CN103334380A - Converting method for external pre-stressed anchor cable and permanent tie bar of swallow-type tie bar arch bridge - Google Patents

Converting method for external pre-stressed anchor cable and permanent tie bar of swallow-type tie bar arch bridge Download PDF

Info

Publication number
CN103334380A
CN103334380A CN201310283750XA CN201310283750A CN103334380A CN 103334380 A CN103334380 A CN 103334380A CN 201310283750X A CN201310283750X A CN 201310283750XA CN 201310283750 A CN201310283750 A CN 201310283750A CN 103334380 A CN103334380 A CN 103334380A
Authority
CN
China
Prior art keywords
anchor cable
rod
external prestressing
permanent
tie bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310283750XA
Other languages
Chinese (zh)
Other versions
CN103334380B (en
Inventor
王斌
孙利军
董炬洪
王昌裕
赖国甫
崔国辉
曾胜群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Seventh Group Co Ltd
Wuhan Engineering Co Ltd of China Railway Seventh Group Co Ltd
Original Assignee
China Railway Seventh Group Co Ltd
Wuhan Engineering Co Ltd of China Railway Seventh Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Seventh Group Co Ltd, Wuhan Engineering Co Ltd of China Railway Seventh Group Co Ltd filed Critical China Railway Seventh Group Co Ltd
Priority to CN201310283750.XA priority Critical patent/CN103334380B/en
Publication of CN103334380A publication Critical patent/CN103334380A/en
Application granted granted Critical
Publication of CN103334380B publication Critical patent/CN103334380B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to a converting method for an external pre-stressed anchor cable and a permanent tie bar of a swallow-type tie bar arch bridge. The converting method for the external pre-stressed anchor cable and the permanent tie bar of the swallow-type tie bar arch bridge comprises the following steps of (1) installation of the external pre-stressed anchor cable, (2) tensioning of the external pre-stressed anchor cable, (3) installation of a concrete support and steering structure, (4) installation of the permanent tie bar, (5) conversion between the external pre-stressed anchor cable and a stress supporting system of the permanent tie bar, and (6) disassembly of the external pre-stressed anchor cable. The converting method for the external pre-stressed anchor cable and the permanent tie bar of the swallow-type tie bar arch bridge has the advantages that adverse factors, caused by a deep water level to construction, of a deep water level, a high water velocity, large influence of floods, influence on passage of a main channel and the like due to the fact that the swallow-type tie bar arch bridge is arranged over the main channel are avoided, a large temporary support does not need to be arranged, materials can be saved, the channel is not polluted, noise is not produced, safety and operability are good, the materials can be recycled, manpower and material resources are saved, working efficiency can be effectively improved, and the construction period can be shortened.

Description

The conversion method of flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod
Technical field
The present invention relates to method for bridge construction, relate in particular to the conversion method of a kind of flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod.
Background technology
In the construction of flying swallow bowstring arch bridge, tie-rod is installed, stretching construction need rely on the limit arch to go up the concrete support and steering structure (being that the limit arch is gone up reinforced concrete upright column) is finished.After limit arch rib construction was finished, the vertical load that limit arch rib and later stage limit arch superstructure produce should be born by falsework.Support is impaired deactivate after, the vertical bearing capacity of limit arch rib is not enough to satisfy that arch is gone up the support of permanent tie-rod and concrete supports and the steering structure construction, causes carrying out stretch-draw work and the follow-up structure construction of permanent tie-rod.For this reason, need take measures to reinforce the limit arch structure in order to finish limit arch upward support and concrete support and the steering structure construction of permanent tie-rod, carry out interim reinforcement system and the conversion of tie-rod forever at last again.Present settling mode has: 1, recover the support method; 2, temporary rest pier method; 3, incremental launching construction method.But above measure all has deficiency, recovers support method and temporary rest pier method and can pollute the navigation channel and noise disturbs residents in construction period, and support or buttress construction period are long, consumptive material is many, can the blocking-up bridge after finishing under main channel and be subject to flood influence, the later stage is removed difficulty.The incremental launching construction method must arrange stressed pedestal at adjacent structure, can produce subsidiary stress to the adjacent concrete structure, influences its safety.Therefore, we press for and a kind ofly can reinforce the limit arch structure, can make the conversion that is well on of interim reinforcement system and permanent tie-rod again.
Summary of the invention
Technical problem to be solved by this invention provides the conversion method of a kind of flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod, and this method can be reinforced the limit arch structure of flying swallow bowstring arch bridge, guarantees carrying out smoothly of construction.
The technical solution adopted in the present invention is: the conversion method of a kind of flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod, it comprises the steps:
The first step, the outer prestress anchorage cable of fixing body;
Second step, the external prestressing anchorage cable stretching;
The 3rd step, the installation of concrete support and steering structure;
In the 4th step, permanent tie-rod is installed;
In the 5th step, the external prestressing anchor cable is changed with the stressed support system of permanent tie-rod;
In the 6th step, remove the external prestressing anchor cable.
Press such scheme, in the step 1, described external prestressing anchor cable is positioned at the downside of permanent tie-rod 1 at vertical plane, is positioned at the outside of permanent tie-rod at horizontal plane, guarantees that external prestressing anchor cable and permanent tie-rod are at the locus incongruity; In the time can not satisfying this condition, must take to locate the parrel locus of prestress anchorage cable and permanent tie-rod outside the obligatory point by force.
Press such scheme, described external prestressing anchor cable is totally four bundles, and 32 steel strand of every bundle adopt by root, symmetry and reeve and the firmly beforehand means installation.
Press such scheme, described steel strand are φ 15.2mm, the steel strand of fpk=1860Mpa.
Press such scheme, in the step 2, the external prestressing anchorage cable stretching adopts grading tension, after every grade of stretch-draw crossstructure is carried out stress, strain detecting, guarantees that structural stress and strain value are in the work amplitude range of design and standard permission.
Press such scheme, in the step 5, in the transition period of external prestressing anchor cable with permanent tie-rod, the external prestressing anchor cable adopts the classification off-loading, and permanent tie-rod adopts and increases lotus step by step.
The described external prestressing anchor cable of this method adopts φ 15.2mm, and the steel strand of fpk=1860Mpa are formed, and steel strand length, arrangement form, quantity can be adjusted according to bridge length, form of structure and force request.
Beneficial effect of the present invention is: 1, avoid being positioned at that the water level that brings in the main channel sky is dark, water velocity is fast, flood influence is big, influencing the main channel unfavorable factor that construction is caused such as current because of bridge.2, do not need large-scale falsework is set, saved material.3, do not pollute the navigation channel, do not produce noise, safety and strong operability.4, the recyclable and utilization again of material.5, save human and material resources, can effectively improve work efficiency, reduction of erection time.
Description of drawings
Fig. 1 is the facade structures schematic diagram of flying swallow bowstring arch bridge.
Fig. 2 is the plane structure schematic diagram of flying swallow bowstring arch bridge.
Fig. 3 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the facade structures schematic diagram of step 1.
Fig. 4 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the plane structure schematic diagram of step 1.
Fig. 5 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the facade structures schematic diagram of step 2.
Fig. 6 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the plane structure schematic diagram of step 2.
Fig. 7 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the facade structures schematic diagram of step 3.
Fig. 8 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the plane structure schematic diagram of step 3.
Fig. 9 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the facade structures schematic diagram of step 4.
Figure 10 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the plane structure schematic diagram of step 4.
Figure 11 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the facade structures schematic diagram of step 5.
Figure 12 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the plane structure schematic diagram of step 5.
Figure 13 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the facade structures schematic diagram of step 6.
Figure 14 be flying swallow bowstring arch bridge external prestressing anchor cable with the conversion method of permanent tie-rod in the plane structure schematic diagram of step 6.
Among the figure: 1, permanent tie-rod, 2, the limit arch rib, 3, concrete supports and steering structure, 4, the external prestressing anchor cable.
The specific embodiment
Be that the present invention will be further described for example with canal river, Qu County two bridge constructions below.
Referring to Fig. 1, Fig. 2, canal river two bridge bridge the beginning and the end mileages are K0+090.5~K0+692.0, and bridge center mileage is K0+383, total length 601.5m.Main bridge is the flying swallow Steel Pipe Concrete Tied-arch Bridge, total length 356m, and the aperture is arranged as (75+206+75) m, and the west arch joins with 86mT shaped steel structure, and arch joins with the 128m continuous beam in the east.Full-bridge arranges the permanent tie-rod of 16 bundles altogether, and each 8 bundle of upstream and downstream, every bundle tie-rod do not have bonding underrelaxation steel strand by the spraying of 37 band PE sheath epoxies and form fpk=1960Mpa.
After canal river two bridge limit arch rib constructions in 2011 are finished, because causing limit arch falsework, the big flood reason deactivates, go up concrete support and steering structure construction for finishing the limit arch, be convenient to main bridge tie-rod and install and stretch-draw, adopt external prestressing anchor cable method to reinforce the limit arch structure.According to actual conditions, the external prestressing anchor cable is arranged in the main bridge scope, runs through limit arch and main arch, 356 meters of effective lengths, and the stretch-draw anchor end is arranged at limit arch abutment head.Main bridge upstream and downstream arch rib respectively arranges 2 bundles, and every bundle does not have bonding underrelaxation steel strand by the spraying of 32 band PE sheath epoxies to be formed, and fpk=1860MPa, anchor cable do not establish flat vertical curve.
After the limit arch structure is reinforced, build fast and finish limit arch upward concrete support and steering structure (being that the limit arch is gone up reinforced concrete upright column).After treating that concrete structure reaches design strength, the permanent tie-rod of Fast Installation 16 bundles carries out external prestressing anchor cable and the stressed support system conversion of permanent tie-rod after finishing.After design, monitoring, supervisor's affirmation system convert, in time remove the external prestressing anchor cable.
The conversion method of flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod, as Fig. 3-shown in Figure 14:
The first step, the installation of external prestressing anchor cable 4;
External prestressing anchor cable 4 is totally 4 bundles, 32 of every bundles, and employing is reeved by root, symmetry and the mode of pretension is installed; External prestressing anchor cable 4 is positioned at permanent tie-rod 1 downside at vertical plane, is positioned at permanent tie-rod 1 outside at horizontal plane, and external prestressing anchor cable 4 does not have in the space with permanent tie-rod 1 joins;
Second step, the stretch-draw of external prestressing anchor cable 4;
Behind external prestressing anchor cable 4 first pretensions to 100 ton/bundle, divides six grades of stretch-draw, 25 tons of every grade of stretching force increments, 250 tons of every bundle external prestressing anchor cable 4 whole pulling force, 4 restraint 1000 tons of external prestressing anchor cables 4 total pulling forces;
In the 3rd step, at limit arch rib 2 concrete is installed and is supported and steering structure 3;
In the 4th step, 600 tons of permanent tie-rod 1 and stretch-draw are installed;
In the 5th step, external prestressing anchor cable 4 is changed with the stressed support system of permanent tie-rod 1;
The system transition period, 4 fens 4 grades of off-loadings of external prestressing anchor cable, 250 tons of every grade of off-loadings (unloading), permanent tie-rod 1 increases lotus step by step, and every grade increases 250 tons of lotuses, and the mode of taking unloading earlier to increase lotus is again carried out; In the system transition period, Zong Suoli maintains (in design allows amplitude range) between 1350~1600 tons, and final permanent tie-rod 1 total stretching force reaches 1600 tons, 0 ton of external prestressing anchor cable 4 stretching force.
In the 6th step, remove external prestressing anchor cable 4.
The present invention can not only improve efficiency of construction, eliminate safe hidden trouble, reduces operating cost, can also reach the purpose that reduces environmental disruption; And can reduce the hydrology, the restriction of geological condition to constructing, application value is big.

Claims (6)

1. the conversion method of a flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod is characterized in that it comprises the steps:
The first step, the outer prestress anchorage cable of fixing body;
Second step, the external prestressing anchorage cable stretching;
The 3rd step, the installation of concrete support and steering structure;
In the 4th step, permanent tie-rod is installed;
In the 5th step, the external prestressing anchor cable is changed with the stressed support system of permanent tie-rod;
In the 6th step, remove the external prestressing anchor cable.
2. flying swallow bowstring arch bridge external prestressing anchor cable as claimed in claim 1 and the forever conversion method of tie-rod, it is characterized in that: in the step 1, described external prestressing anchor cable is positioned at the downside of permanent tie-rod 1 at vertical plane, be positioned at the outside of permanent tie-rod at horizontal plane, guarantee that external prestressing anchor cable and permanent tie-rod are at the locus incongruity.
3. the conversion method of flying swallow bowstring arch bridge external prestressing anchor cable as claimed in claim 2 and permanent tie-rod, it is characterized in that: described external prestressing anchor cable is totally four bundles, and 32 steel strand of every bundle adopt by root, symmetry and reeve and firmly beforehand means is installed.
4. flying swallow bowstring arch bridge external prestressing anchor cable as claimed in claim 3 and the forever conversion method of tie-rod, it is characterized in that: described steel strand are φ 15.2mm, the steel strand of fpk=1860Mpa.
5. flying swallow bowstring arch bridge external prestressing anchor cable as claimed in claim 1 and the forever conversion method of tie-rod, it is characterized in that: in the step 2, the external prestressing anchorage cable stretching adopts grading tension, after every grade of stretch-draw crossstructure is carried out stress, strain detecting.
6. flying swallow bowstring arch bridge external prestressing anchor cable as claimed in claim 1 and the forever conversion method of tie-rod, it is characterized in that: in the step 5, in the transition period of external prestressing anchor cable with permanent tie-rod, the external prestressing anchor cable adopts the classification off-loading, and permanent tie-rod adopts and increases lotus step by step.
CN201310283750.XA 2013-07-05 2013-07-05 The conversion method of flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod Active CN103334380B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310283750.XA CN103334380B (en) 2013-07-05 2013-07-05 The conversion method of flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310283750.XA CN103334380B (en) 2013-07-05 2013-07-05 The conversion method of flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod

Publications (2)

Publication Number Publication Date
CN103334380A true CN103334380A (en) 2013-10-02
CN103334380B CN103334380B (en) 2016-06-15

Family

ID=49242578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310283750.XA Active CN103334380B (en) 2013-07-05 2013-07-05 The conversion method of flying swallow bowstring arch bridge external prestressing anchor cable and permanent tie-rod

Country Status (1)

Country Link
CN (1) CN103334380B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019062271A1 (en) * 2017-09-28 2019-04-04 苏交科集团股份有限公司 Pre-loading device and construction method for concrete crack control at pier top of steel-concrete composite bridge
CN111155822A (en) * 2018-11-20 2020-05-15 中国船舶重工集团海装风电股份有限公司 Steel strand installation method for wind driven generator support tower frame prestressed structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1811070A (en) * 2005-01-28 2006-08-02 上海市第七建筑有限公司 First-arch-then-beam concrete steel skeleton constructing process for through arch bridge with mooring post of steel pipe concrete
JP4104910B2 (en) * 2002-06-05 2008-06-18 三井住友建設株式会社 How to build arch ribs for concrete arch bridges
KR101222620B1 (en) * 2012-05-10 2013-02-06 주식회사 젬콘 Prestressed concrete girder and it's manufacture and construction method which used pretensioning steel plate
KR20130026102A (en) * 2011-09-05 2013-03-13 유명철 Installation method of bridge structure having long span

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4104910B2 (en) * 2002-06-05 2008-06-18 三井住友建設株式会社 How to build arch ribs for concrete arch bridges
CN1811070A (en) * 2005-01-28 2006-08-02 上海市第七建筑有限公司 First-arch-then-beam concrete steel skeleton constructing process for through arch bridge with mooring post of steel pipe concrete
KR20130026102A (en) * 2011-09-05 2013-03-13 유명철 Installation method of bridge structure having long span
KR101222620B1 (en) * 2012-05-10 2013-02-06 주식회사 젬콘 Prestressed concrete girder and it's manufacture and construction method which used pretensioning steel plate

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王为凯: ""六奉公路大治河桥系杆临时索组合牵引施工技术"", 《施工技术》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2019062271A1 (en) * 2017-09-28 2019-04-04 苏交科集团股份有限公司 Pre-loading device and construction method for concrete crack control at pier top of steel-concrete composite bridge
CN111155822A (en) * 2018-11-20 2020-05-15 中国船舶重工集团海装风电股份有限公司 Steel strand installation method for wind driven generator support tower frame prestressed structure

Also Published As

Publication number Publication date
CN103334380B (en) 2016-06-15

Similar Documents

Publication Publication Date Title
CN101545289B (en) All-steel buckling-preventing energy-consuming brace
KR100969005B1 (en) Constructing method of suspension bridge and temporary cable therefor
CN103088750B (en) Especial-big span suspension bridge of uniparted hyperboloid space rope net main cable and construction method thereof
CN100567644C (en) A kind of joist type cable arch bridge structure and job practices
CN203729193U (en) Low tower stay cable reinforced T-type rigid framework system with suspension beams
CN104328740A (en) Large-span steel tubular arched bridge vertical rotation construction and linear control method
CN107724226B (en) Four-rope-surface homodromous rotary stay cable-suspension cable cooperation system bridge
CN103452311A (en) Method for erecting section steel cantilever structure support frame
CN201605523U (en) Suspension cable type floating bridge
CN103774543A (en) Deck bridge with cable-arch combination structure
CN103850182B (en) A kind of vertical antiskid friction plate for improving welded type cable saddle antiskid safety
CN103334380A (en) Converting method for external pre-stressed anchor cable and permanent tie bar of swallow-type tie bar arch bridge
CN101368370A (en) Wind-proof temporary rest pier and wind-proof method for large span stayed-cable bridge cantilever construction
CN212714544U (en) Rhombus is hung basket and is retreated and demolishd horizontal extension reinforcement construction structure
CN212294301U (en) Railway cable-stayed bridge with concrete main beam and steel main beam in mixed matching
CN109898421B (en) Wind-resistant structure and wind-resistant method for integrally lifting arch rib of steel box arch bridge
CN202064276U (en) Cable-girder anchorage structure of railway steel truss cable stayed bridge
KR20120013740A (en) Partially earth-anchored cable-stayed bridge using hinge connection parts and construction method for the same
CN105603890A (en) Extradosed type external cable reinforced girder bridge
CN106968178B (en) Construction method for main beam of cable-stayed suspension bridge
CN203174516U (en) Suspension bridge closure segment construction beam segment traction pre-deflection device
CN104963292A (en) Construction method of reinforced concrete multi-span arch bridge or continuous box structure bridge
CN201933397U (en) Externally prestressing based simple supported-to-continuous structure of concrete beam
CN210458909U (en) Temperature self-adaptive tower beam forward-bridge constant-temperature steel pull rod restraint system
CN211648368U (en) Prefabricated polygonal prestressed concrete tower cylinder

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190423

Address after: 450016 No. 1225 Hanghai East Road, Zhengzhou City, Henan Province

Co-patentee after: Wuhan Engineering Co., Ltd., China Railway 7th Bureau Group Co., Ltd.

Patentee after: China Railway Seventh Group Co., Ltd.

Co-patentee after: The Fourth Engineering Co., Ltd of The Seventh Engineering Group Co., Ltd. of China Railway

Address before: 450016 No. 1225 Hanghai East Road, Zhengzhou City, Henan Province

Co-patentee before: Wuhan Engineering Co., Ltd., China Railway 7th Bureau Group Co., Ltd.

Patentee before: China Railway Seventh Group Co., Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200821

Address after: 450016 No. 1225 East navigation road, Henan, Zhengzhou

Co-patentee after: WUHAN ENGINEERING CO., LTD., CHINA RAILWAY 7TH BUREAU GROUP Co.,Ltd.

Patentee after: CHINA RAILWAY SEVENTH GROUP Co.,Ltd.

Address before: 450016 No. 1225 East navigation road, Henan, Zhengzhou

Co-patentee before: WUHAN ENGINEERING CO., LTD., CHINA RAILWAY 7TH BUREAU GROUP Co.,Ltd.

Patentee before: CHINA RAILWAY SEVENTH GROUP Co.,Ltd.

Co-patentee before: THE FOURTH ENGINEERING CO., LTD. OF CHINA RAILWAY SEVENTH Group