CN103321399B CN201310253725.7A CN201310253725A CN103321399B CN 103321399 B CN103321399 B CN 103321399B CN 201310253725 A CN201310253725 A CN 201310253725A CN 103321399 B CN103321399 B CN 103321399B
Authority
CN
China
Prior art keywords
outside
exterior
leger
horizon bar
rows
Prior art date
Application number
CN201310253725.7A
Other languages
Chinese (zh)
Other versions
CN103321399A (en
Inventor
黄文恒
刘瑞明
李钦
焦连庆
黄臣
王宽亮
钟兴龙
庄绪亮
Original Assignee
北京金港建设股份有限公司
北京金港场道工程建设股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 北京金港建设股份有限公司, 北京金港场道工程建设股份有限公司 filed Critical 北京金港建设股份有限公司
Priority to CN201310253725.7A priority Critical patent/CN103321399B/en
Publication of CN103321399A publication Critical patent/CN103321399A/en
Application granted granted Critical
Publication of CN103321399B publication Critical patent/CN103321399B/en

Links

Abstract

The outer eaves gable place's suspension scaffold of a kind of highrise building Sloping roof and construction method thereof, horizon bar, interior side lever, leger, vertical rod is chosen, little cross bar, scaffold floor, horizontal safety net, horizontal large-mesh, facade safety net, facade large-mesh and wire rope outside this suspension scaffold comprises.Choose horizon bar outward and have two rows, choose outside two rows horizon bar the inner through the perforate of exterior wall water drilling and with inner side lever lock jail.Leger and vertical rod are erected with inside and outside two rows outside exterior wall, the leger of bottom is erected on outside two rows to be chosen on horizon bar, jail locked by described vertical rod bottom and leger, and described little cross bar is connected between inside and outside two row's vertical rods, and scaffold floor is layed in lower exclusively to choose on horizon bar.The present invention can ensure that construction safety, speed of application are fast, quality easily ensures, comprehensive cost is low, solve the outer eaves construction of Sloping roof highrise building and protection question preferably, reach the technique effect that safety, economy, speed of application are fast, construction quality easily ensures.

Description

The outer eaves gable place's suspension scaffold of highrise building Sloping roof and construction method thereof

Technical field

The present invention relates to a kind of building scaffold, particularly the outer eaves construction of a kind of highrise building pitched roof and defensive suspension scaffold and construction method thereof.

Background technology

The selection of the outer eaves form of construction work of highrise building often decides outer eaves construction safety, speed of application, construction quality and integrated cost.When adopting traditional console mode list (two) row's steel pipe scaffold or profile steel overhanging scaffold to carry out the construction of outer eaves, limit construction limit is from top to bottom needed to remove scaffold, scaffold takies that the cycle is longer, comprehensive cost is higher, and need the eaves construction stage outside to carry out shutoff and the metope process at various hole, speed of application is comparatively slow, and construction quality not easily ensures.When adopting hanging basket mode to carry out the construction of outer eaves, shutoff and the metope process at various hole has just been carried out in structural feet hand cradle teardown phase, therefore speed of application is very fast, quality is good, but for Sloping roof highrise building, hanging basket mode cannot carry out the outer eaves construction of Sloping roof part, and the security protection of roofing not easily solves.

Summary of the invention

The invention provides the outer eaves gable place's suspension scaffold of a kind of highrise building Sloping roof and construction method thereof, existing outer eaves construction scaffold be solved and take that the cycle is long, speed of application is slow, construction quality not easily ensures, the technical problem of poor stability.

The technical solution adopted for the present invention to solve the technical problems is:

This highrise building Sloping roof outer eaves gable place suspension scaffold, chooses horizon bar, interior side lever, leger, vertical rod, little cross bar, scaffold floor, horizontal safety net, horizontal large-mesh, facade safety net, facade large-mesh and wire rope outside comprising;

Describedly outer choose horizon bar and have two rows, choose outside two rows horizon bar the inner through the perforate of exterior wall water drilling and with inner side lever lock jail;

Described leger and vertical rod are erected with inside and outside two rows outside exterior wall, the leger of bottom is erected on outside two rows to be chosen on horizon bar, jail locked by described vertical rod and leger, described little cross bar is connected between inside and outside two row's vertical rods, described scaffold floor is layed in exclusively to be chosen on horizon bar down, horizontal safety net and horizontal large-mesh hang on below scaffold floor, and facade safety net and facade large-mesh hang on outside outer row's vertical rod;

Described wire rope one end is fixed by HOOK BOLTS and exterior wall, and the other end is connected on the leger of support body bottom outside.

The internal orifice of described exterior wall water drilling perforate is higher than collar extension.

Choose outside described two rows between horizon bar and be also connected with outside diagonal member arranged in a crossed manner.

Described HOOK BOLTS is fixed by double nut and exterior wall, is lined with pad between double nut and exterior wall.

Described interior side lever is inner side vertical rod or inboard rail.

Described interior side lever is lined with flitch between wall water drilling tapping and exterior wall outside.

Described interior row's vertical rod is lined with flitch between exterior wall water drilling tapping and exterior wall.

The construction method of this highrise building Sloping roof outer eaves gable place suspension scaffold, construction sequence is as follows:

Step one, first at inner side of outer wall snap the line, determines position of opening, carries out the perforate of exterior wall water drilling;

Step 2, chooses horizon bar outward and sets up, by choose outside two rows horizon bar the inner through the perforate of exterior wall water drilling and with inner side lever lock jail;

Step 3, set up outside double-pole scaffold, first outside two rows, choose leger horizon bar being set up bottom, jail is locked in vertical rod and leger, connect the leger on middle part and top again, and the little cross bar between inside and outside two row's vertical rods, then lay scaffold floor lower exclusive choosing on horizon bar, support body below scaffold floor hangs horizontal safety net and horizontal large-mesh, arrange the outer side mounting facade safety net of vertical rod and facade large-mesh outside;

Step 4, draws wire rope off-load, and wire rope one end is fixed by HOOK BOLTS and exterior wall, and the other end is connected on the leger of support body bottom outside.

Feature of the present invention is as follows:

The present invention utilizes the braced structures of horizon bar as suspension scaffold of encorbelmenting, set up the components such as vertical rod, cross bar, diagonal member thereon, make it to form continuous, stable structure, then lay scaffold, hang safety net, final formation is constructed and the defensive closed platform of roofing for outer eaves.Encorbelment the diameter of horizon bar and cantilever span, suspension scaffold unitary construction determine with design as calculated according to the various loads produced during construction.Suspension scaffold by linking component and agent structure is fixed, to guarantee that suspension scaffold is stable, safety, reliable.During construction, various vertical and horizontal loads on suspension scaffold, and is passed to by horizon bar of encorbelmenting and links component, finally passes to agent structure.Material required for the present invention is the conventional circulation material such as conventional steel pipe and buckle, U holder, wooden scaffold floor, Dense mesh screen and large eye net.

Advantage of the present invention is as follows:

1, operator's safety can be ensured when suspension scaffold is set up and removed.

2, operative's protection safety during outer eaves construction.

3, good roofing protection is provided.

4, compared with arranging steel pipe scaffold or profile steel overhanging scaffold with traditional console mode list (two), suspension scaffold simple structure, easy construction, required steel pipe and buckle, U hold in the palm negligible amounts, therefore greatly reduce comprehensive cost.

5, solve Sloping roof highrise building Sloping roof part construction problem, can crossed construction be carried out, ensure the overall duration.Because suspension scaffold does not take roof sections, because eaves construction can be carried out with roofing construction in addition simultaneously, be independent of each other, do not restrict mutually.

The present invention can ensure that construction safety, speed of application are fast, quality easily ensures, comprehensive cost is low, solve the outer eaves construction of Sloping roof highrise building and protection question preferably, reach the technique effect that safety, economy, speed of application are fast, construction quality easily ensures.

Accompanying drawing explanation

Below in conjunction with drawings and Examples, the present invention is further described.

Fig. 1 is structural representation of the present invention.

Reference numeral: choose diagonal member outside side lever in horizon bar, 3-, 4-flitch, 5-leger, 6-, 7-vertical rod, the little cross bar of 8-, 9-HOOK BOLTS, 10-wire rope, 11-scaffold floor, 12-horizontal safety net, 13-facade safety net, 14-facade large-mesh, the horizontal large-mesh of 15-, 16-double nut, 17-pad, 18-exterior wall outside the perforate of 1-exterior wall water drilling, 2-.

Detailed description of the invention

Embodiment is shown in Figure 1, this highrise building Sloping roof outer eaves gable place suspension scaffold, horizon bar 2, interior side lever 3, leger 5, vertical rod 7 is chosen, little cross bar 8, scaffold floor 11, horizontal safety net 12, horizontal large-mesh 15, facade safety net 13, facade large-mesh 14 and wire rope 10 outside comprising.

Choose horizon bar 2 outside described and have two rows, choose horizon bar 2 the inner outside two rows and pass exterior wall water drilling perforate 1 and lock jail with interior side lever 3.The internal orifice of described exterior wall water drilling perforate 1 is higher than collar extension.Described interior side lever 3 is inboard rail or inner side vertical rod, and interior side lever is lined with flitch 4 between wall water drilling perforate 1 place and exterior wall 18 outside.

Described leger 5 and vertical rod 7 are erected with inside and outside two rows outside exterior wall 18, and the leger 5 of bottom is erected on outside two rows to be chosen on horizon bar 2, chooses between horizon bar 2 and be also connected with outside diagonal member 6 arranged in a crossed manner outside two rows.Jail locked by vertical rod 7 and leger 5, and interior row's vertical rod 7 is lined with flitch 4 between exterior wall water drilling perforate 1 place and exterior wall 18.Little cross bar 8 is connected between inside and outside two row's vertical rods 7, and scaffold floor 11 is layed in exclusively to be chosen on horizon bar 2 down, and horizontal safety net 12 and horizontal large-mesh 15 hang on below scaffold floor 11, and facade safety net 13 and facade large-mesh 14 hang on outside outer row's vertical rod 7.

Described wire rope 10 one end is fixed by HOOK BOLTS 9 and exterior wall 18, and the other end is connected on the leger 5 of support body bottom outside.Described HOOK BOLTS 9 is fixed by double nut 16 and exterior wall 18, is lined with pad 17 between double nut and exterior wall.

Construction sequence of the present invention is as follows:

Step one, first at inner side of outer wall snap the line, determines position of opening, and carry out the perforate of exterior wall water drilling with circle No. 50 water drilling drill bits, internal orifice is slightly high, prevents summer exterior wall rainwater to indoor seepage;

Step 2, chooses horizon bar 2 outward and sets up, and passes exterior wall water drilling perforate 1 by choosing horizon bar 2 the inner outside two rows and locks jail with interior side lever 3; Choose outside two rows between horizon bar 2 and be fixed into overall stressed primary structural component with outside diagonal member 6;

Step 3, set up outside double-pole scaffold, first outside two rows, choose the leger 5(leger joint length 2 meters horizon bar 2 being set up bottom, overlap joint is adopted to connect, be convenient to partial dismantling), vertical rod 7 and leger 5 are locked jail (vertical rod advance 1.20 meters, transfer 1.05 meters), connect the leger 5 on middle part and top again, and the little cross bar step pitch of little cross bar 8(1.50 meters between inside and outside two row's vertical rods 7), then scaffold floor 11 is laid lower exclusive choosing on horizon bar 2, support body below scaffold floor 11 hangs horizontal safety net 12 and horizontal large-mesh 15, arrange vertical rod 7 outer side mounting facade safety net 13 and facade large-mesh 14 outside,

Step 4, draws wire rope off-load, and wire rope 10 one end is fixed by HOOK BOLTS 9 and exterior wall 18, and the other end is connected on the leger 5 of support body bottom outside.

Suspension scaffold goes out roofing protection height must not be less than 2000mm.

Suspension scaffold has set up the outer eaves hanging basket cantilever steel girder of rear installation, and the outer hanging basket of installation room successively.

Claims (7)

1. a highrise building Sloping roof outer eaves gable place suspension scaffold, it is characterized in that: outside comprising, choose horizon bar (2), interior side lever (3), leger (5), vertical rod (7), little cross bar (8), scaffold floor (11), horizontal safety net (12), horizontal large-mesh (15), facade safety net (13), facade large-mesh (14) and wire rope (10);
Choose horizon bar (2) outside described and have two rows, choose horizon bar (2) the inner outside two rows and pass exterior wall water drilling perforate (1) and lock jail with interior side lever (3);
Described leger (5) and vertical rod (7) are erected with inside and outside two rows in exterior wall (18) outside, the leger (5) of bottom is erected on outside two rows to be chosen on horizon bar (2), jail locked by described vertical rod (7) and leger (5), described little cross bar (8) is connected between inside and outside two rows' vertical rod (7), described scaffold floor (11) is layed in exclusively to be chosen on horizon bar (2) down, horizontal safety net (12) and horizontal large-mesh (15) hang on scaffold floor (11) below, and facade safety net (13) and facade large-mesh (14) hang on outer row's vertical rod (7) outside;
Described wire rope (10) one end is fixed by HOOK BOLTS (9) and exterior wall (18), and the other end is connected on the leger (5) of support body bottom outside;
Choose outside described two rows between horizon bar (2) and be also connected with outside diagonal member (6) arranged in a crossed manner.
2. highrise building Sloping roof according to claim 1 outer eaves gable place suspension scaffold, is characterized in that: the internal orifice of described exterior wall water drilling perforate (1) is higher than collar extension.
3. highrise building Sloping roof according to claim 1 outer eaves gable place suspension scaffold, is characterized in that: described HOOK BOLTS (9) is fixed by double nut (16) and exterior wall (18), is lined with pad (17) between double nut and exterior wall.
4. highrise building Sloping roof according to claim 1 outer eaves gable place suspension scaffold, is characterized in that: described interior side lever (3) is inner side vertical rod or inboard rail.
5. highrise building Sloping roof according to claim 1 outer eaves gable place suspension scaffold, is characterized in that: described interior side lever (3) is lined with flitch (4) between exterior wall water drilling perforate (1) place and exterior wall (18).
6. highrise building Sloping roof according to claim 1 outer eaves gable place suspension scaffold, is characterized in that: described interior row's vertical rod (7) is lined with flitch (4) between exterior wall water drilling perforate (1) place and exterior wall (18).
7. a construction method for the outer eaves gable place of the highrise building Sloping roof as described in claim 1 ~ 6 any one suspension scaffold, is characterized in that construction sequence is as follows:
Step one, first at inner side of outer wall snap the line, determines position of opening, carries out the perforate of exterior wall water drilling;
Step 2, chooses horizon bar (2) outward and sets up, and passes exterior wall water drilling perforate (1) by choosing horizon bar (2) the inner outside two rows and locks jail with interior side lever (3);
Step 3, set up outside double-pole scaffold, first outside two rows, choose the leger (5) horizon bar (2) being set up bottom, vertical rod (7) and leger (5) are locked jail, connect the leger (5) on middle part and top again, and the little cross bar (8) between inside and outside two rows' vertical rod (7), then scaffold floor (11) is laid lower exclusive choosing on horizon bar (2), the support body of scaffold floor (11) below hangs horizontal safety net (12) and horizontal large-mesh (15), arrange vertical rod (7) outer side mounting facade safety net (13) and facade large-mesh (14) outside,
Step 4, draws wire rope off-load, and wire rope (10) one end is fixed by HOOK BOLTS (9) and exterior wall (18), and the other end is connected on the leger (5) of support body bottom outside.
CN201310253725.7A 2013-06-25 2013-06-25 The outer eaves gable place's suspension scaffold of highrise building Sloping roof and construction method thereof CN103321399B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310253725.7A CN103321399B (en) 2013-06-25 2013-06-25 The outer eaves gable place's suspension scaffold of highrise building Sloping roof and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310253725.7A CN103321399B (en) 2013-06-25 2013-06-25 The outer eaves gable place's suspension scaffold of highrise building Sloping roof and construction method thereof

Publications (2)

Publication Number Publication Date
CN103321399A CN103321399A (en) 2013-09-25
CN103321399B true CN103321399B (en) 2015-12-16

Family

ID=49190421

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310253725.7A CN103321399B (en) 2013-06-25 2013-06-25 The outer eaves gable place's suspension scaffold of highrise building Sloping roof and construction method thereof

Country Status (1)

Country Link
CN (1) CN103321399B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485524B (en) * 2013-10-11 2016-03-23 四川省第四建筑工程公司 Corbel type builder's jack and construction when setting up thereof
CN104131688B (en) * 2014-08-21 2016-04-06 长沙远大住宅工业集团有限公司 The special external hanging type job platform of assembled architecture and method of operating thereof
CN109911106A (en) * 2019-03-14 2019-06-21 上海江南长兴造船有限责任公司 A kind of apparatus for work and method for the installation of container ship positioning pin

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101538896A (en) * 2009-04-03 2009-09-23 标力建设集团有限公司 Construction method for jettied structure at high attitude of high-rise building
JP2010150756A (en) * 2008-12-24 2010-07-08 Shimizu Corp Temporary scaffold apparatus
CN101906870A (en) * 2010-07-29 2010-12-08 正太集团有限公司 Suspended scaffolding
CN102561689A (en) * 2012-02-22 2012-07-11 中国二十二冶集团有限公司 Construction method for cantilever lifting scaffold
CN202324571U (en) * 2011-11-01 2012-07-11 江苏瑞峰建设集团有限公司 Overhanging type double-row scaffold
CN203320920U (en) * 2013-06-25 2013-12-04 北京金港机场建设有限责任公司 Cantilever frame for high-rise building sloping roof outer eave construction and protection at gable

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010150756A (en) * 2008-12-24 2010-07-08 Shimizu Corp Temporary scaffold apparatus
CN101538896A (en) * 2009-04-03 2009-09-23 标力建设集团有限公司 Construction method for jettied structure at high attitude of high-rise building
CN101906870A (en) * 2010-07-29 2010-12-08 正太集团有限公司 Suspended scaffolding
CN202324571U (en) * 2011-11-01 2012-07-11 江苏瑞峰建设集团有限公司 Overhanging type double-row scaffold
CN102561689A (en) * 2012-02-22 2012-07-11 中国二十二冶集团有限公司 Construction method for cantilever lifting scaffold
CN203320920U (en) * 2013-06-25 2013-12-04 北京金港机场建设有限责任公司 Cantilever frame for high-rise building sloping roof outer eave construction and protection at gable

Also Published As

Publication number Publication date
CN103321399A (en) 2013-09-25

Similar Documents

Publication Publication Date Title
CN101775907A (en) Space truss structure aerial pairing integral slide installation method
CN204098463U (en) Builder's jack
CN102535845A (en) Construction method of bearing frame of corridor structure
CN101736893A (en) Overhanging type scaffold supporting system
CN102777182B (en) Rapid end extracting method of large mining height working face
CN102383588A (en) Lifting platform for protecting safety of high-level construction
CN204343301U (en) A kind of Metro station excavation excavation supporting structure
CN104074349B (en) A kind of new-type protection type attachment type raise scaffold
CN103669845B (en) High-altitude long-span overhung cornice formwork bracing system and construction method thereof
CN103195214B (en) Wood roof cornice decking and concrete composite structure in archaized buildings and construction method thereof
CN107345427A (en) Large span bolt-ball net frame and its modularization installation method
CN102864936B (en) Combination lifting construction method for large-scale high hollow building roof of steel structure
CN101597955A (en) Safety scaffold
CN104131703A (en) Method for constructing core tube wall through self-climbing formwork and adopted self-climbing formwork
CN102979312B (en) Indoor aluminum honeycomb board suspended ceiling reverse installation technology
CN103132603A (en) Temperature stress releasing structure of large-size steel structure building
CN101169001A (en) Quadrangular pyramid sphere net case falsework-free constructing and mounting method and hoisting machine tool
CN201221193Y (en) High altitude packway ceiling construction operating platform
CN105350759A (en) Suspended scaffold
CN103821340A (en) Installation method for attached lifting multilayer construction platform
CN103526949A (en) Lifting and slipping device for wall-attached vertical structure and construction method thereof
CN104831939A (en) Bolt ball welding ball mixed node large span cantilever grid structure construction method
CN101936068B (en) Method for constructing cliff scaffold platform
CN103669815A (en) Method for constructing hanging rope and pipe combined all-round scaffold construction platform and protective system
CN206581577U (en) Using housing construction builder's jack

Legal Events

Date Code Title Description
PB01 Publication
C06 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
CB02 Change of applicant information

Address after: 100071 Fengtai District 52 Beijing Feng 1 hospital

Applicant after: BEIJING JINGOLD CONSTRUCTION CO., LTD.

Applicant after: Beijing Jingold Field Road Engineering Construction Co., Ltd.

Address before: 100071 Fengtai District 52 Beijing Feng 1 hospital

Applicant before: Beijing Jingold Airport Construction Co., Ltd.

Applicant before: Beijing Jingold Field Road Engineering Construction Co., Ltd.

C53 Correction of patent for invention or patent application
COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: BEIJING JINGOLD AIRPORT CONSTRUCTION LLC TO: BEIJING JINGOLD AIRPORT CONSTRUCTION CO., LTD.

GR01 Patent grant
C14 Grant of patent or utility model