CN103437346B - Steel pipe pile with the burr and construction method - Google Patents

Steel pipe pile with the burr and construction method Download PDF

Info

Publication number
CN103437346B
CN103437346B CN201310307502.4A CN201310307502A CN103437346B CN 103437346 B CN103437346 B CN 103437346B CN 201310307502 A CN201310307502 A CN 201310307502A CN 103437346 B CN103437346 B CN 103437346B
Authority
CN
China
Prior art keywords
pile
steel pipe
concrete
burr
branch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310307502.4A
Other languages
Chinese (zh)
Other versions
CN103437346A (en
Inventor
孙天明
曾勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang CTB Corrugated Steel Web Co., Ltd.
Original Assignee
Zhejiang Ctb Corrugated Steel Web Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Ctb Corrugated Steel Web Co Ltd filed Critical Zhejiang Ctb Corrugated Steel Web Co Ltd
Priority to CN201310307502.4A priority Critical patent/CN103437346B/en
Publication of CN103437346A publication Critical patent/CN103437346A/en
Application granted granted Critical
Publication of CN103437346B publication Critical patent/CN103437346B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The present invention relates to concrete friction stake, disclose a kind of steel pipe pile with the burr and construction method, comprise steel pipe and be arranged on the concrete pile outside steel pipe, the outer wall of described concrete pile arranges the burr.Technique forms the burr after comprising the concrete setting of high pressure pouring.The present invention arranges the burr by the concrete pile outer wall at steel pipe, add concrete pile and contact area greatly, arrange to steel pipe pile extension on steel pipe pile simultaneously, insert the branch pile in the earth, increase friction pile entirety and the contact area of the earth, improve the frictional force of friction pile, again, by adding of the burr and branch pile, the compactness of soil around pile body is improved further, thus further increases overall friction.On the other hand, when there is the problems such as sinking when friction pile, by entering in stake, can carry out beating through hole, carrying out secondary and arranging that the mode such as branch pile, the burr carries out secondary maintenance and reinforcing to pile body.

Description

Steel pipe pile with the burr and construction method
Technical field
The present invention relates to concrete friction stake, particularly relate to a kind of steel pipe pile with the burr and construction method.
Background technology
Friction pile leans on the frictional force of pile body surface and original place matter soil to bear the weight of superstructure, the pile center position of existing friction pile is concrete, because it does not contact with the earth, does not therefore have due effect, add the weight of friction pile on the contrary, counteract the frictional force of a part.In addition, the outer wall due to friction pile is circular, and it is little with the contact area of the earth, and frictional force is also little.
Summary of the invention
The present invention is directed to friction pile of the prior art is solid pile, Heavy Weight, friction pile outer wall is little with the contact area of the earth, frictional force is little, the shortcomings such as friction pile easily sinks, provide a kind of mode of the hollow friction pile outer setting burr, increase friction pile and the contact area of the earth, improve steel pipe pile and the construction method of the band burr of the frictional force of friction pile.
In order to solve the problems of the technologies described above, the present invention is solved by following technical proposals: comprise steel pipe and be arranged on the concrete pile outside steel pipe, the outer wall of described concrete pile arranges the burr.
As preferably, the described burr is the concrete block be connected as a single entity with concrete pile.
As preferably, perforate arranged by described steel pipe, concrete pile is provided with the concrete services aperture communicated with the perforate of steel pipe, is provided with branch pile in concrete services aperture.
As preferably, described branch pile is inserted greatly through steel pipe and concrete pile.
As preferably, the angle a of described branch pile and the outer wall of concrete pile is less than or equal to 90 °.
As preferably, described steel pipe is the waveform steel pipe that corrugated sheet steel surrounds.
As preferably, described branch pile is steel pipe, steel column or stub.
With the steel pipe pile construction method of the burr, comprise steel pipe pile and the construction method of the described band burr, comprise the following steps:
A, reinforcing cage and waveform hollow steel pipe are put into the stake holes of accomplishing fluently simultaneously; Or first put reinforcing cage and put waveform hollow steel pipe again;
B, between waveform hollow steel pipe and stake holes concreting, generate concrete pile;
C, after concrete pile solidifies, pump the water in steel pipe, and beat through hole in steel pipe, through hole is communicated with steel pipe and the earth;
D, by through hole high pressure pouring concrete;
The burr is formed after the concrete setting of e, high pressure pouring.
As preferably, in described step c, squeeze into branch pile by through hole, until branch pile is inserted in the earth.
Hollow friction pile decreases concrete amount, reduces cost.Its concrete weight reduced, is the value added of hollow friction pile carrying.The burr and branch pile make the soil compactness around stake improve further, and friction factor is improved.And the burr and branch pile not only add friction area, the burr and branch pile self directly bear shearing force, opposing upper load.
The present invention arranges the burr by the concrete pile outer wall at steel pipe, add concrete pile and contact area greatly, arrange to steel pipe pile extension on steel pipe pile simultaneously, insert the branch pile in the earth, increase the contact area of friction pile entirety and the earth, improve the frictional force of friction pile, on the other hand, when there is the problems such as sinking when friction pile, can by entering in stake, carry out beating through hole, carry out secondary and arrange that the mode such as branch pile, the burr carries out secondary maintenance and reinforcing to pile body.
Accompanying drawing explanation
Fig. 1 is the structural representation of the embodiment of the present invention 1.
Fig. 2 is the structural representation of the embodiment of the present invention 2.
Fig. 3 is the structural representation of the embodiment of the present invention 3.
Fig. 4 is the top view of the embodiment of the present invention 2.
Wherein 1-steel pipe, 2-concrete pile, 3-branch pile, 4-lower manhole, 5-greatly, 6-burr, 11-perforate, 21-concrete services aperture.
Detailed description of the invention
Below in conjunction with accompanying drawing 1 to accompanying drawing 4 and detailed description of the invention, the present invention is described in further detail:
Embodiment 1
With the steel pipe pile of the burr, as shown in Figure 1, comprise steel pipe 1 and be arranged on the concrete pile 2 outside steel pipe 1, the outer wall of described concrete pile 2 arranges the burr 6.
The burr 6 is the concrete block be connected as a single entity with concrete pile 2.Steel pipe 1 is arranged perforate 11, concrete pile 2 is provided with the concrete services aperture 21 communicated with the perforate 11 of steel pipe 1, is provided with branch pile 3 in concrete services aperture 21.
Branch pile 3 is inserted in the earth 5 through steel pipe 1 and concrete pile 2.
Branch pile 3 equals 90 ° with the angle a of the outer wall of concrete pile 2.The waveform steel pipe that steel pipe 1 surrounds for corrugated sheet steel.Branch pile 3 is steel pipe.
With the steel pipe pile construction method of the burr, comprise steel pipe pile and the construction method of the described band burr, comprise the following steps:
A, reinforcing cage and waveform hollow steel pipe 1 are put into the stake holes of accomplishing fluently simultaneously;
B, between waveform hollow steel pipe 1 and stake holes concreting, generate concrete pile 2;
C, after concrete pile 2 solidifies substantially, pump the water in steel pipe 1, and beat through hole in steel pipe 1, through hole is communicated with steel pipe 1 and the earth 5;
D, by through hole high pressure pouring concrete;
The burr 6 is formed after the concrete setting of e, high pressure pouring.
In step c, squeeze into branch pile 3 by through hole, until branch pile 3 is inserted in the earth 5.By adding of the burr and branch pile, the compactness of soil around pile body is improved further, thus further increases overall friction.
Embodiment 2
With the steel pipe pile of the burr, as shown in Figure 2,4, comprise steel pipe 1 and be arranged on the concrete pile 2 outside steel pipe 1, the outer wall of described concrete pile 2 arranges the burr 6.
Branch pile 3 equals 70 ° with the angle a of the outer wall of concrete pile 2.The top of the steel pipe pile with the burr is also provided with lower manhole 4.The waveform steel pipe that steel pipe 1 surrounds for corrugated sheet steel.The longitudinal cross-section of waveform steel pipe is linear pattern.Branch pile 3 stub.
With the steel pipe pile construction method of the burr, comprise steel pipe pile and the construction method of the described band burr, comprise the following steps:
A, first put reinforcing cage and put waveform hollow steel pipe 1 again;
B, between waveform hollow steel pipe 1 and stake holes concreting, generate concrete pile 2;
C, after concrete pile 2 solidifies substantially, pump the water in steel pipe 1, and beat through hole in steel pipe 1, through hole is communicated with steel pipe 1 and the earth 5;
D, by through hole high pressure pouring concrete;
The burr 6 is formed after the concrete setting of e, high pressure pouring.
In step c, squeeze into branch pile 3 by through hole, until branch pile 3 is inserted in the earth 5.
Embodiment 3
With the steel pipe pile of the burr, as shown in Figure 3, comprise steel pipe 1 and be arranged on the concrete pile 2 outside steel pipe 1, the outer wall of described concrete pile 2 arranges the burr 6.
The burr 6 is the concrete block be connected as a single entity with concrete pile 2.Steel pipe 1 is arranged perforate 11, concrete pile 2 is provided with the concrete services aperture 21 communicated with the perforate 11 of steel pipe 1, is provided with branch pile 3 in concrete services aperture 21.
Branch pile 3 is inserted in the earth 5 through steel pipe 1 and concrete pile 2.
Branch pile 3 equals 60 ° with the angle a of the outer wall of concrete pile 2.The waveform steel pipe that steel pipe 1 surrounds for corrugated sheet steel.
The top of the steel pipe pile with the burr is also provided with lower manhole 4.The waveform steel pipe that steel pipe 1 surrounds for corrugated sheet steel.The longitudinal cross-section of waveform steel pipe is waveform, and waveform steel pipe is hollow, is formed by corrugated sheet steel bending, and its longitudinal cross-section shape is also identical with the cross section of existing multiple waveforms steel plate, and waveform hollow steel pipe also can be shaping by formed by integrally casting.
Arrange the burr 6 outside concrete services aperture 21, the burr 6 is concrete.Branch pile 3 is steel column.
With the steel pipe pile construction method of the burr, comprise steel pipe pile and the construction method of the described band burr, comprise the following steps:
A, first put reinforcing cage and put waveform hollow steel pipe 1 again;
B, between waveform hollow steel pipe 1 and stake holes concreting, generate concrete pile 2;
C, after concrete pile 2 solidifies substantially, pump the water in steel pipe 1, and beat through hole in steel pipe 1, through hole is communicated with steel pipe 1 and the earth 5;
D, by through hole high pressure pouring concrete;
The burr 6 is formed after the concrete setting of e, high pressure pouring.
In step c, squeeze into branch pile 3 by through hole, until branch pile 3 is inserted in the earth 5.
In described step c, form the burr 6 by through hole high pressure pouring concrete.By arranging the burr, increasing the outer wall of concrete pile 2 and the contact area of the earth, improve the frictional force of friction pile entirety.
Branch pile 3 is inserted by the perforate 11 on steel pipe 1, enter in soil through the concrete services aperture 21 on concrete pile 2, because concrete services aperture 21 is for tiltedly to establish, therefore, after branch pile 3 is inserted, the upper end of branch pile 3 namely with concrete pile 2 link from earth's surface close together, the lower end of branch pile 3 is namely distant from earth's surface with soil contact jaw.When friction pile occurs, when the hard object existed is as stone or rock, friction pile can be blocked firmly in the earth of the branch pile 3 of tiltedly establishing near running into, stop friction pile to continue to sink.
Meanwhile, after concrete pile 2 solidifies, pump the water in waveform hollow steel pipe 1, and beat through hole in waveform hollow steel pipe 1, through hole is communicated with waveform hollow steel pipe 1 and the earth; The burr 6 is formed by through hole high pressure pouring concrete.
In a word, the foregoing is only preferred embodiment of the present invention, all equalizations done according to the present patent application the scope of the claims change and modify, and all should belong to the covering scope of patent of the present invention.

Claims (7)

1. be with the steel pipe pile of the burr, comprise steel pipe (1) and be arranged on steel pipe (1) concrete pile outward (2), it is characterized in that: the outer wall of described concrete pile (2) arranges the burr (6); Perforate (11) arranged by described steel pipe (1), concrete pile (2) is provided with the concrete services aperture (21) communicated with the perforate of steel pipe (1) (11), is provided with branch pile (3) in concrete services aperture (21); The waveform steel pipe that described steel pipe (1) surrounds for corrugated sheet steel.
2. the steel pipe pile of the band burr according to claim 1, is characterized in that: the described burr (6) is the concrete block be connected as a single entity with concrete pile (2).
3. the steel pipe pile of the band burr according to claim 2, is characterized in that: described branch pile (3) is inserted in the earth (5) through steel pipe (1) and concrete pile (2).
4. the steel pipe pile of the band burr according to claim 2, is characterized in that: described branch pile (3) is less than or equal to 90 ° with the angle a of the outer wall of concrete pile (2).
5. the steel pipe pile of the band burr according to claim 2, is characterized in that: described branch pile (3) is steel pipe, steel column or stub.
6. be with the steel pipe pile construction method of the burr, comprise the steel pipe pile of the band burr according to claim 1, it is characterized in that: comprise the following steps:
A, reinforcing cage and waveform hollow steel pipe are put into the stake holes of accomplishing fluently simultaneously; Or first put reinforcing cage and put waveform hollow steel pipe again;
B, between waveform hollow steel pipe and stake holes concreting, generate concrete pile (2);
C, after concrete pile (2) solidifies, pump the water in steel pipe (1), and beat through hole in steel pipe (1), through hole is communicated with steel pipe (1) and the earth (5);
D, by through hole high pressure pouring concrete;
The burr (6) is formed after the concrete setting of e, high pressure pouring.
7. the steel pipe pile construction method of the band burr according to claim 6, is characterized in that: squeeze into branch pile (3) by through hole, until branch pile (3) is inserted in the earth (5).
CN201310307502.4A 2013-07-18 2013-07-18 Steel pipe pile with the burr and construction method Active CN103437346B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310307502.4A CN103437346B (en) 2013-07-18 2013-07-18 Steel pipe pile with the burr and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310307502.4A CN103437346B (en) 2013-07-18 2013-07-18 Steel pipe pile with the burr and construction method

Publications (2)

Publication Number Publication Date
CN103437346A CN103437346A (en) 2013-12-11
CN103437346B true CN103437346B (en) 2016-01-20

Family

ID=49691055

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310307502.4A Active CN103437346B (en) 2013-07-18 2013-07-18 Steel pipe pile with the burr and construction method

Country Status (1)

Country Link
CN (1) CN103437346B (en)

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105544513A (en) * 2015-11-24 2016-05-04 江苏省电力公司连云港供电公司 Steel pipe grouting pile
CN106351209A (en) * 2016-09-21 2017-01-25 成都启立辰智科技有限公司 Concrete pile
CN106836260B (en) * 2016-12-16 2018-09-11 兰州理工大学 A kind of crawler belt steel-pipe pile and construction method reducing negative friction
CN107059843B (en) * 2017-02-24 2018-09-14 湖北思泽新能源科技有限公司 A kind of inflation prestressed steel pipe and construction method
CN106894411B (en) * 2017-02-25 2018-09-14 湖北思泽新能源科技有限公司 A kind of hydraulic pressure prestressed steel pipe
CN106906840A (en) * 2017-03-31 2017-06-30 华电重工股份有限公司 The method of offshore wind farm rock-socketed steel pipe piles and the outer grouting construction of stake
CN107938659A (en) * 2017-11-21 2018-04-20 中国冶集团有限公司 A kind of friction pile and its construction method
CN113152418B (en) * 2021-03-10 2022-07-12 中电建路桥集团有限公司 Preloading tubular pile composite foundation suitable for deep soft soil area
CN113089627B (en) * 2021-03-10 2022-09-20 中电建路桥集团有限公司 Construction method of prestressed pipe pile composite foundation for deep soft soil surcharge preloading

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1284588A (en) * 1999-08-15 2001-02-21 宋兰芳 Corrugated formwork pipe for concrete pile
CN1414186A (en) * 2002-05-10 2003-04-30 贾燎 Sleeve pile and designing method
CN2584668Y (en) * 2002-08-28 2003-11-05 天津大学 Concrete vertical bearing pile with overhanging wedge fin
CN201010899Y (en) * 2006-09-15 2008-01-23 周继发 Corrugated pipe pile
CN201915401U (en) * 2010-12-30 2011-08-03 天津市银龙预应力钢材集团有限公司 Prestressed steel pipe-concrete pipe pile
CN202672140U (en) * 2012-05-29 2013-01-16 上海长凯岩土工程有限公司 Anchor rod static pressure anti-pulling steel pipe pile with lower portion grouted
CN102900076A (en) * 2012-10-24 2013-01-30 广东省第四建筑工程公司 Continuous construction method for concrete pile steel pipe column
CN203583465U (en) * 2013-07-18 2014-05-07 杭州博数土木工程技术有限公司 Steel pipe pile with burls

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000120066A (en) * 1998-10-14 2000-04-25 Nippon Steel Corp Execution method for steel pipe pile

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1284588A (en) * 1999-08-15 2001-02-21 宋兰芳 Corrugated formwork pipe for concrete pile
CN1414186A (en) * 2002-05-10 2003-04-30 贾燎 Sleeve pile and designing method
CN2584668Y (en) * 2002-08-28 2003-11-05 天津大学 Concrete vertical bearing pile with overhanging wedge fin
CN201010899Y (en) * 2006-09-15 2008-01-23 周继发 Corrugated pipe pile
CN201915401U (en) * 2010-12-30 2011-08-03 天津市银龙预应力钢材集团有限公司 Prestressed steel pipe-concrete pipe pile
CN202672140U (en) * 2012-05-29 2013-01-16 上海长凯岩土工程有限公司 Anchor rod static pressure anti-pulling steel pipe pile with lower portion grouted
CN102900076A (en) * 2012-10-24 2013-01-30 广东省第四建筑工程公司 Continuous construction method for concrete pile steel pipe column
CN203583465U (en) * 2013-07-18 2014-05-07 杭州博数土木工程技术有限公司 Steel pipe pile with burls

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
《钢管摩擦桩在软基工程中的应用及施工》;谢晓龙;《四川水力发电》;20090731;第28卷;第99-102页 *

Also Published As

Publication number Publication date
CN103437346A (en) 2013-12-11

Similar Documents

Publication Publication Date Title
CN103437346B (en) Steel pipe pile with the burr and construction method
CN105803925B (en) Quick connection method for prefabricated steel pipe constraint type steel concrete pier columns and cover beam
CN103485333B (en) Waveform hollow steel pipe friction pile and construction method
CN205205856U (en) Hydraulic engineering retaining wall
CN203878461U (en) Wet joint structure for prefabricating and splicing connecting portion between pier stand column and cover beam
CN101220595A (en) Application method of novel post-tensioned pre-stress soil blocking pile
CN205857173U (en) A kind of Novel steel casing sheath applying bored concrete pile on the water
CN203373735U (en) Prefabricated concrete tubular pile with external longitudinal webs
CN203583465U (en) Steel pipe pile with burls
CN104929149A (en) Stiffened embedded type column foot for reducing steel column embedment depth and construction technology thereof
CN204780977U (en) Reduce steel column burried depth's type of putting more energy into and bury formula column base
CN104234268B (en) A kind of prefabricated round type shear wall
CN203904462U (en) Replaceable anode assembling device applied to town gas-electricity protection system
CN108277817B (en) Construction method of high-pile bearing platform tower crane foundation reinforcing structure
CN103437347B (en) Steel pipe branch pile and construction method
CN105625198A (en) Reinforced rigid-framed arch bridge
CN205822507U (en) A kind of steel plate combined shear wall
CN105569073B (en) Suspension type change wall thickness ellipse is inverse to be made vertical shaft and its becomes wall thickness setting method
CN204959733U (en) Bored concrete pile steel reinforcement cage structure
CN204139323U (en) A kind of punching block shell mounting structures
CN202543903U (en) Concrete prefabricated pipe pile
CN205742219U (en) A kind of novel interlocking pile supporting construction
CN202298604U (en) Prestressed reinforcement concrete special-shaped precast pile
CN201217249Y (en) Prestressed concrete side-assist press enhancement type precast pile steel form
CN203487529U (en) Friction piles used for corrugated hollow steel pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: ZHEJIANG CTB CORRUGATED STEEL WEB CO., LTD.

Free format text: FORMER OWNER: HANGZHOU BOSHU CIVIL ENGINEERING TECHNOLOGY CO., LTD.

Effective date: 20141124

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 311215 HANGZHOU, ZHEJIANG PROVINCE TO: 314422 HANGZHOU, ZHEJIANG PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20141124

Address after: 314422, No. 168-2, village, town, Hangzhou, Xiaoshan District, Zhejiang

Applicant after: Zhejiang CTB Corrugated Steel Web Co., Ltd.

Address before: Hangzhou City, Zhejiang province 311215 Xiaoshan economic and Technological Development Zone, North Building 2 room 1711 Ning'an

Applicant before: Hangzhou Boshu Civil Engineering Technology Co., Ltd.

C14 Grant of patent or utility model
GR01 Patent grant