CN103243963B - A kind of suspended holding pole segmental hoisting steel pipe pole method - Google Patents

A kind of suspended holding pole segmental hoisting steel pipe pole method Download PDF

Info

Publication number
CN103243963B
CN103243963B CN201310176729.XA CN201310176729A CN103243963B CN 103243963 B CN103243963 B CN 103243963B CN 201310176729 A CN201310176729 A CN 201310176729A CN 103243963 B CN103243963 B CN 103243963B
Authority
CN
China
Prior art keywords
steel pipe
pole
rope
pulley
traction rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201310176729.XA
Other languages
Chinese (zh)
Other versions
CN103243963A (en
Inventor
戚柏林
丁自强
傅鑫林
应剑烈
戚竞波
曹慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Electric Power Co
Shaoxing Electric Power Bureau
State Grid Corp of China SGCC
Original Assignee
Zhejiang Electric Power Co
Shaoxing Electric Power Bureau
State Grid Corp of China SGCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Electric Power Co, Shaoxing Electric Power Bureau, State Grid Corp of China SGCC filed Critical Zhejiang Electric Power Co
Priority to CN201310176729.XA priority Critical patent/CN103243963B/en
Publication of CN103243963A publication Critical patent/CN103243963A/en
Application granted granted Critical
Publication of CN103243963B publication Critical patent/CN103243963B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The present invention discloses a kind of suspended holding pole segmental hoisting steel pipe pole method, comprises the steps: 1) erect pole on ground; 2) the first steel pipe is erect; 3) suspended holding pole is promoted; 4) lifting residue steel pipe and the steel pipe that cross-arm is housed; 5) suspended holding pole is removed.The invention provides a kind of suspended holding pole segmental hoisting steel pipe pole method, it adopts the construction tool of small portable, Appropriate application space, efficiently solve transport routes difficulty, the problem that fabricating yard is limited, substantially increases installation effectiveness, and reduces installation cost while guarantee installation quality.

Description

一种悬浮抱杆分段吊装钢管杆方法A method for segmentally hoisting steel pipe poles by suspension holding poles

技术领域 technical field

本发明涉及一种钢管杆的安装方法,尤其涉及一种悬浮抱杆分段吊装钢管杆方法。 The invention relates to a method for installing a steel pipe pole, in particular to a method for segmentally hoisting a steel pipe pole by suspending the pole.

背景技术 Background technique

输电线路是电源端(或变电站)向受电端输送电能的通道,有三种形式:铁塔线路、钢管杆(塔)线路和地埋电缆线路。其中铁塔线路造价低而广为应用,但占地面积太大,渐渐被政府拒绝;地埋电缆线路造价昂贵,一般用在城市电网。钢管杆线路占地面积小,拨稍的体形,圆形的断面,叠立在道路边,与环境绿化别有韵味,颇受社会关注。 The transmission line is the channel for transmitting electric energy from the power supply end (or substation) to the power receiving end. There are three forms: iron tower line, steel pipe pole (tower) line and buried cable line. Among them, iron tower lines are widely used because of their low cost, but they occupy too much area and are gradually rejected by the government; buried cable lines are expensive and are generally used in urban power grids. The steel pipe pole line occupies a small area, with a slightly dialed shape and a circular cross-section. It is stacked on the side of the road, which has a unique charm with the environmental greening, and has attracted social attention.

输电线路钢管杆也有不足之处,一般每基电塔高度在30m以上,由6m-12m为一段一段接高而成,每段重在100kN上下,在还没有形成道路通车的区域,因吊装机械不能抵达,如果为了运输和组立杆塔修建临时道路,增加了工程造价,破坏地面,损坏农作物,成为工程实施的瓶颈。 The steel pipe poles of transmission lines also have shortcomings. Generally, the height of each base tower is more than 30m, and it is formed by connecting sections of 6m-12m. If it cannot be reached, if temporary roads are built for transportation and erection of towers, the project cost will be increased, the ground will be destroyed, and crops will be damaged, which will become a bottleneck in the implementation of the project.

发明内容 Contents of the invention

为解决上述问题,本发明的目的在于提供一种悬浮抱杆分段吊装钢管杆方法,其采用小型轻便的施工工具,合理利用空间,有效解决了运输道路困难,安装场地受限的问题,在保证安装质量的同时大大提高了安装效率,且降低了安装成本。 In order to solve the above problems, the object of the present invention is to provide a method for hoisting steel pipe poles by suspension holding poles in sections, which adopts small and portable construction tools, makes reasonable use of space, and effectively solves the problems of difficult transportation roads and limited installation sites. While ensuring the installation quality, the installation efficiency is greatly improved, and the installation cost is reduced.

本发明为达到上述的目的,本发明采用如下技术方案: The present invention is to achieve above-mentioned purpose, the present invention adopts following technical scheme:

一种悬浮抱杆分段吊装钢管杆方法,包括如下步骤: A method for segmentally hoisting steel pipe poles by suspension holding poles, comprising the following steps:

1)在地面竖立抱杆 1) Erect the pole on the ground

首先在地面上安装机动绞磨,接着在机动绞磨上安装牵引绳,牵引绳的另一端安装在抱杆的顶端;当抱杆与地面形成倾斜角后启动机动绞磨,通过牵引绳使抱杆竖立;然后拆卸安装在抱杆顶端的牵引绳; First install the motorized winch on the ground, and then install the traction rope on the motorized winch, and the other end of the traction rope is installed on the top of the pole; when the pole forms an inclination angle with the ground, start the motorized winch, and use the traction rope to make the The pole is erected; then remove the traction rope installed on the top of the pole;

2)竖立第一钢管 2) erect the first steel pipe

当抱杆竖立后在抱杆顶端安装单轮滑车组,接着在抱杆底端安装转向滑轮,机动绞磨上安装的牵引绳通过转向滑轮与单轮滑车组连接;然后在第一钢管的顶端安装吊环螺丝,同时将吊环螺丝与单轮滑车组上的滑轮吊钩相连;接着启动机动绞磨,通过牵引绳使第一钢管竖立;然后将竖立的第一钢管与地面固定,最后拆卸安装在单轮滑车组上的牵引绳; When the pole is erected, a single-wheel block is installed on the top of the pole, and then a steering pulley is installed at the bottom of the pole. The traction rope installed on the motorized winch is connected to the single-wheel block through the steering pulley; and then on the top of the first steel pipe Install the lifting ring screw, and connect the lifting ring screw to the pulley hook on the single-wheel pulley block; then start the motor winch, and make the first steel pipe stand upright through the traction rope; then fix the erected first steel pipe to the ground, and finally disassemble and install it on the The traction rope on the block block;

3)提升悬浮抱杆 3) Raise the suspension pole

当第一钢管固定后将牵引绳与单轮滑车组分离,接着在第一钢管的顶端安装第一滑轮,然后在第一钢管的底端安装第二滑轮;接着机动绞磨上安装的牵引绳依次通过第二滑轮、第一滑轮后与抱杆的底端连接;然后启动机动绞磨,通过牵引绳使抱杆离开底面,当抱杆的底端与第一钢管的顶端重合1.5m—2.0m处停止牵引;接着用钢丝绳将抱杆与第一钢管固定;然后拆卸安装在抱杆底端的牵引绳; After the first steel pipe is fixed, the traction rope is separated from the single-wheel block group, and then the first pulley is installed on the top of the first steel pipe, and then the second pulley is installed on the bottom of the first steel pipe; then the traction rope installed on the motor winch After passing through the second pulley and the first pulley in turn, it is connected to the bottom end of the holding pole; then start the motor winch, and use the traction rope to make the holding pole leave the bottom surface. stop the traction at m; then fix the pole with the first steel pipe with a wire rope; then dismantle the traction rope installed at the bottom of the pole;

4)吊装剩余钢管和装有横担的钢管 4) Lift the remaining steel pipes and steel pipes with cross arms

当抱杆与第一钢管固定后按照所述步骤2)吊装第二钢管,机动绞磨上安装的牵引绳通过第二滑轮与单轮滑车组连接;当第二钢管与第一钢管对直后通过螺栓固定;接着步骤3)和步骤2)依次吊装所需安装的钢管和装有横担的钢管; After the pole is fixed to the first steel pipe, follow the step 2) to hoist the second steel pipe, and the traction rope installed on the motor winch is connected to the single-wheel pulley block through the second pulley; when the second steel pipe is aligned with the first steel pipe Fix by bolts; then step 3) and step 2) to hoist the steel pipes to be installed and the steel pipes with cross arms in sequence;

5)拆除悬浮抱杆 5) Remove the suspension pole

当装有横担的钢管吊装完后,拆卸安装在单轮滑车组上的牵引绳;接着在装有横担的钢管的横担节点位置安装有单轮滑车,机动绞磨上安装的牵引绳依次通过第二滑轮、单轮滑车与抱杆的底端相连;同时在抱杆与钢管之间套接有钢丝绳套,机动绞磨通过放松牵引绳从而使抱杆下降;钢丝绳套跟着下降;当抱杆下降到地面,拆除钢丝绳套,将抱杆放倒在地面,完成整个钢管杆的吊装工序。 After the steel pipe with cross-arm is hoisted, remove the traction rope installed on the single-wheel pulley group; The second pulley and the single-wheel pulley are connected to the bottom of the pole in turn; at the same time, a wire rope sleeve is sleeved between the pole and the steel pipe, and the motorized winch lowers the pole by loosening the traction rope; the wire rope descends accordingly; The pole is lowered to the ground, the steel wire rope cover is removed, and the pole is put down on the ground to complete the hoisting process of the entire steel pipe pole.

所述地面上安装有收松器,接着收松器上安装浪风钢丝绳,浪风钢丝绳的一端安装在抱杆的顶端;当抱杆上升时浪风钢丝绳处于松驰状态,当抱杆静止时浪风钢丝绳处于收紧状态;且浪风钢丝绳水平投影夹角为45°,浪风钢丝绳与地面的夹角为20—30°。 A retractor is installed on the ground, and then a wavewind wire rope is installed on the retractor, and one end of the wavewind wire rope is installed on the top of the pole; when the pole rises, the wavewind wire rope is in a relaxed state, and when the pole is still The wave and wind wire rope is in a tightened state; and the horizontal projection angle of the wave and wind wire rope is 45°, and the angle between the wave and wind wire rope and the ground is 20-30°.

所述抱杆的底端安装有一根枕木。 A sleeper is installed at the bottom end of the pole.

所述抱杆顶端安装有2组单轮滑车组,2组单轮滑车组的滑轮吊钩分别与第一钢管顶端的2个吊环螺丝连接;同时第一钢管上安装有拉绳,拉绳控制第一钢管在上升的过程中与抱杆的距离;所述第二钢管上安装有拉绳,拉绳控制第二钢管在上升过程中与抱杆的距离;且装有横担的钢管上安装有拉绳,拉绳控制装有横担的钢管在上升过程中与抱杆的距离与旋转。 Two sets of single-wheel tackles are installed on the top of the pole, and the pulley hooks of the two sets of single-wheel tackles are respectively connected to the two ring screws on the top of the first steel pipe; at the same time, a pull rope is installed on the first steel pipe, and the pull rope controls The distance between the first steel pipe and the pole during the ascent process; a stay rope is installed on the second steel pipe, and the stay rope controls the distance between the second steel pipe and the pole during the ascent process; There is a stay rope, and the stay rope controls the distance and rotation between the steel pipe with the cross arm and the pole during the ascent process.

本发明的有益效果为:本发明提供一种悬浮抱杆分段吊装钢管杆方法,其采用小型轻便的施工工具,合理利用空间,有效解决了运输道路困难,安装场地受限的问题,在保证安装质量的同时大大提高了安装效率,且降低了安装成本。 The beneficial effects of the present invention are as follows: the present invention provides a method for segmentally hoisting steel pipe poles by suspension holding poles, which adopts small and portable construction tools, rationally utilizes the space, and effectively solves the problems of difficult transportation roads and limited installation sites. While the installation quality is greatly improved, the installation efficiency is greatly improved, and the installation cost is reduced.

附图说明 Description of drawings

图1是竖立抱杆的安装示意图; Fig. 1 is the installation diagram of erecting pole;

图2是竖立第一钢管的安装示意图; Fig. 2 is the installation sketch map of erecting the first steel pipe;

图3是提升悬浮抱杆的安装示意图; Figure 3 is a schematic diagram of the installation of the lifting suspension pole;

图4是吊装第二钢管的安装示意图; Fig. 4 is the installation schematic diagram of hoisting the second steel pipe;

图5是吊装横担钢管的安装示意图; Fig. 5 is the installation sketch map of hoisting cross-arm steel pipe;

图6是拆除悬浮抱杆的安装示意图。 Figure 6 is an installation diagram for removing the suspension pole.

具体实施方式 detailed description

实施例1 Example 1

如图1所示,本实施例提供的一种悬浮抱杆分段吊装钢管杆方法,首先在地面上安装机动绞磨1,接着在机动绞磨1上安装牵引绳3,牵引绳3的另一端安装在抱杆2的顶端。抱杆2纵向与牵引绳3、机动绞磨1、钢管杆砼基础一直线上,抱杆2上端部设置4根浪风钢丝绳71,在地面抱杆2下端垫上枕木块。然后人力或小抱杆将抱杆2抬举离地1.5m以上,接着牵引绳3和机动绞磨1使抱杆2直立状态。以上机械牵引过程中,把握浪风钢丝绳71不紧不松状态,抱杆2直立后收紧浪风钢丝绳71。所述抱杆2的底端安装有一根枕木8。枕木8在整个安装中起到抱杆2根部与钢管杆壁有一个间距,如果没有枕木8的衬上,抱杆2发生倾斜。 As shown in Figure 1, a method for hoisting steel pipe poles by suspension holding a pole in sections provided by this embodiment, first installs a motorized winch 1 on the ground, then installs a traction rope 3 on the motorized winch 1, and the other part of the traction rope 3 One end is installed on the top of the pole 2. The longitudinal direction of the pole 2 is in line with the traction rope 3, the motorized winch mill 1, and the concrete foundation of the steel pipe pole, and 4 waves and wind steel wire ropes 71 are arranged at the upper end of the pole 2, and wooden sleepers are placed on the lower end of the pole 2 on the ground. Then the manpower or the small pole lift the pole 2 above the ground by more than 1.5m, and then the traction rope 3 and the motor winch 1 make the pole 2 stand upright. During the above mechanical traction process, grasp whether the wave wind wire rope 71 is not tight or loose, tighten the wave wind wire rope 71 after the holding pole 2 stands upright. A sleeper 8 is installed on the bottom end of the pole 2 . Sleeper 8 has a distance between the root of the pole and the steel pipe rod wall in the whole installation, if there is no lining of sleeper 8, the pole 2 is inclined.

4根浪风钢丝绳71与地面的4组收松器7分别一一对应,浪风钢丝绳71由人员控制紧松。四根浪风钢丝绳71水平投影夹角45°,地面角20°-30°。 The 4 waves and wind wire ropes 71 correspond to the 4 groups of loosening devices 7 on the ground respectively, and the waves and wind wire ropes 71 are controlled to be loosened by personnel. Four wave wind wire ropes 71 horizontal projection angles are 45 °, ground angles are 20 °-30 °.

如图2所述,吊装第一钢管4。在抱杆2上端部悬挂2组单轮滑车组21,第一钢管4上端的法兰盘眼孔上,安装2个吊环螺丝41,与轮滑车组21滑轮吊钩连接,牵引绳3经过转向滑轮22与机动绞磨1连接。经机动绞磨1运转,第一钢管4徐徐立起来,此时第一钢管4上的拉绳9控制钢管杆与抱杆的距离。 As shown in FIG. 2 , the first steel pipe 4 is hoisted. Hang 2 groups of single wheel pulley blocks 21 on the upper end of the pole 2, and install 2 ring screws 41 on the flange eyelets on the upper end of the first steel pipe 4 to connect with the pulley hooks of the pulley blocks 21, and the traction rope 3 passes through the steering wheel The pulley 22 is connected with the motorized winch 1 . Through motor winch mill 1 operation, the first steel pipe 4 stands up slowly, and now the stay cord 9 on the first steel pipe 4 controls the distance between the steel pipe bar and the holding bar.

如图3所述,提升悬浮抱杆2。第一钢管4吊装完后,第一钢管4根部地脚螺栓及时拧紧。在第一钢管4上端法兰眼孔装一只吊环螺丝41,悬挂一只第一滑轮42,第一钢管4下端绑一只第二滑轮43,牵引钢丝绳3头部与抱杆2根部回定,经第一滑轮42和第二滑轮43引入机动绞磨1。起动绞磨1,抱杆2缓缓上升,此时浪风钢丝绳71呈松弛状态,抱杆与钢管杆共套一个钢绳环23。抱杆2上升至与第一钢管4重合2m处,停止牵引,然后用钢丝绳把抱杆2固定在第一钢管4的爬梯支架处绑扎,然后适度收紧浪风钢丝绳71。 As shown in Figure 3, lift the suspension pole 2. After the first steel pipe 4 had been hoisted, the anchor bolts at the root of the first steel pipe 4 were tightened in time. A ring screw 41 is installed in the flange eye hole at the upper end of the first steel pipe 4, a first pulley 42 is suspended, a second pulley 43 is tied at the lower end of the first steel pipe 4, and the head of the traction wire rope 3 and the root of the pole 2 are fixed. , into the motorized winch 1 through the first pulley 42 and the second pulley 43 . Start winch mill 1, and hold bar 2 to rise slowly, and this moment wave wind steel wire rope 71 is in slack state, and hold bar and steel pipe bar to cover a steel rope ring 23 altogether. The holding pole 2 rises to overlap with the first steel pipe 4 at 2m, stop the traction, then fix the holding pole 2 on the ladder bracket of the first steel pipe 4 with a wire rope and tie it up, then moderately tighten the wave wind wire rope 71.

如图4所述,吊装第二钢管5。在抱杆2上端部悬挂2组单轮滑车组21,第二钢管5上端的法兰盘眼孔上,安装2个吊环螺丝41,与轮滑车组21滑轮吊钩连接,牵引绳3经过第二滑轮43与机动绞磨1连接。经机动绞磨1运转,第二钢管5徐徐吊起,此时第二钢管5端部拉绳9控制第二钢管5与抱杆2的距离。第二钢管5与第一钢管4法兰眼孔对直后,及时拧紧螺栓后,吊装才完成。 As shown in FIG. 4, the second steel pipe 5 is hoisted. Hang 2 groups of single-wheel blocks 21 at the upper end of the pole 2, and install 2 eyebolt screws 41 on the flange eyelets at the top of the second steel pipe 5, which are connected with the 21 pulley hooks of the wheel blocks, and the traction rope 3 passes through the first Two pulleys 43 are connected with motor winch 1. After the operation of the motor-driven winch mill 1, the second steel pipe 5 is slowly hoisted, and now the stay rope 9 at the end of the second steel pipe 5 controls the distance between the second steel pipe 5 and the pole 2. After the second steel pipe 5 is aligned with the first steel pipe 4 flange eyelets, after the bolts are tightened in time, the hoisting is completed.

所述的第2次升悬浮抱杆和吊装第三钢管过程与前述一样。 The process of raising the suspended pole for the second time and hoisting the third steel pipe is the same as above.

如图5所述,吊装装有横担的钢管6。钢管杆上装有横担,整长比其它长,但重量比其它轻。吊点在上导线横担的节点位置,用钢丝绳绕绑做吊点,然后与轮滑车组21滑轮吊钩连接,牵引绳8经过第二滑轮43与机动绞磨1连接。经机动绞磨1运转,吊装装有横担的钢管6徐徐吊起,此时控制钢丝绳9分别设在钢管杆端部和横担端部,控制水平距离和方向。 As shown in Figure 5, the steel pipe 6 with the cross arm is hoisted. The steel pipe pole is equipped with a cross arm, and its overall length is longer than others, but its weight is lighter than others. Suspension point is at the nodal position of upper conductor cross-arm, wraps and binds with wire rope and does suspension point, then is connected with pulley block 21 pulley hooks, and traction rope 8 is connected with motor winch 1 through second pulley 43. Through the operation of the motor winch mill 1, the steel pipe 6 with the cross arm is hoisted slowly, and now the control wire rope 9 is respectively located at the end of the steel pipe rod and the end of the cross arm to control the horizontal distance and direction.

如图6所示,当装有横担的钢管6吊装完后,拆卸安装在单轮滑车组21上的牵引绳3;接着在装有横担的钢管6的横担节点位置安装有单轮滑车61,机动绞磨1上安装的牵引绳3依次通过第二滑轮43、单轮滑车61与抱杆2的底端相连;同时在抱杆2与钢管之间套接有钢丝绳套23,机动绞磨1通过放松牵引绳3从而使抱杆2下降;钢丝绳套23跟着下降;当抱杆2下降到地面,拆除钢丝绳套23,将抱杆2放倒在地面,完成整个钢管杆的吊装工序。 As shown in Figure 6, after the steel pipe 6 with the cross arm is hoisted, the traction rope 3 installed on the single-wheel block group 21 is disassembled; Car 61, the traction rope 3 installed on the motorized winch mill 1 is connected to the bottom of the pole 2 through the second pulley 43 and the single-wheel tackle 61 successively; The winch 1 lowers the holding pole 2 by loosening the traction rope 3; the steel wire rope cover 23 descends; when the holding pole 2 falls to the ground, remove the steel wire rope cover 23, put the holding pole 2 on the ground, and complete the hoisting process of the entire steel pipe pole .

本实施例所述的一种悬浮抱杆分段吊装钢管杆方法,其采用小型轻便的施工工具,合理利用空间,有效解决了运输道路困难,安装场地受限的问题,在保证安装质量的同时大大提高了安装效率,且降低了安装成本。 The method for hoisting steel pipe poles by suspension holding poles in sections described in this embodiment adopts small and portable construction tools, makes reasonable use of space, and effectively solves the problems of difficult transportation roads and limited installation sites, and ensures the quality of installation at the same time The installation efficiency is greatly improved and the installation cost is reduced.

Claims (2)

1.一种悬浮抱杆分段吊装钢管杆方法,其特征在于包括如下步骤: 1. A method for segmentally hoisting steel pipe rods by suspension holding rods, characterized in that it comprises the following steps: 1)在地面竖立抱杆 1) Erect the pole on the ground 首先在地面上安装机动绞磨(1),接着在机动绞磨(1)上安装牵引绳(3),牵引绳(3)的另一端安装在抱杆(2)的顶端;当抱杆(2)与地面形成倾斜角后,通过牵引绳(3)机动绞磨(1)施力,抱杆(2)竖立;然后拆卸安装在抱杆(2)顶端的牵引绳(3); First install the motorized twisted mill (1) on the ground, then install the traction rope (3) on the motorized twisted mill (1), and the other end of the traction rope (3) is installed on the top of the pole (2); when the pole ( 2) After forming an inclination angle with the ground, apply force through the traction rope (3) motorized winch (1), and the pole (2) is erected; then remove the traction rope (3) installed on the top of the pole (2); 2)竖立第一钢管 2) erect the first steel pipe 当抱杆(2)竖立后在抱杆(2)顶端安装单轮滑车组(21),接着在抱杆(2)底端安装转向滑轮(22),机动绞磨(1)上安装的牵引绳(3)通过转向滑轮(22)与单轮滑车组(21)连接;然后在第一钢管(4)的顶端安装吊环螺丝(41),同时将吊环螺丝(41)与单轮滑车组(21)上的滑轮吊钩相连;接着启动机动绞磨(1),通过牵引绳(3)使第一钢管(4)竖立;然后将竖立的第一钢管(4)与地面固定,最后拆卸安装在单轮滑车组(21)上的牵引绳(3); When the pole (2) is erected, a single-wheel block (21) is installed on the top of the pole (2), and then the steering pulley (22) is installed at the bottom of the pole (2), and the traction installed on the motorized winch (1) The rope (3) is connected with the single-wheel block (21) through the turning pulley (22); 21) connected to the pulley hook on the top; then start the motorized winch (1), and erect the first steel pipe (4) through the traction rope (3); then fix the erected first steel pipe (4) to the ground, and finally disassemble and install it The traction rope (3) on the single-wheel blocks (21); 3)提升悬浮抱杆 3) Raise the suspension pole 当第一钢管(4)固定后将牵引绳(3)与单轮滑车组(21)分离,接着在第一钢管(4)的顶端安装第一滑轮(42),然后在第一钢管(4)的底端安装第二滑轮(43);接着机动绞磨(1)上安装的牵引绳(3)依次通过第二滑轮(43)、第一滑轮(42)后与抱杆(2)的底端固定;然后启动机动绞磨(1),通过牵引绳(3)使抱杆(2)离开底面,当抱杆(2)的底端与第一钢管(4)的顶端重合1.5m—2.0m处停止牵引;接着用钢丝绳将抱杆(2)与第一钢管(4)固定;然后拆卸安装在抱杆(2)底端的牵引绳(3); After the first steel pipe (4) is fixed, the traction rope (3) is separated from the single-wheel block group (21), and then the first pulley (42) is installed on the top of the first steel pipe (4), and then the first steel pipe (4) ) is installed at the bottom end of the second pulley (43); then the traction rope (3) installed on the motor winch (1) passes through the second pulley (43), the first pulley (42) and the pole (2) in sequence The bottom end is fixed; then start the motor winch (1), use the traction rope (3) to make the pole (2) leave the bottom surface, when the bottom end of the pole (2) coincides with the top of the first steel pipe (4) by 1.5m— Stop traction at 2.0m; then fix the pole (2) and the first steel pipe (4) with a wire rope; then remove the traction rope (3) installed at the bottom of the pole (2); 4)吊装剩余钢管和装有横担的钢管 4) Lift the remaining steel pipes and steel pipes with cross arms 当抱杆(2)与第一钢管(4)固定后按照所述步骤2)吊装第二钢管(5),机动绞磨(1)上安装的牵引绳(3)通过第二滑轮(43)与单轮滑车组(21)连接;当第二钢管(5)与第一钢管(4)对直后通过螺栓固定;接着步骤3)和步骤2)依次吊装所需安装的钢管和装有横担的钢管(6); After the pole (2) and the first steel pipe (4) are fixed, the second steel pipe (5) is hoisted according to the above step 2), and the traction rope (3) installed on the motor winch (1) passes through the second pulley (43) Connect with the single-wheel pulley group (21); when the second steel pipe (5) is aligned with the first steel pipe (4), fix it with bolts; then step 3) and step 2) hoist the steel pipes to be installed and the cross-arm steel pipe (6); 5)拆除悬浮抱杆 5) Remove the suspension pole 当装有横担的钢管(6)吊装完后,拆卸安装在单轮滑车组(21)上的牵引绳(3);接着在装有横担的钢管(6)的横担节点位置安装有单轮滑车(61),机动绞磨(1)上安装的牵引绳(3)依次通过第二滑轮(43)、单轮滑车(61)与抱杆(2)的底端相连;同时在抱杆(2)与钢管之间套接有钢丝绳套(23),机动绞磨(1)通过放松牵引绳(3)从而使抱杆(2)下降,钢丝绳套(23)跟着下降;当抱杆(2)下降到地面,拆除钢丝绳套(23),将抱杆(2)放倒在地面,完成整个钢管杆的吊装工序; After the steel pipe (6) with cross arm is hoisted, disassemble the traction rope (3) installed on the single-wheel tackle group (21); then install a One-wheel block (61), the traction rope (3) installed on the motor winch (1) is connected to the bottom of the holding bar (2) by the second pulley (43), one-wheel block (61) successively; A steel wire rope cover (23) is sleeved between the rod (2) and the steel pipe, and the motor winch (1) lowers the holding rod (2) by relaxing the traction rope (3), and the steel wire rope cover (23) descends accordingly; when holding the rod (2) Descend to the ground, remove the wire rope cover (23), put the holding pole (2) on the ground, and complete the hoisting process of the entire steel pipe pole; 所述抱杆(2)顶端安装有2组单轮滑车组(21),2组单轮滑车组(21)的滑轮吊钩分别与第一钢管(4)顶端的2个吊环螺丝(41)连接;同时第一钢管(4)上安装有拉绳(9),拉绳(9)控制第一钢管(4)在上升的过程中与抱杆(2)的距离;所述第二钢管(5)上安装有拉绳(9),拉绳(9)控制第二钢管(5)在上升过程中与抱杆(2)的距离;且装有横担的钢管(6)上安装有拉绳(9),拉绳(9)控制装有横担的钢管(6)在上升过程中与抱杆(2)的距离与旋转。 Two sets of single-wheel blocks (21) are installed on the top of the pole (2), and the pulley hooks of the two sets of single-wheel blocks (21) are respectively connected to the two ring screws (41) on the top of the first steel pipe (4). connection; at the same time, a stay rope (9) is installed on the first steel pipe (4), and the stay rope (9) controls the distance between the first steel pipe (4) and the pole (2) in the process of rising; the second steel pipe ( 5) A stay rope (9) is installed on the top, and the stay rope (9) controls the distance between the second steel pipe (5) and the holding pole (2) during the ascent process; Rope (9), stay rope (9) control the distance and the rotation of the steel pipe (6) that crossarm is housed with the pole (2) in the ascent process. 2.根据权利要求1所述的一种悬浮抱杆分段吊装钢管杆方法,其特征在于:所述抱杆(2)的底端安装有一根枕木(8)。 2. The method for segmentally hoisting steel pipe poles with suspended poles according to claim 1, characterized in that: a sleeper (8) is installed at the bottom of the poles (2).
CN201310176729.XA 2013-05-14 2013-05-14 A kind of suspended holding pole segmental hoisting steel pipe pole method Active CN103243963B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310176729.XA CN103243963B (en) 2013-05-14 2013-05-14 A kind of suspended holding pole segmental hoisting steel pipe pole method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310176729.XA CN103243963B (en) 2013-05-14 2013-05-14 A kind of suspended holding pole segmental hoisting steel pipe pole method

Publications (2)

Publication Number Publication Date
CN103243963A CN103243963A (en) 2013-08-14
CN103243963B true CN103243963B (en) 2016-01-20

Family

ID=48923810

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310176729.XA Active CN103243963B (en) 2013-05-14 2013-05-14 A kind of suspended holding pole segmental hoisting steel pipe pole method

Country Status (1)

Country Link
CN (1) CN103243963B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103613024B (en) * 2013-12-03 2016-01-13 国家电网公司 A kind of tubular type rolling device
CN103982074B (en) * 2014-05-06 2016-08-24 国家电网公司 Split type pipe tower hanging method
CN105019713B (en) * 2015-08-13 2017-07-07 国家电网公司 A kind of Novel electric line bar
CN105804484B (en) * 2016-02-17 2018-07-03 浙江省送变电工程公司 High tower pole promotes ground tackle pulley abrasionproof, anti-hopping tool and application method
CN107217909A (en) * 2017-06-27 2017-09-29 电联工程技术股份有限公司 Guywire tower hanging method and the frock using this method
WO2021223446A1 (en) * 2020-12-16 2021-11-11 中铁九局集团电务工程有限公司 Collapse-section pole assembly device and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002004635A (en) * 2000-06-19 2002-01-09 Okagami Kogyo Kk Device for assembling steel pipe column
JP2002061420A (en) * 2000-08-14 2002-02-28 Saito Denki:Kk Device for erecting and recovering temporary utility pole
JP2006124965A (en) * 2004-10-27 2006-05-18 Murayama Doken:Kk Steel tower assembling method and scaffold for the assembling
CN102022019A (en) * 2010-11-03 2011-04-20 河南省电力公司洛阳供电公司 Method for split tower erection of lines in complex terrain
CN102359303A (en) * 2011-10-31 2012-02-22 湖北省输变电工程公司 Extra-high voltage common circuit iron tower assembling method
CN202187601U (en) * 2011-05-17 2012-04-11 王海兵 Single-twisting-grinder double-pole iron tower erecting device of high-voltage power transmission line

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002004635A (en) * 2000-06-19 2002-01-09 Okagami Kogyo Kk Device for assembling steel pipe column
JP2002061420A (en) * 2000-08-14 2002-02-28 Saito Denki:Kk Device for erecting and recovering temporary utility pole
JP2006124965A (en) * 2004-10-27 2006-05-18 Murayama Doken:Kk Steel tower assembling method and scaffold for the assembling
CN102022019A (en) * 2010-11-03 2011-04-20 河南省电力公司洛阳供电公司 Method for split tower erection of lines in complex terrain
CN202187601U (en) * 2011-05-17 2012-04-11 王海兵 Single-twisting-grinder double-pole iron tower erecting device of high-voltage power transmission line
CN102359303A (en) * 2011-10-31 2012-02-22 湖北省输变电工程公司 Extra-high voltage common circuit iron tower assembling method

Also Published As

Publication number Publication date
CN103243963A (en) 2013-08-14

Similar Documents

Publication Publication Date Title
CN103243963B (en) A kind of suspended holding pole segmental hoisting steel pipe pole method
CN202187601U (en) Single-twisting-grinder double-pole iron tower erecting device of high-voltage power transmission line
CN102359303B (en) UHV ordinary line iron tower assembly method
CN104276514B (en) Installation method of ground self-balancing pole
CN203645249U (en) Hook-net-plane-type charged crossing device
CN104727236A (en) Whole striding bridge lowering dismounting system based on ground supporting and construction method thereof
CN205046926U (en) Join in marriage net overhead line and prevent wind draw off mechanism
CN204663121U (en) Packaged type insulating supporting line bar
CN104577875A (en) Construction method of block crossover frame cable of power circuit
CN103236656B (en) Column suspension type crossing structure and operating method thereof
CN102022019B (en) A kind of method of complex terrain route split tower erection
CN202544468U (en) Drawbar-type electrical steel tubular rod
CN208202761U (en) A kind of upright bar structure lifted by crane using old bar
CN103806735B (en) Based on to the electric pole replacing options in electric power pipe network
CN204277336U (en) The vertical bracing frame of herringbone bar group
CN204266133U (en) A kind of pier stud reinforcing cage whole lifting structure
CN204150970U (en) Seat ground self-balancing pole
CN206071208U (en) A kind of electric pole device for erecting pole
CN202383915U (en) Purler type holding pole integrally raising aluminium alloy multifunctional repair tower simulation teaching sand table
CN205046927U (en) Improved generation is joined in marriage net overhead line and is prevent wind draw off mechanism
CN208266866U (en) A kind of wind resistance steady type guy anchor
CN204252013U (en) Across pier self-propelling device
CN203359890U (en) Small-sized electric pole hoisting device
CN202840363U (en) 1000kV UHV AC Line Tension Insulator String Insulation Lifting Bracket
CN206233673U (en) A kind of herringbone holding pole standing device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant