CN103422437B - 波形钢腹板桥梁台阶式施工工艺 - Google Patents

波形钢腹板桥梁台阶式施工工艺 Download PDF

Info

Publication number
CN103422437B
CN103422437B CN201310306337.0A CN201310306337A CN103422437B CN 103422437 B CN103422437 B CN 103422437B CN 201310306337 A CN201310306337 A CN 201310306337A CN 103422437 B CN103422437 B CN 103422437B
Authority
CN
China
Prior art keywords
sections
wavelike steel
steel webplate
base plate
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310306337.0A
Other languages
English (en)
Other versions
CN103422437A (zh
Inventor
孙天明
陈小勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang CTB Corrugated Steel Web Co., Ltd.
Original Assignee
Zhejiang Ctb Corrugated Steel Web Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=49647789&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CN103422437(B) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Zhejiang Ctb Corrugated Steel Web Co Ltd filed Critical Zhejiang Ctb Corrugated Steel Web Co Ltd
Priority to CN201310306337.0A priority Critical patent/CN103422437B/zh
Publication of CN103422437A publication Critical patent/CN103422437A/zh
Application granted granted Critical
Publication of CN103422437B publication Critical patent/CN103422437B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明涉及波形钢腹板桥梁台阶式施工工艺,沿桥梁纵向按施工节段次序分为N节段、N+1节段、N+2节段,每个节段顶板在上,底板在下,波形钢腹板位于顶板和底板之间。三个节段作业:1.N节段施工顶板,N+1节段施工底板;2.N+2节段安装波形钢腹板;3.上述三个节段作业完成后,依次各自进入下一个节段。波形钢腹板桥梁台阶式施工工艺使顶板、底板、波形钢腹板错位施工,工序间无交叉,互不影响,解决了施工中存在的安全隐患。三个工作面可以同时施工,并且基本达到同步完工。避免了等强期间的工人窝工和下个节段施工时的人员不足问题,达到了人力资源在时间轴上合理分配的效果,从而缩短35%以上的工期,节约了施工的成本。

Description

波形钢腹板桥梁台阶式施工工艺
技术领域
本发明涉及一种桥梁施工工艺,尤其涉及波形钢腹板桥梁台阶式施工工艺。
背景技术
随着我国桥梁结构的不断发展,新的桥梁结构形式不断涌现,波形钢腹板桥梁作为一种新的结构,正逐步被应用。普通的波形钢腹板桥梁施工时,顶板、底板同步浇筑,大量工作集中在同一个节段内。由于顶板、底板在上下方向同时作业,会造成顶板模板难以找到适合的支撑点。而底板在顶板下方同时施工,容易受上方顶板施工的影响,存在一定的安全隐患。
发明内容
本发明是为解决现有波形钢腹板桥梁施工中所具有的顶板难以找到适合的支撑点、底板施工存在安全隐患等不足而提出的,旨在提供具有顶板、底板错位施工,且底板施工不受顶板施工的影响的波形钢腹板桥梁台阶式施工工艺。
为了解决上述技术问题,本发明通过下述技术方案得以解决:
波形钢腹板桥梁台阶式施工工艺,沿桥梁纵向按施工节段次序分为N节段、N+1节段、N+2节段,每个节段顶板在上,底板在下,波形钢腹板位于顶板和底板之间。工艺分为以下两种:
三个节段作业:1.N节段施工顶板,N+1节段施工底板;2.N+2节段安装波形钢腹板;3.上述三个节段作业完成后,依次各自进入下一个节段;
两个节段作业:a.N节段施工顶板,N+1节段先安装波形钢腹板,再施工N+1节段底板,b.上述两个节段作业完成后,依次各自进入下一个节段。
通过台阶式的施工工艺,施工顶板时,使顶板模板可以方便的找到适合的支撑点。错位施工还使处于下方的底板施工人员不会受到上方施工的影响,还避免了被上方掉落物品砸伤的情况出现。
作为优选,各个节段所在的垂直空间内同时只展开一项施工工作。避免上下同时施工,造成相互的影响,防止上方杂物掉落,砸伤下方的施工人员。
作为优选,除步骤a以外,其余步骤中的各个节段内独立工作。独立施工,使各个工作区域可以互相不受干扰。
作为优选,三个节段作业方法中,波形钢腹板安装节段领先底板一个节段,波形钢腹板安装节段领先顶板两个节段。三个阶段相互错位,互不干扰,且三个节段可以同时进行施工。
作为优选,两个节段作业方法中,波形钢腹板安装节段与底板位于同一个节段,波形钢腹板安装节段领先顶板一个节段。两个阶段相互错位,互不干扰,且两个节段可以同时进行施工。
作为优选,顶板为钢筋混凝土。钢筋混凝土整体性好、耐久性好,整体强度高。
作为优选,底板为钢筋混凝土。钢筋混凝土整体性好、耐久性好,整体强度高。
底板的重量及支撑底板的模板重量,利用本节段波形钢腹板自身的刚度承担。上述方法利用波形钢腹板刚度大的优势,使施工荷载被分担,施工装备投入减小,顶、底板荷载受力清晰,提高了整体的稳定性。
作为优选,n+2节段波形钢腹板安装时,n+1节段的底板的强度需达到设计强度的30%以上。保证n+2节段波形钢腹板可以得到强有力的支持。
作为优选,顶板节段分界线、底板节段分界线、波形钢腹板节段搭界线三者不在同一条直线上。
按照本发明的技术方案,波形钢腹板桥梁台阶式施工工艺使顶板、底板、波形钢腹板错位施工,工序间无交叉,互不影响,解决了施工中存在的安全隐患。三个工作面可以同时施工,并且基本达到同步完工。避免了等强期间的工人窝工和下个节段施工时的人员不足问题,达到了人力资源在时间轴上合理分配的效果,从而可以缩短35%以上的工期,大大的节约了施工的成本。
附图说明
图1为本发明波形钢腹板桥梁台阶式施工工艺的示意图一。
图2为本发明波形钢腹板桥梁台阶式施工工艺的示意图二。
具体实施方式
下面结合附图与具体实施方式对本发明作进一步详细描述:
实施例1
波形钢腹板桥梁台阶式施工工艺,沿桥梁纵向按施工节段次序分为N节段、N+1节段、N+2节段,每个节段顶板1在上,底板3在下,波形钢腹板2位于顶板1和底板3之间,三个节段作业:1.N节段施工顶板1,N+1节段施工底板3;2.N+2节段安装波形钢腹板2;3.上述三个节段作业完成后,依次各自进入下一个节段;
各个节段所在的垂直空间内同时只展开一项施工工作。
每个步骤中的各个节段内独立工作。
三个节段作业方法中,波形钢腹板2安装节段领先底板3一个节段,波形钢腹板2安装节段领先顶板1两个节段。
顶板1为钢筋混凝土。
底板3为钢筋混凝土。
n+2节段波形钢腹板2安装时,n+1节段的底板3的强度需达到设计强度的30%以上。
顶板1节段分界线、底板3节段分界线、波形钢腹板2节段搭界线三者不在同一条直线上。
实施例2
波形钢腹板桥梁台阶式施工工艺,沿桥梁纵向按施工节段次序分为N节段、N+1节段、N+2节段,每个节段顶板1在上,底板3在下,波形钢腹板2位于顶板1和底板3之间,两个节段作业:a.N节段施工顶板1,N+1节段先安装波形钢腹板2,再施工N+1节段底板3,b.上述两个节段作业完成后,依次各自进入下一个节段。
各个节段所在的垂直空间内同时只展开一项施工工作。
除步骤a以外,其余步骤中的各个节段内独立工作。
两个节段作业方法中:波形钢腹板2安装节段与底板3位于同一个节段,波形钢腹板2安装节段领先顶板1一个节段
顶板1为钢筋混凝土。
底板3为钢筋混凝土。
底板3的重量及支撑底板的模板重量,利用本节段波形钢腹板自身的刚度承担。上述方法利用波形钢腹板刚度大的优势,使施工荷载被分担,施工装备投入减小,顶、底板荷载受力清晰,提高了整体的稳定性。
n+2节段波形钢腹板2安装时,n+1节段的底板3的强度需达到设计强度的30%以上。
顶板1节段分界线、底板3节段分界线、波形钢腹板2节段搭界线三者不在同一条直线上。
总之,以上所述仅为本发明的较佳实施例,凡依本发明申请专利范围所作的均等变化与修饰,皆应属本发明专利的涵盖范围。

Claims (6)

1.波形钢腹板桥梁台阶式施工工艺,沿桥梁纵向按施工节段次序分为N节段、N+1节段、N+2节段,每个节段顶板(1)在上,底板(3)在下,波形钢腹板(2)位于顶板(1)和底板(3)之间,其特征在于:
三个节段作业:1.N节段施工顶板(1),N+1节段施工底板(3);2.N+2节段安装波形钢腹板(2);3.上述三个节段作业完成后,依次各自进入下一个节段;
两个节段作业:a.N节段施工顶板(1),N+1节段先安装波形钢腹板(2),再施工N+1节段底板(3),b.上述两个节段作业完成后,依次各自进入下一个节段;各个节段所在的垂直空间内同时只展开一项施工工作;除步骤a以外,其余步骤中的各个节段内独立工作;n+2节段波形钢腹板(2)安装时,n+1节段的底板(3)的强度需达到设计强度的30%以上。
2.根据权利要求1所述的波形钢腹板桥梁台阶式施工工艺,其特征在于:三个节段作业方法中,波形钢腹板(2)安装节段领先底板(3)一个节段,波形钢腹板(2)安装节段领先顶板(1)两个节段。
3.根据权利要求1所述的波形钢腹板桥梁台阶式施工工艺,其特征在于:两个节段作业方法中:波形钢腹板(2)安装节段与底板(3)位于同一个节段,波形钢腹板(2)安装节段领先顶板(1)一个节段。
4.根据权利要求1所述的波形钢腹板桥梁台阶式施工工艺,其特征在于:顶板(1)为钢筋混凝土。
5.根据权利要求1所述的波形钢腹板桥梁台阶式施工工艺,其特征在于:底板(3)为钢筋混凝土,底板(3)的重量及支撑底板的模板重量,利用本节段波形钢腹板自身的刚度承担。
6.根据权利要求1所述的波形钢腹板桥梁台阶式施工工艺,其特征在于:顶板(1)节段分界线、底板(3)节段分界线、波形钢腹板(2)节段搭界线三者不在同一条直线上。
CN201310306337.0A 2013-07-18 2013-07-18 波形钢腹板桥梁台阶式施工工艺 Active CN103422437B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310306337.0A CN103422437B (zh) 2013-07-18 2013-07-18 波形钢腹板桥梁台阶式施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310306337.0A CN103422437B (zh) 2013-07-18 2013-07-18 波形钢腹板桥梁台阶式施工工艺

Publications (2)

Publication Number Publication Date
CN103422437A CN103422437A (zh) 2013-12-04
CN103422437B true CN103422437B (zh) 2015-11-18

Family

ID=49647789

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310306337.0A Active CN103422437B (zh) 2013-07-18 2013-07-18 波形钢腹板桥梁台阶式施工工艺

Country Status (1)

Country Link
CN (1) CN103422437B (zh)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109797659A (zh) * 2019-03-21 2019-05-24 东南大学 一种波形钢腹板连续梁桥移动支架异步施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004116060A (ja) * 2002-09-25 2004-04-15 Sumitomo Mitsui Construction Co Ltd 波形鋼板ウェブ橋の架設方法
JP2006118314A (ja) * 2004-10-25 2006-05-11 Ps Mitsubishi Construction Co Ltd 波形鋼板ウエブ橋の架設方法
JP2006307575A (ja) * 2005-04-28 2006-11-09 Ps Mitsubishi Construction Co Ltd 波形鋼板ウエブ橋の張出施工方法および架設作業車
JP2006316506A (ja) * 2005-05-12 2006-11-24 Sumitomo Mitsui Construction Co Ltd 橋桁の構築方法
JP2007092313A (ja) * 2005-09-27 2007-04-12 Ps Mitsubishi Construction Co Ltd Pc波形鋼板ウエブ箱桁の構築方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004116060A (ja) * 2002-09-25 2004-04-15 Sumitomo Mitsui Construction Co Ltd 波形鋼板ウェブ橋の架設方法
JP2006118314A (ja) * 2004-10-25 2006-05-11 Ps Mitsubishi Construction Co Ltd 波形鋼板ウエブ橋の架設方法
JP2006307575A (ja) * 2005-04-28 2006-11-09 Ps Mitsubishi Construction Co Ltd 波形鋼板ウエブ橋の張出施工方法および架設作業車
JP2006316506A (ja) * 2005-05-12 2006-11-24 Sumitomo Mitsui Construction Co Ltd 橋桁の構築方法
JP2007092313A (ja) * 2005-09-27 2007-04-12 Ps Mitsubishi Construction Co Ltd Pc波形鋼板ウエブ箱桁の構築方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
波形钢腹板连续刚构与PC连续刚构的对比研究;董晓;《工程科技Ⅱ辑》;20101215(第12期);第69页、第73页、第78页、附图4.1、附图4.3 *

Also Published As

Publication number Publication date
CN103422437A (zh) 2013-12-04

Similar Documents

Publication Publication Date Title
CN104018434B (zh) 建筑隔震橡胶支座的更换方法
CN102849602A (zh) 自动扶梯或自动人行道上防地震保护装置
CN103422437B (zh) 波形钢腹板桥梁台阶式施工工艺
CN104213511B (zh) 一种桥梁施工平台结构及其搭建方法
CN202000265U (zh) 桥梁高墩混凝土施工模板
CN203487639U (zh) 一种钢结构柱脚锚栓精准预埋固定装置
CN203530848U (zh) 桥梁盖梁模板的支撑支架
CN103276909B (zh) 弧形网架拼装方法及其使用的网架拼装胎架
CN204057537U (zh) 一种防坠落施工电梯
CN204386608U (zh) 一种隧道仰拱施工工装
CN104358396B (zh) 盘式脚手架立杆与固定盘分体结构
CN204162999U (zh) 一种桥梁施工平台结构
CN104499728A (zh) 吸收塔平移装置及其施工方法
CN204162235U (zh) 电梯上梁安全检修装置
CN205224272U (zh) 一种钢结构厂房用悬挑结构
CN204341019U (zh) 一种车站站台的临时通行装置
CN204919565U (zh) 基坑支撑拆除使用的钢平台
CN204919608U (zh) 地下车站施工用悬挑系统
CN105113542A (zh) 地下车站施工用悬挑系统及地下车站施工方法
CN204343697U (zh) 一种竖井安全隔离平台
CN104326331A (zh) 一种电梯上梁安全检修装置
CN204569069U (zh) 一种电梯安全部件检测设备专用的导轨联接器装置
CN204324669U (zh) 一种矿用锁紧器楔块的楔紧装置
CN204299144U (zh) 电梯井内模操作平台
CN209011295U (zh) 一种新型钢构件

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: HANGZHOU FENGSHI COLOR PLATE CO., LTD.

Free format text: FORMER OWNER: HANGZHOU BOSHU CIVIL ENGINEERING TECHNOLOGY CO., LTD.

Effective date: 20141113

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 311215 HANGZHOU, ZHEJIANG PROVINCE TO: 311200 HANGZHOU, ZHEJIANG PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20141113

Address after: 311200 Nanyang Economic Development Zone, Xiaoshan District, Zhejiang, Hangzhou

Applicant after: Hangzhou Feng Shi color steel Co., Ltd

Address before: Hangzhou City, Zhejiang province 311215 Xiaoshan economic and Technological Development Zone, North Building 2 room 1711 Ning'an

Applicant before: Hangzhou Boshu Civil Engineering Technology Co., Ltd.

ASS Succession or assignment of patent right

Owner name: ZHEJIANG CTB CORRUGATED STEEL WEB CO., LTD.

Free format text: FORMER OWNER: HANGZHOU FENGSHI COLOR PLATE CO., LTD.

Effective date: 20150227

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 311200 HANGZHOU, ZHEJIANG PROVINCE TO: 314422 HANGZHOU, ZHEJIANG PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20150227

Address after: 314422, No. 168-2, village, town, Hangzhou, Xiaoshan District, Zhejiang

Applicant after: Zhejiang CTB Corrugated Steel Web Co., Ltd.

Address before: 311200 Nanyang Economic Development Zone, Xiaoshan District, Zhejiang, Hangzhou

Applicant before: Hangzhou Feng Shi color steel Co., Ltd

C14 Grant of patent or utility model
GR01 Patent grant