CN103452121A - Long pile and short pile combined single-row pile and horizontal internal support pile supporting structure and construction method thereof - Google Patents

Long pile and short pile combined single-row pile and horizontal internal support pile supporting structure and construction method thereof Download PDF

Info

Publication number
CN103452121A
CN103452121A CN2013103744837A CN201310374483A CN103452121A CN 103452121 A CN103452121 A CN 103452121A CN 2013103744837 A CN2013103744837 A CN 2013103744837A CN 201310374483 A CN201310374483 A CN 201310374483A CN 103452121 A CN103452121 A CN 103452121A
Authority
CN
China
Prior art keywords
stake
pile
piles
inner support
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013103744837A
Other languages
Chinese (zh)
Inventor
丁洪元
宁国立
陈斌
昌钰
刘耀峰
杨鹏程
刘军
常永兴
韩华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Original Assignee
Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC filed Critical Wuhan Surveying Geotechnical Research Institute Co Ltd of MCC
Priority to CN2013103744837A priority Critical patent/CN103452121A/en
Publication of CN103452121A publication Critical patent/CN103452121A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention discloses a long pile and short pile combined single-row pile and horizontal internal support pile supporting structure and a construction method thereof. The structure is characterized in that long piles and short piles are arranged in a staggering way at equal intervals in a single row of pile; the clear spacing between two adjacent piles is 200 to 400mm; two rows of concrete deep stirring piles are arranged behind a support pile to serve as a waterproof curtain; the layer number of internal supports is 1 to 3; the first layer of horizontal internal supports is generally arranged on the top of the support pile; the distance between the adjacent internal supports which are arranged up and down is 4 to 6m. When the supporting structure is designed, in all the rows of piles, parameters of the short piles are calculated to make sure that the requirements on the horizontal displacement, the bending capacity and the overturning resistance of the short piles are met and then parameters of the long piles are calculated to make sure that the requirement on the deep slide stability of the long piles is met. The construction method comprises the following main construction steps of constructing the long piles, constructing the short piles, constructing the concrete deep stirring pile curtain, hardening the ground before excavating a foundation pit, constructing a drainage facility, excavating the first layer of earth, constructing a pile top beam and the horizontal internal supports, excavating the second layer of earth, and performing the other steps until the earth is excavated to the bottom of the foundation pit.

Description

A kind of stake support supporting and protection structure and job practices thereof of single stake+horizontal inner support of length stake combination
Technical field
The present invention relates to the Deep Foundation Pit Supporting Project technical field, specifically a kind of stake support supporting and protection structure and job practices thereof of single stake+horizontal inner support of length stake combination.
Background technology
In the Deep Thick Soft Ground Area Deep Thick Soft Ground zone of Wuhan Area particularly, in order to guarantee the Against Deep sliding of foundation ditch, monolithic stability, anti-protuberance is stablized requirements such as reaching overturning or slip resistance analysis, foundation pit supporting pile need to enter down the good ground that covers better performances through Deep Thick Soft Ground, the stake of soldier pile is long mainly to be determined by the buried depth that covers good ground under Soft Soil Layer, little with the cutting depth relation of foundation ditch self, in this case, when the excavation of foundation pit degree of depth is deepened, the general stake footpath that only needs to adjust soldier pile of design of its support, the layer t53fg number of the arrangement of reinforcement of pile body and additional horizontal inner support, the long variation of stake of soldier pile is little.The result caused thus is: for the foundation ditch of the middle deep about cutting depth 7 ~ 10m, its soldier pile length is more than 20m, even reach more than 30 meter, increased widely the cost of pattern foundation pit supporting structure, profligacy country and social resource, with the low-carbon environment-friendly theory of current whole society promotion, run in the opposite direction.
Summary of the invention
The present invention is directed to the long present situation that unanimously causes the social resources significant wastage of the long long and adjacent soldier pile stake of Deep Thick Soft Ground Area base pit engineering soldier pile stake, a kind of stake support supporting and protection structure and job practices thereof of single stake+horizontal inner support of length stake combination are provided, this foundation pit supporting construction and job practices thereof are applicable to any stratum, especially remarkable in the deep soft soil layer economic benefit.
The stake support supporting and protection structure of the single stake+horizontal inner support of a kind of length stake of the present invention combination, comprise: one is long and the other is short that interval is arranged for single stake, establish two draining earth deep-mixed piles after soldier pile and make water-stop curtain, be connected with the steel concrete waling on soldier pile, on the steel concrete waling, be connected with inner support.
Described single stake is single deposited reinforced concrete pile.
The cross sectional shape of described single deposited reinforced concrete pile is circular or square.
The stake footpath of described cement-soil mixing pile is 500mm, pile spacing 350mm, and row of piles is apart from 400mm.
The length stake equidistantly arranges, the clear spacing of adjacent two piles is 200 ~ 400mm, and the excessive effect of the barrier to weak soil of clear spacing reduces, and is unfavorable for anti-deep sliding stability requirement.
Described inner support is steel pipe support, shaped steel support or steel concrete support.
The number of plies of inner support depends on the excavation of foundation pit degree of depth, surrounding enviroment condition and sitework geological conditions etc., is generally 1 ~ 3 layer, and the 1st layer of horizontal inner support generally is located at the soldier pile top, and the spacing of neighbouring two-layer inner support is 4 ~ 6m.
The waling of described inner support is the steel concrete waling, and the waling of the 1st layer of horizontal inner support is steel concrete Guan Liang, and the waling of all the other each layer of horizontal inner supports is reinforced concrete waist rail.
When Foundation Pit Support Design is calculated, all campshed is first pressed stub calculating, guarantees that its horizontal movement, anti-bending bearing capacity, overturning or slip resistance analysis meet the demands; Then calculate by long stake, guarantee that its deep sliding stability meets the demands.
A kind of job practices of stake support supporting and protection structure of single stake+horizontal inner support of length stake combination, its step is as follows:
1. long pile driving construction: measure unwrapping wire, rig is in place, pore-forming, and clear hole, reinforcing cage system peace, conduit is installed, secondary pile hole cleaning, underwater concrete perfusion;
2. stub construction: measure unwrapping wire, rig is in place, pore-forming, and clear hole, reinforcing cage system peace, conduit is installed, secondary pile hole cleaning, underwater concrete perfusion;
3. cement-soil mixing pile curtain construction: deep mixer is located, and the preparation cement paste, stir sinking in advance, and whitewashing is stirred, promoted, and repeats stirring and sinks, and repeats to stir whitewashing and is promoted to aperture, shutdown, cleaning, displacement;
4. before excavation of foundation pit, to the ground in the 3~5m scope of top, slope, adopt the C20 plain concrete of thick 6~8cm to make cure process, in 1.0m left and right, top, distance slope, top, one slope catchwater is set;
5. the 1st layer of soil excavation is at the bottom of soldier pile stake apical cap beam;
6. Guan Liang construction;
7. the horizontal inner support construction of first floor;
8. descend one deck soil excavation;
If 9. the number of plies of horizontal inner support is more than 1 layer, successively by soil excavation at the bottom of the waist rail of each layer of horizontal inner support, each layer of horizontal inner support of constructing successively;
10. repeating step 8., by the pit earthwork stage excavation to foundation ditch bottom.
The stake support supporting and protection structure of the single stake+horizontal inner support of a kind of length stake of the present invention combination and job practices thereof adopt the stake support supporting and protection structure of the single stake+horizontal inner support of length stake combination, can save the consumption of the constructional materialss such as reinforcing bar, concrete, cement, duration can be saved again, thereby for the Construction Party reduces investment outlay, reduce the wasting of resources, reach the target of low-carbon environment-friendly, energy-saving and emission-reduction.
The accompanying drawing explanation
The engineering effort figure of the stake support supporting and protection structure of the single stake that Fig. 1 is length stake combination+2 layers of horizontal steel tube support.
The engineering facade design sketch of the stake support supporting and protection structure of the single stake that Fig. 2 is length stake combination+2 layers of horizontal steel tube support.
The engineering effort figure of the stake support supporting and protection structure of the single stake that Fig. 3 is length stake combination+1 layer of horizontal reinforcement concrete support.
The engineering facade design sketch of the stake support supporting and protection structure of the single stake that Fig. 4 is length stake combination+1 layer of horizontal reinforcement concrete support.
The engineering of the stake support supporting and protection structure of the single stake+horizontal reinforcement concrete support that Fig. 5 is length stake combination is overlooked design sketch.
The specific embodiment
embodiment mono-
Shown in Fig. 1, Fig. 2, Fig. 5, the job practices of the stake support supporting and protection structure of a kind of single stake of length stake combination+2 layers of horizontal steel tube support, its step is as follows:
1. long pile driving construction: measure unwrapping wire, rig is in place, pore-forming, and clear hole, reinforcing cage system peace, conduit is installed, secondary pile hole cleaning, underwater concrete perfusion;
2. stub construction: measure unwrapping wire, rig is in place, pore-forming, and clear hole, reinforcing cage system peace, conduit is installed, secondary pile hole cleaning, underwater concrete perfusion;
3. cement-soil mixing pile curtain construction: deep mixer is located, and the preparation cement paste, stir sinking in advance, and whitewashing is stirred, promoted, and repeats stirring and sinks, and repeats to stir whitewashing and is promoted to aperture, shutdown, cleaning, displacement;
4. before excavation of foundation pit, to the ground in the 3~5m scope of top, slope, adopt the C20 plain concrete of thick 6~8cm to make cure process, in 1.0m left and right, top, distance slope, top, one slope catchwater is set;
5. the 1st layer of soil excavation is at the bottom of soldier pile stake apical cap beam;
6. stake apical cap beam, the 1st layer of steel pipe support construction;
7. descend one deck soil excavation;
8. by the bottom of the waist rail of 2 layers of horizontal reinforcement concrete support of soil excavation to the, construction reinforced bar concrete breast beam and the 2nd layer of steel pipe support;
9. repeating step 7., by the pit earthwork stage excavation to foundation ditch bottom;
embodiment bis-
Shown in Fig. 3, Fig. 4, Fig. 5, the job practices of the stake support supporting and protection structure of a kind of single stake of length stake combination+1 layer of horizontal reinforcement concrete support, its step is as follows:
1. long pile driving construction: measure unwrapping wire, rig is in place, pore-forming, and clear hole, reinforcing cage system peace, conduit is installed, secondary pile hole cleaning, underwater concrete perfusion;
2. stub construction: measure unwrapping wire, rig is in place, pore-forming, and clear hole, reinforcing cage system peace, conduit is installed, secondary pile hole cleaning, underwater concrete perfusion;
3. cement-soil mixing pile curtain construction: deep mixer is located, and the preparation cement paste, stir sinking in advance, and whitewashing is stirred, promoted, and repeats stirring and sinks, and repeats to stir whitewashing and is promoted to aperture, shutdown, cleaning, displacement;
4. before excavation of foundation pit, to the ground in the 3~5m scope of top, slope, adopt the C20 plain concrete of thick 6~8cm to make cure process, in 1.0m left and right, top, distance slope, top, one slope catchwater is set;
5. the 1st layer of soil excavation is at the bottom of soldier pile stake apical cap beam;
6. stake apical cap beam, steel concrete support construction;
7. descend one deck soil excavation;
8. repeating step 7., by the pit earthwork stage excavation to foundation ditch bottom.

Claims (6)

1. supporting and protection structure is supportted in the stake of the single stake+horizontal inner support of a length stake combination, it is characterized in that: comprise single stake one is long and the other is short that interval is arranged, establish two draining earth deep-mixed piles after soldier pile and make water-stop curtain, be connected with the steel concrete waling on soldier pile, on the steel concrete waling, be connected with inner support.
2. supporting and protection structure is supportted in the stake of the single stake+horizontal inner support of root a tree name a kind of length stake combination claimed in claim 1, it is characterized in that: described single stake is single deposited reinforced concrete pile, and the cross sectional shape of stake is circular or square.
3. supporting and protection structure is supportted in the stake of the single stake+horizontal inner support of root a tree name a kind of length stake combination claimed in claim 1, it is characterized in that: for the length stake, equidistantly arrange for described single, the clear spacing of adjacent two piles is 200 ~ 400mm.
4. supporting and protection structure is supportted in the stake of the single stake+horizontal inner support of root a tree name a kind of length stake combination claimed in claim 1, it is characterized in that: the stake footpath of described cement-soil mixing pile is 500mm, pile spacing 350mm, and row of piles is apart from 400mm.
5. supporting and protection structure is supportted in the stake of the single stake+horizontal inner support of root a tree name a kind of length stake combination claimed in claim 1, it is characterized in that: described inner support is steel pipe support, shaped steel support or steel concrete support.
6. the job practices of supporting and protection structure is supportted in the stake of the single stake+horizontal inner support of a length stake combination, and it is characterized in that: its step is as follows:
1. long pile driving construction: measure unwrapping wire, rig is in place, pore-forming, and clear hole, reinforcing cage system peace, conduit is installed, secondary pile hole cleaning, underwater concrete perfusion;
2. stub construction: measure unwrapping wire, rig is in place, pore-forming, and clear hole, reinforcing cage system peace, conduit is installed, secondary pile hole cleaning, underwater concrete perfusion;
3. cement-soil mixing pile curtain construction: deep mixer is located, and the preparation cement paste, stir sinking in advance, and whitewashing is stirred, promoted, and repeats stirring and sinks, and repeats to stir whitewashing and is promoted to aperture, shutdown, cleaning, displacement;
4. before excavation of foundation pit, to the ground in the 3~5m scope of top, slope, adopt the C20 plain concrete of thick 6~8cm to make cure process, in 1.0m left and right, top, distance slope, top, one slope catchwater is set;
5. the 1st layer of soil excavation is at the bottom of soldier pile stake apical cap beam;
6. Guan Liang construction;
7. the horizontal inner support construction of first floor;
8. descend one deck soil excavation;
If 9. the number of plies of horizontal inner support is more than 1 layer, successively by soil excavation at the bottom of the waist rail of each layer of horizontal inner support, each layer of horizontal inner support of constructing successively;
10. repeating step 8., by the pit earthwork stage excavation to foundation ditch bottom.
CN2013103744837A 2013-08-26 2013-08-26 Long pile and short pile combined single-row pile and horizontal internal support pile supporting structure and construction method thereof Pending CN103452121A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013103744837A CN103452121A (en) 2013-08-26 2013-08-26 Long pile and short pile combined single-row pile and horizontal internal support pile supporting structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013103744837A CN103452121A (en) 2013-08-26 2013-08-26 Long pile and short pile combined single-row pile and horizontal internal support pile supporting structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN103452121A true CN103452121A (en) 2013-12-18

Family

ID=49734928

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013103744837A Pending CN103452121A (en) 2013-08-26 2013-08-26 Long pile and short pile combined single-row pile and horizontal internal support pile supporting structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN103452121A (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967015A (en) * 2014-05-21 2014-08-06 刘绍国 Water-stopping deep foundation pit excavation method and structure thereof
CN104018496A (en) * 2014-05-13 2014-09-03 中冶集团武汉勘察研究院有限公司 Round-section slide-resistant pile with pile body provided with horizontal haunched beam and construction method of round-section slide-resistant pile
CN104404967A (en) * 2014-11-26 2015-03-11 南京东大鸿基新技术发展有限公司 Rigid frame foundation pit support structure and construction method
CN104452771A (en) * 2014-11-06 2015-03-25 左克伟 Counterfort type row pile supporting method for foundation pit
CN104790412A (en) * 2015-04-07 2015-07-22 罗海军 Large-width foundation pit supporting construction method under confined water condition
CN105178329A (en) * 2015-08-08 2015-12-23 广州市设计院 Wall supporting type supporting structure and construction method of foundation pit underground continuous wall
CN106013172A (en) * 2016-07-01 2016-10-12 杭州江润科技有限公司 Double row pile and diagonal brace combined soft soil deep foundation pit supporting structure and construction method
CN106120804A (en) * 2016-06-26 2016-11-16 中建三局集团有限公司 A kind of two grades of support systems of super-giant foundation pit double-row pile and construction method thereof
CN106223345A (en) * 2016-09-14 2016-12-14 上海强劲地基工程股份有限公司 A kind of length interleaved formula Soil-cement piling wall construction equipment and construction method
CN106759373A (en) * 2016-11-17 2017-05-31 中冶集团武汉勘察研究院有限公司 A kind of computational methods of long-short pile combined support structure
CN107503355A (en) * 2017-07-20 2017-12-22 广东省建筑工程集团有限公司 Shaped steel formula double-row pile foundation pit supporting system and its construction method are inserted after outer row
CN107794927A (en) * 2017-09-11 2018-03-13 广州机施建设集团有限公司 A kind of deep foundation pit earthwork digging method with hard rock geology
CN108005085A (en) * 2017-12-04 2018-05-08 广东中南建设有限公司 Foundation pit supporting construction and its construction method
CN108343071A (en) * 2018-03-19 2018-07-31 南京市测绘勘察研究院股份有限公司 A kind of foundation pit supporting construction and construction method of steel sheet pile combined deposited pile
CN108708381A (en) * 2018-06-08 2018-10-26 中国铁道科学研究院深圳研究设计院 A kind of load retaining wall double-row pile combination large span support combinations support system
CN109113070A (en) * 2018-08-24 2019-01-01 洛阳理工学院 External supporting structure and construction method in a kind of building foundation pit
CN109137933A (en) * 2018-09-29 2019-01-04 浙江理工大学 Pit Bracing in Soft Soil method without inner support
CN109403341A (en) * 2018-10-31 2019-03-01 中建局集团建设发展有限公司 A kind of compound gravity retaining wall structure of soft clay area ultra-deep foundation pit and its engineering method
CN111441361A (en) * 2020-03-05 2020-07-24 浙江省建筑设计研究院 Pit enclosure system of shaft type underground stereo garage and construction method
CN112779853A (en) * 2019-11-07 2021-05-11 中冶京诚工程技术有限公司 Abutment and design and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006291462A (en) * 2005-04-06 2006-10-26 Kowa Seisakusho:Kk Removing method and removing instrument for earth retaining supporting jack
CN201321616Y (en) * 2008-12-23 2009-10-07 中铁二院工程集团有限责任公司 Deep foundation pit supporting, reinforcing, anti-seepage and waterproof structure
CN102011404A (en) * 2010-11-24 2011-04-13 温州中城建设集团有限公司 Pit supporting structure and construction method thereof
CN202830938U (en) * 2012-10-18 2013-03-27 上海强劲地基工程股份有限公司 Supporting structure for controlling foundation trench stability
CN202936772U (en) * 2012-11-14 2013-05-15 河南省电力勘测设计院 Long-short vibro-replacement stone column for treating badly liquefied foundation
CN202989900U (en) * 2012-12-18 2013-06-12 内蒙古电力勘测设计院 Foundation arrangement structure of vibro-replacement broken stone long pile and vibro-replacement stone short pile

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006291462A (en) * 2005-04-06 2006-10-26 Kowa Seisakusho:Kk Removing method and removing instrument for earth retaining supporting jack
CN201321616Y (en) * 2008-12-23 2009-10-07 中铁二院工程集团有限责任公司 Deep foundation pit supporting, reinforcing, anti-seepage and waterproof structure
CN102011404A (en) * 2010-11-24 2011-04-13 温州中城建设集团有限公司 Pit supporting structure and construction method thereof
CN202830938U (en) * 2012-10-18 2013-03-27 上海强劲地基工程股份有限公司 Supporting structure for controlling foundation trench stability
CN202936772U (en) * 2012-11-14 2013-05-15 河南省电力勘测设计院 Long-short vibro-replacement stone column for treating badly liquefied foundation
CN202989900U (en) * 2012-12-18 2013-06-12 内蒙古电力勘测设计院 Foundation arrangement structure of vibro-replacement broken stone long pile and vibro-replacement stone short pile

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李竹等: "带水平支撑长短桩组合排桩工作性状模型试验研究", 《岩土工程学报》, vol. 32, 31 July 2010 (2010-07-31) *

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104018496A (en) * 2014-05-13 2014-09-03 中冶集团武汉勘察研究院有限公司 Round-section slide-resistant pile with pile body provided with horizontal haunched beam and construction method of round-section slide-resistant pile
CN104018496B (en) * 2014-05-13 2017-01-04 中冶集团武汉勘察研究院有限公司 A kind of pile body arranges circular cross-section friction pile and the construction method thereof of Horizontal hunche beam
CN103967015A (en) * 2014-05-21 2014-08-06 刘绍国 Water-stopping deep foundation pit excavation method and structure thereof
CN103967015B (en) * 2014-05-21 2016-04-27 刘绍国 A kind of water seal for deep foundation pit excavation method and structure thereof
CN104452771A (en) * 2014-11-06 2015-03-25 左克伟 Counterfort type row pile supporting method for foundation pit
CN104404967B (en) * 2014-11-26 2016-09-21 南京东大鸿基新技术发展有限公司 Rigid frame posture internal support of foundation pit structure and construction method
CN104404967A (en) * 2014-11-26 2015-03-11 南京东大鸿基新技术发展有限公司 Rigid frame foundation pit support structure and construction method
CN104790412A (en) * 2015-04-07 2015-07-22 罗海军 Large-width foundation pit supporting construction method under confined water condition
CN106120803A (en) * 2015-04-07 2016-11-16 罗海军 Base pit stand construction in the case of artesian water
CN105178329A (en) * 2015-08-08 2015-12-23 广州市设计院 Wall supporting type supporting structure and construction method of foundation pit underground continuous wall
CN106120804A (en) * 2016-06-26 2016-11-16 中建三局集团有限公司 A kind of two grades of support systems of super-giant foundation pit double-row pile and construction method thereof
CN106120804B (en) * 2016-06-26 2018-12-11 中建三局集团有限公司 A kind of super-giant foundation pit double-row pile second level support system and its construction method
CN106013172A (en) * 2016-07-01 2016-10-12 杭州江润科技有限公司 Double row pile and diagonal brace combined soft soil deep foundation pit supporting structure and construction method
CN106013172B (en) * 2016-07-01 2018-02-27 新宇建设有限公司 Double-row pile combines Deep Foundation Pit Support for Soft Soil structure and construction method with diagonal brace
CN106223345A (en) * 2016-09-14 2016-12-14 上海强劲地基工程股份有限公司 A kind of length interleaved formula Soil-cement piling wall construction equipment and construction method
CN106759373A (en) * 2016-11-17 2017-05-31 中冶集团武汉勘察研究院有限公司 A kind of computational methods of long-short pile combined support structure
CN107503355A (en) * 2017-07-20 2017-12-22 广东省建筑工程集团有限公司 Shaped steel formula double-row pile foundation pit supporting system and its construction method are inserted after outer row
CN107503355B (en) * 2017-07-20 2023-10-13 广东省建筑工程集团有限公司 Externally-arranged rear-inserted steel type double-row pile foundation pit supporting system and construction method thereof
CN107794927A (en) * 2017-09-11 2018-03-13 广州机施建设集团有限公司 A kind of deep foundation pit earthwork digging method with hard rock geology
CN107794927B (en) * 2017-09-11 2019-12-24 广州机施建设集团有限公司 Deep foundation pit earthwork excavation method with hard rock geology
CN108005085A (en) * 2017-12-04 2018-05-08 广东中南建设有限公司 Foundation pit supporting construction and its construction method
CN108343071A (en) * 2018-03-19 2018-07-31 南京市测绘勘察研究院股份有限公司 A kind of foundation pit supporting construction and construction method of steel sheet pile combined deposited pile
CN108708381A (en) * 2018-06-08 2018-10-26 中国铁道科学研究院深圳研究设计院 A kind of load retaining wall double-row pile combination large span support combinations support system
CN109113070A (en) * 2018-08-24 2019-01-01 洛阳理工学院 External supporting structure and construction method in a kind of building foundation pit
CN109137933A (en) * 2018-09-29 2019-01-04 浙江理工大学 Pit Bracing in Soft Soil method without inner support
CN109403341A (en) * 2018-10-31 2019-03-01 中建局集团建设发展有限公司 A kind of compound gravity retaining wall structure of soft clay area ultra-deep foundation pit and its engineering method
CN112779853A (en) * 2019-11-07 2021-05-11 中冶京诚工程技术有限公司 Abutment and design and construction method thereof
CN111441361A (en) * 2020-03-05 2020-07-24 浙江省建筑设计研究院 Pit enclosure system of shaft type underground stereo garage and construction method

Similar Documents

Publication Publication Date Title
CN103452121A (en) Long pile and short pile combined single-row pile and horizontal internal support pile supporting structure and construction method thereof
CN204370431U (en) A kind of occlusion long-short pile space enclosing structure
CN106013171B (en) A kind of semi-rigid supporting construction semi-flexible and method of deep-foundation side wall
CN206512723U (en) A kind of multiple-layer horizontal coupling beam double-row pile and underground pipe gallery monolithic construction
CN103938634B (en) A kind of deep foundation pit supporting structure and construction method
CN205314116U (en) Continuous type of combined type drilling cling compound structure
CN208379610U (en) A kind of broken line alternating expression double-row pile foundation pit support structure
CN107794946B (en) Underground comprehensive pipe rack structure deeply buried in soft soil and construction method thereof
CN202689031U (en) Deep foundation pit retaining and protecting retaining wall
CN103775110A (en) Underground excavation construction method for multilayer underground space of soft soil area
CN104775440A (en) Mineshaft-type underground garage deep foundation pit supporting structure
CN104563147B (en) Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
CN105569051A (en) Foundation pit support system of sandy pebble boulder geological stratification and construction method
CN110206038A (en) Supporting construction and construction method at a kind of concave foundation pit external corner
CN101353896A (en) Semi-inverse construction method of super large diameter, ultra-burial depth storage pond
CN104264683A (en) Concave ultra-deep foundation pit zoned supporting method for three-side surrounded cultural protection building
CN104131566B (en) A kind of basement is without the construction method of horizontal support foundation ditch
CN102330436A (en) Composite retaining structure and composite retaining method for half geotechnical layer ultradeep round spiral flow tank
CN107700474A (en) A kind of existing construction foundation reinforcement means and campshed formula diaphram wall
CN103628487B (en) Circular deep foundation ditch retaining wall reversed construction method
CN204356780U (en) A kind of prefabricated abnormity stake on an empty stomach for deep foundation pit supporting structure
CN205804367U (en) A kind of construction prefabricated components assembling structure
CN103046556B (en) Without inner support annular space enclosing structure and preparation method thereof
CN205382942U (en) Multilayer underground space curtain posture subsurface excavated construction's supporting construction under existing facility
CN107313454B (en) Construction method of underground garage

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131218