CN103437555A - 一种墙体接地盘安装方法 - Google Patents

一种墙体接地盘安装方法 Download PDF

Info

Publication number
CN103437555A
CN103437555A CN2013103742494A CN201310374249A CN103437555A CN 103437555 A CN103437555 A CN 103437555A CN 2013103742494 A CN2013103742494 A CN 2013103742494A CN 201310374249 A CN201310374249 A CN 201310374249A CN 103437555 A CN103437555 A CN 103437555A
Authority
CN
China
Prior art keywords
template
grounding disc
grounding plate
grounding
casting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013103742494A
Other languages
English (en)
Other versions
CN103437555B (zh
Inventor
李庆兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Nuclear Engineering Research and Design Institute Co Ltd
Original Assignee
STATE NUCLEAR POWER ENGINEERING Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by STATE NUCLEAR POWER ENGINEERING Co filed Critical STATE NUCLEAR POWER ENGINEERING Co
Priority to CN201310374249.4A priority Critical patent/CN103437555B/zh
Publication of CN103437555A publication Critical patent/CN103437555A/zh
Application granted granted Critical
Publication of CN103437555B publication Critical patent/CN103437555B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明提供了一种砼墙体接地盘安装方法,其特征在于,步骤为:根据图纸在模板相应位置标出铸造接地盘的螺栓孔位置,在确定好的位置对模板进行开孔,孔径根据螺栓直径确定;将与接地盘配套的螺栓拧在接地盘的孔上,将螺栓穿过模板后,垫上垫片再把螺帽拧在螺栓上,将铸造接地盘和模板固定紧;将模板准确定位,拧紧对拉螺栓,装好加固肋板;模板拆除后,用黄油将盘面的螺栓密封,保证螺栓孔丝牙可用。本发明提高了接地盘的安装质量;取消了原有安装方式的固定支撑体系,节省了钢筋的使用量,降低了施工成本;缩短了接地盘的安装时间。本发明适用于核电、水电、火电、地铁、城市建筑工程中使用螺栓孔洞型铸造接地盘的建筑墙体接地盘安装工程。

Description

一种墙体接地盘安装方法技术领域
[0001] 本发明涉及一种在核电、水电、火电、地铁、城市建筑工程等领域中使用螺栓孔洞型接地盘的建筑墙体接地盘安装工程。
背景技术
[0002] 如图1及图2所示,目前在砼墙体中安装螺栓孔洞型铸造接地盘的工艺如下:首先,在墙体钢筋绑扎完毕后敷设接地铜缆1,采用放热焊将接地铜缆I与铸造接地盘2焊接。然后,将铸造接地盘2固定在预制好的钢筋焊接支架3上。钢筋焊接支架3根据安装位置不同,共有如图3A及图3B所示的两种形式,钢筋焊接支架3上具有多个焊接点4。随后,把钢筋焊接支架3固定在墙体主筋上,保持铸造接地盘2表面要与浇筑后的砼墙面相平,钢筋焊接支架3的背部焊接两根钢筋5,钢筋5贯穿浇注后的墙体,用于支撑钢筋焊接支架3,防止支设模板6时铸造接地盘2被挤压凹陷进烧筑后的墙体内。最后,支设模板6,烧筑混凝土,混凝土浇注完成后形成墙体,再将模板6拆除。
[0003] 上述工艺存在以下技术问题:
[0004] 第一、由钢筋焊接支架3及钢筋5构成的固定支架体系易在工程施工过程中受到混凝土浇筑扰动及施工人员攀爬支撑等外力影响,导致铸造接地盘2凹陷、移位、倾斜。
[0005] 第二、模板6支设导致铸造接地盘2凹陷。模板6与安装好的铸造接地盘2之间缝隙较大,混凝土浇筑完成后铸造接地盘2被混凝土覆盖,从墙体表面基本上找不到预埋的铸造接地盘2,导致铸造接地盘2凹陷在墙体内。
[0006] 第三、混凝土在浇注过程中容易出现轻微涨模现象,导致墙体表面部分区域凸起,从而造成铸造接地盘2深陷在烧.筑后的墙体内。
[0007] 第四、模板6在支设时容易将铸造接地盘2固定支架体系后方的支架垫块压碎,导致支架体系失效,最终导致混凝土浇注后,铸造接地盘2倾斜、移位、凹陷。
发明内容
[0008] 本发明要解决的技术问题是防止铸造接地盘发生凹陷、移位及倾斜。
[0009] 为了解决上述技术问题,本发明的技术方案是提供了一种墙体接地盘安装方法,其步骤为:
[0010] 步骤1、在墙体钢筋绑扎完毕后敷设接地铜缆,将接地铜缆与铸造接地盘焊接,;其特征在于:
[0011] 步骤2、根据图纸上铸造接地盘的安装位置在模板的相应位置标出铸造接地盘的螺栓孔,确定开孔位置,在确定好的开孔位置处对模板进行开孔,孔径根据与铸造接地盘相匹配的螺栓直径确定;
[0012] 步骤3、将与铸造接地盘相匹配的螺栓拧入步骤2开好的孔中,从而将铸造接地盘和模板固定连接;
[0013] 步骤4、模板准确定位后,浇筑混凝土形成墙体,再拧出螺栓将模板拆除;[0014] 步骤5、将铸造接地盘露于墙面的螺栓孔密封,在防止杂物进入铸造接地盘螺栓孔的同时,保证该螺栓孔的丝牙可用。
[0015] 优选地,在步骤3中,将所述铸造接地盘与所述模板固定连接后,在所述模板上做上醒目标识以提醒工人在拆卸模板时不要破坏接地盘,并确保在拆卸模板之前将固定铸造接地盘的螺栓拆除。
[0016] 优选地,在所述步骤5中,采用黄油将所述铸造接地盘的螺栓孔密封。
[0017] 本发明提高了接地盘的安装质量;取消了原有安装方式的固定支撑体系,节省了钢筋的使用量,降低了施工成本;缩短了接地盘的安装时间。本发明适用于核电、水电、火电、地铁、城市建筑工程中使用螺栓孔洞型铸造接地盘的建筑墙体接地盘安装工程。
附图说明
[0018] 图1为背景技术中所述的接地盘安装侧面示意图;
[0019] 图2为背景技术中所述的接地盘安装正面示意图;
[0020] 图3A为一种形式的钢筋焊接支架;
[0021] 图3B为另一种形式的钢筋焊接支架;
[0022] 图4为本发明所述铸造接地盘的安装方式示意图。
具体实施方式
[0023] 为使本发明更明显易懂,兹以优选实施例,并配合附图作详细说明如下。
[0024] 结合图4,本发明提供的一种墙体接地盘安装方法,其步骤为:
[0025] 步骤1、在墙体钢筋绑扎完毕后敷设接地铜缆1,采用放热焊将接地铜缆I与铸造接地盘2焊接;
[0026] 步骤2、根据图纸上铸造接地盘2的安装位置在模板6的相应位置标出若干铸造接地盘2的螺栓孔,确定开孔位置,在确定好的开孔位置处对模板6进行开孔,孔径根据与铸造接地盘2相匹配的螺栓直径确定;
[0027] 步骤3、将与铸造接地盘2相匹配的螺栓拧入步骤2开好的孔中,将螺栓穿过模板6后,垫上垫片再把螺帽拧在螺栓上,将铸造接地盘2和模板6固定紧,并在模板6的相应位置处做上醒目的标识以提醒工人在拆卸模板6时注意不要破坏铸造接地盘2,并确保在拆卸模板6之前必须将固定铸造接地盘2的螺栓拆掉;
[0028] 步骤4、将模板6准确定位,拧紧对拉螺栓,装好加固肋板,浇筑混凝土形成墙体,再拧出螺栓将模板6拆除;
[0029] 步骤5、用黄油将铸造接地盘2露于墙面的螺栓孔密封,在防止杂物进入铸造接地盘2螺栓孔的同时,保证该螺栓孔的丝牙可用。
[0030] 本发明可以用于艾力高(ERICO)墙体接地盘及其类似接地盘的安装。

Claims (3)

1.一种墙体接地盘安装方法,其步骤为: 步骤1、在墙体钢筋绑扎完毕后敷设接地铜缆(I),将接地铜缆(I)与铸造接地盘(2)焊接,其特征在于: 步骤2、根据图纸上铸造接地盘(2)的安装位置在模板¢)的相应位置标出铸造接地盘(2)的螺栓孔,确定开孔位置,在确定好的开孔位置处对模板(6)进行开孔,孔径根据与铸造接地盘(2)相匹配的螺栓直径确定; 步骤3、将与铸造接地盘(2)相匹配的螺栓拧入步骤2开好的孔中,从而将铸造接地盘(2)和模板(6)固定连接; 步骤4、模板(6)准确定位后,浇筑混凝土形成墙体,再拧出螺栓将模板(6)拆除; 步骤5、将铸造接地盘(2)露于墙面的螺栓孔密封,在防止杂物进入铸造接地盘(2)螺栓孔的同时,保证该螺栓孔的丝牙可用。
2.如权利要求1所述的一种墙体接地盘安装方法,其特征在于,在步骤3中,将所述铸造接地盘(2)与所述模板¢)固定连接后,在所述模板(6)上做上醒目标识以提醒工人在拆卸模板时不要破坏接地盘,并确保在拆卸模板(6)之前将固定铸造接地盘(2)的螺栓拆除。
3.如权利要求1所述的一种墙体接地盘安装方法,其特征在于,在所述步骤5中,采用黄油将所述铸造接地盘(2)的螺栓孔密`封。
CN201310374249.4A 2013-08-23 2013-08-23 一种墙体接地盘安装方法 Active CN103437555B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310374249.4A CN103437555B (zh) 2013-08-23 2013-08-23 一种墙体接地盘安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310374249.4A CN103437555B (zh) 2013-08-23 2013-08-23 一种墙体接地盘安装方法

Publications (2)

Publication Number Publication Date
CN103437555A true CN103437555A (zh) 2013-12-11
CN103437555B CN103437555B (zh) 2015-09-23

Family

ID=49691262

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310374249.4A Active CN103437555B (zh) 2013-08-23 2013-08-23 一种墙体接地盘安装方法

Country Status (1)

Country Link
CN (1) CN103437555B (zh)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1061200A (ja) * 1996-08-22 1998-03-03 Kansai Paint Co Ltd 壁補強工法及びこれに用いる樹脂液注入器
DE20014270U1 (de) * 2000-08-18 2000-10-05 Welz Gmbh Metallverarbeitung R Seitenschalung für Bodenplatten oder Fundamente aus Ortbeton
CN102220806A (zh) * 2011-03-30 2011-10-19 中联世纪建设集团有限公司 一种超高悬空单面竖向模板支撑加固的施工方法
WO2012169913A1 (en) * 2011-06-08 2012-12-13 Polkowski Mateusz Anchor for installation of windows or doors in buildings and method of installation of windows or doors in buildings

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH1061200A (ja) * 1996-08-22 1998-03-03 Kansai Paint Co Ltd 壁補強工法及びこれに用いる樹脂液注入器
DE20014270U1 (de) * 2000-08-18 2000-10-05 Welz Gmbh Metallverarbeitung R Seitenschalung für Bodenplatten oder Fundamente aus Ortbeton
CN102220806A (zh) * 2011-03-30 2011-10-19 中联世纪建设集团有限公司 一种超高悬空单面竖向模板支撑加固的施工方法
WO2012169913A1 (en) * 2011-06-08 2012-12-13 Polkowski Mateusz Anchor for installation of windows or doors in buildings and method of installation of windows or doors in buildings

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
铁道部电务局电务设计事务所: "《铁路设计手册 通信》", 31 July 1962, 人民铁道出版社 *

Also Published As

Publication number Publication date
CN103437555B (zh) 2015-09-23

Similar Documents

Publication Publication Date Title
CN203639932U (zh) 一种用于铁路高柱信号机机柱安装的预埋基础结构
CN103437555A (zh) 一种墙体接地盘安装方法
CN105908752B (zh) 一种用于侧墙混泥土浇筑的支模拆模系统及其工作过程
CN107964978A (zh) 风力发电机基础锚栓加固结构及基础锚栓断裂加固方法
CN202900288U (zh) 一种隧道小半径段衬砌浇筑的型钢骨架组合结构
KR20100073881A (ko) 모래를 이용한 가설받침 및 이를 이용한 교량상부구조 지지방법
CN103486335A (zh) 一种用于超高层施工混凝土泵输管的固定方法
CN209429136U (zh) 一种用于坑中坑的混凝土维护板
CN203700899U (zh) 钢质工具式临时施工道路
CN209741907U (zh) 一种综合管廊集水坑钢格栅安装结构
CN207177286U (zh) 装配式剪力墙预留后加区域模具
CN109281408B (zh) 一种综合管廊预埋件及其固定方法
JP2010216085A (ja) 支承固定構造
JP2009150067A (ja) 既設支承装置の更新方法及び更新構造
CN206667933U (zh) 一种装配式施工围挡
CN206554526U (zh) 一种预埋件固定装置
CN204960453U (zh) 新型交通监控杆
CN201827604U (zh) 一种高精度万用机械设备底座
CN204551259U (zh) 塔梁固结机构和相应的斜拉桥
CN203834959U (zh) 一种建筑施工用的安全防护栏
CN204225555U (zh) 一种可重复利用的装配式拌合站储料仓隔墙
CN104120733B (zh) 输电线路铁塔基础下沉补差构件
CN211143731U (zh) 一种后浇带支撑结构
CN106965300A (zh) 锯齿形预制板边模
CN105887910B (zh) 一种用于基础承台的支模拆模系统及其工作过程

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
COR Change of bibliographic data
CB03 Change of inventor or designer information

Inventor after: Li Qingxing

Inventor after: Zhou Chunmei

Inventor after: Yin Qingbin

Inventor before: Li Qingxing

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210127

Address after: No. 29 Hong Cao Road, Xuhui District, Shanghai

Patentee after: SHANGHAI NUCLEAR ENGINEERING RESEARCH & DESIGN INSTITUTE Co.,Ltd.

Address before: 200233 Building 2, Lane 888, Tianlin Road, Minhang District, Shanghai

Patentee before: STATE NUCLEAR POWER ENGINEERING Co.