CN103437474A - Novel stirrup shear connector and manufacturing and mounting method - Google Patents

Novel stirrup shear connector and manufacturing and mounting method Download PDF

Info

Publication number
CN103437474A
CN103437474A CN2013104120544A CN201310412054A CN103437474A CN 103437474 A CN103437474 A CN 103437474A CN 2013104120544 A CN2013104120544 A CN 2013104120544A CN 201310412054 A CN201310412054 A CN 201310412054A CN 103437474 A CN103437474 A CN 103437474A
Authority
CN
China
Prior art keywords
stirrup
shear connector
reinforcement
novel
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013104120544A
Other languages
Chinese (zh)
Inventor
胡夏闽
徐晓晖
唐伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Tech University
Original Assignee
Nanjing Tech University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Tech University filed Critical Nanjing Tech University
Priority to CN2013104120544A priority Critical patent/CN103437474A/en
Publication of CN103437474A publication Critical patent/CN103437474A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

本发明公开了一种新型箍筋剪力连接件及制备安装方法,该连接件包括:箍筋剪力连接件、箍筋、纵向钢筋、钢梁、模板、端板、横向钢筋;该制备安装方法包括:制作钢梁以及箍筋并焊接构件,纵向钢筋放置在箍筋内侧四角完成绑扎;结构吊装;楼面板支护模板绑扎钢筋;浇筑混凝土;混凝土正常养护再拆模。本发明通过纵向钢筋和箍筋绑扎起来的钢筋笼与钢梁上翼缘焊接起来,再与混凝土板中的横向、纵向钢筋绑扎起来,形成一个整体,有效的提高了钢梁-混凝土组合构件的抗剪强度和刚度;实现了混凝土与钢梁的协同受力,构造简单、方便施工;限制了掀起变形;增加了混凝土与钢梁的塑性即可变形的能力,提高了混凝土与钢梁的稳定性和可靠性。

The invention discloses a novel stirrup shear connector and a preparation and installation method. The connector includes: a stirrup shear connector, stirrups, longitudinal reinforcement, steel beams, templates, end plates, and transverse reinforcement; the preparation and installation The method includes: making steel beams and stirrups and welding components, placing longitudinal steel bars at the four corners inside the stirrups to complete binding; hoisting the structure; binding steel bars with floor plate support formwork; pouring concrete; In the present invention, the reinforcement cage bound by longitudinal reinforcement and stirrup is welded to the upper flange of the steel beam, and then bound to the transverse and longitudinal reinforcement in the concrete slab to form a whole, which effectively improves the shear resistance of the steel beam-concrete composite member Strength and rigidity; realize the synergistic force bearing of concrete and steel beams, simple structure and convenient construction; limit lift-off deformation; increase the plastic deformation ability of concrete and steel beams, and improve the stability and stability of concrete and steel beams reliability.

Description

A kind of novel stirrup shear connector and prepare mounting method
Technical field
The invention belongs to steel-concrete composite beam connector technical field, relate in particular to a kind of novel stirrup shear connector and prepare mounting method.
Background technology
Steel-concrete composite beam is, by shear connector, girder steel and concrete slab are linked to be to integral body and cooperative bending resistance component.Shear connector is the critical component of steel-concrete composite beam, and its Main Function has two: the one, be used for bearing and transmitting the longitudinal shear between girder steel and concrete slab; The 2nd, be used for resisting the effect that starts between concrete slab and girder steel.In general, shear connector can be divided into rigid connector and the large class of flexible connecting member two, and concrete can be divided into following four kinds: peg connector, bent-up bar connector, shaped steel shear connector, open pore steel plate connector.
The shortcoming that the peg connector exists: the peg connector belongs to flexible connecting member, and larger distortion can be arranged, and along with the progress of distortion, bearing capacity there will be very large reduction.In addition, the head of a nail on peg has and certain anti-ly starts effect (girder steel and concrete slab produce gap between inconsistent causing of distortion under the power effect), but slabbing action, and the fracture propagation in head of a nail surrounding concrete is very fast, the outstanding area of the head of a nail is less in addition, and it is limited in one's ability that antagonism is lifted.
The shortcoming of shaped steel shear connector: volume is larger, and its steel quantity consumption is large, and large welding capacity makes the larger shortcomings such as residual strain by welding of generation on steel plate.
The shortcoming of open pore steel plate connector: in the open pore steel plate connector, be exactly typically FBL connector and Twin-FBL connector, brittle fracture easily appears, and perforated panel connector stress of living in and concreting direction have larger negative effect to its shear stiffness, operational phase shear strength, and steel using amount is very large, moreover, the existence of steel plate also separates concrete some separating, directly affect the globality of concrete slab, make the well collaborative work of concrete and girder steel, finally affect the bearing capacity of combining structure.
The shortcoming of bent-up bar connector: the one-way of Transfer of Shear, can only transmit the shearing of fixed-direction, can not transmit the shearing of alternating direction.Therefore, the setting party of bent-up bar connector is to very tight, to construction require highly, in addition, the bent-up bar section is unfavorable for the layout of reinforcement in concrete.
Summary of the invention
The purpose of the embodiment of the present invention is to provide a kind of novel stirrup shear connector and prepares mounting method, is intended to solve that existing peg connector non-deformability is poor, shaped steel shear connector steel quantity consumption large and exist welding residual stress, open pore steel plate connector to be prone to brittle fracture, problem that the bent-up bar connector is high to construction requirement.
The embodiment of the present invention is achieved in that a kind of novel stirrup shear connector, and this novel stirrup shear connector comprises: stirrup shear connector, stirrup, longitudinal reinforcement, girder steel, template, end plate, transverse reinforcement;
Longitudinal reinforcement is placed on the stirrup inboard, and stirrup is arranged on the top flange of girder steel, and template-setup is on the top of end plate, and the stirrup shear connector is arranged on the centre position of template, and transverse reinforcement is arranged on template, the setting of staggering of transverse reinforcement and stirrup.
Further, the stirrup cross section is set to rectangle.
Further, longitudinal reinforcement is placed on the stirrup inboard by colligation.
Further, stirrup is arranged on the top flange of girder steel by welding.
Further, the stirrup shear connector is arranged on the centre position of template by end plate.
Further, transverse reinforcement and the stirrup setting of staggering.
Another purpose of the embodiment of the present invention is to provide a kind of mounting method for preparing of novel stirrup shear connector, and the mounting method for preparing of this novel stirrup shear connector comprises the following steps:
Make girder steel and stirrup welded unit, longitudinal reinforcement is placed on inboard four jiaos of stirrup and completes colligation;
Structure hoisting;
The assembling reinforcement of floor plate support template;
Concreting;
The normal maintenance of concrete form removal again.
Further, the diameter of the spacing of stirrup and diameter and longitudinal reinforcement and spacing are all determined according to the actual conditions of engineering.
Further, the assembling reinforcement of floor plate support template is the layer cloth muscle, has between two-layer reinforcing bar and supports to guarantee maintaining distance between two-layer reinforcing bar.
Novel stirrup shear connector provided by the invention and prepare mounting method, reinforcing cage and the girder steel top flange of by longitudinal reinforcement and stirrup colligation, getting up weld, then with concrete slab in laterally, the longitudinal reinforcement colligation gets up, and forms an integral body;
The present invention has the following advantages:
1. outer load is done the used time, and the lateral deformation that stirrup has limited concrete slab is set, and effectively improves shear strength and the rigidity of girder steel-concrete combined component;
2. by concreting, concrete and girder steel are realized vertical and vertical shearing resistance by this stirrup shear connector, and concrete and connector interweave mutually, have improved overall performance and vertical shear resistance;
3. longitudinal reinforcement and stirrup setting, realized the cooperative bearing of concrete and girder steel, simple structure, convenient construction;
4. the setting of stirrup, limited lateral deformation, is beneficial to the distortion of controlling whole concrete and girder steel element, limited and started distortion;
5. the plasticity that has effectively increased concrete and girder steel is deformable ability, has improved stability and the reliability of concrete and girder steel;
6. on original basis, transformed, it is very general that longitudinal reinforcement and stirrup are used in concrete and girder steel engineering, is easy to obtain, the convenient making.
The accompanying drawing explanation
Fig. 1 is the structural representation of the novel stirrup shear connector that provides of the embodiment of the present invention;
Fig. 2 is the Novel steel beam that provides of the embodiment of the present invention and the apparatus structure schematic diagram of stirrup connector;
In figure: 1, stirrup shear connector; 1-1, stirrup; 1-2, longitudinal reinforcement; 2, girder steel; 3, template; 4, end plate; 5, transverse reinforcement;
Fig. 3 is that the novel stirrup shear connector that the embodiment of the present invention provides prepares the mounting method flow chart.
Fig. 4 is the floor plate support template assembling reinforcement top view that the embodiment of the present invention provides.
The specific embodiment
In order to make purpose of the present invention, technical scheme and advantage clearer, below in conjunction with embodiment, the present invention is further elaborated.Should be appreciated that specific embodiment described herein, only in order to explain the present invention, is not intended to limit the present invention.
As shown in Figure 1, the novel stirrup shear connector of the embodiment of the present invention mainly is comprised of stirrup shear connector 1, stirrup 1-1, longitudinal reinforcement 1-2, girder steel 2, template 3, end plate 4, transverse reinforcement 5; Stirrup 1-1 cross section is rectangle, and longitudinal reinforcement 1-2 is placed on stirrup 1-1 inboard, and colligation is tetra-jiaos of stirrup 1-1, and stirrup 1-1 and girder steel 2 top flanges weld together; Template 3 is arranged on the top of end plate 4, and stirrup shear connector 1 is arranged on the centre position of template 3 by end plate 4, and transverse reinforcement 5 is arranged on template 3, as shown in Figure 4, and transverse reinforcement 5 and the stirrup 1-1 setting of staggering;
As shown in Figure 3, the mounting method for preparing of the novel stirrup shear connector of the embodiment of the present invention comprises the following steps:
S301: make girder steel and stirrup welded unit;
S302: structure hoisting;
S303: floor plate support template assembling reinforcement;
S304: concreting;
S305: the normal maintenance of concrete form removal again.
The concrete steps that prepare mounting method of the novel stirrup shear connector of the embodiment of the present invention are:
In step S301, girder steel 2 and stirrup 1-1(are as Fig. 1 and Fig. 2) all make and complete welding job in factory; Longitudinal reinforcement 1-2 is placed on inboard four jiaos of stirrup 1-1 and completes colligation (referring to Fig. 1), and the diameter of the spacing of stirrup 1-1 and diameter and longitudinal reinforcement 1-2 and spacing all will be determined according to the actual conditions of engineering; Then adjust whole stirrup 1-1 cage edge and top flange distance and by stirrup 1-1 and girder steel 2 top flange firm welding;
In step S303, at first formwork supporting plate 3, and then the transverse reinforcement 5 of colligation concrete slab the inside and vertical just muscle 1-2, and the assembling reinforcement of floor plate support template is the layer cloth muscle, between two-layer reinforcing bar, have to support between two-layer reinforcing bar, to maintain a certain distance guaranteeing.
The foregoing is only preferred embodiment of the present invention, not in order to limit the present invention, all any modifications of doing within the spirit and principles in the present invention, be equal to and replace and improvement etc., within all should being included in protection scope of the present invention.

Claims (9)

1.一种新型箍筋剪力连接件的制备安装方法,其特征在于,该新型箍筋剪力连接件的制备安装方法包括以下步骤:1. a preparation and installation method of a novel stirrup shear connector, characterized in that, the preparation and installation method of this novel stirrup shear connector comprises the following steps: 制作钢梁以及箍筋并焊接构件,纵向钢筋放置在箍筋内侧四角完成绑扎;Make steel beams and stirrups and weld the components, and place the longitudinal steel bars at the inner four corners of the stirrups to complete the binding; 结构吊装;structural hoisting; 楼面板支护模板绑扎钢筋;Floor slab support formwork binding reinforcement; 浇筑混凝土;pouring concrete; 混凝土正常养护再拆模。The concrete should be cured normally before the formwork is removed. 2.如权利要求1所述的新型箍筋剪力连接件的制备安装方法,其特征在于,箍筋的间距和直径以及纵向钢筋的直径和间距都根据工程的实际情况确定。2. The preparation and installation method of the novel stirrup shear connector as claimed in claim 1, wherein the spacing and diameter of the stirrup and the diameter and spacing of the longitudinal reinforcement are determined according to the actual situation of the project. 3.如权利要求1所述的新型箍筋剪力连接件的制备安装方法,其特征在于,楼面板支护模板绑扎钢筋为双层布筋,两层钢筋之间有支撑以保证两层钢筋之间保持有距离。3. the preparation installation method of novel stirrup shear connector as claimed in claim 1, it is characterized in that, floor slab support formwork binding reinforcement is double-layer fabric reinforcement, there is support between two layers of reinforcement to ensure that two layers of reinforcement Keep a distance between them. 4.一种新型箍筋剪力连接件,其特征在于,该新型箍筋剪力连接件包括:箍筋剪力连接件、箍筋、纵向钢筋、钢梁、模板、端板、横向钢筋;4. A novel stirrup shear connector, characterized in that the novel stirrup shear connector comprises: a stirrup shear connector, stirrups, longitudinal reinforcement, steel beams, templates, end plates, and transverse reinforcement; 纵向钢筋放置在箍筋内侧,箍筋设置在钢梁的上翼缘,模板设置在端板的上部,箍筋剪力连接件设置在模板的中间位置,横向钢筋设置在模板上,横向钢筋与箍筋错开设置。The longitudinal reinforcement is placed inside the stirrup, the stirrup is set on the upper flange of the steel beam, the formwork is set on the upper part of the end plate, the stirrup shear connector is set in the middle of the formwork, the transverse reinforcement is set on the formwork, and the transverse reinforcement and The stirrups are staggered. 5.如权利要求4所述的新型箍筋剪力连接件,其特征在于,箍筋横截面设置为矩形。5. The novel stirrup shear connector according to claim 4, characterized in that the cross section of the stirrup is set as a rectangle. 6.如权利要求4所述的新型箍筋剪力连接件,其特征在于,纵向钢筋通过绑扎放置在箍筋内侧。6. The novel stirrup shear connector according to claim 4, characterized in that the longitudinal reinforcement is placed inside the stirrup by binding. 7.如权利要求4所述的新型箍筋剪力连接件,其特征在于,箍筋通过焊接设置在钢梁的上翼缘。7. The novel stirrup shear connector according to claim 4, characterized in that the stirrup is arranged on the upper flange of the steel beam by welding. 8.如权利要求4所述的新型箍筋剪力连接件,其特征在于,箍筋剪力连接件通过绑扎设置在模板的中间位置。8. The novel stirrup shear connector according to claim 4, characterized in that, the stirrup shear connector is arranged in the middle of the template by binding. 9.如权利要求4所述的新型箍筋剪力连接件,其特征在于,横向钢筋与箍筋错开设置。9. The novel stirrup shear connector according to claim 4, characterized in that the transverse reinforcement and the stirrup are arranged in a staggered manner.
CN2013104120544A 2013-09-11 2013-09-11 Novel stirrup shear connector and manufacturing and mounting method Pending CN103437474A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013104120544A CN103437474A (en) 2013-09-11 2013-09-11 Novel stirrup shear connector and manufacturing and mounting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013104120544A CN103437474A (en) 2013-09-11 2013-09-11 Novel stirrup shear connector and manufacturing and mounting method

Publications (1)

Publication Number Publication Date
CN103437474A true CN103437474A (en) 2013-12-11

Family

ID=49691183

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013104120544A Pending CN103437474A (en) 2013-09-11 2013-09-11 Novel stirrup shear connector and manufacturing and mounting method

Country Status (1)

Country Link
CN (1) CN103437474A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107227821A (en) * 2017-07-24 2017-10-03 崔冰 A kind of dry type connects precast assembly steel reinforced concrete combination beam
CN108035241A (en) * 2017-12-22 2018-05-15 苏交科集团股份有限公司 Assembled steel-concrete composite bridge and construction process thereof
CN109338899A (en) * 2018-11-30 2019-02-15 西安科技大学 A steel-concrete composite beam without welded connectors and its construction method
CN110814208A (en) * 2019-09-30 2020-02-21 浙江交工集团股份有限公司 Processing technology of stirrup
CN111236068A (en) * 2020-03-06 2020-06-05 中国国家铁路集团有限公司 A spliced prefabricated steel-concrete bridge deck
CN115467546A (en) * 2022-08-22 2022-12-13 陈万里 Reinforced structure of building column and construction method thereof
CN118855231A (en) * 2024-07-30 2024-10-29 中国二十冶集团有限公司 Connection method of steel beam and concrete structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2004224895A1 (en) * 2003-10-28 2005-05-19 Bluescope Steel Limited Structural element
CN102182141A (en) * 2011-03-18 2011-09-14 清华大学 Longitudinal non-shearing-resistant T-shaped anti-pulling connecting piece and construction method thereof
CN203701279U (en) * 2013-09-11 2014-07-09 南京工业大学 Novel stirrup shear connector

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2004224895A1 (en) * 2003-10-28 2005-05-19 Bluescope Steel Limited Structural element
CN102182141A (en) * 2011-03-18 2011-09-14 清华大学 Longitudinal non-shearing-resistant T-shaped anti-pulling connecting piece and construction method thereof
CN203701279U (en) * 2013-09-11 2014-07-09 南京工业大学 Novel stirrup shear connector

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
建筑施工手册第四版编写组: "钢筋工程", 《建筑施工手册第四版》, 31 May 2003 (2003-05-31), pages 294 - 296 *
朱炯,罗智星: "钢-混凝土组合梁剪切连接件评述", 《能源技术与管理》, no. 6, 31 December 2007 (2007-12-31) *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107227821A (en) * 2017-07-24 2017-10-03 崔冰 A kind of dry type connects precast assembly steel reinforced concrete combination beam
CN108035241A (en) * 2017-12-22 2018-05-15 苏交科集团股份有限公司 Assembled steel-concrete composite bridge and construction process thereof
CN109338899A (en) * 2018-11-30 2019-02-15 西安科技大学 A steel-concrete composite beam without welded connectors and its construction method
CN109338899B (en) * 2018-11-30 2023-06-09 西安科技大学 Steel-concrete composite beam without welding connector and construction method thereof
CN110814208A (en) * 2019-09-30 2020-02-21 浙江交工集团股份有限公司 Processing technology of stirrup
CN111236068A (en) * 2020-03-06 2020-06-05 中国国家铁路集团有限公司 A spliced prefabricated steel-concrete bridge deck
CN115467546A (en) * 2022-08-22 2022-12-13 陈万里 Reinforced structure of building column and construction method thereof
CN118855231A (en) * 2024-07-30 2024-10-29 中国二十冶集团有限公司 Connection method of steel beam and concrete structure

Similar Documents

Publication Publication Date Title
CN103437474A (en) Novel stirrup shear connector and manufacturing and mounting method
CN103510639B (en) A kind of can the overlaid plate type shear wall of restore funcitons and implementation method thereof
CN103470040A (en) Splicing method of composite floor slab and beam
CN103498533A (en) Prestressed H-shaped steel reinforced concrete superposed beam
CN103114524A (en) Light type wave-shaped steel and high-strength activity powder concrete composite bridge panel
CN102995755B (en) RCS (reinforced concrete structure) combined node with continuous webs and partially-cut flanges
CN102182141A (en) Longitudinal non-shearing-resistant T-shaped anti-pulling connecting piece and construction method thereof
CN110512785B (en) One-way composite slab without end tongue and groove reinforcement, formwork structure and construction method
CN203440965U (en) Splicing structure of laminated floor slab
CN203200656U (en) Light corrugated steel-high strength reactive powder concrete combined bridge deck slab
CN204356996U (en) The U-shaped beam of prefabricated reinforced concrete with horizontal steel diaphragm
CN103422603A (en) Spiral stirrup shear connector and manufacturing and mounting method
CN108560418A (en) A kind of form of reinforcement is UHPC and the NC laminated plate of triangular space rack
CN110409288B (en) One-way slidable shear connector and construction method
CN203701279U (en) Novel stirrup shear connector
CN101845862B (en) Manufacture method of ribbed superposed prestress reinforced concrete precast slab
CN109881790A (en) Steel bar template integrated wall adds movable reinforcing bar connecting structure and installation method
CN203547019U (en) Prestressed H-shaped steel reinforced concrete superposed beam
CN206545308U (en) A kind of Steel Castellated Beams rib concrete folding plate
CN206529681U (en) A kind of setback steel web prestressed concrete continuous beam
CN203487638U (en) Spiral stirrup shear connector
CN220565524U (en) Large-width prestressed reinforcement truss composite floor slab
CN203640155U (en) Truss concrete superposed beam
CN103498530B (en) A kind of prestressing force perforation shape web T-steel concrete combination beam
CN201162299Y (en) A two-way laminated concrete slab with one-way floor

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131211