CN103332269B - 背负式海上风电整机运输安装船 - Google Patents

背负式海上风电整机运输安装船 Download PDF

Info

Publication number
CN103332269B
CN103332269B CN201310191905.7A CN201310191905A CN103332269B CN 103332269 B CN103332269 B CN 103332269B CN 201310191905 A CN201310191905 A CN 201310191905A CN 103332269 B CN103332269 B CN 103332269B
Authority
CN
China
Prior art keywords
offshore wind
foundation
hull
wind power
transportation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310191905.7A
Other languages
English (en)
Other versions
CN103332269A (zh
Inventor
李爱东
丁红岩
练继建
黄宣旭
徐宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Daoda Wind Power Equipment Technology Co ltd
Original Assignee
JIANGSU DAODA OFFSHORE WIND POWER ENGINEERING TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU DAODA OFFSHORE WIND POWER ENGINEERING TECHNOLOGY Co Ltd filed Critical JIANGSU DAODA OFFSHORE WIND POWER ENGINEERING TECHNOLOGY Co Ltd
Priority to CN201310191905.7A priority Critical patent/CN103332269B/zh
Publication of CN103332269A publication Critical patent/CN103332269A/zh
Application granted granted Critical
Publication of CN103332269B publication Critical patent/CN103332269B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Wind Motors (AREA)

Abstract

本发明涉及一种海上浮动式结构物的运输和安装装备。背负式海上风电整机运输安装船,包括船体,在船首和船尾均设有U型的下层凹槽、U型的上层凹槽,下层凹槽的尺寸根据筒型基础的筒体直径确定,上层船体凹槽的尺寸根据筒型基础过渡段的最大直径确定,下层凹槽宽、上层凹槽窄。本发明利用筒型基础的浮力实现基础与运输船大面积的接触,载货主要部分在水中,重心低,运输的安全性更好;通过上宽下窄的凹槽实现对基础结构的三向约束,保证了风机基础在浮运状态下与船体的同步;通过设置门式桁架柔性扶正、橡胶靠垫等柔性约束、船艏方向的液压顶升等系统,提高了整机运输的安全性,实现了海上风电整机在陆上整体建造并调试、海上运输安装一体化作业。

Description

背负式海上风电整机运输安装船
技术领域
本发明属于海洋船舶领域,具体地,涉及一种海上浮动式结构物的运输和安装装备。
背景技术
筒型基础结构是近年来快速发展的一种新型基础结构,为底部开口的半封闭筒型结构型式,筒型基础可以漂浮于水面上。
随着筒型基础在海上风电的应用技术逐步取得完善,工程实际应用也将取得突破性进展,将筒型基础作为基础的海上风力发电机组可实现陆上建造并调试、海上运输及安装,能最大限度的在陆上完成作业,缩短海上安装时间,提高安装效率。
筒型基础作为海上风机基础的推广应用,形成了一种集风机基础(筒型基础)、塔筒、机舱、叶片于一体的新型海上风电整机。此新型海上风电整机能够实现陆上建造和调试,而海上风电整机的运输和安装难度大,需要采用一种专用的海上风电整机运输安装船。
发明内容
为克服现有技术的缺陷,本发明提供一种背负式海上风电整机运输安装船,解决海上风电整机的运输、安装问题,同时也可以解决风电整机的迁移、拆除问题,还可以解决海上风电机组部件的运输、安装、拆除问题。
为实现上述目的,本发明采用如下技术方案:
一种背负式海上风电整机运输安装船,包括船体,其特征在于:在船首和船尾均设有U型的下层凹槽、U型的上层凹槽,下层凹槽的尺寸根据筒型基础的筒体直径确定,上层船体凹槽的尺寸根据筒型基础过渡段的最大直径确定,下层凹槽宽、上层凹槽窄。
优选的,船体分上下两层,下层凹槽在下层船体形成,上层凹槽在上层船体形成。
优选的,所述安装船的甲板顶面沿上层凹槽周向布置多套起重机构;起重机构由卷扬机、钢丝绳、定滑轮组、动滑轮组、锁紧机构组成;起重机构的钢丝绳穿过上层甲板直达下层凹槽,多套起重机构由一套控制系统实现同步控制,以确保在作业过程中起重机构联动。
优选的,所述安装船的下层凹槽的顶面和侧面均设有橡胶垫。
优选的,所述安装船的下层凹槽的顶面和侧面均设有枕木、气囊靠垫。
优选的,在所述安装船的甲板上设置门式桁架,门式桁架跨越上层凹槽,门式桁架上端的平台上设有抱紧器,抱紧器采用液压油缸操作。
优选的,在U型凹槽下部船艏方向,左右设置带橡胶靠垫的水平液压顶升系统;水平液压顶升系统由控制系统、基座、液压千斤顶、旋转顶板、橡胶靠垫组成;液压千斤顶的安装方向指向筒型基础的圆心;液压顶升系统的旋转顶板可以在水平方向一定角度的转动,以确保靠垫在筒型基础运动中始终贴合筒体,从船艏方向向船艉方向施加水平力。
优选的,所述安装船设有多点系泊定位系统,用于海上整机安装时的移船和定位。
利用上述背负式海上风机运输船实施背负式运输与安装的方法,其特征在于,具体操作步骤为:
第一步,利用筒型基础的自浮能力,拖至船体的凹槽中,利用船上的起重机构,提升筒型基础与船体连接。在筒型基础内注入压缩空气,基础浮力进一步增加,形成筒型基础顶靠船体的背负式连接,起重机构锁定,锁紧靠垫、液压顶升机构等约束机构,完成筒型基础与船体的同步;
第二步,利用陆上设备及门式吊机,吊装海上风电整机上部结构,形成海上风电整机;
第三步,采用背负式运输方式,运至风电场指定位置;
第四步,打开筒型基础的放气阀,逐步减少基础浮力,使得基础与船体底部脱离;同时,利用船上的起重机构,采用同步技术,结合筒型基础的下沉技术,将海上风电整机沉放至海床、并调平;
第五步,船上起重机构自动脱钩,船舶返航。
优选的,风机运输安装船可以实现一次运输、安装、回收2个或者2个以上带筒型基础的海上风机整机。
相对于现有技术,本发明的优越性在于:本发明的背负式海上风电整机运输技术,利用筒型基础的浮力实现基础与运输船大面积的接触,承担运输荷载;载货主要部分在水中,重心低,运输的安全性更好;通过在船体艏艉或侧边开有适合容纳筒型基础的上宽下窄的凹槽,实现对基础结构的三向约束,保证了风机基础在浮运状态下与船体的同步;通过设置门式桁架柔性扶正、橡胶靠垫等柔性约束、船艏方向的液压顶升等系统,分别对基础、塔筒、风机施加全方位的柔性防护,大大提高了整机运输的安全性,从而有效地解决了海上风电整机的整体运输和安装问题;进而实现海上风电整机在陆上整体建造并调试、海上运输安装一体化作业。
附图说明
图1为背负式运输安装船主视示意图;
图2为背负式运输安装船侧视示意图;
图3为背负式运输安装船平面示意图;
图4为背负式运输安装船的凹槽固定方式示意图;
图5为背负式运输原理示意图。
图中,1、船体,2、下层凹槽,3、上层凹槽,4、门式桁架,5、海上风电整机下部结构,6、海上风电整机上部结构,7、起重机构,8、橡胶垫,9、水平液压顶升机构。
具体实施方式
如图1、图2、图3所示,背负式海上风电整机运输安装船,包括船体1,船体1分上下两层,在船首和船尾均设有U型的下层凹槽2、U型的上层凹槽3,下层凹槽2在下层船体形成,上层凹槽3在上层船体形成,下层凹槽3的尺寸根据筒型基础的筒体直径确定,上层船体凹槽的尺寸根据筒型基础过渡段的最大直径确定,下层凹槽2宽、上层凹槽3窄,可以对漂浮于水面的筒型基础形成三个方向的约束。
海上风电整机包括海上风电整机下部结构5、海上风电整机上部结构6,海上风电整机下部结构5为筒型基础;海上风电整机上部结构6包括塔筒、机舱、叶片。
所述安装船的甲板顶面沿上层凹槽周向布置多套起重机构7,起重机构7由卷扬机、钢丝绳、定滑轮组、动滑轮组、锁紧机构组成,属于现有技术。起重机构7的钢丝绳穿过上层甲板直达下层凹槽2,多套起重机构7由一套控制系统实现同步控制,以确保在作业过程中起重机构7联动,为筒型基础5提供20000KN以上的起吊力,可以与筒型基础5的浮力协同作用,实现平稳上浮、沉放。同时,在运输过程中,其锁紧机构可以锁紧钢丝绳,保证船体1与筒型基础5的连接;用来在运输过程中进一步约束风机基础,在沉放过程中辅助整机下沉。筒型基础5抵达指定位置后,采用起重机构7将筒型基础5与船体连接,从而基础与船体成为一体,其钢丝绳锁紧后,在运输过程中为筒型基础5施加垂直方向的额外的约束,增加安全因素利于运输。
起重机构7可以为已经安装完成的整机或筒型基础的回收提供起吊力,使得本发明风机安装运输船同时具备回收风电整机的功能。
所述安装船的下层凹槽2的顶面和侧面均设有橡胶垫8,也可采用枕木、气囊靠垫代替橡胶垫8,用于在运输和安装过程中,保护风机基础。
在所述安装船的甲板上设置门式桁架4,门式桁架4跨越上层凹槽3,门式桁架4上端的平台上设有抱紧器,抱紧器采用液压油缸操作,用于在运输安装过程中对海上风电机舱和塔筒提供柔性防护。
在运输筒型基础5的过程中,由于海水和波浪对运动中的筒型基础5会产生向船艏方向的作用力,而导致远离船体的趋势。如图4所示,为实现在运输过程中对基础提供船艏方向的约束,基础与船体在水平方向上的同步,在U型凹槽下部船艏方向,左右设置带橡胶靠垫的水平液压顶升系统9。水平液压顶升系统9由控制系统、基座、液压千斤顶、旋转顶板、橡胶靠垫组成;水平液压顶升系统属于现有技术。液压千斤顶的安装方向指向筒型基础5的圆心。液压顶升系统9的旋转顶板可以在水平方向一定角度的转动,以确保靠垫在筒型基础5运动中始终贴合筒体,从船艏方向向船艉方向施加水平力,避免因筒型基础5向船艏方向的水平运动,导致筒型基础5与船体1之间的运动失调。
背负式运输的原理和步骤如图5所示,被运输的风机基础浮于水中,采用充气措施,使基础受到的浮力大于或等于风机整机重量;风机基础依靠浮力以背负的方式,通过缓冲橡胶垫,顶在船体结构的底部,从而形成与船体的连接,这种以面接触代替了吊运方式的点接触的运输方式,解决了荷载集中、受力结构复杂的问题。与传统的大件放置于船舶甲板的运输方式相比,本发明背负式运输风机整机在水中,对船体施加向上的力,其重心更低,稳性更好。
所述安装船设有多点系泊定位系统,用于海上整机安装时的移船和定位。
利用本发明的背负式海上风机运输船实施背负式运输与安装,具体操作步骤为:
第一步,利用筒型基础5的自浮能力,拖至船体的凹槽中,利用船上的起重机构7,提升筒型基础5与船体1连接。在筒型基础5内注入压缩空气,基础浮力进一步增加,形成筒型基础顶靠船体的背负式连接,起重机构锁定,锁紧靠垫、液压顶升机构等约束机构,完成筒型基础与船体的同步;
第二步,利用陆上设备及门式吊机4,吊装海上风电整机上部结构6,形成海上风电整机;
第三步,采用背负式运输方式,运至风电场指定位置;
第四步,打开筒型基础的放气阀,逐步减少基础浮力,使得基础与船体底部脱离。同时,利用船上的起重机构7,采用同步技术,结合筒型基础的下沉技术,将海上风电整机沉放至海床、并调平;
第五步,船上起重机构7自动脱钩,船舶返航。
本发明也适用于以筒型基础为基础结构的其它海上结构物的运输和安装。本发明的风机运输安装船,可以实现一次运输、安装、回收2个或者2个以上带筒型基础的海上风机整机。
实施例
设筒型基础5的直径为35米,过渡段最大直径为22米,筒体高度10米。此筒型基础在5米吃水下可以提供浮力F约50000KN,其自身重量产生重力G约30000KN,富余的20000KN浮力,通过船底部橡胶靠垫传递到船体1的底部,所产生的20000KN反作用力使得筒型基础和船体形成完全同步的固定连接,使得筒型基础与船体实现浮运同步。同时,由于筒型基础大部分处于水下,其整体重心大大低于被置于甲板上运输的方式,其运输稳性和安全性明显增加。
筒型基础5与海上风电整机上部结构6构成海上风电整机,轮毂高度约95米。为运输安装此海上风电整机,所采用的背负式海上风电整机运输安装船的船体部分1在两端分为上下两层,下层开有边长38米的方形(或多边形、圆形)凹槽2,上层开有直径23米的圆形(或多边形)凹槽3,所述凹槽3的上部周围安装有桁架式吊机4。船体1上设有多个起重机构7,用于运输时筒型基础5与船体1之间的固接和辅助海上风电整机的沉放。筒型基础5与船体之间设有橡胶垫8用于防撞保护。凹槽的船艏方向设置水平液压顶升9用于提供船艏方向的约束。
具体操作步骤为:
第一步,利用筒型基础5的自浮能力,拖至船体的凹槽中,利用船上的起重机构7,提升筒型基础5与船体1连接。在筒型基础5内注入压缩空气,基础浮力进一步增加,形成筒型基础顶靠船体的背负式连接,起重机构锁定,锁紧靠垫、液压顶升机构等约束机构。完成筒型基础与船体的同步。
第二步,利用陆上设备及门式桁架4上的吊机,吊装海上风电整机上部结构6,形成海上风电整机。
第三步,采用背负式运输方式,运至风电场指定位置。
第四步,打开筒型基础的放气阀,逐步减少基础浮力,使得基础与船体底部脱离。同时,利用船上的起重机构7,采用同步技术,结合筒型基础的下沉技术,将海上风电整机沉放至海床、并调平。
第五步,船上起重机构7自动脱钩,船舶返航。

Claims (10)

1.一种背负式海上风电整机运输安装船,包括船体,其特征在于:在船艏和船艉均设有U型的下层凹槽、U型的上层凹槽,下层凹槽的尺寸根据筒型基础的筒体直径确定,上层凹槽的尺寸根据筒型基础过渡段的最大直径确定,下层凹槽宽、上层凹槽窄。
2.根据权利要求1所述的背负式海上风电整机运输安装船,其特征在于:船体分上下两层,下层凹槽在下层船体形成,上层凹槽在上层船体形成。
3.根据权利要求2所述的背负式海上风电整机运输安装船,其特征在于:所述安装船的甲板顶面沿上层凹槽周向布置多套起重机构;起重机构由卷扬机、钢丝绳、定滑轮组、动滑轮组、锁紧机构组成;起重机构的钢丝绳穿过上层甲板直达下层凹槽,多套起重机构由一套控制系统实现同步控制,以确保在作业过程中起重机构联动。
4.根据权利要求3所述的背负式海上风电整机运输安装船,其特征在于:所述安装船的下层凹槽的顶面和侧面均设有橡胶垫。
5.根据权利要求4所述的背负式海上风电整机运输安装船,其特征在于:所述安装船的下层凹槽的顶面和侧面均设有枕木、气囊靠垫。
6.根据权利要求5所述的背负式海上风电整机运输安装船,其特征在于:在所述安装船的甲板上设置门式桁架,门式桁架跨越上层凹槽,门式桁架上端的平台上设有抱紧器,抱紧器采用液压油缸操作。
7.根据权利要求6所述的背负式海上风电整机运输安装船,其特征在于:在U型的下层凹槽下部船艏方向左右设置带橡胶靠垫的水平液压顶升系统;水平液压顶升系统由控制系统、基座、液压千斤顶、旋转顶板、橡胶靠垫组成;液压千斤顶的安装方向指向筒型基础的圆心;液压顶升系统的旋转顶板可以在水平方向一定角度的转动,以确保靠垫在筒型基础运动中始终贴合筒体,从船艏方向向船艉方向施加水平力;所述安装船设有多点系泊定位系统,用于海上整机安装时的移船和定位。
8.利用权利要求1-7之一所述的背负式海上风电整机运输安装船实施背负式运输与安装的方法,其特征在于,具体操作步骤为:
第一步,利用筒型基础的自浮能力,将筒型基础拖至船体的凹槽中,利用船上的起重机构,提升筒型基础与船体连接;
在筒型基础内注入压缩空气,筒型基础浮力进一步增加,形成筒型基础顶靠船体的背负式连接,起重机构锁定,锁紧靠垫、液压顶升机构,完成筒型基础与船体的同步;
第二步,利用陆上设备及门式吊机,吊装海上风电整机上部结构,形成海上风电整机;
第三步,采用背负式运输方式,运至风电场指定位置;
第四步,打开筒型基础的放气阀,逐步减少筒型基础浮力,使得筒型基础与船体底部脱离;同时,利用船上的起重机构,采用同步技术,结合筒型基础的下沉技术,将海上风电整机沉放至海床、并调平;
第五步,船上起重机构自动脱钩,船舶返航。
9.根据权利要求8所述的利用背负式海上风电整机运输安装船实施背负式运输与安装的方法,其特征在于,海上风电整机运输安装船可以实现一次运输、安装、回收2个以上带筒型基础的海上风机整机。
10.一种背负式运输方法,采用权利要求1-7之一所述的背负式海上风电整机运输安装船,其特征在于:被运输的筒型基础浮于水中,采用充气措施,使筒型基础受到的浮力大于或等于风机整机重量;筒型基础依靠浮力以背负的方式,通过缓冲橡胶垫,顶在船体结构的底部,从而形成与船体的连接。
CN201310191905.7A 2013-05-22 2013-05-22 背负式海上风电整机运输安装船 Active CN103332269B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310191905.7A CN103332269B (zh) 2013-05-22 2013-05-22 背负式海上风电整机运输安装船

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310191905.7A CN103332269B (zh) 2013-05-22 2013-05-22 背负式海上风电整机运输安装船

Publications (2)

Publication Number Publication Date
CN103332269A CN103332269A (zh) 2013-10-02
CN103332269B true CN103332269B (zh) 2016-06-15

Family

ID=49240499

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310191905.7A Active CN103332269B (zh) 2013-05-22 2013-05-22 背负式海上风电整机运输安装船

Country Status (1)

Country Link
CN (1) CN103332269B (zh)

Families Citing this family (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103523175B (zh) * 2013-10-18 2016-02-03 广东明阳风电产业集团有限公司 一种风电机组导管架底端固定装置
CN103921900B (zh) * 2014-01-31 2017-10-10 中交一航局第二工程有限公司 母子双浮体海上风力发电机组整体运输安装一体船的施工方法
CN106894953B (zh) * 2017-02-28 2018-11-20 天津大学 一种海上四筒基础式风电整机安装船及其一步式施工方法
CN106965906B (zh) * 2017-02-28 2018-11-20 天津大学 一种海上三筒基础式风电整机安装船及其一步式施工方法
CN106882334B (zh) * 2017-02-28 2018-10-30 天津大学 一种海上风电多筒基础背负式安装船及其一步式施工方法
CN107128447A (zh) * 2017-04-25 2017-09-05 南通欣通船舶与海洋工程设计有限公司 一种驳船整体运输风机的系统
CN108016575B (zh) * 2018-01-03 2024-07-26 中交第三航务工程局有限公司 一种浮式风机及tlp平台运输安装一体船及其运输安装方法
CN108032062B (zh) * 2018-01-08 2023-08-18 大连理工大学 一种基于爆破的海上单桩风机的整体拆卸装置与方法
CN108589764A (zh) * 2018-07-02 2018-09-28 天津大学 筒型基础风机整体深水沉放姿态控制方法
CN108951593B (zh) * 2018-07-24 2023-12-08 中国电建集团华东勘测设计研究院有限公司 基于四桶导管架复合基础的海上风机安装系统及安装方法
ES2785802B2 (es) * 2019-04-05 2021-05-19 Esteyco S A Procedimiento de instalacion de un aerogenerador de torre mar adentro
CN111764394A (zh) * 2020-07-06 2020-10-13 华电重工股份有限公司 一种筒型基础安装方法
CN111910675B (zh) * 2020-08-11 2025-04-22 天津大学 一种深水海上风电筒型基础安装装置和方法
CN111907650A (zh) * 2020-08-11 2020-11-10 天津大学 一种新型海上风电筒型基础浮运装置
WO2022084344A1 (en) * 2020-10-22 2022-04-28 Itrec B.V. Installation of a wind turbine on a floating foundation
CN112814015B (zh) * 2021-01-12 2024-05-28 大连理工大学 一种多桩基础和浮式风机的组合结构体系及单船安装方法
CN112814014B (zh) * 2021-01-12 2024-05-28 大连理工大学 一种单桩基础和浮式风机的组合结构体系及双船安装方法
CN113184117A (zh) * 2021-05-01 2021-07-30 天津大学 一种新型Spar式风机整机浮运方法
CN113605394B (zh) * 2021-06-16 2022-11-18 中国能源建设集团广东省电力设计研究院有限公司 一种海上风电多筒导管架基础施工方法及施工船
CN113978622B (zh) * 2021-06-16 2024-06-04 丁红岩 海上多筒导管架基础运输方法及一体式运输船
CN114183310B (zh) * 2021-12-09 2023-07-28 天津大学 一种海上风电筒型基础的运输装置
CN114604373B (zh) * 2022-03-11 2023-05-12 上海勘测设计研究院有限公司 一种压载式海上风电整机运输安装船及方法
CN114670976B (zh) * 2022-03-11 2023-05-16 上海勘测设计研究院有限公司 一种背压式海上风电整机运输安装船及方法
CN115092330B (zh) * 2022-07-20 2023-05-26 长江勘测规划设计研究有限责任公司 海上风电筒型基础全自由度限位的浮运固定装置
CN115977090A (zh) * 2022-12-23 2023-04-18 天津大学 由吸力筒和气囊联合辅助的海上坐底定位导管架装置
CN116142393B (zh) * 2023-02-03 2023-12-08 上海勘测设计研究院有限公司 一种用于运输海上风电整机的安装运输船及运输方法
CN116605361B (zh) * 2023-05-22 2024-04-12 江苏海龙风电科技股份有限公司 一种海上风机整体运输安装船及运输安装方法
CN118273886B (zh) * 2024-06-03 2024-10-01 威海德创船舶技术有限公司 一种风电船桁架
CN118358711B (zh) * 2024-06-20 2024-08-27 江苏道达风电设备科技有限公司 一种海上筒型基础安装辅助设备及方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1767976A (zh) * 2003-04-04 2006-05-03 斯文·E·汉森洛吉玛公司 运输风轮机的船舶、移动风轮机的方法和近海风力农场的风轮机
CN102107720A (zh) * 2011-01-14 2011-06-29 上海交通大学 海上风机整体式设置系统
CN102161375A (zh) * 2011-01-31 2011-08-24 江苏道达海上风电工程科技有限公司 风电机组设备运输安装船及其应用
CN102639868A (zh) * 2010-07-12 2012-08-15 江苏道达海上风电工程科技有限公司 海上风机整机
CN202624591U (zh) * 2011-12-31 2012-12-26 江苏道达海洋装备技术有限公司 风电安装船结构
CN102926949A (zh) * 2012-11-19 2013-02-13 天津大学 一种海上风电整机浮运方法
CN103057672A (zh) * 2011-10-21 2013-04-24 南通海纳德船舶设计有限公司 海上风机机组整机的运输和安装作业平台

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4401703B2 (ja) * 2003-08-27 2010-01-20 三井造船株式会社 洋上風力発電装置の設置方法
ES2444436T3 (es) * 2010-10-01 2014-02-25 Nordic Yards Holding Gmbh Barco y procedimiento para transportar y colocar estructuras offshore

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1767976A (zh) * 2003-04-04 2006-05-03 斯文·E·汉森洛吉玛公司 运输风轮机的船舶、移动风轮机的方法和近海风力农场的风轮机
CN102639868A (zh) * 2010-07-12 2012-08-15 江苏道达海上风电工程科技有限公司 海上风机整机
CN102107720A (zh) * 2011-01-14 2011-06-29 上海交通大学 海上风机整体式设置系统
CN102161375A (zh) * 2011-01-31 2011-08-24 江苏道达海上风电工程科技有限公司 风电机组设备运输安装船及其应用
CN103057672A (zh) * 2011-10-21 2013-04-24 南通海纳德船舶设计有限公司 海上风机机组整机的运输和安装作业平台
CN202624591U (zh) * 2011-12-31 2012-12-26 江苏道达海洋装备技术有限公司 风电安装船结构
CN102926949A (zh) * 2012-11-19 2013-02-13 天津大学 一种海上风电整机浮运方法

Also Published As

Publication number Publication date
CN103332269A (zh) 2013-10-02

Similar Documents

Publication Publication Date Title
CN103332269B (zh) 背负式海上风电整机运输安装船
CN103228530B (zh) 浮体结构物作业系统、浮体结构物、作业船及浮体结构物的作业方法
CN111469993A (zh) 一种桶形基础锚固的自安装式漂浮式风机基础及自安装方法
CN102369134B (zh) 海上风机的安装方法及回收方法
US20110129334A1 (en) Wind turbine holding and lifting system and movable operating platform above water
US20120266796A1 (en) Offshore wind turbine installation
CN106014874B (zh) 海上风力发电机组的安装方法
CN1767976A (zh) 运输风轮机的船舶、移动风轮机的方法和近海风力农场的风轮机
CN102079476A (zh) 一种风机抱举装置及移动式水上作业平台
CN106965906B (zh) 一种海上三筒基础式风电整机安装船及其一步式施工方法
CN101293599B (zh) 船厂龙门起重机整机卸船至船坞的方法
CN103422483A (zh) 浅水导管架浮托安装的方法
CN111791991A (zh) 在船舶与海上设施之间固定和转移负载的方法及其设备
CN104805814A (zh) 自升式平台桩腿的安装方法
CN101844611B (zh) 一种用于海洋工程钻井平台接载下水的方法
US12420894B2 (en) Systems and methods for a rack structure for a transport vessel adapted for use with an offshore self-elevating vessel
CN115788782A (zh) 一种漂浮式风机海上安装工艺
JP2012112370A (ja) 洋上風車設置用船舶およびこれを用いた洋上風車設置方法
CN103661827A (zh) 海上潮间带区域的风机总成安装系统及其施工方法
CN103979081B (zh) 深吃水海上浮动式风力机整体安装工作船
CN102923261A (zh) 一种坐底式海上风机安装驳船
CN106894953B (zh) 一种海上四筒基础式风电整机安装船及其一步式施工方法
CN108674597A (zh) 一种自升式风电安装平台
CN115853713A (zh) 一种基于起重船和驳船的漂浮式风机基础下水方法
CN115258092A (zh) 一种浮运式水上光伏整体安装方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20160809

Address after: 226333 No. 8, the Yellow River Road, Binhai Park, Jiangsu, Nantong

Patentee after: JIANGSU DAODA WIND POWER EQUIPMENT TECHNOLOGY CO.,LTD.

Address before: 226200, 108 Xinfeng street, Xin'an Town, Nantong, Jiangsu, Qidong

Patentee before: JlANGSU DAODA OFFSHORE WIND CONSTRUCTION TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20181102

Address after: 226000 Jianghai Road 159, Nantong economic and Technological Development Zone, Jiangsu

Patentee after: JlANGSU DAODA OFFSHORE WIND CONSTRUCTION TECHNOLOGY Co.,Ltd.

Address before: 226333 8 the Yellow River Road, Binhai Park, Nantong, Jiangsu

Patentee before: JIANGSU DAODA WIND POWER EQUIPMENT TECHNOLOGY CO.,LTD.

PP01 Preservation of patent right

Effective date of registration: 20190716

Granted publication date: 20160615

PP01 Preservation of patent right
PD01 Discharge of preservation of patent

Date of cancellation: 20201210

Granted publication date: 20160615

PD01 Discharge of preservation of patent
TR01 Transfer of patent right

Effective date of registration: 20210622

Address after: No.8, Huanghe Road, tongzhouwan Jianghai joint development demonstration zone, Nantong City, Jiangsu Province, 226000

Patentee after: JIANGSU DAODA WIND POWER EQUIPMENT TECHNOLOGY CO.,LTD.

Address before: 226000 Jianghai Road 159, Nantong economic and Technological Development Zone, Jiangsu

Patentee before: JlANGSU DAODA OFFSHORE WIND CONSTRUCTION TECHNOLOGY Co.,Ltd.

TR01 Transfer of patent right
PP01 Preservation of patent right

Effective date of registration: 20250904

Granted publication date: 20160615

PP01 Preservation of patent right