CN103255903A - Workshop indoor steel plate concrete composite floor structure and manufacturing method thereof - Google Patents

Workshop indoor steel plate concrete composite floor structure and manufacturing method thereof Download PDF

Info

Publication number
CN103255903A
CN103255903A CN2013101940679A CN201310194067A CN103255903A CN 103255903 A CN103255903 A CN 103255903A CN 2013101940679 A CN2013101940679 A CN 2013101940679A CN 201310194067 A CN201310194067 A CN 201310194067A CN 103255903 A CN103255903 A CN 103255903A
Authority
CN
China
Prior art keywords
steel plate
surface layer
plate surface
layer
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013101940679A
Other languages
Chinese (zh)
Other versions
CN103255903B (en
Inventor
沈志平
余能彬
张建忠
孙洪
李敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Zhengye Engineering & Investment Inc Ltd
Original Assignee
Guizhou Zhengye Engineering & Investment Inc Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Zhengye Engineering & Investment Inc Ltd filed Critical Guizhou Zhengye Engineering & Investment Inc Ltd
Priority to CN201310194067.9A priority Critical patent/CN103255903B/en
Publication of CN103255903A publication Critical patent/CN103255903A/en
Application granted granted Critical
Publication of CN103255903B publication Critical patent/CN103255903B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)
  • Foundations (AREA)

Abstract

本发明公开了一种车间室内钢板砼复合地面结构,它包括基层(7),位于最下端,其次为垫层(6),钢板面层(3)四个角分别开有通孔,四个角下有混凝土基础(1),混凝土基础(1)预埋有钢筋(2),钢筋(2)的露出端伸入钢板面层(3)的通孔内,钢筋(2)的露出端与钢板面层(3)焊接,钢板面层(3)与细石混凝土面层(9)连接处有变形缝(8),钢板面层(3)与垫层(6)之间是找平层(4)和结合层(5),找平层(4)位于结合层(5)上,细石混凝土面层(9)与垫层(6)之间是结合层(5);解决车间局部有多次较大冲击荷载的地面采用整块钢板地面或多块厚钢板进行焊接连接方式存在的造价成本高和弯曲变形等问题。

Figure 201310194067

The invention discloses a steel plate concrete composite floor structure in a workshop, which comprises a base layer (7), which is located at the lowermost end, followed by a cushion layer (6), four corners of the steel plate surface layer (3) respectively have through holes, four There is a concrete foundation (1) under the corner, and the concrete foundation (1) is pre-embedded with steel bars (2), and the exposed ends of the steel bars (2) extend into the through holes of the steel plate surface layer (3), and the exposed ends of the steel bars (2) The steel plate surface (3) is welded, there is a deformation joint (8) at the connection between the steel plate surface (3) and the fine stone concrete surface (9), and there is a leveling layer ( 4) and the bonding layer (5), the leveling layer (4) is located on the bonding layer (5), and the bonding layer (5) is between the fine stone concrete surface layer (9) and the cushion layer (6); solve the local The ground with the second largest impact load adopts a whole steel plate ground or multiple thick steel plates for welding connection, which has problems such as high cost and bending deformation.

Figure 201310194067

Description

一种车间室内钢板砼复合地面结构及其制作方法Indoor steel plate concrete composite floor structure and its manufacturing method

技术领域 technical field

本发明属于建筑地面结构技术,尤其涉及一种车间室内钢板砼复合地面结构及其制作方法。 The invention belongs to the building ground structure technology, in particular to a steel plate concrete composite ground structure in a workshop and a manufacturing method thereof.

背景技术 Background technique

车间室内地面的特点是面积大,承受荷载重。不同的生产工艺,生产工段对地面的强度,刚度,抗冲击、耐振、耐磨、耐碾压性能等要求不尽相同。因此,在工程建设中,多类型地面组合拼接处理是常用的方法。而对于局部有多次较大冲击荷载的地面,经常采用整块钢板地面,或多块厚钢板进行焊接连接并用膨胀螺丝和地面固定的方法。然而这种制作方法由于大量的使用厚钢板而导致地面整体造价较高,而且在长期多次的冲击荷载作用下,整块焊接钢板地面将会产生弯曲变形等等一系列的问题。 The indoor floor of the workshop is characterized by a large area and heavy loads. Different production processes and production sections have different requirements for ground strength, stiffness, impact resistance, vibration resistance, wear resistance, and rolling resistance. Therefore, in engineering construction, multi-type ground combination splicing is a common method. For the ground with multiple large impact loads locally, the whole steel plate ground or multiple thick steel plates are often used for welding and connection and fixed with expansion screws and the ground. However, due to the large number of thick steel plates used in this production method, the overall cost of the ground is relatively high, and under the action of multiple impact loads for a long time, the whole welded steel plate ground will produce a series of problems such as bending deformation and so on.

发明内容 Contents of the invention

本发明要解决的技术问题:提供一种车间室内钢板砼复合地面结构及其制作方法,以解决车间对于局部有多次较大冲击荷载的地面,由于采用整块钢板地面,或多块厚钢板进行焊接连接并用膨胀螺丝与地面固定的方式,存在的造价成本高和在长期反复冲击荷载作用下,整块焊接钢板地面将会产生弯曲变形等问题。 The technical problem to be solved by the present invention is to provide an indoor steel plate concrete composite ground structure and its manufacturing method, so as to solve the problem that the ground in the workshop has multiple large impact loads locally, because the whole steel plate ground, or multiple thick steel plates Welding the connection and fixing it to the ground with expansion screws has problems such as high cost and the fact that the entire welded steel plate ground will be bent and deformed under long-term repeated impact loads.

本发明技术方案: Technical scheme of the present invention:

一种车间室内钢板砼复合地面结构,它包括垫层和基层,基层位于最下端,其次为垫层,钢板面层四个角分别开有通孔,四个角下有混凝土基础,混凝土基础预埋有钢筋,钢筋的露出端伸入钢板面层的通孔内,钢筋的露出端与钢板面层焊接,钢板面层与细石混凝土面层连接处有变形缝,钢板面层与垫层之间是找平层和结合层,找平层位于结合层上,细石混凝土面层与垫层之间是结合层。 A steel plate concrete composite ground structure in a workshop, which includes a cushion and a base, the base is located at the bottom, followed by a cushion, the four corners of the steel plate surface are respectively opened with through holes, and there are concrete foundations under the four corners, the concrete foundation is pre-prepared Embedded steel bars, the exposed end of the steel bar extends into the through hole of the steel plate surface, the exposed end of the steel bar is welded to the steel plate surface, there is a deformation joint at the connection between the steel plate surface and the fine stone concrete surface, and the gap between the steel plate surface and the cushion Between the leveling layer and the bonding layer, the leveling layer is located on the bonding layer, and the bonding layer is between the fine stone concrete surface layer and the cushion layer.

钢筋的露出端伸入钢板面层四个角上的通孔内的距离为钢板面层厚度的50%-70%。 The exposed end of the steel bar protrudes into the through holes on the four corners of the steel plate surface layer for 50%-70% of the thickness of the steel plate surface layer.

变形缝的宽度为5-20毫米,变形缝用可变形材料填充。 The width of the deformation seam is 5-20mm, and the deformation seam is filled with deformable material.

钢板面层的厚度大于5毫米。 The thickness of the steel plate surface layer is greater than 5mm.

找平层的厚度大于20毫米。 The thickness of the leveling layer is greater than 20 mm.

垫层的厚度大于60毫米。 The thickness of the cushion is greater than 60mm.

所述的车间室内钢板砼复合地面结构的制作方法,它包括下述步骤: The manufacturing method of the steel plate concrete composite ground structure in the workshop includes the following steps:

步骤1、确定钢板面层四个角下部设置基础的位置,制作混凝土基础,并在混凝土基础内预埋钢筋,对地基土进行夯实处理; Step 1. Determine the position of the foundation at the lower part of the four corners of the steel plate surface, make a concrete foundation, and pre-embed steel bars in the concrete foundation, and compact the foundation soil;

步骤2、施工制作垫层,采用强度等级在C7.5以上的混凝土,垫层6的厚度要大于60毫米; Step 2, construct and make the cushion layer, adopt concrete with a strength grade above C7.5, and the thickness of the cushion layer 6 must be greater than 60 mm;

步骤3、制作结合层,采用水泥浆与水灰比为0.4-0.5的材料制作; Step 3, making a bonding layer, which is made of materials with a cement slurry to water-cement ratio of 0.4-0.5;

步骤4、制作找平层,采用1比2的干性混凝土砂浆制作; Step 4, making a leveling layer, using 1:2 dry concrete mortar;

步骤5、铺设钢板面层,在找平层上铺设钢板面层,将混凝土基础内预埋钢筋的露出端伸入钢板面层的四个角上的孔内,然后将钢筋与钢板面层焊接后抛光处理; Step 5. Lay the steel plate surface layer, lay the steel plate surface layer on the leveling layer, extend the exposed ends of the pre-embedded steel bars in the concrete foundation into the holes on the four corners of the steel plate surface layer, and then weld the steel bars to the steel plate surface layer Polishing;

步骤6、制作细石混凝土面层,在垫层上做厚40毫米,强度为C20的细石混凝土面层; Step 6, make fine stone concrete surface course, make thick 40 millimeters on cushion course, the fine stone concrete surface course that intensity is C20;

步骤7、在钢板面层与细石混凝土面层之间和各个钢板面层之间的变形缝内填充可变材料。 Step 7. Fill variable materials in the deformation joints between the steel plate surface layer and the fine stone concrete surface layer and between each steel plate surface layer.

本发明有益效果: Beneficial effects of the present invention:

本发明钢板面层上的冲击荷载被均匀的分给了钢板下设的混凝土基础,在很大程度上,调整了不均匀的沉降,保证了钢板的平整度;垫层采用强度等级在C7.5以上厚度要大于60毫米的混凝土,加强了基层的强度,更好的承载了上部的冲击荷载。根据荷载大小不同,本发明采用细石混凝土面层与钢板面层拼装工艺,与大面积采用钢板面层的传统方法相比,有效地降低了成本;变形缝及其变形材料的填充,主要解决了在温度和收缩变形可能引起的应力集中,以及上部荷载分布不均匀而产生的变形,与现有技术相比,本发明既有效的满足不同生产工艺以及不同生产工段的使用及强度和刚度的要求,解决了在较大的冲击荷载作用下采用整块焊接的钢板地面所产生的变形问题,施工简便,工程造价低;解决了车间对于局部有多次较大冲击荷载的地面,由于采用整块钢板地面,或多块厚钢板进行焊接连接并用膨胀螺丝与地面固定的方式,存在的造价成本高和在长期反复冲击荷载作用下,整块焊接钢板地面将会产生弯曲变形等问题。 The impact load on the steel plate surface layer of the present invention is evenly distributed to the concrete foundation under the steel plate, to a large extent, the uneven settlement is adjusted, and the flatness of the steel plate is guaranteed; the cushion layer adopts a strength grade of C7. 5. Concrete with a thickness greater than 60 mm strengthens the strength of the base layer and better bears the impact load of the upper part. According to the different loads, the present invention adopts the assembly process of fine stone concrete surface and steel plate surface, which effectively reduces the cost compared with the traditional method of using steel plate surface in a large area; the filling of deformation joints and deformation materials mainly solves the problem of The stress concentration that may be caused by temperature and shrinkage deformation, as well as the deformation caused by uneven load distribution on the upper part, compared with the prior art, the present invention not only effectively meets the requirements of different production processes and different production sections, but also the strength and rigidity. requirements, it solves the deformation problem caused by the use of a whole piece of welded steel plate floor under the action of a large impact load, the construction is simple, and the project cost is low; it solves the problem of the ground with multiple large impact loads in the workshop due to the use of the whole One steel plate floor, or multiple thick steel plates are welded and fixed to the ground with expansion screws. There are problems such as high cost and long-term repeated impact loads. The whole welded steel plate floor will produce bending deformation and other problems.

附图说明:Description of drawings:

图1为本发明平面结构示意图; Fig. 1 is a schematic diagram of the plane structure of the present invention;

图2为图1的1-1处剖面示意图; Fig. 2 is a schematic cross-sectional view at 1-1 of Fig. 1;

图3为图1的2-2处剖面示意图。 Fig. 3 is a schematic cross-sectional view at 2-2 in Fig. 1 .

具体实施方式:Detailed ways:

一种车间室内钢板砼复合地面结构,它包括(见图1、2和3)垫层6和基层7,基层7位于最下端,其次为垫层6,垫层位于基层7上,钢板面层3四个角分别开有通孔,钢板面层3四个角下有混凝土基础1,混凝土基础1预埋有钢筋2,钢筋2的露出端伸入钢板面层3四个角上的通孔内,钢筋2的露出端与钢板面层3焊接后采用抛光处理,钢板面层3与细石混凝土面层9连接处有变形缝8,钢板面层3与垫层6之间是找平层4和结合层5,找平层4位于结合层5上,细石混凝土面层9与垫层6之间是结合层5。 A steel plate concrete composite floor structure in a workshop, which includes (see Figures 1, 2 and 3) a cushion layer 6 and a base layer 7, the base layer 7 is located at the bottom, followed by a cushion layer 6, the cushion layer is located on the base layer 7, and the steel plate surface layer There are through holes in the four corners of 3, and there is a concrete foundation 1 under the four corners of the steel plate surface layer 3, and the concrete foundation 1 is pre-embedded with steel bars 2, and the exposed ends of the steel bars 2 extend into the through holes in the four corners of the steel plate surface layer 3 Inside, the exposed end of the steel bar 2 is welded to the steel plate surface layer 3 and polished. There is a deformation joint 8 at the connection between the steel plate surface layer 3 and the fine stone concrete surface layer 9. There is a leveling layer 4 between the steel plate surface layer 3 and the cushion layer 6. And the bonding layer 5, the leveling layer 4 is located on the bonding layer 5, and the bonding layer 5 is between the fine stone concrete surface layer 9 and the cushion layer 6.

为了保证钢筋2与钢板面层3之间焊接牢固,钢筋2的露出端伸入钢板面层3四个角上的通孔内的距离为钢板面层3厚度的50%-70%,剩余通孔空间用焊接材料填充平整,可以确保钢板面层地面光滑平整而且钢板面层3可以牢固在地面上。 In order to ensure that the welding between the steel bar 2 and the steel plate surface layer 3 is firm, the exposed end of the steel bar 2 extends into the through holes on the four corners of the steel plate surface layer 3. The distance is 50%-70% of the thickness of the steel plate surface layer 3, and the remaining The hole space is filled evenly with welding materials, which can ensure that the steel plate surface layer is smooth and flat and that the steel plate surface layer 3 can be firmly on the ground.

变形缝8的宽度为5-20毫米,变形缝8用可变形材料填充,可变形材料选用玻璃胶,变形缝的设置是为了保证钢板面层3与细石混泥土面层9之间由于热胀冷缩不产生挤压变形,变形缝用可变形材料玻璃胶填充,可以确保面层之间没有缝隙而且可以避免面层之间挤压变形。 The width of deformation joint 8 is 5-20 millimeters, and deformation joint 8 is filled with deformable material, and deformable material selects glass glue, and the setting of deformation joint is to ensure that between steel plate surface layer 3 and fine stone concrete surface layer 9 due to heat Expansion and contraction do not produce extrusion deformation, and the deformation joints are filled with deformable material glass glue, which can ensure that there is no gap between the surface layers and avoid extrusion deformation between the surface layers.

为了确保钢板面层3能够承受住地面冲击载荷,钢板面层3的厚度大于5毫米。 In order to ensure that the steel plate surface layer 3 can withstand ground impact loads, the thickness of the steel plate surface layer 3 is greater than 5 mm.

为了分散冲击载荷保证整个地面的强度,找平层4的厚度大于20毫米,垫层6的厚度大于60毫米。 In order to disperse the impact load and ensure the strength of the entire ground, the thickness of the leveling layer 4 is greater than 20 mm, and the thickness of the cushion layer 6 is greater than 60 mm.

车间室内钢板砼复合地面结构的制作方法,采用下述步骤: The manufacturing method of the steel plate concrete composite ground structure in the workshop adopts the following steps:

步骤1、确定钢板面层3四个角下部设置基础的位置,制作混凝土基础1,并在混凝土基础1内预埋钢筋2,然后对地基土进行夯实处理; Step 1. Determine the position of the foundation at the lower part of the four corners of the steel plate surface layer 3, make the concrete foundation 1, and pre-embed the steel bar 2 in the concrete foundation 1, and then tamp the foundation soil;

步骤2、施工制作垫层6,采用强度等级在C7.5以上的混凝土,垫层6的厚度要大于60毫米; Step 2, construct and make the cushion layer 6, adopt concrete whose strength grade is above C7.5, and the thickness of the cushion layer 6 must be greater than 60 mm;

步骤3、制作结合层5,采用水泥浆与水灰比为0.4-0.5的材料制作; Step 3, making the bonding layer 5, which is made of materials with a cement slurry to water-cement ratio of 0.4-0.5;

步骤4、制作找平层4,采用1比2-3的干性混凝土砂浆制作;找平层4厚度要大于20毫米; Step 4, making the leveling layer 4, which is made of dry concrete mortar with a ratio of 1 to 2-3; the thickness of the leveling layer 4 must be greater than 20 mm;

步骤5、铺设钢板面层3,在找平层4上铺设钢板面层3,将混凝土基础1内预埋钢筋2的露出端伸入钢板面层3的四个角上的孔内,然后将钢筋2与钢板面层3焊接后抛光处理,钢筋2的露出端伸入钢板面层3四个角上的通孔内的距离为钢板面层3厚度的50%-70%,剩余通孔空间用焊接材料填充平整,可以确保钢板面层地面光滑平整而且钢板面层3可以牢固在地面上; Step 5. Lay the steel plate surface layer 3, lay the steel plate surface layer 3 on the leveling layer 4, extend the exposed ends of the pre-embedded steel bars 2 in the concrete foundation 1 into the holes on the four corners of the steel plate surface layer 3, and then place the steel bars 2 After welding with the steel plate surface layer 3, it is polished, and the exposed end of the steel bar 2 extends into the through holes on the four corners of the steel plate surface layer 3. The distance is 50%-70% of the thickness of the steel plate surface layer 3, and the remaining through hole space is used The welding material is filled evenly, which can ensure that the ground of the steel plate surface is smooth and flat, and the steel plate surface 3 can be firmly fixed on the ground;

步骤6、制作细石混凝土面层9,在垫层6上做厚40毫米以上,强度为C20的细石混凝土面层9; Step 6, making the fine stone concrete surface layer 9, and making a fine stone concrete surface layer 9 with a thickness of more than 40 mm and a strength of C20 on the cushion layer 6;

步骤7、在钢板面层3与细石混凝土面层9之间和各个钢板面层3之间的变形缝8内填充可变材料,可变形材料采用玻璃胶。 Step 7. Fill the deformation joints 8 between the steel plate surface 3 and the fine stone concrete surface 9 and between each steel plate surface 3 with variable material, and the deformable material is glass glue.

Claims (7)

1. workshop indoor steel plate concrete combined floor structure, it comprises bed course (6) and basic unit (7), basic unit (7) is positioned at bottom, secondly be bed course (6), it is characterized in that: (3) four angles of steel plate surface layer have through hole, concrete foundation (1) is arranged under four angles, concrete foundation (1) is embedded with reinforcing bar (2), the bared end of reinforcing bar (2) stretches in the through hole of steel plate surface layer (3), the bared end of reinforcing bar (2) and steel plate surface layer (3) welding, steel plate surface layer (3) has deformation joint (8) with pea gravel concreten surface layer (9) junction, be leveling layer (4) and setting course (5) between steel plate surface layer (3) and the bed course (6), leveling layer (4) is positioned on the setting course (5), is setting course (5) between pea gravel concreten surface layer (9) and the bed course (6).
2. a kind of workshop according to claim 1 indoor steel plate concrete combined floor structure is characterized in that: the distance that the bared end of reinforcing bar (2) stretches in the through hole on (3) four angles of steel plate surface layer is the 50%-70% of steel plate surface layer (3) thickness.
3. a kind of workshop according to claim 1 indoor steel plate concrete combined floor structure, it is characterized in that: the width of deformation joint (8) is the 5-20 millimeter, deformation joint (8) is filled with deformable material.
4. a kind of workshop according to claim 1 indoor steel plate concrete combined floor structure, it is characterized in that: the thickness of steel plate surface layer (3) is greater than 5 millimeters.
5. a kind of workshop according to claim 1 indoor steel plate concrete combined floor structure, it is characterized in that: the thickness of leveling layer (4) is greater than 20 millimeters.
6. a kind of workshop according to claim 1 indoor steel plate concrete combined floor structure, it is characterized in that: the thickness of bed course (6) is greater than 60 millimeters.
7. the preparation method of the indoor steel plate concrete in the described workshop of claim 1 combined floor structure, it comprises the steps:
Step 1, determine that (3) four bottoms, angle of steel plate surface layer arrange the position on basis, make concrete foundation (1), and in concrete foundation (1) embedded bar (2), foundation soil is tamped processing;
Bed course (6) is made in step 2, construction, adopts the concrete of strength grade more than C7.5, and the thickness of bed course 6 is greater than 60 millimeters;
Step 3, making setting course (5), adopting cement paste and water/binder ratio is the material making of 0.4-0.5;
Step 4, making leveling layer (4) adopt 1 to 2 dryness concrete mortar making;
Step 5, laying steel plate surface layer (3), lay steel plate surface layer (3) at leveling layer (4), the bared end of the interior embedded bar of concrete foundation (1) (2) is stretched in the hole on four angles of steel plate surface layer (3), then with reinforcing bar (2) and steel plate surface layer (3) welding back polishing;
Step 6, making pea gravel concreten surface layer (9) are done thick 40 millimeters at bed course (6), and intensity is the pea gravel concreten surface layer (9) of C20;
Step 7, fill changeable material between steel plate surface layer (3) and pea gravel concreten surface layer (9) and in the deformation joint (8) between each steel plate surface layer (3).
CN201310194067.9A 2013-05-23 2013-05-23 Workshop indoor steel plate concrete composite floor structure and manufacturing method thereof Expired - Fee Related CN103255903B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310194067.9A CN103255903B (en) 2013-05-23 2013-05-23 Workshop indoor steel plate concrete composite floor structure and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310194067.9A CN103255903B (en) 2013-05-23 2013-05-23 Workshop indoor steel plate concrete composite floor structure and manufacturing method thereof

Publications (2)

Publication Number Publication Date
CN103255903A true CN103255903A (en) 2013-08-21
CN103255903B CN103255903B (en) 2015-07-08

Family

ID=48960086

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310194067.9A Expired - Fee Related CN103255903B (en) 2013-05-23 2013-05-23 Workshop indoor steel plate concrete composite floor structure and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN103255903B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105256973A (en) * 2015-09-11 2016-01-20 苏州水木清华设计营造有限公司 Method for paving and constructing floor tiles with elevation cushion blocks
CN106759854A (en) * 2016-11-23 2017-05-31 上海交通大学 Complex load steel plate concrete platform
CN111877679A (en) * 2020-07-29 2020-11-03 广州市柏舍装饰设计有限公司 Construction process of high-strength floor in subway space

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4118493B2 (en) * 2000-08-08 2008-07-16 三洋工業株式会社 Outdoor laying floor panel structure
JP4308029B2 (en) * 2004-01-09 2009-08-05 日鐵住金建材株式会社 Floor board material connecting bracket, floor board material connecting method and floor structure thereof
CN202248762U (en) * 2011-09-21 2012-05-30 程义侠 Solid wood composite floor
CN202299284U (en) * 2011-10-21 2012-07-04 魏代云 Multilayer Laminate Flooring
CN203257049U (en) * 2013-05-23 2013-10-30 贵州正业工程技术投资有限公司 Indoor steel plate-concrete composite ground structure of workshop

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4118493B2 (en) * 2000-08-08 2008-07-16 三洋工業株式会社 Outdoor laying floor panel structure
JP4308029B2 (en) * 2004-01-09 2009-08-05 日鐵住金建材株式会社 Floor board material connecting bracket, floor board material connecting method and floor structure thereof
CN202248762U (en) * 2011-09-21 2012-05-30 程义侠 Solid wood composite floor
CN202299284U (en) * 2011-10-21 2012-07-04 魏代云 Multilayer Laminate Flooring
CN203257049U (en) * 2013-05-23 2013-10-30 贵州正业工程技术投资有限公司 Indoor steel plate-concrete composite ground structure of workshop

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105256973A (en) * 2015-09-11 2016-01-20 苏州水木清华设计营造有限公司 Method for paving and constructing floor tiles with elevation cushion blocks
CN106759854A (en) * 2016-11-23 2017-05-31 上海交通大学 Complex load steel plate concrete platform
CN111877679A (en) * 2020-07-29 2020-11-03 广州市柏舍装饰设计有限公司 Construction process of high-strength floor in subway space
CN111877679B (en) * 2020-07-29 2021-09-28 广州市柏舍装饰设计有限公司 Construction process of high-strength floor in subway space

Also Published As

Publication number Publication date
CN103255903B (en) 2015-07-08

Similar Documents

Publication Publication Date Title
CN104831752B (en) Prefabricated inspection well and construction method thereof
CN112921738B (en) Highway pavement structure and construction method thereof
CN103255903B (en) Workshop indoor steel plate concrete composite floor structure and manufacturing method thereof
CN202208877U (en) Ground pavement expansion joint structure on concrete cushion layer expansion joint
CN104018644B (en) One can move, can reclaim lightweight ground
CN105735076A (en) Pillow beam type precast concrete structure layer and assembling method thereof
CN104763127B (en) A kind of resistance to heavy duty acid-proof terrace and its construction method
CN112177233A (en) Tenon-and-mortise hollow building block and building method thereof
CN205420942U (en) Concatenation infiltration brick
CN104389358B (en) A kind of fire hydrant box back side body of wall and construction method thereof
CN104790678A (en) Rapid construction masonry wall with mortar replaced by glue and construction method of rapid construction brickwork wall
CN207812488U (en) Globality underground pipe gallery
CN105220809A (en) The syndeton of a kind of arch top board and bracket stake and construction method thereof
CN105350700A (en) High toughness masonry wall and preparation method
CN103031793B (en) Fast in-place paving construction method for thick and heavy stone blocks
CN203257049U (en) Indoor steel plate-concrete composite ground structure of workshop
CN206942089U (en) A kind of ceramic tile leveling structure
CN203856096U (en) Novel free stone masonry building structure
CN107386491B (en) Shear connection structure for hollow block masonry, masonry wall and construction method
CN214143828U (en) Stone floor tile ground settlement joint
CN115874654A (en) Formwork-free and decoration-free construction method for ECP hanging boards used in concrete retaining walls
CN203856165U (en) Floor-heating ground structure
CN104563354B (en) Combined long-span ribbed slab structure
CN115538726A (en) A method of manufacturing a stainless steel floor
CN206800418U (en) A kind of buried canal case and pipe gallery soil arch load-relieving structure of drainning off floodwaters

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Shen Zhiping

Inventor after: Yu Nengbin

Inventor after: Chen Jun

Inventor after: Sun Hong

Inventor after: Li Min

Inventor before: Shen Zhiping

Inventor before: Yu Nengbin

Inventor before: Zhang Jianzhong

Inventor before: Sun Hong

Inventor before: Li Min

COR Change of bibliographic data
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150708

CF01 Termination of patent right due to non-payment of annual fee