CN103422714B - A kind of high ferro is the safety protecting method of wired construction and the protective fence of formation thereof both - Google Patents

A kind of high ferro is the safety protecting method of wired construction and the protective fence of formation thereof both Download PDF

Info

Publication number
CN103422714B
CN103422714B CN201210166499.4A CN201210166499A CN103422714B CN 103422714 B CN103422714 B CN 103422714B CN 201210166499 A CN201210166499 A CN 201210166499A CN 103422714 B CN103422714 B CN 103422714B
Authority
CN
China
Prior art keywords
steel
polyvinyl chloride
longitudinal
station platform
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210166499.4A
Other languages
Chinese (zh)
Other versions
CN103422714A (en
Inventor
黄伟强
张传州
舒建辉
周晓兵
汤波
刘准
王俊河
黄炳文
蔡文胜
符万春
田晓兰
罗君华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 25th Bureau Group Co Ltd
China Railway Urban Construction Group Co Ltd
Second Engineering Co Ltd of China Railway Urban Construction Group Co Ltd
Original Assignee
Zhong Tie Chengjian Group Co Ltd
Middle Iron Chengjian Group Second Engineering Co Ltd
China Railway 25th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhong Tie Chengjian Group Co Ltd, Middle Iron Chengjian Group Second Engineering Co Ltd, China Railway 25th Bureau Group Co Ltd filed Critical Zhong Tie Chengjian Group Co Ltd
Priority to CN201210166499.4A priority Critical patent/CN103422714B/en
Publication of CN103422714A publication Critical patent/CN103422714A/en
Application granted granted Critical
Publication of CN103422714B publication Critical patent/CN103422714B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Fencing (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

本发明公开了一种高铁既有线施工的安全防护方法及其形成的防护围栏,其包括安装在两个钢轨上的聚氯乙烯半管、横向设置在两根钢轨上的底部横杆、既有线施工作业放置从钢轨向站台方向偏移相同距离的位置上的纵向钢管、竖立在一根钢轨一侧的竖向立杆、连接竖向立杆和纵向钢管的长斜杆、放置在竖向立杆且高于站台的三排水平钢管、设置在三排水平钢管的彩钢板、设置在彩钢板下方的双层钢丝网以及设置在彩钢板上的警示条幅,本发明结构稳固,易于维护;使施工区域和行车区域有效隔离,大大降低了施工与行车间的相互干扰;而且通过鲜明的警示条幅,能时刻提高作业人员的安全意识,提高对既有线行车设备的安全保障;大大提高了工作效率,加快了工程进度。

The invention discloses a safety protection method for the construction of an existing high-speed railway line and a protective fence formed therefor, which comprises a polyvinyl chloride half-pipe installed on two steel rails, a bottom cross bar horizontally arranged on the two steel rails, an existing line The construction work places longitudinal steel pipes at positions offset by the same distance from the rails to the platform, vertical poles erected on one side of the rail, long oblique poles connecting the vertical poles and longitudinal steel pipes, Three rows of horizontal steel pipes with poles higher than the platform, color steel plates arranged on the three rows of horizontal steel pipes, double-layer steel wire mesh arranged under the color steel plates, and warning banners arranged on the color steel plates, the structure of the invention is stable and easy to maintain; The construction area and the driving area are effectively isolated, which greatly reduces the mutual interference between the construction and the driving workshop; and through the clear warning banners, the safety awareness of the operators can be improved at all times, and the safety of the existing line driving equipment can be improved; the work efficiency is greatly improved , to speed up the progress of the project.

Description

一种高铁既有线施工的安全防护方法及其形成的防护围栏A safety protection method for the construction of an existing high-speed railway line and the protective fence formed therewith

技术领域technical field

本发明属于铁路施工技术领域,具体涉及一种高铁既有线施工的安全防护方法及其形成的防护围栏。The invention belongs to the technical field of railway construction, and in particular relates to a safety protection method for the construction of existing high-speed railway lines and a protective fence formed therefrom.

背景技术Background technique

既有线是指原先已经建造好的线路,通常是要对此线路进行改造。既有线的安全防护措施也是业界一直关注的问题。由于高铁客运专线既有线车站及站场改扩建工程在国内尚属首例,相应的客运专线既有线施工安全技术研究并不多见,车站建设中所采取的具体的安全技术措施更是缺乏实例。随着高铁客运专线的蓬勃发展,类似工程也将越来越多。而在这种长期、大面积、高强度的施工中确保既有线行车及施工安全的技术措施也必将逐步的发展和完善。The existing line refers to the line that has been built before, and usually the line needs to be transformed. The security protection measures for existing wires have also been a concern of the industry. Since the station and station yard reconstruction and expansion project of the existing high-speed passenger dedicated line is the first case in China, the corresponding research on the safety technology of the existing passenger dedicated line construction is rare, and the specific safety technical measures adopted in the construction of the station are even less practical. . With the vigorous development of high-speed rail passenger dedicated lines, there will be more and more similar projects. In this long-term, large-area, high-intensity construction, the technical measures to ensure the safety of existing line traffic and construction will also be gradually developed and perfected.

而且目前采用的安全防护措施是列车运行与既有线施工作业分开执行,一般既有线施工作业都安排在每日0点到4点,作业时间短,工作效率低。Moreover, the current safety protection measures are that the train operation is carried out separately from the existing line construction operations. Generally, the existing line construction operations are scheduled from 0:00 to 4:00 every day, with short operating hours and low work efficiency.

发明内容Contents of the invention

本发明的目的在于针对上述现有技术的不足,提供一种结构稳固、降低干扰及提高工作效率的高铁既有线施工的安全防护方法及其形成的防护围栏。The purpose of the present invention is to provide a safety protection method for the construction of existing high-speed rail lines with a stable structure, reduced interference and improved work efficiency and the protective fence formed to address the above-mentioned deficiencies in the prior art.

本发明的技术方案是这样实现的:Technical scheme of the present invention is realized like this:

一种技术方案:A technical solution:

一种高铁既有线施工的安全防护方法,其包括以下步骤:A safety protection method for high-speed rail existing line construction, which comprises the following steps:

1)在到发线的两根钢轨的上下两侧对应覆盖半圆柱状的聚氯乙烯半管,且每根钢轨上间隔一定距离均匀分布若干个聚氯乙烯半管;1) The upper and lower sides of the two rails on the delivery line are covered with semi-cylindrical polyvinyl chloride half-pipes, and several polyvinyl chloride half-pipes are evenly distributed at a certain distance on each rail;

2)在两根钢轨上横向放置若干与聚氯乙烯半管对应的底部横杆,每根底部横杆放置在两根钢轨的上侧聚氯乙烯半管上,该底部横杆的一端抵靠在车站站台的侧面,通过圆钢将底部横杆的另一端与每根钢轨及对应的上下两侧的聚氯乙烯半管捆绑固定在一起;2) A number of bottom cross bars corresponding to the PVC half pipes are horizontally placed on the two rails, each bottom cross bar is placed on the upper side PVC half pipes of the two steel rails, and one end of the bottom cross bar is against the On the side of the station platform, the other end of the bottom crossbar is bound to each steel rail and the corresponding PVC half-pipes on the upper and lower sides through round steel;

3)在所述底部横杆上纵向铺设若干纵向钢管,该纵向钢管分成两列分别放置在从两根钢轨向车站站台方向偏移相同距离的位置上,且每根纵向钢管通过十字扣件与每个底部横杆固定;3) A number of longitudinal steel pipes are vertically laid on the bottom cross bar, and the longitudinal steel pipes are divided into two rows and placed on the positions offset by the same distance from the two rails to the station platform direction, and each longitudinal steel pipe is connected to the cross fastener through a cross fastener. Each bottom crossbar is fixed;

4)在靠近车站站台的钢轨的外侧安装若干与底部横杆对应的竖向立杆,每个竖向立杆通过十字扣件与靠近车站站台的纵向钢管固定;4) Install a number of vertical uprights corresponding to the bottom crossbar on the outer side of the rail near the station platform, and each vertical upright is fixed to the longitudinal steel pipe near the station platform through cross fasteners;

5)与每个竖向立杆对应的安装一长斜杆,该长斜杆的上端通过十字扣件与竖向立杆固定,长斜杆的底端通过十字扣件与远离车站站台的纵向钢管固定,长斜杆、竖向立杆与底部横杆构成三角形,长斜杆的底端套设有聚氯乙烯管;5) A long oblique rod is installed corresponding to each vertical vertical rod, the upper end of the long oblique rod is fixed to the vertical rod through a cross fastener, and the bottom end of the long oblique rod is connected to the longitudinal direction away from the station platform through a cross fastener. The steel pipe is fixed, the long oblique rod, the vertical vertical rod and the bottom horizontal rod form a triangle, and the bottom end of the long oblique rod is covered with a polyvinyl chloride pipe;

6)在上述竖向立杆且高于车站站台的位置上通过十字扣件安装固定有若干水平钢管,该等水平钢管在竖直方向上均匀分成三排;6) A number of horizontal steel pipes are installed and fixed by cross fasteners on the above-mentioned vertical pole and higher than the station platform, and the horizontal steel pipes are evenly divided into three rows in the vertical direction;

7)在靠近车站站台一侧安装有纵向排列的双层钢丝网,双层钢丝网的上端通过塑料自锁式扎带锁紧固定在最下排的水平钢管上,双层钢丝网的下端通过塑料自锁式扎带锁紧固定在靠近车站站台的纵向钢管上;7) A longitudinally arranged double-layer steel wire mesh is installed on the side close to the station platform. The upper end of the double-layer steel wire mesh is locked and fixed on the bottom row of horizontal steel pipes through plastic self-locking cable ties. The lower end of the double-layer steel wire mesh passes through The plastic self-locking cable tie is locked and fixed on the longitudinal steel pipe near the station platform;

8)在三排水平钢管上安装若干纵向排列的彩钢板,相邻的彩钢板边缘重叠放置,彩钢板在对应每一排的水平钢管处均设有上下排列的固定孔,然后通过镀锌铁丝套住水平钢管再穿过上下固定孔拧紧;8) Install a number of longitudinally arranged color steel plates on three rows of horizontal steel pipes. The edges of adjacent color steel plates are overlapped. The color steel plates are provided with fixing holes arranged up and down corresponding to each row of horizontal steel pipes, and then passed through galvanized wire sleeves. Hold the horizontal steel pipe and tighten it through the upper and lower fixing holes;

9)在纵向排列的彩钢板的中间位置绑扎固定纵长的钢丝绳;9) Bind and fix the longitudinally long steel wire rope at the middle position of the color steel plates arranged longitudinally;

10)在彩钢板上间隔一定距离粘贴一个警示条幅。10) Paste a warning banner at a certain distance on the color steel plate.

所述1)中的聚氯乙烯半管在每根钢轨上相隔的距离为3米,该半圆柱状的聚氯乙烯半管是直径为110毫米的聚氯乙烯圆管剖开形成的,且半圆柱状的聚氯乙烯半管的长度在200毫米-300毫米之间。The distance between the polyvinyl chloride half-pipes in 1) on each rail is 3 meters, and the semi-cylindrical polyvinyl chloride half-pipe is formed by cutting a polyvinyl chloride round pipe with a diameter of 110 mm, and the semicircular The length of the columnar polyvinyl chloride half pipe is between 200 mm and 300 mm.

所述2)中的底部横杆直径为48毫米,长为3米;圆钢的直径为6毫米。The diameter of the bottom cross bar in said 2) is 48 millimeters, and the length is 3 meters; the diameter of the round steel is 6 millimeters.

所述3)中纵向钢管从每根钢轨偏移的距离为30厘米,纵向钢管直径为48毫米,长为6米。The offset distance of the longitudinal steel pipe from each rail in 3) is 30 centimeters, the diameter of the longitudinal steel pipe is 48 millimeters, and the length is 6 meters.

所述4)中竖向立杆长为3.5米。The length of the vertical pole in said 4) is 3.5 meters.

所述5)中长斜杆长为3.5米,长斜杆的底端套设的聚氯乙烯管直径为63毫米,长为20厘米。5) The length of the middle and long oblique rods is 3.5 meters, and the diameter of the polyvinyl chloride pipe sleeved at the bottom of the long oblique rods is 63 millimeters, and the length is 20 centimeters.

所述6)中水平钢管长为6米,三排水平钢管中每相邻两个水平钢管的间距为0.8米,最下排的水平钢管安装在竖向立杆的1.7米处。The length of the horizontal steel pipe in 6) is 6 meters, the distance between every two adjacent horizontal steel pipes in the three rows of horizontal steel pipes is 0.8 meters, and the horizontal steel pipes in the bottom row are installed at 1.7 meters of the vertical pole.

所述7)中的双层钢丝网包括浸塑钢丝网和不锈钢丝网,两种的钢丝网的网眼均为正方形,边长分别5厘米和0.3厘米。The double-layer steel wire mesh in 7) includes plastic-impregnated steel wire mesh and stainless steel wire mesh, and the meshes of the two kinds of steel wire mesh are square, and the side lengths are 5 cm and 0.3 cm respectively.

所述8)中的彩钢板厚度为0.4毫米,相邻两个彩钢板重叠部分的纵向固定孔也重叠。The thickness of the color steel plate in the above 8) is 0.4 mm, and the longitudinal fixing holes of the overlapping parts of two adjacent color steel plates also overlap.

另一种技术方案Another technical solution

一种如上述任一项所述的高铁既有线施工的安全防护方法及其形成的防护围栏,其包括对应安装在到发线两个钢轨的上下两侧的半圆柱状的聚氯乙烯半管、横向放置在两根钢轨的聚氯乙烯半管上的底部横杆、分别放置在从两根钢轨向车站站台方向偏移相同距离的两列纵向钢管、安装在靠近车站站台的钢轨的外侧的与底部横杆对应的竖向立杆、连接竖向立杆和远离车站站台的纵向钢管的长斜杆、套设在长斜杆的底端的聚氯乙烯管、安装在竖向立杆且位于车站站台上方的均匀分布的三排水平钢管、安装在三排水平钢管上且纵向排列的彩钢板、安装在彩钢板下方且连接最下排水平钢管与纵向钢管的双层钢丝网以及间隔粘贴在彩钢板上的警示条幅,每根钢轨上间隔一定距离均匀分布若干个聚氯乙烯半管;该底部横杆的一端抵靠在车站站台的侧面,另一端通过圆钢将底部横杆与对应的钢轨及上下两侧的聚氯乙烯半管捆绑固定在一起;每个纵向钢管通过十字扣件与每个底部横杆固定;每个竖向立杆通过十字扣件与靠近车站站台的纵向钢管固定;长斜杆和水平钢管均通过十字扣件固定;相邻的彩钢板边缘重叠放置,彩钢板在对应每一排的水平钢管处均设有上下排列的固定孔,然后通过镀锌铁丝套住水平钢管再穿过上下固定孔拧紧;双层钢丝网通过塑料自锁式扎带锁紧固定。A safety protection method for the construction of an existing high-speed railway line as described in any one of the above and the protective fence formed thereof, which includes a semi-cylindrical polyvinyl chloride half-pipe correspondingly installed on the upper and lower sides of the two rails of the arrival and departure line, The bottom crossbar placed transversely on the PVC half-pipes of the two rails, the two rows of longitudinal steel pipes that are offset from the two rails to the station platform by the same distance, and the rails installed on the outside of the rails close to the station platform. The vertical pole corresponding to the bottom crossbar, the long oblique pole connecting the vertical pole and the longitudinal steel pipe away from the station platform, the polyvinyl chloride pipe sleeved at the bottom end of the long oblique pole, installed on the vertical pole and located at the station Three rows of horizontal steel pipes evenly distributed above the platform, color steel plates installed on the three rows of horizontal steel pipes and arranged vertically, double-layer steel wire mesh installed under the color steel plates and connecting the bottom row of horizontal steel pipes and longitudinal steel The warning banner on the steel plate, several polyvinyl chloride half pipes are evenly distributed on each rail at a certain distance; one end of the bottom cross bar is against the side of the station platform, and the other end connects the bottom cross bar to the corresponding steel rail through round steel and the PVC half-pipes on the upper and lower sides are bound and fixed together; each longitudinal steel pipe is fixed to each bottom cross bar through a cross fastener; each vertical pole is fixed to a longitudinal steel pipe near the station platform through a cross fastener; Both the long oblique rod and the horizontal steel pipe are fixed by cross fasteners; the edges of adjacent color steel plates are overlapped, and the color steel plates are provided with fixing holes arranged up and down corresponding to each row of horizontal steel pipes, and then the horizontal steel pipes are covered by galvanized iron wires Then pass through the upper and lower fixing holes and tighten; the double-layer steel wire mesh is locked and fixed by plastic self-locking cable ties.

本发明采用上述方法,形成了一个防护围栏,此方法操作简单快捷,结构稳固,易于维护;防护围栏的搭设形成了封闭的施工环境,使施工区域和行车区域有效隔离,大大降低了施工与行车间的相互干扰;而且通过鲜明的警示条幅,能时刻提高作业人员的安全意识,提高对既有线行车设备的安全保障;此方法也将原来临近既有线施工的大部分工作作业时间从每日4小时扩展为每日24小时,大大提高了工作效率,加快了工程进度。The present invention adopts the above method to form a protective fence, which is simple and quick to operate, stable in structure, and easy to maintain; the erection of the protective fence forms a closed construction environment, effectively isolates the construction area from the driving area, and greatly reduces the construction and transportation costs. The mutual interference of the workshop; and through the clear warning banners, the safety awareness of the operators can be improved at all times, and the safety of the existing line driving equipment can be improved; The hours are extended to 24 hours a day, which greatly improves work efficiency and speeds up the progress of the project.

附图说明Description of drawings

下面结合附图中的实施例对本发明作进一步的详细说明,但并不构成对本发明的任何限制。The present invention will be described in further detail below in conjunction with the embodiments in the accompanying drawings, but this does not constitute any limitation to the present invention.

图1是本发明防护围栏的结构示意图。Fig. 1 is a structural schematic diagram of the protective fence of the present invention.

图2是图1所示的钢轨与聚氯乙烯管固定的局部示意图。Fig. 2 is a partial schematic diagram of fixing the steel rail and the polyvinyl chloride pipe shown in Fig. 1 .

图3是图1所示的彩钢板与水平钢管固定的局部示意图。Fig. 3 is a partial schematic diagram of fixing the color steel plate and the horizontal steel pipe shown in Fig. 1 .

图4是本发明防护围栏在使用状态下的侧视示意图。Fig. 4 is a schematic side view of the protective fence of the present invention in use.

图中:聚氯乙烯半管1、底部横杆2、纵向钢管3、竖向立杆4、长斜杆5、聚氯乙烯管6、水平钢管7、彩钢板8、双层钢丝网9、警示条幅10、圆钢11、十字扣件12、镀锌铁丝13、钢丝绳14、塑料自锁式扎带15、固定孔16、钢轨17、车站站台18。In the figure: polyvinyl chloride half pipe 1, bottom cross bar 2, longitudinal steel pipe 3, vertical pole 4, long oblique bar 5, polyvinyl chloride pipe 6, horizontal steel pipe 7, color steel plate 8, double-layer steel wire mesh 9, Warning banner 10, round steel 11, cross fastener 12, galvanized iron wire 13, steel wire rope 14, plastic self-locking cable tie 15, fixing hole 16, rail 17, station platform 18.

具体实施方式detailed description

如图1所示,本发明一种用于高速铁路客运专线的既有线施工安全防护方法形成的防护围栏,其包括对应安装在到发线两个钢轨17的上下两侧的半圆柱状的聚氯乙烯半管1、横向放置在两根钢轨的聚氯乙烯半管上的底部横杆2、分别放置在从两根钢轨17向车站站台18方向偏移相同距离的两列纵向钢管3、安装在靠近车站站台18的钢轨17的外侧的与底部横杆对应的竖向立杆4、连接竖向立杆4和远离车站站台18的纵向钢管3的长斜杆5、套设在长斜杆5的底端的聚氯乙烯管6、安装在竖向立杆4且位于车站站台18上方的均匀分布的三排水平钢管7、安装在三排水平钢管7上且纵向排列的彩钢板8、安装在彩钢板8下方且连接最下排水平钢7与纵向钢管3的双层钢丝网9以及间隔安装在彩钢板上的警示条幅10。底部横杆2的一端抵靠在车站站台的侧面,另一端通过圆钢将底部横杆2与对应的钢轨及上下两侧的聚氯乙烯半管1捆绑固定在一起。纵向钢管3与底部横杆2、竖向立杆4与靠近车站站台的纵向钢管3、长斜杆5与竖向立杆和远离车站站台的纵向钢管3、三排水平钢管7与竖向立杆4,它们均采用十字扣件12相互固定。彩钢板8边缘重叠放置,且通过镀锌铁丝13套住水平钢管6,彩钢板8的中间位置绑扎固定纵长的钢丝绳14;双层钢丝网9通过塑料自锁式扎带15锁紧固定。彩钢板8在对应每一排的水平钢管7处均设有上下排列的固定孔16,镀锌铁丝13套住水平钢管7再穿过上下固定孔16拧紧,相邻两个彩钢板8重叠部分的纵向固定孔16也重叠。该双层钢丝网9包括浸塑钢丝网和不锈钢丝网,两种的钢丝网的网眼均为正方形,边长分别5厘米和0.3厘米。As shown in Fig. 1, a kind of protection fence that the present invention is used for the existing line construction safety protection method of high-speed railway passenger dedicated line is formed, and it comprises the semi-cylindrical polychloride that is correspondingly installed on the upper and lower sides of two rails 17 of arrival and departure lines. Vinyl half-pipe 1, the bottom crossbar placed horizontally on the polyvinyl chloride half-pipe of the two rails 2, respectively placed on two columns of vertical steel pipes offset by the same distance from the two rails 17 to the direction of the station platform 18 3, installed on The vertical pole 4 corresponding to the bottom cross bar on the outside of the rail 17 close to the station platform 18, the long oblique pole 5 connecting the vertical pole 4 and the longitudinal steel pipe 3 away from the station platform 18, sleeved on the long oblique pole 5 The polyvinyl chloride pipe 6 at the bottom of the vertical pole 4, the evenly distributed three rows of horizontal steel pipes 7 above the station platform 18, the color steel plates 8 arranged vertically on the three rows of horizontal steel pipes 7, installed on the Below the color steel plate 8 and connecting the lowermost row of horizontal steel 7 and the double-layer steel wire mesh 9 of the longitudinal steel pipe 3 and the warning banners 10 installed on the color steel plate at intervals. One end of the bottom cross bar 2 leans against the side of the station platform, and the other end binds the bottom cross bar 2 with the corresponding steel rail and the polyvinyl chloride half pipes 1 on the upper and lower sides through round steel. Longitudinal steel pipe 3 and bottom horizontal bar 2, vertical vertical pole 4 and longitudinal steel pipe 3 close to the station platform, long oblique pole 5 and vertical pole and longitudinal steel pipe 3 far away from the station platform, three rows of horizontal steel pipes 7 and vertical vertical steel pipe Rods 4, they all adopt cross fasteners 12 to fix each other. The edge of color steel plate 8 overlaps and places, and entangles horizontal steel pipe 6 by galvanized iron wire 13, and the middle position of color steel plate 8 binds and fixes longitudinal steel wire rope 14; The color steel plate 8 is provided with fixing holes 16 arranged up and down corresponding to the horizontal steel pipes 7 of each row, and the galvanized iron wire 13 is encased in the horizontal steel pipes 7 and then passed through the upper and lower fixing holes 16 to be tightened. The longitudinal fixing holes 16 also overlap. The double-layer steel wire mesh 9 includes plastic-impregnated steel wire mesh and stainless steel wire mesh. The meshes of the two kinds of steel wire mesh are square, and the side lengths are 5 cm and 0.3 cm respectively.

本发明中采用元件尺寸如下:Adopt element size among the present invention as follows:

1)半圆柱状的聚氯乙烯半管1是直径为110毫米的聚氯乙烯圆管剖开形成的,且半圆柱状的聚氯乙烯半管1的长度在200毫米-300毫米之间。1) The semi-cylindrical polyvinyl chloride half-pipe 1 is formed by cutting a polyvinyl chloride round pipe with a diameter of 110 mm, and the length of the semi-cylindrical polyvinyl chloride half-pipe 1 is between 200 mm and 300 mm.

2)底部横杆2直径为48毫米,长为3米,材料为钢管。2) The bottom cross bar 2 has a diameter of 48 mm and a length of 3 meters, and the material is a steel pipe.

3)纵向钢管3直径为48毫米,长为6米。3) The longitudinal steel pipe 3 has a diameter of 48 mm and a length of 6 meters.

4)竖向立杆4长为3.5米,材料为钢管。4) The length of the vertical pole 4 is 3.5 meters, and the material is a steel pipe.

5)长斜杆5长为3.5米,材料为钢管。5) The length of the long oblique rod 5 is 3.5 meters, and the material is a steel pipe.

6)长斜杆5底端套设的聚氯乙烯管6直径为63毫米,长为20厘米。6) The polyvinyl chloride pipe 6 that is sleeved at the bottom of the long oblique rod 5 has a diameter of 63 millimeters and a length of 20 centimeters.

7)水平钢管7长为6米。7) The length of the horizontal steel pipe 7 is 6 meters.

8)彩钢板8厚度为0.4毫米。8) The color steel plate 8 has a thickness of 0.4 mm.

9)圆钢11的直径为6毫米。9) The diameter of the round steel 11 is 6 millimeters.

10)钢丝绳14的直径为12.5毫米。10) The diameter of the steel wire rope 14 is 12.5 millimeters.

本发明一种用于高速铁路客运专线的既有线施工安全防护方法,其包括以下步骤:The present invention is an existing line construction safety protection method for high-speed railway passenger dedicated line, which comprises the following steps:

1)在到发线的两根钢轨的上下两侧对应覆盖半圆柱状的聚氯乙烯半管1,且每根钢轨上间隔3米均匀分布若干个聚氯乙烯半管1,聚氯乙烯半管1可以保护钢轨防止受损或短接;1) The upper and lower sides of the two rails on the delivery line are covered with semi-cylindrical polyvinyl chloride half pipes 1, and several polyvinyl chloride half pipes 1 are evenly distributed on each rail at an interval of 3 meters. 1 It can protect the rail from damage or short circuit;

2)在两根钢轨上横向放置若干与聚氯乙烯半管1对应的底部横杆2,每根底部横杆2放置在两根钢轨的上侧聚氯乙烯半管1上,该底部横杆2的一端抵靠在车站站台的侧面,通过圆钢11将底部横杆2的另一端与每根钢轨及对应的上下两侧的聚氯乙烯半管1捆绑固定在一起;2) A number of bottom cross bars 2 corresponding to the polyvinyl chloride half-pipe 1 are horizontally placed on the two rails, and each bottom cross bar 2 is placed on the upper side polyvinyl chloride half-pipe 1 of the two steel rails. The bottom cross bar One end of 2 leans against the side of the station platform, and the other end of the bottom cross bar 2 is bound and fixed together with each steel rail and the corresponding upper and lower sides of the polyvinyl chloride half pipe 1 through the round steel 11;

3)在所述底部横杆2上纵向铺设若干纵向钢管3,该纵向钢管3分成两列分别放置在从两根钢轨向车站站台方向偏移30厘米的位置上,且每个纵向钢管3通过十字扣件12与每个底部横杆2固定,纵向钢管3的设置是为了防止底部横杆2滑移;3) A number of longitudinal steel pipes 3 are vertically laid on the bottom cross bar 2, and the longitudinal steel pipes 3 are divided into two columns and placed at positions offset by 30 cm from the two rails to the station platform, and each longitudinal steel pipe 3 passes through The cross fastener 12 is fixed to each bottom cross bar 2, and the longitudinal steel pipe 3 is arranged to prevent the bottom cross bar 2 from slipping;

4)在靠近车站站台的钢轨的外侧安装若干与底部横杆对应的竖向立杆4,每个竖向立杆通过十字扣件与靠近车站站台的纵向钢管3固定;4) Install several vertical uprights 4 corresponding to the bottom crossbar on the outer side of the rail near the station platform, and each vertical upright is fixed to the longitudinal steel pipe 3 near the station platform through cross fasteners;

5)与每个竖向立杆4对应的安装一长斜杆5,该长斜杆5的上端通过十字扣件12与竖向立杆4固定,长斜杆5的底端通过十字扣件与远离车站站台的纵向钢管3固定,长斜杆5、竖向立杆4与底部横杆2构成三角形,长斜杆5的底端套设有聚氯乙烯管6,这样可以防止长斜杆5与钢轨接触发生短路;5) A long oblique rod 5 is installed corresponding to each vertical vertical rod 4, the upper end of the long oblique rod 5 is fixed to the vertical vertical rod 4 by a cross fastener 12, and the bottom end of the long oblique rod 5 is fixed by a cross fastener Fixed with the longitudinal steel pipe 3 away from the station platform, the long oblique rod 5, the vertical vertical rod 4 and the bottom cross bar 2 form a triangle, and the bottom end of the long oblique rod 5 is provided with a polyvinyl chloride pipe 6, which can prevent the long oblique rod from 5 A short circuit occurs in contact with the rail;

6)在上述竖向立杆4且高于车站站台的位置上通过十字扣件12安装固定有若干水平钢管7,该等水平钢管7在竖直方向上均匀分成三排,最下排的水平钢管7安装在竖向立杆4的1.7米处,三排水平钢管7中每相邻两个水平钢管7的间距为0.8米;6) A number of horizontal steel pipes 7 are installed and fixed by cross fasteners 12 on the above-mentioned vertical pole 4 and higher than the station platform. These horizontal steel pipes 7 are evenly divided into three rows in the vertical direction. The steel pipe 7 is installed at 1.7 meters of the vertical pole 4, and the distance between every two adjacent horizontal steel pipes 7 in the three rows of horizontal steel pipes 7 is 0.8 meters;

7)在靠近车站站台18一侧安装有纵向排列的双层钢丝网9,双层钢丝网9的上端通过塑料自锁式扎带15锁紧固定在最下排的水平钢管7上,双层钢丝网9的下端通过塑料自锁式扎带15锁紧固定在靠近车站站台的纵向钢管3上,该双层钢丝网是为了减小列车运行时产生的风力,进而防止该风力对施工的影响;7) On the side close to the station platform 18, a longitudinally arranged double-layer steel wire mesh 9 is installed, and the upper end of the double-layer steel wire mesh 9 is locked and fixed on the lowermost horizontal steel pipe 7 through a plastic self-locking cable tie 15. The lower end of the steel wire mesh 9 is locked and fixed on the longitudinal steel pipe 3 close to the station platform by plastic self-locking cable ties 15. The double-layer steel mesh is to reduce the wind force generated when the train is running, thereby preventing the wind force from affecting the construction. ;

8)在三排水平钢管7上安装若干纵向排列的彩钢板8,相邻的彩钢板7边缘重叠放置,彩钢板7在对应每一排的水平钢管7处均设有上下排列的固定孔16,然后通过镀锌铁丝13套住水平钢管7再穿过上下固定孔16拧紧,相邻两个彩钢板6重叠部分的纵向固定孔16也重叠;8) Install several longitudinally arranged color steel plates 8 on the three rows of horizontal steel pipes 7, the edges of adjacent color steel plates 7 are overlapped, and the color steel plates 7 are provided with fixing holes 16 arranged up and down corresponding to each row of horizontal steel pipes 7 , and then entangle the horizontal steel pipe 7 through the galvanized iron wire 13 and then pass through the upper and lower fixing holes 16 to tighten, and the longitudinal fixing holes 16 of the overlapping parts of two adjacent color steel plates 6 also overlap;

9)在纵向排列的彩钢板8的中间位置绑扎固定纵长的钢丝绳14,这样可以增强彩钢板8的整体稳定性;9) Bind and fix the longitudinally long steel wire rope 14 at the middle position of the color steel plates 8 arranged longitudinally, so that the overall stability of the color steel plates 8 can be enhanced;

10)在彩钢板8上间隔一定距离安装一个警示条幅10,增加安全意识。10) Install a warning banner 10 at a certain distance on the color steel plate 8 to increase safety awareness.

本发明的方法操作简单快捷,结构稳固,易于维护;防护围栏的搭设形成了封闭的施工环境,使施工区域和行车区域有效隔离,大大降低了施工与行车间的相互干扰;而且通过鲜明的警示条幅,能时刻提高作业人员的安全意识,提高对既有线行车设备的安全保障;此方法也将临近既有线施工的大部分工作作业时间从每日4小时扩展为每日24小时,大大提高了工作效率,加快了工程进度。The method of the present invention is simple and fast in operation, stable in structure and easy to maintain; the construction of the protective fence forms a closed construction environment, which effectively isolates the construction area from the driving area, greatly reducing the mutual interference between construction and driving; and through clear warnings Banners can always improve the safety awareness of operators and improve the safety of existing line driving equipment; this method also expands the working time of most of the work near the existing line construction from 4 hours a day to 24 hours a day, greatly improving Work efficiency, speed up the progress of the project.

Claims (10)

1. a safety protecting method for high ferro both wired construction, is characterized in that: comprise the following steps:
1) cover half-terete polyvinyl chloride semicanal in the both sides up and down of two one steel rails to hair line correspondence, and every one steel rail keeps at a certain distance away be uniformly distributed several polyvinyl chloride semicanals;
2) on two one steel rails, laterally some bottom bars corresponding with polyvinyl chloride semicanal are placed, every root bottom part cross bar is placed on the upside polyvinyl chloride semicanal of two one steel rails, one end of this bottom bar is resisted against the side of station platform, the other end by round steel by bottom bar and corresponding rail and up and down the polyvinyl chloride semicanal of both sides bundle and be fixed together;
3) on described bottom bar, longitudinally some longitudinal steel pipes are laid, this longitudinal steel pipe is divided into two row and is placed on respectively the position of the skew same distance from two one steel rails to station platform direction, and the longitudinal steel pipe of every root is fixed by cruciform fastening for falsework and each bottom bar;
4) install some vertical vertical rods corresponding with bottom bar in the outside of the rail near station platform, each vertical vertical rod is fixed by cruciform fastening for falsework and the longitudinal steel pipe near station platform;
5) corresponding with each vertical vertical rod installation one long diagonal brace, the upper end of this long diagonal brace is fixed by cruciform fastening for falsework and vertical vertical rod, the bottom of long diagonal brace is fixed by cruciform fastening for falsework and the longitudinal steel pipe away from station platform, long diagonal brace, vertical vertical rod and bottom bar form triangle, and the bottom of long diagonal brace is arranged with polyvinyl chloride pipe;
6) be mounted with some horizontal steel tube higher than on the position of station platform by cruciform fastening for falsework in above-mentioned vertical vertical rod, these horizontal steel tube in the vertical directions are evenly divided into three rows;
7) at the clad steel silk screen being provided with longitudinal arrangement near station platform side, the upper end of clad steel silk screen is locked on the horizontal steel tube descending most row by plastics self-locking band, and the lower end of clad steel silk screen is locked on the longitudinal steel pipe near station platform by plastics self-locking band;
8) color steel of some longitudinal arrangements is installed on three row of horizontal steel pipes, adjacent color steel imbricate is placed, color steel is equipped with at the horizontal steel tube place of each row corresponding the fixing hole be arranged above and below, and then entangles horizontal steel tube by galvanized wire and tightens through upper lower fixed hole;
9) wire rope of lengthwise is fixed in the centre position colligation of the color steel of longitudinal arrangement;
10) stickup one that keeps at a certain distance away on color steel warning vertically hung scroll.
2. the safety protecting method of high ferro according to claim 1 both wired construction, it is characterized in that: the distance that the polyvinyl chloride semicanal described 1) is separated by every one steel rail is 3 meters, to be diameter be this half-terete polyvinyl chloride semicanal that the polyvinyl chloride pipe of 110 millimeters cuts formation open, and the length of half-terete polyvinyl chloride semicanal is between 200 millimeters-300 millimeters.
3. the safety protecting method of high ferro according to claim 1 both wired construction, it is characterized in that: the bottom bar diameter described 2) is 48 millimeters, length is 3 meters; The diameter of round steel is 6 millimeters.
4. the safety protecting method of high ferro according to claim 1 both wired construction, it is characterized in that: described 3), longitudinal steel pipe is 30 centimetres from the distance that every one steel rail offsets, longitudinal diameter of steel tube is 48 millimeters, and length is 6 meters.
5. the safety protecting method of high ferro according to claim 1 both wired construction, is characterized in that: described 4), vertical vertical rod length is 3.5 meters.
6. the safety protecting method of high ferro according to claim 1 both wired construction, is characterized in that: described 5), long diagonal brace length is 3.5 meters, and the polyvinyl chloride pipe diameter that the bottom of long diagonal brace is sheathed is 63 millimeters, and length is 20 centimetres.
7. the safety protecting method of high ferro according to claim 1 both wired construction, it is characterized in that: described 6), horizontal steel tube length is 6 meters, in three row of horizontal steel pipes, often the spacing of adjacent two horizontal steel tubes is 0.8 meter, descends the horizontal steel tube of row to be arranged on 1.7 meters of of vertical vertical rod most.
8. the safety protecting method of high ferro according to claim 1 both wired construction, it is characterized in that: the clad steel silk screen described 7) comprises leaching plastic-steel silk screen and stainless steel cloth, the mesh of the gauze wire cloth of two kinds is square, the length of side 5 centimetres and 0.3 centimetre respectively.
9. the safety protecting method of high ferro according to claim 1 both wired construction, it is characterized in that: the color steel thickness described 8) is 0.4 millimeter, longitudinal fixing hole of adjacent two color steel laps is also overlapping.
10. the protective fence that formed of the safety protecting method of a high ferro as claimed in any one of claims 1-9 wherein both wired construction, it is characterized in that: comprise the half-terete polyvinyl chloride semicanal that correspondence is arranged on the both sides up and down of hair line two rail, laterally be placed on the bottom bar on the polyvinyl chloride semicanal of two one steel rails, be placed on the longitudinal steel pipe of two row offseting same distance from two one steel rails to station platform direction respectively, be arranged on the vertical vertical rod corresponding with bottom bar in the outside of the rail near station platform, connect the long diagonal brace of vertical vertical rod and the longitudinal steel pipe away from station platform, be set in the polyvinyl chloride pipe of the bottom of long diagonal brace, be arranged on vertical vertical rod and be positioned at the equally distributed three row of horizontal steel pipes above station platform, to be arranged on three row of horizontal steel pipes and the color steel of longitudinal arrangement, being arranged on below color steel and connecting descends the clad steel silk screen of row of horizontal steel pipe and longitudinal steel pipe and interval to be pasted onto warning vertically hung scroll on color steel most, every one steel rail keeps at a certain distance away and is uniformly distributed several polyvinyl chloride semicanals, one end of this bottom bar is resisted against the side of station platform, the other end by round steel by bottom bar and corresponding rail and up and down the polyvinyl chloride semicanal of both sides bundle and be fixed together, each longitudinal steel pipe is fixed by cruciform fastening for falsework and each bottom bar, each vertical vertical rod is fixed by cruciform fastening for falsework and the longitudinal steel pipe near station platform, long diagonal brace and horizontal steel tube are all fixed by cruciform fastening for falsework, adjacent color steel imbricate is placed, and color steel is equipped with at the horizontal steel tube place of each row corresponding the fixing hole be arranged above and below, and then entangles horizontal steel tube by galvanized wire and tightens through upper lower fixed hole, double-layer wire Netcom crosses plastics self-locking band and is locked.
CN201210166499.4A 2012-05-24 2012-05-24 A kind of high ferro is the safety protecting method of wired construction and the protective fence of formation thereof both Expired - Fee Related CN103422714B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210166499.4A CN103422714B (en) 2012-05-24 2012-05-24 A kind of high ferro is the safety protecting method of wired construction and the protective fence of formation thereof both

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210166499.4A CN103422714B (en) 2012-05-24 2012-05-24 A kind of high ferro is the safety protecting method of wired construction and the protective fence of formation thereof both

Publications (2)

Publication Number Publication Date
CN103422714A CN103422714A (en) 2013-12-04
CN103422714B true CN103422714B (en) 2016-04-06

Family

ID=49648056

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210166499.4A Expired - Fee Related CN103422714B (en) 2012-05-24 2012-05-24 A kind of high ferro is the safety protecting method of wired construction and the protective fence of formation thereof both

Country Status (1)

Country Link
CN (1) CN103422714B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107217912B (en) * 2017-06-01 2019-06-14 中铁城建集团第二工程有限公司 A kind of superelevation physical isolation construction method for neighbouring high-speed rail Business Line construction
CN107255434A (en) * 2017-07-17 2017-10-17 贵州大学 A kind of bridge demolition side safeguard structure for that will be split
CN108019095B (en) * 2017-10-31 2019-12-17 余光明 Simple guardrail locking device
US10961731B2 (en) * 2017-12-15 2021-03-30 Jonathan J. Melic Safety fence assembly
CN110761613A (en) * 2019-11-11 2020-02-07 中国葛洲坝集团第二工程有限公司 Construction enclosure
CN114000770B (en) * 2020-07-28 2023-03-21 上海机场(集团)有限公司 Novel visual shielding object and assembling method thereof
CN112144539A (en) * 2020-09-23 2020-12-29 中国一冶集团有限公司 Deep foundation pit protective fence and protective fence installation method
CN117005725B (en) * 2023-06-30 2025-08-22 上海地铁维护保障有限公司工务分公司 Isolation structure and method for over-station construction

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2904836A1 (en) * 2006-08-09 2008-02-15 Europ De Travaux Ferroviaires DEVICE FOR ENSURING THE PROTECTION OF PEOPLE WORKING ON A RAILWAY WORKSITE
WO2010114367A1 (en) * 2009-03-30 2010-10-07 Roof Safety Systems B.V. Safety structure for a railway line
AU2012100415A4 (en) * 2012-04-13 2012-05-10 Alumitec Pty Ltd Temporary safety railing system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2904836A1 (en) * 2006-08-09 2008-02-15 Europ De Travaux Ferroviaires DEVICE FOR ENSURING THE PROTECTION OF PEOPLE WORKING ON A RAILWAY WORKSITE
WO2010114367A1 (en) * 2009-03-30 2010-10-07 Roof Safety Systems B.V. Safety structure for a railway line
AU2012100415A4 (en) * 2012-04-13 2012-05-10 Alumitec Pty Ltd Temporary safety railing system

Also Published As

Publication number Publication date
CN103422714A (en) 2013-12-04

Similar Documents

Publication Publication Date Title
CN103422714A (en) Safety protection method for high speed rail existing line construction and protection guardrail formed by using same
CN204151692U (en) A kind of modular assembly formula connection system for guide rail
CN207098456U (en) A kind of crossover tower auxiliary cross-arm block component for being used to live across operation
CN202899600U (en) Building site faces swift formula installation in limit and tears protection device open
CN104993421B (en) A kind of portable pay-off crossing frame
CN103236656B (en) Column suspension type crossing structure and operating method thereof
CN202227701U (en) Assembled horizontal passage device
CN202530816U (en) A hurricane-shielding reinforcing device of a prefabricated house
CN204793847U (en) Frame is strideed across to portable unwrapping wire
CN103138206A (en) Device and method to replace overhead ground wire of high-voltage overhead power transmission line by means of suspending of PPR pipes
CN106532557B (en) Across 10KV line construction platform tools devices
CN202194395U (en) Tool type edge protector rack
CN203769406U (en) Height-adjustable tower support for wireless private network equipment
CN205206367U (en) Side is inserted formula elevartor shaft guard gate and is simply installed
CN203430009U (en) Construction hanging basket
CN204252642U (en) A kind of building operations guardrail
CN203445520U (en) Live spanning device
CN203166405U (en) Trans-road line laying support
CN202324680U (en) Protection device of elevator shaft
CN204112824U (en) A kind of high-tension pole increases lightning protection device
CN102957113B (en) Decoration construction temporary power construction system
CN105781133A (en) Simple edge protecting system and construction method thereof
CN203086060U (en) Device for replacing overhead ground wires of high-voltage overhead power transmission line by using PPR (polypropylene random) pipe suspension
CN203008504U (en) Hard rod type protective barrier
CN209494202U (en) The hardened structure of big one's parents people's ring wall formula riding track

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB02 Change of applicant information

Address after: 5-7, building 510600, building 8, Gonghe West Road, Guangzhou, Yuexiu District, Guangdong

Applicant after: China Railway Urban Construction Group Second Engineering Co.,Ltd.

Applicant after: CHINA RAILWAY 25TH BUREAU GROUP Co.,Ltd.

Address before: 5-7, building 510600, building 8, Gonghe West Road, Guangzhou, Yuexiu District, Guangdong

Applicant before: Construction Installation Engineering Co., Ltd. of China Railway 25th Bureau Group

Applicant before: CHINA RAILWAY 25TH BUREAU GROUP Co.,Ltd.

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20151030

Address after: 510600, building 8, Gonghe West Road, Guangzhou, Yuexiu District, Guangdong

Applicant after: China Railway Urban Construction Group Second Engineering Co.,Ltd.

Applicant after: CHINA RAILWAY 25TH BUREAU GROUP Co.,Ltd.

Applicant after: CHINA RAILWAY URBAN CONSTRUCTION GROUP Co.,Ltd.

Address before: 5-7, building 510600, building 8, Gonghe West Road, Guangzhou, Yuexiu District, Guangdong

Applicant before: China Railway Urban Construction Group Second Engineering Co.,Ltd.

Applicant before: CHINA RAILWAY 25TH BUREAU GROUP Co.,Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160406