may not be pre-mounted on tile batten 132.User subsequently can be by slabstone Lining 140 shelve (lay) on suspender member 134 (see Fig. 7), and slabstone 130 is declined (drop) to suspender member 134 On (see Fig. 7).Suspender member 134 (see Fig. 7) is preferably the stainless steel component of spring temper.User is careful confirmation Keyway (keyway) or seam are alignd with the ridge row 178 of slabstone 130.Then, user can install locking following The next row tile batten 132 of slabstone 130 row, and repeat this process.In one embodiment, user is every a row Keyway is made to deviate 1/2 slabstone 130.Last row can be entered by user " plug firmly ".User subsequently can on roof to Lower four rows, and repeat this process.The perspective view of this slabstone installation process is illustrated in the figure 7, and Fig. 8 illustrates gutter The perspective view that slabstone at 104 is installed.The more details that slabstone 130 is installed is illustrated in Figure 12-15.
In figure 9 a, the top view of the tile batten 132 with the suspender member 134 used in context of methods is illustrated.Excellent The suspender member 134 that choosing is formed by the rustless steel of spring temper can be mounted easily and dismantle, in order to provide slabstone The suitable support of 130.Suspender member 134 provides convenient method quickly and easily to mount and dismount each slabstone 130. In the embodiment illustrated in figure 9 a, suspender member 134 has short component 158 and long component 160.Long component 160 There is the far-end (at one end on towards hook-like part 162) of bending, and remaining end is adjacent to the first outwardly extending arm 166. In some embodiments, long component 160 can be modified to include broader far-end or two far-ends.First extroversion is prolonged Semi-girder 166 adjacent central connecting elements 168.This central connection member 168 is adjacent to the second outwardly extending arm 170.This is second years old Outwardly extending arm 170 is adjacent to short component 158.Although suspender member 134 be mostly in a plane, but long component 160 Extend with an angle on the plane of the first outwardly extending arm 166, with a curved downward at angles, and outside first The position of the point in the linear plane of adjutage 166 terminates.This exemplary is quilt in Figure 19 A and 19B Illustrate in greater detail.When installing suspender member 134, user will insert the second of suspender member 134 the outwardly extending arm 170 In the opening formed by the first hanger holder 142.Hanger holder 142 is generally defined to bag by tile batten 132 (pocket) shape or channel-shaped receiving portion, to receive the part of suspender member 134.Hanger holder 142 can be formed as Constitute a part of the whole with tile batten 132, or be formed as being attached to the separable element of tile batten.Suspender member The first outwardly extending arm 166 of 134 will be inserted in the opening formed by neighbouring hanger holder 142 subsequently.When During dismounting suspender member 134, user extrudes short component 158 and long component 160 simultaneously, with from the first hanger holder 142 Suspender member 134 is dismantled with neighbouring hanger holder 142.
It would be recognized that suspender member 134 can be taked variously-shaped and structure to interact with tile batten 132, and by stone Board member is maintained on roof.It practice, hanger holder can correspondingly change to take corresponding to, or be adapted to The shapes and sizes of various suspender member shapes and sizes.For example, referring to Fig. 9 B, the head 200 of suspender member 234 can be in The structure of existing annular or basic annular.Tile batten 232 can be provided so that hanger holder 242 be shaped as with The shape of the head 200 of suspender member 234 is corresponding.Suspender member 234 can also include short component 258 and long component 260, So that suspender member 234 by with describe about Fig. 9 A similar in the way of be inserted in hanger holder 242.
In another embodiment described in Fig. 9 C, the head 300 of suspender member 334 can be formed with hexagonal Shape or the most hexagonal shape.Corresponding hanger holder 342 may be provided as and the head of suspender member 334 The shape of 300 is corresponding.It practice, in some embodiments, it is solid that suspender member fixture 342 can be included in suspender member The breach at summit (apex) place of locking member, fixes being removably secured to suspender member in hexagon front end 300 During part, it is allowed to hexagon front end 300 extends through this hanger holder.Suspender member 334 can also include short component 358 With long component 360, in order to suspender member 334 by with describe about Fig. 9 A similar in the way of be inserted into hanger holder In 342.
It should be appreciated that also contemplate other embodiments, wherein the size and shape of the head of suspender member is configured to install In the corresponding receiving portion (such as example described above hanger holder) of tile batten, thus allow slabstone It is maintained on roof structure.In such embodiments, suspender member can be removably secured to tile batten, Thus allow suspender member maybe can relocate along the length of tile batten is removable.This is determining the side of the length along tile batten Motility is provided to when where setting up suspender member.It practice, bigger roofing slate may need hanging of greater number Suspension member, and less roofing slate may need fewer number of suspender member.Therefore, according to the teaching of the disclosure, the effect of resource Rate can be maximized.The relation that can be detachably secured between suspender member and tile batten also allows for the disclosure The Fast Installation of Roof system.
Also contemplating extra exemplary, wherein the shapes and sizes of the head of suspender member are provided to be loaded into, Buckle into (snap into), or be attached in tile batten the corresponding receiving portion (example limited in other dismountable modes As, hanger holder).For example, referring to Fig. 9 D, the head 400 of suspender member 434 can include projection (projection) 440, the shapes and sizes of described projection 440 are provided to snap fit and close (snap-fit) corresponding to tile batten 432 In lattice structure 450 (receiving portion).It is, of course, possible to design any amount of projection 440, as long as they can Snap fit is closed, or is otherwise attach to tile batten 132.Further, in fig. 9e, the head 500 of suspender member 534 Can include that a pair projection 540, the pair of projection 540 are designed to be assembled to the correspondence of tile batten 532 In socket piece (receptacle) 570.In such embodiments, the projection 540 of suspender member 534 can be basic On be L-shaped, to minimize the distance that projection extends out from head 500.It practice, projection 540 can be Fix, or the second position can be driven to from primary importance.Certainly, projection 540 can be taked to allow hanging Any shape of the operable joint of part 534 and tile batten 532.
Figure 10 is the front view of the roofing board 102 of berm ridge 156 installation of diagram slabstone 130.The berm ridge 156 of roofing board 102 It is in the first area spreading out profile with slabstone 130.User will install tile batten on the top of substrate 110 132.Suspender member 134 is inserted in the hanger holder 142 of tile batten 132.User will be slate liner 140 It is shelved on suspender member 134, and slabstone 130 is dropped on suspender member 134.At berm ridge 156, apply between berm ridge Spacing body 126, which is followed by hip spacer covering 148.Slabstone trim piece 146 is applied in and passes through faceplate screw 144 are attached to berm ridge 156.
In fig. 11, it is illustrated that the top view of the roofing board 102 that ridge 118 is installed is illustrated.Along with step installed by ridge 118 Rapid carrying out, installs ridge spacer 122 and is carried out as follows, i.e. user will be by assuring that ridge spacer 122 be preferred Ground is uniformly spaced apart on ridge 118, and the roofing nail of 1.5 inch or screw is preferably used along ridge 118 Each side be fastened at preferably 24 inches center distance.User will be put preferably 13 inches of wide slate liner 140 Put on ridge spacer 122, so that the centrage of slate liner 140 is placed in the middle along ridge 118.Preferably make Construct by 10-12 step-length, it is ensured that the preferably minimum of bond end seam 12 inches.Then, user is along chalk Line uses the roofing nail of nail gun and preferably 1.25 inch 0.120 zinc-plated standard coiled strip charging to install top tile batten (see figure 12).Suspender member 134 (see Figure 12) is inserted into the hanger holder 142 of tile batten 132 (see Figure 12) (see figure 12) in.In some embodiments, except at gable/edge 112 (see Fig. 4) place of cornicing, tile batten 132 is (see figure 12) center at suspender member (see Figure 12) is fastened.User shelves stone along suspender member 134 (see Figure 12) row Plate liner 140, and filled under (tuck) plastics ridge spacer cover 152.Ridge spacer cover 152 preferably should overlap top row slate liner 140 with the minimum of three inches.Then, user will be by by each stone The bottom margin of plate 130 is placed in the suspender member 134 (see Figure 12) of top row and shelves first row slabstone 130.Suspender member 134 (see Figure 12) are preferably pre-installed with the center distance of 6 inches.Slabstone 130 preferably 12 inches is wide takes advantage of 12 English The slabstone (quarried slate) that the standard stone pit of modest ability gathers.Certainly, it is contemplated that for other intervals of suspender member 134 The slabstone 130 of size and other sizes falls into the scope of the present disclosure.Also, it is to be appreciated that according to the principle of the disclosure, permissible Use other watts in addition to slabstone.It practice, according to principle herein, it is contemplated that use any roofing or Exterior Wall Components. Suspender member 134 (see Figure 12) is preferably spaced apart on slabstone 130 equably.Each suspender member 134 (see Figure 12) Should be preferably from 3 inches of the edge of each slabstone 130 complete slice.In the case of less sheet, preferably make at least two Suspender member 134 (see Figure 12) supports each slabstone 130.Suspender member 134 (see Figure 12) can be dismantled easily with And replace, in order to increase to the spacing of preferably 1.5 inches.In some embodiments, if measuring and needing slabstone 130 Sheet is less than 4 inches wide, and the most neighbouring sheet should be cut in, so that little sheet is preferably the minimum of 4 inches.Cutting edge Edge can be placed side by side so that cut edge disappears, and non-discernable.User preferably confirms that ridge spacer covers Cover material 152 overlaps top row slabstone 130 with the preferred minimum of 2 inches.The top of the slabstone 130 of top row preferably from The bottom of ridge spacer 122 is not distal to 1 inch.Ridge trim piece 150 will be every with the hole 186 got out in advance by two Individual slabstone 130 mode that nail or screw are fixing is mounted, between hole that said two gets out in advance 186 is directly through ridge Spacing body 122 is in roofing board 102.16 inches of trim piece 150 preferably prebored hole take advantage of the standard stone pit of 7 inches to adopt The slabstone of collection.Must meet at the top end of ridge 118 in the edge of each trim piece 150, and a sheet should somewhat be taken Connect another sheet, thus form clean, the seam of weatherability.If so desired, user can not being subject to match colors The joint sealing material (caulk) of climatic effect is applied to seam.Joint sealing material is preferably high-quality outdoor level silicone.Then, next Individual ridge trim piece 150 is mounted by the way of overlapping the most mounted with the length of preferably 6 inches.If so desired, Each nail can cover with weather proof joint sealing material.Ridge trim piece 150 should be with the preferred minimum of 2 inches The top of amount overlap joint first row slabstone 130.It should be noted that the securing member in ridge trim piece 150 is not excessively fastened (overdrive).Slabstone 130 should be able to somewhat swing.Visible after ridge trim piece 150 is mounted any mould Material ridge spacer cover 152 can use cutter to be repaired carefully.Figure 12 is diagram slabstone 130 ridge 118 The side view of the roofing board 102 installed.
In fig. 13, the detailed view of exemplary slate 130 installation steps 1 is illustrated.In installation steps 1, use Person installs tile batten 132 on the Article 4 chalk line from top or ridge 108 in the way of end-to-end.The most every 6 English Very little, user uses roof nail 138 at each tile batten 132 of the center of each suspender member 134 fastening.Then, stone Plate liner 140 is mounted by it being put along tile batten 132 discharge, and described tile batten 132 uses suspender member 134 Support slate liner 140.Recommend every slate liner 140 preferably up to 25 feet long.Slate liner 140 is on limit Side lap-joint should preferably overlap the minimum of 12 inches.Slate liner 140 should with delustring (dull finish) towards Upper or bright prone mode is mounted.In some embodiments, do not have nail to be pushed into and penetrate slate liner 140. Then, user by with careful keep suspender member 134 on slabstone 130 placed in the middle by the way of slabstone 130 is placed on hanging Slabstone 130 is installed on part 134.In some embodiments, each slabstone 130 should have two suspender members 134 Supportting it, described suspender member 134 is evenly spaced apart with each lateral edges of slabstone 130.Complete slabstone 130 should have Have preferably apart from the suspender member 134 of each lateral edges 3 inches.At the initial or end often arranged, one-half slate offset is pushed away Recommend, and can be by being placed on extra suspender member 134 in tile batten 132 at the hanger holder 142 provided Realize.Tile batten 132 can use tinsmith snips (tin snips) to cut.User should align in the way of end-to-end Tile batten 132, preferably maintains spacing (or the tile batten 132 of 6 inches between the suspender member 134 of slabstone 130 In three empty hanger holder 142).Tile batten 132 should be kept from ridge spacer 122 or gable/cornice Edge metal component 154 (see Fig. 5) retreats the position of 1/2 inch.
Figure 14 is the detailed view of exemplary slate 130 installation steps 2.In these installation steps, user will be installed The tile batten 132 of next row 180.Tile batten 132 should lock onto in following slabstone 130.User is it should be ensured that hang Suspension member 134 is preferably evenly spaced out on following slabstone 130.Suspender member 134 should be preferably from each slabstone 3 inches of each edge.Tinsmith snips are used to cut tile batten 132 in end, in order to suspender member 134 is spaced apart.
In fig .15, the detailed view of exemplary slate 130 installation steps 3 is illustrated.In these installation steps, The top row of each construction part, unlimited row 182 is created.In order to complete the installation of the row 182 opened wide, user should By being slipped into by slate liner 140 under the slabstone 130 of top row 184, slate liner 140 is installed.Slate liner 140 Bottom margin is maintained at appropriate location by suspender member 134.Then, user is by sliding by the top of slabstone 130 Enter under top row 184, until the bottom margin of slabstone 130 crosses (clear) suspender member 134 below to install slabstone 130. User pulls down slightly or pushes away slabstone 130, until suspender member 134 supports the bottom margin of slabstone 130.Preferably, The slate liner 140 of one piece 18 inches wide is used as shoehorn (shoehorn), and this is by being firstly inserted into it, so Rear slabstone 130 slides into comparalive ease and carries out in appropriate location.Shoehorn is removed, and this process is repeated.
Although being described above each embodiment according to principle disclosed herein, it should be appreciated that, they are only It is to be presented in the way of embodiment rather than restriction.Therefore invention or the range of multiple invention and scope not should by more than Any one in the exemplary described is limited, but should want according only to any right proposed from the disclosure Sue for peace their equivalent is defined.Further, above advantage and feature are provided in the embodiment described, but not Can be restricted to include the some or all of process of above advantage and structure by the application of the claims so proposed.
It addition, section header here is to keep consistent with the suggestion according to 37CFR1.77, or provide in structure Point out and be provided.These titles should in no way limit or characterization can from the disclosure propose any claim The invention of statement or multiple invention.Specifically and by way of example, although title is mentioned " technical field ", but power Profit claim should not limited by selecting the language describing so-called field under this title.Further, " background skill Art " in the description of technology be should not be construed as any invention in the disclosure or multiple invention, some technology is existing There is the approval of technology." summary of the invention " also should not be considered as the invention of elaboration in the claim proposed or multiple invention Feature.Further, should not be used to advocate in the disclosure to any mentioning of " invention " the most in the singular Only have single novel point.Multiple inventions can be set forth according to the restriction of the multiple claim proposed from the disclosure, and Such claim limits the invention protected by it or multiple invention, and their equivalent accordingly.In all situations Under, the scope of such claims should be according to the disclosure, and value based on themselves is considered, and should be by The title here illustrated is retrained.

Claims (9)

1. a system for the roofing element for giving support to a roof in structure, described system includes:
At least one tile batten extended along the part of described roof structure, described tile batten has and is limited at therein connecing Receiving portions;And
Multiple erectings by overhang, described erecting by overhang has head, and described head is removably secured to described reception Part;
Wherein said head has a most annular or hexagonal shape, and described head be configured and dimensioned to snap into institute State in receiving portion;
Erecting by overhang described at least one of which includes multiple projections that the described head from it extends out, the plurality of Projection may operate to engage described receiving portion.
2. the system as claimed in claim 1, at least one in wherein said receiving portion is included in described tile batten The lattice-shaped structure limited, described projection may operate to engage described lattice-shaped structure removably.
3. the system as claimed in claim 1, can moving from primary importance at least partially of wherein said projection To the second position.
4. the system as claimed in claim 1, wherein said projection is substantially l-shaped.
5. system as claimed in claim 4, at least one in wherein said receiving portion includes socket piece, described convex Go out part to may operate to engage described socket piece removably.
6. the system as claimed in claim 1, wherein said erecting by overhang also include the short component that extends from described head and Long component.
7., for the method assembling the roofing element on roof structure, described method includes:
Tile batten is fixed to roof, and described tile batten has and is limited at receiving portion therein;
Multiple erecting by overhang, described erecting by overhang is provided to have head, and the multiple components extended out from described head, The plurality of component may operate to engage described receiving portion, wherein said head and receiving portion have correspondence shape and Wherein said head has a most annular or hexagonal shape, and described head be configured and dimensioned to snap into described in connect In receiving portions;
Described erecting by overhang is snapped in described receiving portion, thus removably described erecting by overhang is fixed to Described tile batten;And
On described tile batten and in the way of engaging with described erecting by overhang component, described roofing element is set.
8. method as claimed in claim 7, is additionally included in before arranging described roofing element on described tile batten, On described tile batten and in the way of engaging with described erecting by overhang, lining component is set.
9. method as claimed in claim 7, also includes dismantling described erecting by overhang from described receiving portion, and by institute State erecting by overhang to snap in another receiving portion.
CN201310224491.3A 2007-03-15 2007-04-16 Roof system and method Active CN103541517B (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
US11/686,791 US8033072B2 (en) 2004-09-13 2007-03-15 Roofing system and method
US11/686,791 2007-03-15
CNA2007100901417A CN101265739A (en) 2007-03-15 2007-04-16 Roofing system and method

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CNA2007100901417A Division CN101265739A (en) 2007-03-15 2007-04-16 Roofing system and method

Publications (2)

Publication Number Publication Date
CN103541517A CN103541517A (en) 2014-01-29
CN103541517B true CN103541517B (en) 2016-08-24

Family

ID=39764700

Family Applications (3)

Application Number Title Priority Date Filing Date
CNA2007100901417A Pending CN101265739A (en) 2007-03-15 2007-04-16 Roofing system and method
CN201310224491.3A Active CN103541517B (en) 2007-03-15 2007-04-16 Roof system and method
CN201310224107.XA Pending CN103541516A (en) 2007-03-15 2007-04-16 Roofing system and method

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CNA2007100901417A Pending CN101265739A (en) 2007-03-15 2007-04-16 Roofing system and method

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201310224107.XA Pending CN103541516A (en) 2007-03-15 2007-04-16 Roofing system and method

Country Status (3)

Country Link
CN (3) CN101265739A (en)
CA (1) CA2625597C (en)
MX (1) MX2008003674A (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DK2783053T3 (en) * 2011-11-23 2016-06-13 Building Materials Invest Corp TPO-bar system
WO2016033636A1 (en) * 2014-09-01 2016-03-10 Christopher Lyndon Higgins Improved roofing elements and system
CN109184085B (en) * 2018-08-22 2020-05-05 北京定荣家科技有限公司 Asphalt tile laying method for light steel villa
CN114045990A (en) * 2021-12-09 2022-02-15 上海昇慧材料科技有限公司 Tile hanging device and mounting method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4314433A (en) * 1978-11-13 1982-02-09 Monier Colourtile Pty. Ltd. Roof tile fixing clip
FR2516134A1 (en) * 1981-11-12 1983-05-13 Goubaud Michel Clip esp. for installing roofing slate - comprises rod carrying returned point and hook at opposite ends
WO1994024384A1 (en) * 1993-04-22 1994-10-27 Richard Waddington Improved shingle roofing assembly
FR2865752A1 (en) * 2004-01-30 2005-08-05 Boishamon Philippe Du Roofing and/or cladding producing method for e.g. roofing company, involves connecting pre-hooked battens by flexible bands, on sheet being installed on surface to be covered up, and installing slates by rotating fixation hooks
NL1028468C2 (en) * 2005-03-04 2006-09-11 Bove Holding B V Fastening system for roofing tiles on pitched roof surface, includes tile clips which fasten roofing tiles to battens extending horizontally parallel to each other
CN2853955Y (en) * 2005-07-19 2007-01-03 林启章 Fixed mount for house tile

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR566215A (en) * 1923-05-15 1924-02-11 Round wire slate hook, wafer
CN1180125A (en) * 1996-08-30 1998-04-29 佳能株式会社 Horizontal-roofing roof and mounting method thereof
CN2844278Y (en) * 2005-07-15 2006-12-06 崇原(厦门)眼镜工业有限公司 A kind of Tile fixing strip

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4314433A (en) * 1978-11-13 1982-02-09 Monier Colourtile Pty. Ltd. Roof tile fixing clip
FR2516134A1 (en) * 1981-11-12 1983-05-13 Goubaud Michel Clip esp. for installing roofing slate - comprises rod carrying returned point and hook at opposite ends
WO1994024384A1 (en) * 1993-04-22 1994-10-27 Richard Waddington Improved shingle roofing assembly
FR2865752A1 (en) * 2004-01-30 2005-08-05 Boishamon Philippe Du Roofing and/or cladding producing method for e.g. roofing company, involves connecting pre-hooked battens by flexible bands, on sheet being installed on surface to be covered up, and installing slates by rotating fixation hooks
NL1028468C2 (en) * 2005-03-04 2006-09-11 Bove Holding B V Fastening system for roofing tiles on pitched roof surface, includes tile clips which fasten roofing tiles to battens extending horizontally parallel to each other
CN2853955Y (en) * 2005-07-19 2007-01-03 林启章 Fixed mount for house tile

Also Published As

Publication number Publication date
CN101265739A (en) 2008-09-17
MX2008003674A (en) 2009-02-26
CA2625597A1 (en) 2008-09-15
CA2625597C (en) 2015-03-31
CN103541516A (en) 2014-01-29
CN103541517A (en) 2014-01-29

Similar Documents

Publication Publication Date Title
US7454873B2 (en) Roof system and method for installation
US8033072B2 (en) Roofing system and method
US5765328A (en) Drainage system for decks
US7069698B2 (en) Method and apparatus for coupling structures to roofing
US5511351A (en) Drainage system for decks
US8297020B1 (en) Top down trap lock two-ply shingle system for roofs
US4300319A (en) Building eaves shield
US4195452A (en) Gutter and hanger arrangement
US20110314753A1 (en) Solar roofing system and method of installing the same
US20060201094A1 (en) Roofing shingle
US20060283096A1 (en) Gutter and roof protection system
AU2009200601A1 (en) Corrugated shield
US9097021B1 (en) Weather shielding system for slate and tile roofs
CN103541517B (en) Roof system and method
US20100011691A1 (en) Roof system and method of fabrication and installation
US20080010933A1 (en) Insulated pitched roofing system and method of installing same
US20080216442A1 (en) Roofing system
JP4384725B1 (en) Roof waterproof sheet, building waterproof sheet, building waterproof sheet installation method, building construction unit using the building waterproof sheet
NZ519103A (en) Gutter protector and guttering incorporating same
US9926704B1 (en) Roof panel system and hanger method for installation
JP4925222B2 (en) Building waterproof sheet, installation method of building waterproof sheet, building construction unit using building waterproof sheet
JP2010037930A5 (en)
US20040200174A1 (en) Lightweight roofing slate
US11060766B2 (en) Smart roof system and method
JPH0216242A (en) Roof tile and tiled roof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant