CN103530827A - Assembly type building component intelligent management system based on BIM (building information modeling) - Google Patents

Assembly type building component intelligent management system based on BIM (building information modeling) Download PDF

Info

Publication number
CN103530827A
CN103530827A CN201310452676.XA CN201310452676A CN103530827A CN 103530827 A CN103530827 A CN 103530827A CN 201310452676 A CN201310452676 A CN 201310452676A CN 103530827 A CN103530827 A CN 103530827A
Authority
CN
China
Prior art keywords
bim
rfid
amp
workstation
spot
Prior art date
Application number
CN201310452676.XA
Other languages
Chinese (zh)
Inventor
王宽
Original Assignee
中铁建设集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中铁建设集团有限公司 filed Critical 中铁建设集团有限公司
Priority to CN201310452676.XA priority Critical patent/CN103530827A/en
Publication of CN103530827A publication Critical patent/CN103530827A/en

Links

Abstract

The invention relates to an assembly type building component intelligent management system based on BIM (building information modeling). The assembly type building component intelligent management system comprises public Internet, wherein the public Internet is respectively connected with a BIM work station, a BIM and RFID (radio frequency identification) display terminal, a factory BIM and RFID work station, a BIM and RFID moving work station, an in-site BIM and RFID work station and a logistics BIM and RFID reading terminal, a BIM server is arranged between the public Internet and the BIM work station, the factory BIM and RFID work station is connected with a high-capacity active RFID anti-metal label, the BIM and RFID moving work station is connected with the in-site BIM and RFID reading terminal and an in-site BIM and RFID writing terminal, and the in-site BIM and RFID reading terminal and the in-site BIM and RFID writing terminal are connected with the in-site BIM and RFID work station. Compared with the prior art, the assembly type building component intelligent management system has the advantages that the information chain is complete, the informationization degree is high, the advantages of the BIM technology is sufficiently realized, the work efficiency and the accuracy of the component management in the assembly type building construction can be obviously improved, the remote component monitoring and the construction schedule monitoring can be realized, the component information collection is convenient, and in addition, the component installation efficiency can be improved.

Description

A kind of assembled architecture member intelligent management system based on BIM

Technical field

The present invention relates to a kind of assembled architecture member intelligent management system based on BIM.

Background technology

About BIM technology: BIM(Building Information Modeling, BIM) be to using every relevant information data of construction-engineering project as the basis of model, carry out the foundation of BUILDINGS MODELS.BIM is after CAD (computer-aided design (CAD)) technology, appears at the another important Computer Applied Technology of engineering construction industry, will cause once technical revolution of building trade.This technology is utilized digital modeling software, improves the efficiency of Project design, construction and management, and can bring significant economic benefit to relevant enterprise.

About RFID technology: radio-frequency (RF) identification is RFID(Radio Frequency IDentification) technology, claim again electronic tag, radio frequency identification, it is a kind of communication technology, can identify specific objective and read and write related data by radio signals, and without setting up machinery between recognition system and specific objective or optics contacts.The technology such as conventional have low frequency (125k ~ 134.2K), high frequency (13.56Mhz), a ultrahigh frequency, passive.Rfid interrogator also divides portable with fixed, RFID technology application is at present very wide, as library, and gate control system, food security is traced to the source etc.Product derivative in RFID technology probably has three major types: passive RFID product, active RFID product, half active RFID product.Active RFID product, is to grow up recent years, and the characteristic of its far distance automatic identification has determined application space and market potential quality that it is huge.In far distance automatic identification field, as intelligent hospital, intelligent parking lot, intelligent transportation, wisdom city, there is major application in the fields such as the wisdom earth and Internet of Things.Active RFID is a dark horse in this field, belongs to far distance automatic recognition category.Product groundwork frequency has ultrahigh frequency 433MHZ, microwave 2.45GHZ and 5.8GMHZ.

About assembled architecture: assembled architecture refers to the building forming at assemble in site with prefabricated member.The advantage of this building is that construction speed is fast, and climate conditionality is little, saves labour and can improve construction quality.Building house can, as production of machinery, manufacture in batch completely.As long as prefabricated house component, transport to assemble in site and get up just to have become.Early stage assembled architecture profile is more stiff, stereotyped.People improved in design afterwards, had increased dirigibility and diversity, and assembled architecture not only can be built in batch, and pattern is abundant.

RFID technology has started application at building engineering field at present, but prior art design, processing, logistics, material management and the chain rupture of construction and installation procedural information, the application system that there is no to form the science of improving, component information is imperfect, quantity of information is little, and application efficiency is low.And prior art does not have and the effective combination of BIM technology, the common RFID label of employing, anti-metal interference performance is poor, reads distance short, and quantity of information is little, cannot write BIM information, can not effectively adapt to the requirement of assembled architecture construction.

Summary of the invention

The object of this invention is to provide a kind of assembled architecture member intelligent management system based on BIM, for the over contract unit that constructs, carry out material management and the construction project time management work of the various members of assembled architecture.

The object of the invention is to be achieved through the following technical solutions:

A kind of assembled architecture member intelligent management system based on BIM; comprise public internet, described public internet be connected with respectively the digital building information model that can build whole and each member of assembled architecture BIM workstation, can remote synchronization show the BIM&amp of various information; RFID display terminal, can show or process the digital building information model data of whole and each member of assembled architecture and write the BIM&amp of factory of the identification code of each member; RFID workstation, the BIM&amp that the identification code of the BIM data of assembled architecture and member is carried out to field management; RFID movable work station and on-the-spot BIM& RFID workstation and flow B IM& RFID reading terminals, is provided with BIM server between described public internet and BIM workstation, the described BIM&amp of factory; RFID workstation is connected with for storing the large capacity active RFID anti-metal tag of identification code and the basic BIM parameter of each member, described BIM& RFID movable work station is connected with the on-the-spot BIM&amp of reading element information at the scene; RFID reading terminals and the on-the-spot BIM&amp that component information is modified; RFID writes terminal, on-the-spot BIM& RFID reading terminals and on-the-spot BIM& RFID writes terminal and described on-the-spot BIM& RFID workstation connects.

Further, described BIM& RFID display terminal, the BIM&amp of factory; RFID workstation, BIM& RFID movable work station, on-the-spot BIM& RFID workstation, flow B IM& RFID reading terminals, on-the-spot BIM& RFID reading terminals and and on-the-spot BIM& It is desktop computer, notebook computer, panel computer or smart mobile phone that RFID writes terminal.

Further, described BIM workstation, BIM server and BIM& RFID display terminal is one or more.

Further, in described large capacity active RFID anti-metal tag, be provided with chip, preferred, described chip is MB89R112 chip.

Beneficial effect of the present invention is: 1, message sense is complete, and the level of informatization is high.The BIM model information that design link is set up; can be in links transmission and application such as processing, logistics, material management and construction and installation; form complete information chain, can significantly improve work efficiency and the accuracy of component management in links, compare prior art and set up BIM& RFID display terminal, BIM& RFID movable work station, on-the-spot BIM& RFID writes the information-based assemblies such as terminal, and System information degree is high; 2, given full play to the advantage of BIM technology, abundant and the complete information of assembled architecture BIM model is write to large capacity active RFID anti-metal tag and stores in each workstation and terminal, greatly promoted information quality and quantity in building element RFID label; 3, utilize large capacity active RFID anti-metal tag can remote read-write, the strong characteristic of anti-metal interference performance, facilitated component information collection, and can really realize member remote monitoring and construction speed monitoring, the efficiency that lifting member is installed.

Accompanying drawing explanation

With reference to the accompanying drawings the present invention is described in further detail below.

Fig. 1 is the structured flowchart of the assembled architecture member intelligent management system based on BIM described in the embodiment of the present invention.

In figure:

1, public internet; 2, BIM workstation; 3, BIM server; 4, BIM& RFID display terminal; 5, the BIM&amp of factory; RFID workstation; 6, large capacity active RFID anti-metal tag; 7, BIM& RFID movable work station; 8, on-the-spot BIM& RFID workstation; 9, flow B IM& RFID reading terminals; 10, on-the-spot BIM& RFID reading terminals; 11, on-the-spot BIM& RFID writes terminal.

Embodiment

As shown in Figure 1, the assembled architecture member intelligent management system based on BIM described in the embodiment of the present invention, comprises public internet, and described public internet is connected with respectively BIM workstation, BIM& RFID display terminal, the BIM&amp of factory; RFID workstation, BIM& RFID movable work station, on-the-spot BIM& RFID workstation and flow B IM& RFID reading terminals, is provided with BIM server between described public internet and BIM workstation, the described BIM&amp of factory; RFID workstation is connected with large capacity active RFID anti-metal tag, described BIM& RFID movable work station is connected with on-the-spot BIM& RFID reading terminals and on-the-spot BIM& RFID writes terminal, on-the-spot BIM& RFID reading terminals and on-the-spot BIM& RFID writes terminal and described on-the-spot BIM& RFID workstation connects; Described BIM& RFID display terminal, the BIM&amp of factory; RFID workstation, BIM& RFID movable work station, on-the-spot BIM& RFID workstation, flow B IM& RFID reading terminals, on-the-spot BIM& RFID reading terminals and and on-the-spot BIM& It is desktop computer, notebook computer, panel computer or smart mobile phone that RFID writes terminal, comprises software and RFID read-write assembly; Described BIM workstation, BIM server and BIM& RFID display terminal is one or more; In described large capacity active RFID anti-metal tag, be provided with chip; Described chip is MB89R112.

The present invention is provided with described BIM workstation, BIM server, is responsible for building the digital building information model of assembled architecture integral body and each member, i.e. BIM model.Described BIM workstation, BIM server are generally many, and concrete quantity determines according to engineering and scope of the enterprise.Particularly, a plurality of designers use respectively the BIM model of the various members of existing software building assembled architecture at a plurality of BIM workstations, and build the various piece of buildings, the BIM model of each career field, and on BIM server, realize collaborative design by internal network, finally complete the BIM model of whole buildings.The abundant information that is comprising various members in the BIM model of buildings, the place that comprise member title, physical dimension, material, weight, color, the three-dimensional localization information in buildings, progress msg, transports to is cost information etc. even.

Described BIM server is sent to described BIM&amp by described public internet by the BIM data of buildings, member; RFID display terminal, the BIM&amp of factory; RFID workstation, BIM& RFID movable work station, on-the-spot BIM& RFID workstation and flow B IM& In RFID reading terminals, store and application, and can synchronously upgrade.

The described BIM&amp of factory; RFID workstation can be used existing software the BIM data of the member receiving to be shown and process, write identification code (UID) and the BIM information code of each member, and writes large capacity active RFID anti-metal tag.Large capacity active RFID anti-metal tag still has sufficient storage space outside the identification code (UID) of storage member, can use prior art by comprise member title, physical dimension, material, color, three-dimensional localization information in buildings, progress msg even the BIM information code of cost information write this label.

The chip of described large capacity active RFID anti-metal tag can be used the product of any prior art, and such as the MB89R112 chip of FerVID series, capacity can reach 64K.Large capacity active RFID anti-metal tag, anti-metal interference performance is strong, and effectively transmitting range can reach 70 ~ 90 meters, can use fastened by screw on the member of metal or other materials, and should there be lead sealing label and member junction.Member is installed after also acceptance(check), can select label to dismantle and reuse.Large capacity active RFID anti-metal tag adopts prior art to carry out the whole hardware and software design of low-power consumption, and the standby life-span of battery non-exchanging can reach more than 2 years.The BIM&amp of tag battery Ying factory; Before RFID workstation writing labels, enable again.

The present invention is provided with described BIM& RFID movable work station and on-the-spot BIM& RFID workstation can be checked the BIM model of member and buildings, collects on-the-spot BIM& The identification code that enters on-the-spot member (UID) and BIM information code that RFID reading terminals reads, and according to above information, logistics, handling of goods and materials and construction speed are monitored and managed.

The present invention is provided with BIM& RFID display terminal can remote synchronization show described BIM server, the BIM&amp of factory; RFID workstation, BIM& RFID movable work station and on-the-spot BIM& Various information in RFID workstation, are convenient to real-time monitoring and the management of company manager to links such as design, processing, logistics, construction and installation.Described BIM& RFID display terminal can be located at any place that can network, and quantity can be expanded.

The present invention is provided with described on-the-spot BIM& RFID reading terminals and on-the-spot BIM& RFID writes terminal, reading element information at the scene, or component information is modified, and corresponding information can be uploaded to BIM& RFID movable work station and on-the-spot BIM& RFID workstation.

The present invention is provided with described on-the-spot BIM& RFID writes terminal, can be some structure manufacture RFID labels of on-the-spot processing, or after the semi-manufacture of factory process are processed at the scene, its RFID label is modified and supplemented.

Various parts of the present invention, and use RFID communication between large capacity active RFID anti-metal tag.Between other various parts, can utilize prior art to communicate by modes such as cable network, Wi-Fi, 3G mobile communications networks.

Specific embodiment one:

Over contract building-up work by the present invention for an assembled-type house.First, designing unit is used BIM workstation, BIM server to move the design that existing software has completed the BIM model of this assembled-type house.Then, it is shared that designing unit carries out the BIM model of this assembled-type house network in BIM server.By described public internet, the operator of links can use described BIM& RFID display terminal, the BIM&amp of factory; RFID workstation, BIM& RFID movable work station, on-the-spot BIM& RFID workstation and flow B IM& RFID reading terminals is downloaded the BIM model of this assembled-type house.

In factory, first the producer produces each member according to the parameter in the BIM model of this assembled-type house.Then, operator is at the BIM&amp of factory; On RFID workstation, use prior art to encode the BIM model data of each member, and write large capacity active RFID anti-metal tag with together with the identification code (UID) of member.Afterwards, the active label of data writing power-on is installed in respective members, and member entrucking transports to installs ground.In logistics transportation process, if exist means of transport to change the situations such as (such as Automobile Transportation transfers shipping to), collecting and distributing packing, can use flow B IM&amp midway; Information on RFID reading terminals reading element label, manages the process of means of transport replacing and collecting and distributing packing, avoids the mistakes and omissions of logistics link.

At this place, gate, assembled-type house working-yard, be provided with the on-the-spot BIM&amp with door type RFID reading assembly; RFID reading terminals.After transport vehicle transport member arrives, by the on-the-spot BIM&amp at place, Shi, gate, gate; RFID reading terminals reads the data of all members automatically, and is uploaded to the BIM&amp that building site goods and materials supervisor carries; On-the-spot BIM&amp in RFID movable work station and Site Office; In RFID workstation, inventory managers can work out the inventory of the material of showing up fast according to these information.Scene is also provided with the on-the-spot BIM&amp of hand-held; RFID reading terminals, is convenient to goods and materials supervisor and at any time material is verified, checked.

In this assembled-type house work progress, construction manager can be used the on-the-spot BIM&amp of hand-held in optional position at the scene; Information in the large capacity active RFID anti-metal tag of the real-time reading element of RFID reading terminals, and then realize following functions:<img TranNum="84" file="201310452676X100002DEST_PATH_IMAGE002.GIF" he="21" img-content="drawing" img-format="GIF" inline="no" orientation="portrait" wi="16"/>member installation progress is monitored.Such as, the commander of tower crane and managerial personnel, the member that each part is lifted by tower crane is all used the on-the-spot BIM&amp that indicates tower crane special use; RFID reading terminals reads RFID label data, and reading result is uploaded to workstation, construction configuration management personnel and just can recognize that this member has entered tower crane and lifted link by consulting the data that the special-purpose reading terminals of middle tower crane of workstation uploads far away from the enterprise administrator in strange land, thus understand the installation progress of this member.<img TranNum="85" file="201310452676X100002DEST_PATH_IMAGE004.GIF" he="21" img-content="drawing" img-format="GIF" inline="no" orientation="portrait" wi="16"/>improve the level of informatization of work progress, improve operating efficiency.Still take tower crane as example, the commander of tower crane and managerial personnel, by reading physical dimension accurately and weight (even lifting schematic diagram) and the installation coordinate in BIM model of member in RFID label, saved in-site measurement link, effectively avoid overweight, accurately determine installation site, can science, formulate Hoisting Program quickly and safely.

The present invention is not limited to above-mentioned preferred forms; anyone can draw other various forms of products under enlightenment of the present invention; no matter but do any variation in its shape or structure; every have identical with a application or akin technical scheme, within all dropping on protection scope of the present invention.

Claims (5)

1. the assembled architecture member intelligent management system based on BIM; comprise public internet, it is characterized in that: described public internet be connected with respectively the digital building information model that can build whole and each member of assembled architecture BIM workstation, can remote synchronization show the BIM&amp of various information; RFID display terminal, can show or process the digital building information model data of whole and each member of assembled architecture and write the BIM&amp of factory of the identification code of each member; RFID workstation, the BIM&amp that the identification code of the BIM data of assembled architecture and member is carried out to field management; RFID movable work station and on-the-spot BIM& RFID workstation and flow B IM& RFID reading terminals, is provided with BIM server between described public internet and BIM workstation, the described BIM&amp of factory; RFID workstation is connected with for storing the large capacity active RFID anti-metal tag of identification code and the basic BIM parameter of each member, described BIM& RFID movable work station is connected with the on-the-spot BIM&amp of reading element information at the scene; RFID reading terminals and the on-the-spot BIM&amp that component information is modified; RFID writes terminal, on-the-spot BIM& RFID reading terminals and on-the-spot BIM& RFID writes terminal and described on-the-spot BIM& RFID workstation connects.
2. the assembled architecture member intelligent management system based on BIM according to claim 1, is characterized in that: described BIM& RFID display terminal, the BIM&amp of factory; RFID workstation, BIM& RFID movable work station, on-the-spot BIM& RFID workstation, flow B IM& RFID reading terminals, on-the-spot BIM& RFID reading terminals and and on-the-spot BIM& It is desktop computer, notebook computer, panel computer or smart mobile phone that RFID writes terminal.
3. the assembled architecture member intelligent management system based on BIM according to claim 2, is characterized in that: described BIM workstation, BIM server and BIM& RFID display terminal is one or more.
4. the assembled architecture member intelligent management system based on BIM according to claim 1, is characterized in that: in described large capacity active RFID anti-metal tag, be provided with chip.
5. according to the assembled architecture member intelligent management system based on BIM described in claim 4, it is characterized in that: described chip is MB89R112.
CN201310452676.XA 2013-09-26 2013-09-26 Assembly type building component intelligent management system based on BIM (building information modeling) CN103530827A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310452676.XA CN103530827A (en) 2013-09-26 2013-09-26 Assembly type building component intelligent management system based on BIM (building information modeling)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310452676.XA CN103530827A (en) 2013-09-26 2013-09-26 Assembly type building component intelligent management system based on BIM (building information modeling)

Publications (1)

Publication Number Publication Date
CN103530827A true CN103530827A (en) 2014-01-22

Family

ID=49932811

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310452676.XA CN103530827A (en) 2013-09-26 2013-09-26 Assembly type building component intelligent management system based on BIM (building information modeling)

Country Status (1)

Country Link
CN (1) CN103530827A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104268708A (en) * 2014-10-09 2015-01-07 湖南普云智能科技有限公司 Building template intelligent managing system and method based on cloud intelligence technology
CN104460506A (en) * 2014-11-13 2015-03-25 湖南普云智能科技有限公司 Method for achieving template unmanned construction
CN104778488A (en) * 2014-11-28 2015-07-15 华北水利水电大学 Steel-structure building positioning paster based on BIM
CN104915741A (en) * 2014-03-11 2015-09-16 汪再军 Building facility operation management system based on BIM technology
CN105223876A (en) * 2015-10-23 2016-01-06 山东大卫国际建筑设计有限公司 A kind of building electromechanical equipment TT&C system
CN106600239A (en) * 2016-12-28 2017-04-26 中建科技有限公司 Assembly type building construction full process data cooperation management system based on BIM
CN106639317A (en) * 2016-12-23 2017-05-10 浙江省建工集团有限责任公司 Prefabricated building complete set constructing technology
CN106663142A (en) * 2014-06-26 2017-05-10 三星电子株式会社 Method and apparatus for detecting building information
CN106760557A (en) * 2016-12-23 2017-05-31 浙江省建工集团有限责任公司 A kind of rear-mounted construction method of prefabrication component chip
CN106777751A (en) * 2016-12-30 2017-05-31 译筑信息科技(上海)有限公司 Architecture information processing method and processing device
CN106869308A (en) * 2017-03-13 2017-06-20 同济大学 A kind of quick turnover method of assembled architecture support system based on BIM
CN107507105A (en) * 2017-08-14 2017-12-22 广东工业大学 A kind of component information input method, device and handheld device
CN107663947A (en) * 2017-10-31 2018-02-06 中国冶集团有限公司 Autoclaved aerated concrete slab construction method in assembled architecture based on BIM
CN108532953A (en) * 2018-05-18 2018-09-14 宝业湖北建工集团有限公司 Overhanging board construction method based on BIM and construction techniques
CN108616815A (en) * 2018-05-06 2018-10-02 北京工业大学 A kind of prefabricated component positioning Lift-on/Lift-off System based on LoRa technologies

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100740144B1 (en) * 2005-05-30 2007-07-18 삼성물산 주식회사 System of safety supervision using hard hat attached rfid tag on-the-job construction
CN201134030Y (en) * 2007-12-07 2008-10-15 上海盛锐软件技术有限公司 RFID control system in industrial production line
CN103268576A (en) * 2013-05-29 2013-08-28 上海大学 System and method for checking and accepting quality of precast concrete component

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100740144B1 (en) * 2005-05-30 2007-07-18 삼성물산 주식회사 System of safety supervision using hard hat attached rfid tag on-the-job construction
CN201134030Y (en) * 2007-12-07 2008-10-15 上海盛锐软件技术有限公司 RFID control system in industrial production line
CN103268576A (en) * 2013-05-29 2013-08-28 上海大学 System and method for checking and accepting quality of precast concrete component

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李天华: "装配式建筑寿命周期管理中BIM与RFID应用研究", 《中国优秀硕士学位论文全文数据库》 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104915741A (en) * 2014-03-11 2015-09-16 汪再军 Building facility operation management system based on BIM technology
CN106663142A (en) * 2014-06-26 2017-05-10 三星电子株式会社 Method and apparatus for detecting building information
CN104268708B (en) * 2014-10-09 2017-11-14 湖南普云智能科技股份有限公司 A kind of building template intelligent management system and method based on cloud intellectual technology
CN104268708A (en) * 2014-10-09 2015-01-07 湖南普云智能科技有限公司 Building template intelligent managing system and method based on cloud intelligence technology
CN104460506A (en) * 2014-11-13 2015-03-25 湖南普云智能科技有限公司 Method for achieving template unmanned construction
CN104460506B (en) * 2014-11-13 2017-04-12 湖南普云智能科技股份有限公司 Method for achieving template unmanned construction
CN104778488B (en) * 2014-11-28 2018-04-10 华北水利水电大学 Steel building site based on BIM
CN104778488A (en) * 2014-11-28 2015-07-15 华北水利水电大学 Steel-structure building positioning paster based on BIM
CN105223876A (en) * 2015-10-23 2016-01-06 山东大卫国际建筑设计有限公司 A kind of building electromechanical equipment TT&C system
CN106639317A (en) * 2016-12-23 2017-05-10 浙江省建工集团有限责任公司 Prefabricated building complete set constructing technology
CN106760557A (en) * 2016-12-23 2017-05-31 浙江省建工集团有限责任公司 A kind of rear-mounted construction method of prefabrication component chip
CN106600239A (en) * 2016-12-28 2017-04-26 中建科技有限公司 Assembly type building construction full process data cooperation management system based on BIM
CN106777751A (en) * 2016-12-30 2017-05-31 译筑信息科技(上海)有限公司 Architecture information processing method and processing device
CN106869308A (en) * 2017-03-13 2017-06-20 同济大学 A kind of quick turnover method of assembled architecture support system based on BIM
CN107507105A (en) * 2017-08-14 2017-12-22 广东工业大学 A kind of component information input method, device and handheld device
CN107663947A (en) * 2017-10-31 2018-02-06 中国冶集团有限公司 Autoclaved aerated concrete slab construction method in assembled architecture based on BIM
CN108616815A (en) * 2018-05-06 2018-10-02 北京工业大学 A kind of prefabricated component positioning Lift-on/Lift-off System based on LoRa technologies
CN108532953A (en) * 2018-05-18 2018-09-14 宝业湖北建工集团有限公司 Overhanging board construction method based on BIM and construction techniques

Similar Documents

Publication Publication Date Title
Chen et al. A vision of IoT: Applications, challenges, and opportunities with china perspective
Zhang et al. Real-time information capturing and integration framework of the internet of manufacturing things
CN103472788B (en) Based on the operation tunnel maintaining healthy monitoring management method of BIM
Chen et al. Research on key technology and applications for internet of things
CN103116348B (en) production line control system and control method thereof
Zhang et al. Smart box-enabled product–service system for cloud logistics
Silva et al. A dependability evaluation tool for the Internet of Things
CN100458823C (en) Automatic crusing robot system based on radio-frequency identification technology
CN103971220A (en) Intelligent hazardous chemical substance warehouse management system
CN100470555C (en) Incremental association of metadata to production data
KR20090037082A (en) Apparatus of analizing the construction productivity using rfid based on the wireless communication and thereof
CN103559562A (en) Power grid intelligent operation system and achieving method thereof
CN101866172B (en) RFID technology based concrete quality monitoring system and working method thereof
CN104573759A (en) Functional vehicle monitoring method based on radio frequency tag technology
Zhang et al. Real-time work-in-progress management for smart object-enabled ubiquitous shop-floor environment
Wang Intelligent and integrated RFID (II-RFID) system for improving traceability in manufacturing
CN102426525B (en) Panoramic modeling method of multi-application system
CN103576632B (en) Pig growth environmental monitoring based on technology of Internet of things and control system and method
CN102799975B (en) Full life circle management system for food based on RFID (radio frequency identification) and implementation method thereof
CN102801773A (en) Internet of things system and acquisition and monitoring method for article information
CN105427674A (en) System and method for real-time unmanned plane flight state evaluation early warning
CN202217318U (en) Tyre supply chain management system based on RFID
CN101576616A (en) Indoor positioning system based on RFID technology
Sutrisna et al. Cyber-physical systems integration of building information models and the physical construction
Mo et al. RFID infrastructure design: a case study of two Australian RFID projects

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20140122