CN103225401A - Method for filling expansion joint of enclosing wall of transformer substation - Google Patents

Method for filling expansion joint of enclosing wall of transformer substation Download PDF

Info

Publication number
CN103225401A
CN103225401A CN2013101384108A CN201310138410A CN103225401A CN 103225401 A CN103225401 A CN 103225401A CN 2013101384108 A CN2013101384108 A CN 2013101384108A CN 201310138410 A CN201310138410 A CN 201310138410A CN 103225401 A CN103225401 A CN 103225401A
Authority
CN
China
Prior art keywords
shrinkage joint
enclosure wall
transformer station
line paper
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101384108A
Other languages
Chinese (zh)
Inventor
王亚楠
齐玉良
张建华
郝长青
孙晓桦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Tianjin Electric Power Transmission and Transformation Engineering Corp
Original Assignee
State Grid Corp of China SGCC
Tianjin Electric Power Transmission and Transformation Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Tianjin Electric Power Transmission and Transformation Engineering Corp filed Critical State Grid Corp of China SGCC
Priority to CN2013101384108A priority Critical patent/CN103225401A/en
Publication of CN103225401A publication Critical patent/CN103225401A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a method for filling expansion joints of enclosing walls of a transformer substation. The method comprises the following steps: (1) manufacturing joints; (2) cleaning; (3) supporting; and (4) gluing. The conventional zigzag expansion joint is replaced by a straight-through type expansion joint, so that high-strength sundries in the expansion joints of the wall after masonry are easier to clean, the expansion joints are easier to effectively fill, and the whole aesthetic degree of the enclosing wall masonry molding after the expansion joints are filled is increased.

Description

A kind of transformer station enclosure wall shrinkage joint fill method
Technical field
The invention belongs to the power construction field, relate to the shrinkage joint of transformer station's enclosure wall, especially a kind of transformer station enclosure wall shrinkage joint fill method.
Background technology
At present, most of transformer stations entity enclosure wall all adopts loam brick to build by laying bricks or stones, between two entity enclosure wall piers, be reserved with the shrinkage joint, this shrinkage joint is indentation, foreign material were cleared up sordid situation after building construction usually appearred in the shrinkage joint of this complications, this foreign material intensity is higher, makes body of wall not play the effect at shrinkage joint thus in the sedimentation and deformation process, thereby makes enclosure wall produce cracking.Simultaneously, in work progress, the shrinkage joint is subjected to all multifactor influences, fills imprecision in the shrinkage joint in follow-up construction, and rainwater is irritated into body of wall, causes flexible, the uneven deformation of wall that makes of sedimentation, loses the effect of prolonging life.
Summary of the invention
The objective of the invention is to overcome the deficiencies in the prior art part, provide that a kind of with low cost, technology is simple, straight, transformer station's enclosure wall shrinkage joint fill method.
Technical scheme of the present invention is:
A kind of transformer station enclosure wall shrinkage joint fill method the steps include:
⑴ system seam: transformer station's enclosure wall adopts split brick to build by laying bricks or stones, reserves the straight shrinkage joint between two enclosure wall piers;
⑵ cleaning: reject foreign material in the shrinkage joint, confirm that the enclosure wall masonry corner of both sides, shrinkage joint is a right-angle plane;
⑶ support: evenly put into a plurality of polyphenyl rods in the shrinkage joint, vertical and coaxial being arranged in the shrinkage joint of a plurality of polyphenyl rods;
⑷ gluing: evenly squeeze into weather-resistant glue in the shrinkage joint, colloid surface layer does not exceed pier surface and pier flush.
And the described shrinkage joint of step ⑴ width is 1 ~ 2cm.
And the described polyphenyl rod of step ⑶ diameter is 1.5 ~ 2.5cm.
And the described weather-resistant glue of step ⑷ is the seam shape that crouches in the shrinkage joint.
And, before the described gluing of step ⑷, on two enclosure wall pier inwalls of both sides, shrinkage joint, paste the U.S. line paper of one deck respectively, this U.S.'s line paper is between polyphenyl rod and pier inwall and all stretch out outside the shrinkage joint outside the U.S. line paper, in beating the glue process, weather-resistant glue flows out or is expressed on the U.S. line paper that stretches out outside the shrinkage joint the U.S. line paper outside the shrinkage joint of tearing.
Advantage of the present invention and good effect are:
1, the present invention replaces with existing indentation shrinkage joint at the shrinkage joint of straight, make in the shrinkage joint of body of wall after building by laying bricks or stones the bigger foreign material of intensity be easier to cleaning, make the shrinkage joint be easier to effective filling simultaneously, after filled at the shrinkage joint, the overall appearance degree of enclosure wall masonry moulding also was improved.
2, the present invention as the bed course that is coated with weather-resistant glue, avoids U.S. line paper weather-resistant glue flow out or extrudes at the shrinkage joint outside and flow to or cover body of wall and lay bricks, thereby has guaranteed the standard and the aesthetic measure of shrinkage joint filling.
3, the present invention has adopted the polyphenyl rod as the flexible support post, in the shrinkage joint around the support column, adopt weather-resistant glue to fill, fundamentally stopped rainwater thus and irritated into that body of wall causes the sedimentation inequality to make the deformation of wall problem, thereby the related enclosure wall that has solved the shrinkage joint inner stuffing and caused produces cracking, has increased the application life of transformer station's enclosure wall.
Description of drawings
Fig. 1 is the structural representation (broken section) after fill at the shrinkage joint among the present invention;
Fig. 2 is that A-A among Fig. 1 is to the structure sectional view.
The specific embodiment
The invention will be further described below in conjunction with accompanying drawing and by specific embodiment, and following examples are descriptive, are not determinate, can not limit protection scope of the present invention with this.
A kind of transformer station enclosure wall shrinkage joint fill method the steps include:
⑴ system seam: transformer station's enclosure wall adopts split brick to build by laying bricks or stones, reserves the straight shrinkage joint between two enclosure wall piers, and the shrinkage joint width is 1 ~ 2cm;
⑵ cleaning: reject foreign material in the shrinkage joint, confirm that the enclosure wall masonry corner of both sides, shrinkage joint is a right-angle plane;
⑶ support: evenly put into a plurality of polyphenyl rods in the shrinkage joint, polyphenyl rod diameter exceeds the wide 0.5cm in shrinkage joint, vertical and coaxial being arranged in the shrinkage joint of a plurality of polyphenyl rods;
⑷ gluing: on two enclosure wall pier inwalls of both sides, shrinkage joint, paste the U.S. line paper of one deck respectively, this U.S.'s line paper is between polyphenyl rod and pier inwall and all stretch out outside the shrinkage joint outside the U.S. line paper, in the shrinkage joint, evenly squeeze into weather-resistant glue, weather-resistant glue is the seam shape that crouches in the shrinkage joint, guarantee that thus colloid makes, beat real, guaranteed also that simultaneously the smooth nothing of colloid surface layer stays that to weigh down gauffer thickness even, in this process, a certain amount of weather-resistant glue flows out or is expressed on the U.S. line paper that stretches out outside the shrinkage joint, tear U.S. line paper outside the shrinkage joint guarantees that thus colloid surface layer does not exceed the pier surface.

Claims (5)

1. transformer station's enclosure wall shrinkage joint fill method is characterized in that: the steps include:
⑴ system seam: transformer station's enclosure wall adopts split brick to build by laying bricks or stones, reserves the straight shrinkage joint between two enclosure wall piers;
⑵ cleaning: reject foreign material in the shrinkage joint, confirm that the enclosure wall masonry corner of both sides, shrinkage joint is a right-angle plane;
⑶ support: evenly put into a plurality of polyphenyl rods in the shrinkage joint, vertical and coaxial being arranged in the shrinkage joint of a plurality of polyphenyl rods;
⑷ gluing: evenly squeeze into weather-resistant glue in the shrinkage joint, colloid surface layer does not exceed pier surface and pier flush.
2. transformer station according to claim 1 enclosure wall shrinkage joint fill method is characterized in that: the described shrinkage joint of step ⑴ width is 1 ~ 2cm.
3. transformer station according to claim 1 enclosure wall shrinkage joint fill method is characterized in that: the described polyphenyl rod of step ⑶ diameter is 1.5 ~ 2.5cm.
4. transformer station according to claim 1 enclosure wall shrinkage joint fill method is characterized in that: the described weather-resistant glue of step ⑷ is the seam shape that crouches in the shrinkage joint.
5. transformer station according to claim 1 enclosure wall shrinkage joint fill method, it is characterized in that: before the described gluing of step ⑷, on two enclosure wall pier inwalls of both sides, shrinkage joint, paste the U.S. line paper of one deck respectively, this U.S.'s line paper is between polyphenyl rod and pier inwall and all stretch out outside the shrinkage joint outside the U.S. line paper, in beating the glue process, weather-resistant glue flows out or is expressed on the U.S. line paper that stretches out outside the shrinkage joint the U.S. line paper outside the shrinkage joint of tearing.
CN2013101384108A 2013-04-19 2013-04-19 Method for filling expansion joint of enclosing wall of transformer substation Pending CN103225401A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101384108A CN103225401A (en) 2013-04-19 2013-04-19 Method for filling expansion joint of enclosing wall of transformer substation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101384108A CN103225401A (en) 2013-04-19 2013-04-19 Method for filling expansion joint of enclosing wall of transformer substation

Publications (1)

Publication Number Publication Date
CN103225401A true CN103225401A (en) 2013-07-31

Family

ID=48836023

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101384108A Pending CN103225401A (en) 2013-04-19 2013-04-19 Method for filling expansion joint of enclosing wall of transformer substation

Country Status (1)

Country Link
CN (1) CN103225401A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522384A (en) * 2016-10-11 2017-03-22 天津送变电工程公司 Construction method for preventing first floor building of transformer station from blooming

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4105360A1 (en) * 1990-12-09 1992-06-11 Studien Ges Fuer Unterirdische Road tunnel trough structure - has drainage system in and below caps at expansion joint strips
CN1811103A (en) * 2006-03-02 2006-08-02 江苏丰彩漆业技术有限公司 Outer wall heat insulating and decorating plate and its construction process
CN201314083Y (en) * 2008-08-05 2009-09-23 深圳市建筑装饰(集团)有限公司 Novel decoration construction structure of architectural main body expansion joint
CN201581510U (en) * 2009-12-05 2010-09-15 山东天齐置业集团股份有限公司 Advanced water-stop post-pouring belt of foundation slab

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4105360A1 (en) * 1990-12-09 1992-06-11 Studien Ges Fuer Unterirdische Road tunnel trough structure - has drainage system in and below caps at expansion joint strips
CN1811103A (en) * 2006-03-02 2006-08-02 江苏丰彩漆业技术有限公司 Outer wall heat insulating and decorating plate and its construction process
CN201314083Y (en) * 2008-08-05 2009-09-23 深圳市建筑装饰(集团)有限公司 Novel decoration construction structure of architectural main body expansion joint
CN201581510U (en) * 2009-12-05 2010-09-15 山东天齐置业集团股份有限公司 Advanced water-stop post-pouring belt of foundation slab

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
L17991793: "《国家电网公司输变电工程工艺标准库》", 《百度文库》, 18 February 2012 (2012-02-18) *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106522384A (en) * 2016-10-11 2017-03-22 天津送变电工程公司 Construction method for preventing first floor building of transformer station from blooming

Similar Documents

Publication Publication Date Title
CN104975652B (en) A kind of precast concrete docks attachment structure
CN106677440A (en) Roofing parapet water-floating structure and construction method thereof
CN106481090B (en) A kind of Shockproof reinforcing method of existing reinforced concrete concrete frame joint
CN104631662A (en) Hollow steel mesh keel inner formwork cement partition wall construction method
CN203994171U (en) A kind of building prefabricated components becomes punch die
CN103711232A (en) L-shaped frame component and lightweight concrete wall prefabricated type shear wall and connection construction method
CN103866866B (en) Super High Core Walls Structure and housing water node after setting a roof beam in place
CN203905327U (en) Adjustable grinding device for waterproof roll
CN103225401A (en) Method for filling expansion joint of enclosing wall of transformer substation
CN106836592A (en) Overlapped hollow floor system after partial precast assembled
CN103696513A (en) Prefabricated shear wall with crossed frame member and lightweight concrete wall bodies and connection construction method
CN208486388U (en) Waterproof precast floor slab
CN103410344B (en) A kind of steel concrete wall beam strengthen device and wall beam Enhancement Method
CN104594529A (en) Outer wall of steel structure plant, model frame of upright post at corner and outer wall construction method
CN204418425U (en) Steel-structure factory building exterior wall and steel-structure factory building exterior wall corner column framed
CN204081081U (en) A kind of furred ceiling of novel crack resistence and wall connecting node structure
CN207268017U (en) A kind of assembling type steel structure floor seal type side mould node
CN203876019U (en) Pore-forming member manufacturing preformed hole of precast concrete component
CN203174782U (en) Filling structure for expansion joint of fences of transformer substation
CN208137480U (en) A kind of novel joist rod structure
CN206707086U (en) Truss plate cast-in-situ reinforced concrete hollow superimposed sheet
CN204703368U (en) Sandwich type insulation blocks
CN204098286U (en) A kind of washroom dash leads wall
CN204531153U (en) Prestressed concrete overlapped slab
CN205601032U (en) But roof beam cap flange subassembly of fast switch over

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130731