CN103308808A - System and method for testing secondary device of intelligent substation automatically - Google Patents

System and method for testing secondary device of intelligent substation automatically Download PDF

Info

Publication number
CN103308808A
CN103308808A CN2013102473645A CN201310247364A CN103308808A CN 103308808 A CN103308808 A CN 103308808A CN 2013102473645 A CN2013102473645 A CN 2013102473645A CN 201310247364 A CN201310247364 A CN 201310247364A CN 103308808 A CN103308808 A CN 103308808A
Authority
CN
China
Prior art keywords
test
stage
secondary device
user
control platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013102473645A
Other languages
Chinese (zh)
Inventor
谭靖
李大勇
张志朋
曹北建
李枫
李刚
杨惠林
霍忠峰
向前
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Tianjin Electric Power Corp
Original Assignee
State Grid Corp of China SGCC
Tianjin Electric Power Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Tianjin Electric Power Corp filed Critical State Grid Corp of China SGCC
Priority to CN2013102473645A priority Critical patent/CN103308808A/en
Publication of CN103308808A publication Critical patent/CN103308808A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Testing Electric Properties And Detecting Electric Faults (AREA)

Abstract

A system and a method for testing a secondary device of an intelligent substation automatically are disclosed. The system comprises a user control platform, a digital tester and a digital secondary device, all of which are connected in sequence. By adopting a computer software technology, an intelligent equipment testing technology and an intelligent equipment communication interface technology, the system and method for testing the secondary device of the intelligent substation automatically realize closed-loop automatic testing of the digital secondary device, enables the inspection work of the secondary device of the intelligent substation to be simplified, standardized, automated and processized, solves the problems of standard inspection and automatic testing of the digital secondary devices of different types efficiently, improves the current testing work mode greatly, fills the blank in the field of the testing method of the digital secondary device, increases work efficiency and inspection quality of the inspection of the digital secondary device greatly, and achieves important reform and breakthrough for the current inspection work mode of the digital secondary device.

Description

Secondary equipment of intelligent converting station Auto-Test System and method of testing
Technical field
The invention belongs to electric power power transmission and transformation control technology field, particularly relate to a kind of secondary equipment of intelligent converting station Auto-Test System and method of testing.
Background technology
Along with the development that scientific-technical progress and China's intelligent grid are built, intelligent substation had obtained widely promotion and application in recent years.In intelligent substation, the digitizing secondary device has been cancelled analog loopback, AC sampling and open into leaving and adopt digital quantity fully, this has higher requirement to work for inspection, so that traditional secondary device testing tool can not satisfy the needs of digitizing secondary device test.Because intelligent substation belongs to new things, the maintainer lacks test experience and the method for testing of digitizing secondary device, and this is so that easy insufficient, the halfway situation of generation check in the work for inspection.
Summary of the invention
In order to address the above problem, the object of the present invention is to provide a kind of secondary equipment of intelligent converting station Auto-Test System and method of testing.
In order to achieve the above object, secondary equipment of intelligent converting station Auto-Test System provided by the invention comprises: user's report control platform, digital tester and digitizing secondary device; Wherein: user's report control platform is the operation control terminal of whole test macro, it is connected with digital tester, user's report control platform mainly is comprised of master controller, storer, man-machine mutual interface and input-output device, the demonstration storage operation that is used for being written into of the input of completing user steering order, associated electrical document, extraction and detecting information, and process, judge and finally generate test report to testing resulting data;
Digital tester is the digital detecting device for the intelligent substation electrical secondary system, and it is connected with user's report control platform by netting twine to upper, is connected with the digitizing secondary device by the MMS interface to lower;
The digitizing secondary device is detected object concrete in the intelligent substation electrical secondary system.
Described digital tester and digitizing secondary device are many, every digital tester is connected with a digitizing secondary device respectively, adopt mode directly in parallel to realize between many digital testers interconnected, wherein only have a digital tester to be connected with user's report control platform.
Described user's report control platform can replace with industrial computer or PC computer generation.
Secondary equipment of intelligent converting station automatic test approach provided by the invention comprises the following step of carrying out in order:
Step 1, the S101 stage of reading definite value and relevant configuration file: operating personnel read definite value and the relevant configuration file of digitizing secondary device by user's report control platform, in conjunction with the test job requirement, obtain the automatically required whole parameters of test;
Step 2, the S102 stage of generation testing scheme: operating personnel choose all or part of function of this equipment according to type and the test job requirement of digitizing secondary device at user's report control platform, generate testing scheme;
Step 3, fill in S103 stage of non-electric quantity test prompts information: if in testing scheme, there is Non-Electricity Measurement, needed information when in testing scheme, indicating Non-Electricity Measurement;
Step 4, the S104 stage of a test of beginning: load testing scheme at user's report control platform, the initialization test pointer, and start test;
Step 5, determine whether the S105 stage of electric parameters test: system judges whether current test event is the electric parameters test, if judged result is "Yes", then next step enters the S106 stage, otherwise jump to the porch in S113 stage, next step enters the S113 stage;
Step 6, tester are carried out the S106 stage of fault simulation: digital tester is according to test request, and output voltage and the magnitude of current simulate the needed environment of test to tested digitizing secondary device;
Step 7, the S107 stage of monitoring equipment action situation: system monitors the action situation of digitizing secondary device by digital tester, and parses action data and the message information that needs, and is uploaded to user's report control platform;
Step 8 judges whether the S108 stage of moving: system judges whether the action of digitizing secondary device is correct, if judged result is "Yes", then next step enters the S109 stage, otherwise jumps to the porch in S115 stage, and next step enters the S115 stage;
Step 9, the S109 stage of operation of recording information: system storage is the relevant information of action this time;
Step 10, move S110 stage of correct evaluation: system judges according to action message this time whether action is correct, if judged result is "Yes", then next step enters the S111 stage, otherwise jump to the porch in S115 stage, next step enters the S115 stage;
Step 11, determine whether last S111 stage: whether the test event in system's automatic decision testing scheme is finished, and judges namely whether the test pointer is on last; If judged result is "Yes", illustrate that test event all finishes, then next step enters the S112 stage; Otherwise jump to the porch in S116 stage, next step enters the S116 stage, continues the next item test;
Step 12, the S112 stage of generation test report: generate test report at user's report control platform, the test operation flow process so far finishes;
Step 13, the S113 stage of simulation non electrical quantity test environment: this stage is the first step of non electrical quantity test, artificially simulates the non electrical quantity test environment according to information;
Step 14, the S114 stage of operation of recording information: then the relevant information by user's report control platform record this time moves enters the S108 stage;
Step 15, the S115 stage of the test parameter of revised version item test: system is revised the test parameter of this test according to the result of this test, in order to again test;
Step 10 six, prepare the S116 stage that the next item down is tested: this test is finished, and will test the next test event of pointed, then forwards the porch in S104 stage to, and next step carries out the S104 stage, continues the next item test.
Secondary equipment of intelligent converting station Auto-Test System provided by the invention and method adopt computer software technology, the smart machine measuring technology, smart machine communication interface technology, realization is to the closed loop automatic testing of digitizing secondary device, so that the secondary equipment of intelligent converting station work for inspection is oversimplified, standardization, robotization and procedure, the standardization check and the problem of automatically testing of the digitizing secondary device of different model have effectively been solved, greatly improved existing test job mode, filled up the blank in digitizing secondary device method of testing field, greatly having improved work efficiency and the quality inspection of the check of digitizing secondary device, is major reform and the breakthrough to existing digitizing secondary device work for inspection mode.
Description of drawings
Fig. 1 is the structural representation of secondary equipment of intelligent converting station Auto-Test System provided by the invention.
Fig. 2 is the test flow chart of secondary equipment of intelligent converting station automatic test approach provided by the invention.
Embodiment
Below in conjunction with the drawings and specific embodiments secondary equipment of intelligent converting station Auto-Test System provided by the invention and method of testing are elaborated.
As shown in Figure 1, secondary equipment of intelligent converting station Auto-Test System provided by the invention comprises: user's report control platform 1, digital tester 2 and digitizing secondary device 3; Wherein: user's report control platform 1 is the operation control terminal of whole test macro, it is connected with digital tester 2, user's report control platform 1 mainly is comprised of master controller, storer, man-machine mutual interface and input-output device, be used for the operations such as demonstration storage of being written into of the input of completing user steering order, associated electrical document, extraction and detecting information, and process, judge and finally generate test report to testing resulting data;
Digital tester 2 is the digital detecting device for the intelligent substation electrical secondary system, and it is connected with user's report control platform 1 by netting twine to upper, is connected with digitizing secondary device 3 by the MMS interface to lower;
Digitizing secondary device 3 is detected object concrete in the intelligent substation electrical secondary system; Usually in the intelligent substation electrical secondary system, often include a plurality of digitizing secondary devices 3, a common test item is directed to a digitizing secondary device 3, and a plurality of digitizing secondary devices 3 need a plurality of projects to detect.
In described secondary equipment of intelligent converting station Auto-Test System, when carry out for a plurality of digitizing secondary devices 3 comprise the detection of a plurality of projects the time, need many digital testers 2 of configuration, every digital tester 2 is tested for a digitizing secondary device 3 respectively; At this moment, every digital tester 2 is connected with a digitizing secondary device 3 respectively, adopts mode directly in parallel to realize between many digital testers 2 interconnected, wherein only has a digital tester 2 to be connected with user's report control platform 1.
Described user's report control platform 1 can replace with industrial computer or PC computer generation.
As shown in Figure 2, secondary equipment of intelligent converting station automatic test approach provided by the invention comprises the following step of carrying out in order:
Step 1, read the S101 stage of definite value and relevant configuration file: operating personnel read definite value and relevant configuration file as the digitizing secondary device 3 of tested object by user's report control platform 1, in conjunction with the test job requirement, obtain the automatically required whole parameters of test;
Step 2 generates S102 stage of testing scheme: operating personnel choose all or part of function of this equipment according to type and test job requirement as the digitizing secondary device 3 of tested object at user's report control platform 1, generate testing scheme;
Step 3, fill in S103 stage of non-electric quantity test prompts information: if in testing scheme, there is Non-Electricity Measurement, needed information when in testing scheme, indicating Non-Electricity Measurement;
Step 4, the S104 stage of a test of beginning: load testing scheme at user's report control platform 1, the initialization test pointer, and start test;
Step 5, determine whether the S105 stage of electric parameters test: system judges whether current test event is the electric parameters test, if judged result is "Yes", then next step enters the S106 stage, otherwise jump to the porch in S113 stage, next step enters the S113 stage;
Step 6, tester are carried out the S106 stage of fault simulation: digital tester 2 is according to test request, and output voltage and the magnitude of current simulate the needed environment of test to tested digitizing secondary device 3;
Step 7, the S107 stage of monitoring equipment action situation: system monitors the action situation of tested digitizing secondary device 3 by digital tester 2, and parses action data and the message information that needs, and is uploaded to user's report control platform 1;
Step 8 judges whether the S108 stage of moving: system judges whether the action of digitizing secondary device 3 is correct, if judged result is "Yes", then next step enters the S109 stage, otherwise jumps to the porch in S115 stage, and next step enters the S115 stage;
Step 9, the S109 stage of operation of recording information: system storage is the relevant information of action this time;
Step 10, move S110 stage of correct evaluation: system judges according to action message this time whether action is correct, if judged result is "Yes", then next step enters the S111 stage, otherwise jump to the porch in S115 stage, next step enters the S115 stage;
Step 11, determine whether last S111 stage: whether the test event in system's automatic decision testing scheme is finished, and judges namely whether the test pointer is on last; If judged result is "Yes", illustrate that test event all finishes, then next step enters the S112 stage; Otherwise jump to the porch in S116 stage, next step enters the S116 stage, continues the next item test;
Step 12, the S112 stage of generation test report: generate test report at user's report control platform 1, the test operation flow process so far finishes;
Step 13, the S113 stage of simulation non electrical quantity test environment: this stage is the first step of non electrical quantity test, artificially simulates the non electrical quantity test environment according to information;
Step 14, the S114 stage of operation of recording information: then the relevant information by user's report control platform 1 record this time moves enters the S108 stage;
Step 15, the S115 stage of the test parameter of revised version item test: system is revised the test parameter of this test according to the result of this test, in order to again test;
Step 10 six, prepare the S116 stage that the next item down is tested: this test is finished, and will test the next test event of pointed, then forwards the porch in S104 stage to, and next step carries out the S104 stage, continues the next item test.
Secondary equipment of intelligent converting station Auto-Test System provided by the invention and method of testing, be conducive to realize the simplification of secondary equipment of intelligent converting station work for inspection, standardization, robotization and procedure, the standardization check and the problem of automatically testing of the digitizing secondary device of different model have effectively been solved, greatly improved existing test job mode, filled up the blank in digitizing secondary device method of testing field, greatly having improved work efficiency and the quality inspection of the check of digitizing secondary device, is major reform and the breakthrough to existing digitizing secondary device work for inspection mode.

Claims (4)

1. secondary equipment of intelligent converting station Auto-Test System, it is characterized in that: described secondary equipment of intelligent converting station Auto-Test System comprises: user's report control platform (1), digital tester (2) and digitizing secondary device (3); Wherein: user's report control platform (1) is the operation control terminal of whole test macro, it is connected with digital tester (2), user's report control platform (1) mainly is comprised of master controller, storer, man-machine mutual interface and input-output device, the demonstration storage operation that is used for being written into of the input of completing user steering order, associated electrical document, extraction and detecting information, and process, judge and finally generate test report to testing resulting data;
Digital tester (2) is the digital detecting device for the intelligent substation electrical secondary system, and it is connected with user's report control platform (1) by netting twine to upper, to being connected with digitizing secondary device (3) by the MMS interface down;
Digitizing secondary device (3) is detected object concrete in the intelligent substation electrical secondary system.
2. secondary equipment of intelligent converting station Auto-Test System according to claim 1 is characterized in that: described digital tester (2) and digitizing secondary device (3) are many, every digital tester (2) is connected with a digitizing secondary device (3) respectively, adopt mode directly in parallel to realize between many digital testers (2) interconnected, wherein only have a digital tester (2) to be connected with user's report control platform (1).
3. secondary equipment of intelligent converting station Auto-Test System according to claim 1 is characterized in that: described user's report control platform (1) can replace with industrial computer or PC computer generation.
4. one kind is adopted the method for testing of secondary equipment of intelligent converting station Auto-Test System as claimed in claim 1 to comprise the following step of carrying out in order:
Step 1, read the S101 stage of definite value and relevant configuration file: operating personnel read definite value and the relevant configuration file of digitizing secondary device (3) by user's report control platform (1), in conjunction with the test job requirement, obtain the automatically required whole parameters of test;
Step 2, the S102 stage of generation testing scheme: operating personnel choose all or part of function of this equipment according to type and the test job requirement of digitizing secondary device (3) at user's report control platform (1), generate testing scheme;
Step 3, fill in S103 stage of non-electric quantity test prompts information: if in testing scheme, there is Non-Electricity Measurement, needed information when in testing scheme, indicating Non-Electricity Measurement;
Step 4, the S104 stage of a test of beginning: load testing scheme at user's report control platform (1), the initialization test pointer, and start test;
Step 5, determine whether the S105 stage of electric parameters test: system judges whether current test event is the electric parameters test, if judged result is "Yes", then next step enters the S106 stage, otherwise jump to the porch in S113 stage, next step enters the S113 stage;
Step 6, tester are carried out the S106 stage of fault simulation: digital tester (2) is according to test request, and output voltage and the magnitude of current simulate the needed environment of test to tested digitizing secondary device (3);
Step 7, the S107 stage of monitoring equipment action situation: system monitors the action situation of digitizing secondary device (3) by digital tester (2), and parse action data and the message information that needs, be uploaded to user's report control platform (1);
Step 8, judge whether S108 stage of moving: system judges whether the action of digitizing secondary device (3) is correct, if judged result is "Yes", then next step enters the S109 stage, otherwise jump to the porch in S115 stage, next step enters the S115 stage;
Step 9, the S109 stage of operation of recording information: system storage is the relevant information of action this time;
Step 10, move S110 stage of correct evaluation: system judges according to action message this time whether action is correct, if judged result is "Yes", then next step enters the S111 stage, otherwise jump to the porch in S115 stage, next step enters the S115 stage;
Step 11, determine whether last S111 stage: whether the test event in system's automatic decision testing scheme is finished, and judges namely whether the test pointer is on last; If judged result is "Yes", illustrate that test event all finishes, then next step enters the S112 stage; Otherwise jump to the porch in S116 stage, next step enters the S116 stage, continues the next item test;
Step 12, the S112 stage of generation test report: generate test report at user's report control platform (1), the test operation flow process so far finishes;
Step 13, the S113 stage of simulation non electrical quantity test environment: this stage is the first step of non electrical quantity test, artificially simulates the non electrical quantity test environment according to information;
Step 14, the S114 stage of operation of recording information: then the relevant information by user's report control platform (1) record this time moves enters the S108 stage;
Step 15, the S115 stage of the test parameter of revised version item test: system is revised the test parameter of this test according to the result of this test, in order to again test;
Step 10 six, prepare the S116 stage that the next item down is tested: this test is finished, and will test the next test event of pointed, then forwards the porch in S104 stage to, and next step carries out the S104 stage, continues the next item test.
CN2013102473645A 2013-06-20 2013-06-20 System and method for testing secondary device of intelligent substation automatically Pending CN103308808A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013102473645A CN103308808A (en) 2013-06-20 2013-06-20 System and method for testing secondary device of intelligent substation automatically

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013102473645A CN103308808A (en) 2013-06-20 2013-06-20 System and method for testing secondary device of intelligent substation automatically

Publications (1)

Publication Number Publication Date
CN103308808A true CN103308808A (en) 2013-09-18

Family

ID=49134240

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013102473645A Pending CN103308808A (en) 2013-06-20 2013-06-20 System and method for testing secondary device of intelligent substation automatically

Country Status (1)

Country Link
CN (1) CN103308808A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103646576A (en) * 2013-12-23 2014-03-19 北京农业职业学院 GS-MS (gas chromatography-mass spectrometry) simulation system
CN103985022A (en) * 2014-06-11 2014-08-13 国家电网公司 Intelligent substation secondary equipment operation and maintenance decision support system and data analysis method
CN103984877A (en) * 2014-06-11 2014-08-13 国家电网公司 Evaluation system and method for running quality of secondary equipment of electric power system
CN104198797A (en) * 2014-08-26 2014-12-10 广东电网公司电力科学研究院 Voltage detection method, system and device
CN104569686A (en) * 2015-01-19 2015-04-29 国家电网公司 Intelligent substation and intelligent secondary device testing system thereof
CN106199249A (en) * 2016-06-28 2016-12-07 积成电子股份有限公司 A kind of automatic closed loop test system towards intelligent substation and method of testing

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080147334A1 (en) * 2005-01-27 2008-06-19 Electro Industries/Gauge Tech. Metering Device with Control Functionally and Method Thereof
CN201393089Y (en) * 2009-03-31 2010-01-27 华东电力试验研究院有限公司 Monitoring system for the operation status of secondary equipment in digital substation
CN102169147A (en) * 2010-12-28 2011-08-31 山东电力集团公司聊城供电公司 Automatic test system of relay protection device
CN102361348A (en) * 2011-09-28 2012-02-22 江苏方天电力技术有限公司 Method for monitoring time setting state of secondary equipment of intelligent converting station
CN102608464A (en) * 2012-03-21 2012-07-25 山东电力集团公司济南供电公司 Modularized automatic test assembly system of rely protection device and test method of modularized automatic test assembly system
CN202384838U (en) * 2011-12-13 2012-08-15 东北电力科学研究院有限公司 Real-time simulation test platform for secondary system of smart substation
CN202421366U (en) * 2011-12-16 2012-09-05 武汉凯默电气有限公司 Hand-held optical digital tester used for testing smart grid
CN203365568U (en) * 2013-06-20 2013-12-25 国家电网公司 System for testing secondary device of intelligent substation automatically

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20080147334A1 (en) * 2005-01-27 2008-06-19 Electro Industries/Gauge Tech. Metering Device with Control Functionally and Method Thereof
CN201393089Y (en) * 2009-03-31 2010-01-27 华东电力试验研究院有限公司 Monitoring system for the operation status of secondary equipment in digital substation
CN102169147A (en) * 2010-12-28 2011-08-31 山东电力集团公司聊城供电公司 Automatic test system of relay protection device
CN102361348A (en) * 2011-09-28 2012-02-22 江苏方天电力技术有限公司 Method for monitoring time setting state of secondary equipment of intelligent converting station
CN202384838U (en) * 2011-12-13 2012-08-15 东北电力科学研究院有限公司 Real-time simulation test platform for secondary system of smart substation
CN202421366U (en) * 2011-12-16 2012-09-05 武汉凯默电气有限公司 Hand-held optical digital tester used for testing smart grid
CN102608464A (en) * 2012-03-21 2012-07-25 山东电力集团公司济南供电公司 Modularized automatic test assembly system of rely protection device and test method of modularized automatic test assembly system
CN203365568U (en) * 2013-06-20 2013-12-25 国家电网公司 System for testing secondary device of intelligent substation automatically

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
张明亮 等: "数字化变电站二次系统仿真测试方案", 《电力系统自动化》, vol. 34, no. 10, 25 May 2010 (2010-05-25), pages 90 - 92 *
梅德冬 等: "智能变电站二次设备自动检测系统设计", 《低压电器》, no. 4, 28 February 2011 (2011-02-28), pages 43 - 46 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103646576A (en) * 2013-12-23 2014-03-19 北京农业职业学院 GS-MS (gas chromatography-mass spectrometry) simulation system
CN103985022A (en) * 2014-06-11 2014-08-13 国家电网公司 Intelligent substation secondary equipment operation and maintenance decision support system and data analysis method
CN103984877A (en) * 2014-06-11 2014-08-13 国家电网公司 Evaluation system and method for running quality of secondary equipment of electric power system
CN104198797A (en) * 2014-08-26 2014-12-10 广东电网公司电力科学研究院 Voltage detection method, system and device
CN104569686A (en) * 2015-01-19 2015-04-29 国家电网公司 Intelligent substation and intelligent secondary device testing system thereof
CN104569686B (en) * 2015-01-19 2017-12-15 国家电网公司 A kind of intelligent substation and its intelligent secondary device test system
CN106199249A (en) * 2016-06-28 2016-12-07 积成电子股份有限公司 A kind of automatic closed loop test system towards intelligent substation and method of testing

Similar Documents

Publication Publication Date Title
CN109444566B (en) An electric vehicle charging facility testing device and method
CN104569688B (en) A kind of distribution terminal automatization test system and method
CN103744422B (en) A kind of to the protective relaying device automatic test approach based on IEC61850 standard
CN103308808A (en) System and method for testing secondary device of intelligent substation automatically
CN103323714A (en) Automatic test method based on report template technology in intelligent substation test system
CN102437655B (en) Analogue display method and system of virtual terminals of intelligent substation
CN103576025B (en) A kind of detection test system for energy storage power station grid connection
CN107085156A (en) Microcomputer type relay protection and automatic test instrument automatic checkout system
CN103941207A (en) Electric power measurement automation terminal detection method and system
CN105629180A (en) Test method, test device and controller
CN104868599A (en) Intelligent substation message simulation test and association analysis system, and simulation method
CN105425201A (en) Metering chip simulation test method used for intelligent electric energy meter software reliability detection
CN103425573A (en) Code testing information collecting method and system
CN108132449A (en) The information standardization automatic check device and method of a kind of relay protection
CN105929278B (en) A kind of unsteady flow module high voltage test macro and method
CN107505520A (en) Scene-type intelligence automatically testing platform and method
CN104391244A (en) Closed loop test method of relay protection apparatus and system thereof
CN104375024A (en) In-situ self-inspection and metering device and method of automatic test system
CN104090259A (en) Automatic gauge test platform and method based on Python script
CN108776278A (en) A kind of the configuration type relay protection test system and method for topological correlation
CN106329720A (en) Detecting and debugging method for reconstruction and extension project secondary system for intelligent substation
CN105242134B (en) A kind of distributed test method suitable for intelligent high-voltage equipment system level testing
CN104391247A (en) Relay protection test method and system based on IEC61850 digital tester
CN102707712B (en) Electronic equipment fault diagnosis method and system
CN111999579A (en) Automatic detection system and method for charging pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130918