CN103212952A - Manufacturing method of super-large-diameter large-wall thick longitudinal submerged arc welded pipe - Google Patents

Manufacturing method of super-large-diameter large-wall thick longitudinal submerged arc welded pipe Download PDF

Info

Publication number
CN103212952A
CN103212952A CN2013101473277A CN201310147327A CN103212952A CN 103212952 A CN103212952 A CN 103212952A CN 2013101473277 A CN2013101473277 A CN 2013101473277A CN 201310147327 A CN201310147327 A CN 201310147327A CN 103212952 A CN103212952 A CN 103212952A
Authority
CN
China
Prior art keywords
submerged arc
super
welding
steel plate
arc welded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013101473277A
Other languages
Chinese (zh)
Other versions
CN103212952B (en
Inventor
赵国
张志明
葛玉宏
王旭
王习彬
陈小伟
刘涛
曹华勇
王旺甫
刘增强
王立柱
吕育栋
韩铁利
吴娟
白学伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING JULONG STEEL PIPE Co.,Ltd.
China National Petroleum Corp
CNPC Bohai Equipment Manufacturing Co Ltd
Julong Steel Pipe Co Ltd
Original Assignee
Hebei Huayou Steel Pipe Design Institute Co Ltd
CNPC Bohai Equipment Manufacturing Co Ltd
Julong Steel Pipe Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei Huayou Steel Pipe Design Institute Co Ltd, CNPC Bohai Equipment Manufacturing Co Ltd, Julong Steel Pipe Co Ltd filed Critical Hebei Huayou Steel Pipe Design Institute Co Ltd
Priority to CN201310147327.7A priority Critical patent/CN103212952B/en
Publication of CN103212952A publication Critical patent/CN103212952A/en
Application granted granted Critical
Publication of CN103212952B publication Critical patent/CN103212952B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a manufacturing method of a super-large-diameter large-wall thick longitudinal submerged arc welded pipe. The super-large-diameter large-wall thick longitudinal submerged arc welded pipe is made of X80 hot-rolled stated steel plates according with the API5L-2007 (44 version) standard of the American petroleum institute in chemical composition percentage, and a microscopic structure of the super-large-diameter large-wall thick longitudinal submerged arc welded pipe is an AF+B organization. The manufacturing method of the super-large-diameter large-wall thick longitudinal submerged arc welded pipe comprises the following steps: automatic flaw detection of a steel plate, edge preparation, pre-springing, molding, pre-welding, inner welding and outer welding, a first ultrasonic wave automatic inspection, a first X-ray inspection, mechanical hole enlargement, pipe end processing, hydrostatic testing, edge preparation, a second ultrasonic inspection, a second X-ray inspection, a second pipe end ultrasonic manual inspection, an external dimension inspection, postweld heat treatment, an appearance inspection and anticorrosive coating. The manufacturing method of the super-large-diameter large-wall thick longitudinal submerged arc welded pipe has the advantages of solving various technical problems of the production of the super-large-diameter large-wall thick longitudinal submerged arc welded pipe through strict technical controlling of working procedures, and enabling performances of a produced steel pipe to completely meet the requirement of a national standard.

Description

The big wall thickness straight-line joint submerged arc welding tube of super large caliber manufacture method
Technical field
The present invention relates to straight-line joint submerged arc welding tube manufacturing technology field.
Background technology
Petroleum gas is as important energy source, and ratio shared in China's energy resource structure constantly increases, and demand is vigorous day by day.Utilizing long distance line that petroleum gas is transported to customer objective ground from the grown place, is a kind of safe, efficient and economic means of transportation, and this has become the main mode that land oil gas is carried at present.
The grade of steel of China's natural gas main pipeline is brought up to X80 by X52, the wall thickness of one-level area caliber φ 1219mm gas trunklines pipeline has reached 22mm, year displacement is 300 billion cubic meters, if the year displacement will be brought up to more than 450 billion cubic meters, main technological route has two: (1) adopts the technology path that improves discharge pressure, requires to bring up to more than the 17MPa from existing 12MPa discharge pressure.(2) adopt the technology path that increases the conveyance conduit bore, require to bring up to 1422 from existing 1219.
The world has several at the pipeline of the 45000000000 m3/a displacements of building and planning to build at present, as Muscovite Ba Funiankewo-Wuqia natural gas line, adopt the K65 grade of steel that is similar to X80, caliber φ 1420mm, discharge pressure 11.8MPa, about 50,000,000,000 m3/a of mono-tube design displacement.In addition, the pipeline of similar displacement is also being established in the North America, and as seen, the The Enlargement Tendency of welded tube bore is obvious.
The direct influence that the increase of caliber and pressure brings is the increase of thickness of steel pipe.The increase of thickness of steel pipe will bring difficulty to moulding, the welding of the rolling and steel pipe of steel plate.Therefore, make the big wall thickness straight-line joint submerged arc welding tube of super large caliber and also have certain defective technically.
Summary of the invention
The technical problem to be solved in the present invention provides the big wall thickness straight-line joint submerged arc welding tube of the super large caliber manufacture method that a kind of every performance meets standard-required fully.
For solving the problems of the technologies described above, the technical solution used in the present invention is:
The big wall thickness straight-line joint submerged arc welding tube of a kind of super large caliber manufacture method, it adopts chemical composition percentage to meet the API 5L-2007 of American Petroleum Institute (44 editions) standard, microscopic structure is the X80 hot-rolled state steel plate manufacturing of AF+B tissue, and its manufacturing process comprises the steps: steel plate automatic flaw detection, groove processing, pre-bending, moulding, prewelding, interior outside weld, ultrasonic wave automatic inspection for the first time, X-ray examination for the first time, machinery expanding, pipe end processing, the water pressure test, groove processing, ultrasonic examination for the second time, X-ray examination for the second time, pipe end ultrasonic manual examination (check) for the second time, appearance and dimension check, post weld heat treatment, visual examination and corrosion-inhibiting coating;
In the described groove manufacturing procedure, the steel plate angle of groove up and down is 34.75 °~35 °, and last groove depth is 10.75~11.25mm; The width of root face is 9.075mm~9.125mm, and angle is 4 °;
Described inside and outside welder's preface all adopts four Lincoln welds that steel pipe inboard and outside bevel for welding are welded, and gage of wire is 3.9~4.1mm, and speed of welding is 1.3~1.35m/min; Weld heat input is 55~56KJ/cm.
Described molding procedure adopts the JCO moulding, at first utilize the JCO make-up machine to carry out repeatedly punching press through half of the steel plate behind the pre-crimp, be pressed into " J " shape, then second half of steel plate carried out same repeatedly punching press, be pressed into " C " shape, the middle pressing one-time at whole steel plate makes it form " O " shape of opening at last; In the above-mentioned Sheet Metal Forming Technology, adopt the compacting number of times in 25~29 steps, single drafts 180~190mm.
Described inside and outside welder's preface all adopts four Lincoln welds that steel pipe inboard and outside bevel for welding are welded; First is dc reverse connection, electric current 1050~1150A, voltage 30~34V; Second for exchanging electric current 850~950A, voltage 32~36V; The 3rd for exchanging electric current 650~750A, voltage 38~42V; The 4th for exchanging electric current 550~650A, voltage 38~42V.
In the described machinery expanding operation steel pipe total length is carried out 0.5%~1.2% hole enlargement.
Beneficial effect of the present invention is as follows:
(1) by composition, tissue and heat treated control, make steel plate have high tenacity and good welding performance to the X80 steel plate.
(2) by in the JCO moulding process, according to steel plate width, thickness, intensity and die size, Accurate Analysis is determined rational punching press number of times and single drafts, the big wall thickness straight-line joint submerged arc welding tube of the super large caliber JCO forming process light plate resilience that has solved X80 grade of steel diameter and be φ 1422mm, wall thickness and be 30.8mm is little, a tubular difficult problem that is not easy to control, according to analysis result and field trial, analyze steel plate forming process spring-go amount, rationally determine draught per pass, make to have good circularity after the steel pipe moulding and body is directly spent.
(3) in the welding procedure, at first, guarantee that weld seam has the intensity of a little higher than mother metal and good toughness by selecting the special welding material.When determining welding parameter; take into full account in three wire bonds effect of each; by each electric current of reasonable setting, voltage, angle, distance between weldingwires and speed of welding, make weld seam obtain suitable depth of penetration and good shapes, help gas and covering slag come-up in the welding process simultaneously.On this basis,, each current/voltage is further optimized, taked lower welding wire energy, guarantee the performance of welding heat affected zone in order to reduce the influence of sweating heat to heat affected area toughness.Weld seam finally obtains based on tissue acicular ferrite and ferrite bainite, that have excellent toughness, and welding heat affected zone obtains the tissue of tiny granular bainite and ferrite bainite simultaneously, has solved Steel Welded Joint toughness problem.
(4) in the expanding technology, according to the apparent size situation after the steel pipe moulding, determine to obtain the enlarging rate of optimum efficiency by numerical analysis, verify again by field trial with to the result of correlated performance data analysis, determine best expanding technology, guarantee that apparent size and physicochemical property meet standard-required behind the pipe expanding, solved steel pipe when machinery expanding because the problem that work hardening causes intensity increase, toughness and uniform elongation to reduce, important appearance index such as also improved that pipe end circularity and body are directly spent simultaneously.
The specific embodiment
Embodiment
Employing chemical composition percentage meets the API 5L-2007 of American Petroleum Institute (44 editions) standard, microscopic structure is the X80 hot-rolled state steel plate of AF+B tissue, carrying out caliber is that 1422mm, wall thickness are the manufacturing of the straight-line joint submerged arc welding tube of 30.8mm, and concrete processing step is as follows:
(1) ultrasonic wave steel plate automatic flaw detection: utilize full-automatic steel plate ultrasonic test equipment, in the edges of boards 50mm scope of steel plate both sides and middle part is checked.
(2) mill limit, groove processing: the bevel angle up and down of steel plate is 35 °, and the width of root face is 9.1mm.The purpose of finished edge is to guarantee that welding process can complete penetration, forms suitable weld seam pattern, avoids occurring defectives such as lack of penetration in the high-speed welding process, guarantees the quality of welding point, the realization good quality and high output.Choose steel plate according to steel pipe intended diameter and thickness, and at the steel plate both sides milling bevel for welding of weld seam correspondence.
(3) pre-bending: require and the caliber size requirement according to steel pipe curvature, adopt pre-joggling machine that edges of boards are bent to satisfactory curvature.
(4) JCO moulding: adopting caliber is that φ 1422mm, wall thickness are the steel pipe of 30.8mm, at first utilize the JCO make-up machine to carry out repeatedly punching press through half of the steel plate behind the pre-crimp, be pressed into " J " shape, carry out same repeatedly punching press again with its second half, be pressed into " C " shape, the middle pressing one-time at whole steel plate makes it form " O " shape of opening at last; In the above-mentioned Sheet Metal Forming Technology, adopt the compacting number of times in 27 steps, single drafts 185mm.
(5) prewelding: by adjusting the position of joint close Prewelding machine pressure roller; make the bevel for welding of steel pipe is good after the moulding coupling together; guarantee that misalignment, gap size meet the requirements; adopt gas shield welding mode to weld simultaneously; form continuously, standard, stay-in-grade pre-welding line, guarantee inside and outside steel pipe welding operating mode stable when astute and able.
(6) interior outside weld: adopt four Lincoln welds to weld in steel pipe inboard and outside bevel for welding; First is dc reverse connection, electric current 1100A, voltage 32V; Second for exchanging electric current 900A, voltage 34V; The 3rd for exchanging electric current 700A, voltage 40V; The 4th for exchanging electric current 600A, voltage 40V; Gage of wire is 4.0mm; Speed of welding is 1.3~1.35m/min; Weld heat input is 55~56KJ/cm.
(7) pipe end ultrasonic manual examination (check) for the first time: weld seam in the pipe end 300mm scope and weld seam two side areas are carried out manual ultrasonic examination;
(8) ultrasonic wave automatic inspection for the first time: steel pipe inner and outer welding and heat affected area, weld seam both sides part after the welding are carried out ultrasonic examination;
(9) X-ray examination for the first time: the steel pipe inner and outer welding after adopting image processing system to welding carries out 100% industrial television inspection, guarantees flaw detection sensitivity.
(10) machinery expanding: the steel pipe total length is carried out 0.5%~1.2% hole enlargement to improve the apparent size precision of steel pipe,, and improve the internal stress distribution of steel pipe as ovality, linearity.
(11) pipe end processing: the steel pipe end face is processed, guaranteed smooth.For the good seal of next step water pressure test is got ready.
(12) water pressure test: steel pipe is carried out 100% hydrostatic test, and test pressure is 90%~100% of the regulation SMYS, checks the strength level of steel pipe and whether has leakage point.
(13) groove processing: the above-mentioned steel pipe that is up to the standards is carried out pipe end processing, reach the pipe end groove dimensional requirement of customer requirement.
(14) ultrasonic examination for the second time: steel pipe inner and outer welding behind hole enlargement, the hydraulic pressure and heat affected area, weld seam both sides part are carried out 100% inspection, to get rid of hole enlargement, the issuable defective of hydraulic pressure.
(15) X-ray examination for the second time: the steel pipe inner and outer welding behind hole enlargement, the hydraulic pressure carried out 100% industrial television inspection and pipe end film making and check, to get rid of hole enlargement, the issuable defective of hydraulic pressure.
(16) pipe end ultrasonic manual examination (check) for the second time: the body in the pipe end 300mm scope, weld seam and heat affected area, weld seam both sides part, groove face are checked.
(17) appearance and dimension check: the shaping steel tube apparent size is measured according to designing requirement.
(18) post weld heat treatment: heat treatment parameter butt welded seam and heat affected area, weld seam both sides part according to design are heat-treated, and discharge welding interior stress.
(19) outward appearance is through looking into and corrosion-inhibiting coating: the steel pipe that heat treatment is finished carries out the pipe end ovality and body is directly spent inspection, and qualified steel pipe carries out coating and preservative treatment according to designing requirement to steel pipe inwall or outer wall.
In sum, the technology control by each operation strictness, every performance of final steel pipe is met fully every requirement of " natural-gas transfer pipeline with OD1422mm X80 straight-line joint submerged arc welding tube technical conditions exposure draft ".

Claims (4)

1. the big wall thickness straight-line joint submerged arc welding tube of super large caliber manufacture method, it is characterized in that, it adopts chemical composition percentage to meet the API 5L-2007 of American Petroleum Institute (44 editions) standard, microscopic structure is the X80 hot-rolled state steel plate manufacturing of AF+B tissue, and its manufacturing process comprises the steps: steel plate automatic flaw detection, groove processing, pre-bending, moulding, prewelding, interior outside weld, ultrasonic wave automatic inspection for the first time, X-ray examination for the first time, machinery expanding, pipe end processing, the water pressure test, groove processing, ultrasonic examination for the second time, X-ray examination for the second time, pipe end ultrasonic manual examination (check) for the second time, appearance and dimension check, post weld heat treatment, visual examination and corrosion-inhibiting coating;
In the described groove manufacturing procedure, the steel plate angle of groove up and down is 34.75 °~35 °, and last groove depth is 10.75~11.25mm; The width of root face is 9.075mm~9.125mm, and angle is 4 °;
Described inside and outside welder's preface all adopts four Lincoln welds that steel pipe inboard and outside bevel for welding are welded, and gage of wire is 3.9~4.1mm, and speed of welding is 1.3~1.35m/min; Weld heat input is 55~56KJ/cm.
2. the big wall thickness straight-line joint submerged arc welding tube of super large caliber according to claim 1 manufacture method, it is characterized in that, described molding procedure adopts the JCO moulding, at first utilize the JCO make-up machine to carry out repeatedly punching press through half of the steel plate behind the pre-crimp, be pressed into " J " shape, then second half of steel plate carried out same repeatedly punching press, be pressed into " C " shape, make " O " shape of its formation opening at last at middle the pressing one-time of whole steel plate; In the above-mentioned Sheet Metal Forming Technology, adopt the compacting number of times in 25~29 steps, single drafts 180~190mm.
3. the big wall thickness straight-line joint submerged arc welding tube of super large caliber according to claim 1 manufacture method is characterized in that, described inside and outside welder's preface all adopts four Lincoln welds that steel pipe inboard and outside bevel for welding are welded; First is dc reverse connection, electric current 1050~1150A, voltage 30~34V; Second for exchanging electric current 850~950A, voltage 32~36V; The 3rd for exchanging electric current 650~750A, voltage 38~42V; The 4th for exchanging electric current 550~650A, voltage 38~42V.
4. the big wall thickness straight-line joint submerged arc welding tube of super large caliber according to claim 1 manufacture method is characterized in that, in the described machinery expanding operation steel pipe total length is carried out 0.5%~1.2% hole enlargement.
CN201310147327.7A 2013-04-25 2013-04-25 Super large caliber large wall thickness straight-line joint submerged arc welding tube manufacture method Active CN103212952B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310147327.7A CN103212952B (en) 2013-04-25 2013-04-25 Super large caliber large wall thickness straight-line joint submerged arc welding tube manufacture method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310147327.7A CN103212952B (en) 2013-04-25 2013-04-25 Super large caliber large wall thickness straight-line joint submerged arc welding tube manufacture method

Publications (2)

Publication Number Publication Date
CN103212952A true CN103212952A (en) 2013-07-24
CN103212952B CN103212952B (en) 2015-09-16

Family

ID=48811284

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310147327.7A Active CN103212952B (en) 2013-04-25 2013-04-25 Super large caliber large wall thickness straight-line joint submerged arc welding tube manufacture method

Country Status (1)

Country Link
CN (1) CN103212952B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103521549A (en) * 2013-10-07 2014-01-22 宝鸡石油钢管有限责任公司 Manufacturing method of X100 high-steel-grade large-opening-diameter thick-wall longitudinal submerged-arc welded pipe
CN105834697A (en) * 2016-05-20 2016-08-10 中国石油大学(华东) Manufacturing method of X80 pipeline steel straight welded pipe
CN106694609A (en) * 2015-11-16 2017-05-24 宝鸡石油钢管有限责任公司 Method for manufacturing X80-stage phi1422 mm longitudinal submerged arc welding pipe
CN106694610A (en) * 2017-03-29 2017-05-24 无锡市蓝博金属制品有限公司 Preparation process of oil filler pipe
CN108581375A (en) * 2018-04-08 2018-09-28 太原科技大学 A kind of preparation method having the stainless steel and carbon steel composite tube that cover side
CN109530855A (en) * 2018-12-24 2019-03-29 合肥紫金钢管股份有限公司 The big mouth longitudinal submerged arc welded pipe welding technique of offshore wind farm
CN111719085A (en) * 2020-06-30 2020-09-29 中国石油集团渤海石油装备制造有限公司 Marine vessel and method of making same
CN111872645A (en) * 2020-08-06 2020-11-03 中国石油天然气集团有限公司 Manufacturing method of X80 steel grade OD1422mm large-wall-thickness straight welded pipe
CN114535939A (en) * 2022-03-22 2022-05-27 湖南胜利湘钢钢管有限公司 Method for manufacturing longitudinal submerged arc welded pipe

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04182094A (en) * 1990-11-14 1992-06-29 Sumitomo Metal Ind Ltd Circumferential welding method for high strength steel pipe
CN101204720A (en) * 2007-12-10 2008-06-25 华北石油管理局第一机械厂 Manufacture method of X80 pipeline JCOE direct sew submerged arc welding tube
CN101205597A (en) * 2007-12-10 2008-06-25 华北石油管理局第一机械厂 Method for manufacturing X100 pipeline steel submerged arc straight weld pipe
CN102303195A (en) * 2011-08-25 2012-01-04 中国石油集团渤海石油装备制造有限公司 Welding wire for X80 steel low-temperature resistant steel pipe and pipe fittings
CN102310119A (en) * 2011-09-02 2012-01-11 中国石油集团渤海石油装备制造有限公司 Manufacturing method of X65 pipeline steel longitudinal submerged arc welded pipe for undersea use
CN102397941A (en) * 2011-11-14 2012-04-04 中国石油集团渤海石油装备制造有限公司 Manufacturing method for X90 pipeline steel longitudinal submerged arc welding pipe

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04182094A (en) * 1990-11-14 1992-06-29 Sumitomo Metal Ind Ltd Circumferential welding method for high strength steel pipe
CN101204720A (en) * 2007-12-10 2008-06-25 华北石油管理局第一机械厂 Manufacture method of X80 pipeline JCOE direct sew submerged arc welding tube
CN101205597A (en) * 2007-12-10 2008-06-25 华北石油管理局第一机械厂 Method for manufacturing X100 pipeline steel submerged arc straight weld pipe
CN102303195A (en) * 2011-08-25 2012-01-04 中国石油集团渤海石油装备制造有限公司 Welding wire for X80 steel low-temperature resistant steel pipe and pipe fittings
CN102310119A (en) * 2011-09-02 2012-01-11 中国石油集团渤海石油装备制造有限公司 Manufacturing method of X65 pipeline steel longitudinal submerged arc welded pipe for undersea use
CN102397941A (en) * 2011-11-14 2012-04-04 中国石油集团渤海石油装备制造有限公司 Manufacturing method for X90 pipeline steel longitudinal submerged arc welding pipe

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103521549A (en) * 2013-10-07 2014-01-22 宝鸡石油钢管有限责任公司 Manufacturing method of X100 high-steel-grade large-opening-diameter thick-wall longitudinal submerged-arc welded pipe
CN103521549B (en) * 2013-10-07 2015-09-16 宝鸡石油钢管有限责任公司 A kind of manufacture method of X100 Hi-grade steel heavy caliber thick wall straight-line joint submerged arc welding tube
CN106694609A (en) * 2015-11-16 2017-05-24 宝鸡石油钢管有限责任公司 Method for manufacturing X80-stage phi1422 mm longitudinal submerged arc welding pipe
CN105834697A (en) * 2016-05-20 2016-08-10 中国石油大学(华东) Manufacturing method of X80 pipeline steel straight welded pipe
CN106694610A (en) * 2017-03-29 2017-05-24 无锡市蓝博金属制品有限公司 Preparation process of oil filler pipe
CN108581375A (en) * 2018-04-08 2018-09-28 太原科技大学 A kind of preparation method having the stainless steel and carbon steel composite tube that cover side
CN109530855A (en) * 2018-12-24 2019-03-29 合肥紫金钢管股份有限公司 The big mouth longitudinal submerged arc welded pipe welding technique of offshore wind farm
CN109530855B (en) * 2018-12-24 2021-09-10 合肥紫金钢管股份有限公司 Welding method of large-opening longitudinal submerged arc welded steel pipe for offshore wind power
CN111719085A (en) * 2020-06-30 2020-09-29 中国石油集团渤海石油装备制造有限公司 Marine vessel and method of making same
CN111872645A (en) * 2020-08-06 2020-11-03 中国石油天然气集团有限公司 Manufacturing method of X80 steel grade OD1422mm large-wall-thickness straight welded pipe
CN114535939A (en) * 2022-03-22 2022-05-27 湖南胜利湘钢钢管有限公司 Method for manufacturing longitudinal submerged arc welded pipe

Also Published As

Publication number Publication date
CN103212952B (en) 2015-09-16

Similar Documents

Publication Publication Date Title
CN103212952B (en) Super large caliber large wall thickness straight-line joint submerged arc welding tube manufacture method
CN102310119B (en) Manufacturing method of X65 pipeline steel longitudinal submerged arc welded pipe for undersea use
CN101204720B (en) Manufacture method of X80 pipeline JCOE direct sew submerged arc welding tube
CN102950432A (en) Q245R longitudinal submerged arc welded natural gas blow-down pipe manufacturing method
CN103540867B (en) A kind of X80 level straight-line joint submerged arc welding tube of anti-H 2 S stress corrosion and manufacture method thereof
CN101205597B (en) Method for manufacturing X100 pipeline steel submerged arc straight weld pipe
CN103556054B (en) A kind of high strength medium caliber heavy wall Submarine linepipe and manufacture method thereof
CN103556079B (en) The high strength marine riser supervisor that a kind of anti-fatigue performance is excellent and manufacture method thereof
CN105817844B (en) The manufacture method of X80 pipeline steel spiral welded pipes
CN103240512B (en) Welding technology for K65 low-temperature-resistant hot bend pipe mains
CN103521549B (en) A kind of manufacture method of X100 Hi-grade steel heavy caliber thick wall straight-line joint submerged arc welding tube
CN102248023A (en) Method for manufacturing X70 steel-level large deformation-resistant longitudinally submerged arc welding pipe
CN103084427B (en) Manufacturing method of hardenability steel tube
CN102330034A (en) X65MS steel-grade spiral welded tube for acidic corrosion environment and manufacturing method thereof
CN101205596A (en) X120 pipeline steel submerged arc straight weld pipe and manufacture technique thereof
CN102397941A (en) Manufacturing method for X90 pipeline steel longitudinal submerged arc welding pipe
CN103521550A (en) Manufacturing method of X90 grade pipeline steel large-opening-diameter thick-wall longitudinal submerged-arc welded pipe
CN105880952A (en) Production process of longitudinal submerged arc welded pipe for oil and gas transmission
CN105834697B (en) The manufacture method of X80 pipe line steel ERWs
CN106540987A (en) A kind of X80 levels pipe line steel heavy caliber thick wall spiral submerged arc welded pipe manufacturing method
CN103397253A (en) Hydrogen sulfide corrosion resistant high-strength X70MS longitudinal submerged arc welded tube and manufacturing method thereof
CN108620448B (en) Method for manufacturing large-diameter and high-strength spiral welded pipe
CN106540986A (en) A kind of X90 levels pipe line steel large-caliber spiral submerged-arc welded (SAW) pipe manufacture method
CN102000906A (en) Longitudinal submerged arc welding production line for stainless steel tubes and carbon steel tubes
CN107803574A (en) A kind of X100 levels pipe line steel large-caliber spiral submerged-arc welded (SAW) pipe manufacture method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200921

Address after: 100007 Beijing, Dongzhimen, North Street, No. 9, No.

Patentee after: CHINA NATIONAL PETROLEUM Corp.

Patentee after: CNPC Bohai Petroleum Equipment Manufacturing Co.,Ltd.

Patentee after: NANJING JULONG STEEL PIPE Co.,Ltd.

Patentee after: JULONG STEEL PIPE Co.,Ltd.

Address before: 300457, No. 3, Tianjin TEDA service outsourcing industry park, No. 19 West Ring Road, Tianjin, Tanggu

Patentee before: CNPC Bohai Petroleum Equipment Manufacturing Co.,Ltd.

Patentee before: NANJING JULONG STEEL PIPE Co.,Ltd.

Patentee before: JULONG STEEL PIPE Co.,Ltd.

Patentee before: HEBEI HUAYOU STEEL PIPE DESIGN RESEARCH INSTITUTE Co.,Ltd.