Bridge pier column under a kind of high salt concentration solution corrosion environment
Technical field
The present invention relates to a kind of bridge construction, specifically, relate to a kind of bridge pier column anti-corrosion structure.
Background technology
" highway engineering concrete structure anticorrosion technique standard (JTG/T B07-01-2006) " stipulates that clearly " the anticorrosion durability of highway concrete structure should design according to the different designs base period of structure, different environment for use classification and function grade thereof.The residing local environment of different parts in the different component in the same structure and same member has the different time, should give and treats with a certain discrimination.The etch-proof durability Design of concrete structure should guarantee the applicability of structure in its long-term service life, the needs of recoverability and safety, the maintenance that must propose in the use requires with detecting "; simultaneously " highway bridge and culvert design general specification " to propose the basic design principle of bridge be " advanced technology, safe and reliable, be suitable for durable, economical rationality ", so the durable anticorrosion design of highway bridge member is must obligato one to design link.
Standard is according to the different design reference period of bridge member, environment for use classification and environmental activity grade, etch-proof durability Design to bridge member has proposed concrete regulation requirement, standard can take additional anticorrosive measure to carry out durability Design at being subjected to environment seriously to act on the member position of (D, E and F level) in the important engineering simultaneously.
The concrete-bridge pier stud corrosion situation that is under the high salt concentration solution corrosion environment is extremely serious, therefore this concrete-bridge pier stud durability Design has been proposed challenge.The pier stud corrosiveness grade of high salt concentration solution corrosion ambient conditions is higher, is generally the F level.According to " highway engineering concrete structure anticorrosion technique standard JTG/T B07-01-2006 " requirement, for being subjected to environment seriously to act on the structure position of (D, E and F level) in the important engineering, except the essential structure of satisfying standard requires and materials ' durability requires, also need take necessary additional anticorrosive measure.
Bridge pier column is positioned at the fluctuation of water table district, and the corrosion that suffers mainly is near high salt concentration crystal corrosion, freeze thawing and the carbonization the face of land.The additional anticorrosive measure of bridge pier column routine has the antiseptic concrete surface layer, outer Baogang casing etc., but the antiseptic concrete surface layer is lower than 20 years general service life, and outer Baogang casing steel using amount is big, therefore the additional anticorrosive measure cost of this kind is higher, and the later maintenance workload is big.
Summary of the invention
The present invention will solve is bridge pier column life requirement technical problems of high under the high salt concentration solution corrosion environment, and a kind of bridge pier column is provided, and can improve structure durability, reduces the later maintenance difficulty, easy construction, and construction costs is low.
In order to solve the problems of the technologies described above, the present invention is achieved by following technical scheme:
Bridge pier column under a kind of high salt concentration solution corrosion environment comprises the pier stud body that is arranged on the cushion cap, and described pier stud body periphery is provided with the post boots by described cushion cap end face to the scope more than the peak level of salt pond; Described post boots and described pier stud body have at interval and at interval in be perfused with sealing compound; Described post boots top is provided with the rain cover that is fixed on the described pier stud body, and described rain cover has low domatic of the high outer rim of inner edge, and its external diameter is greater than the external diameter of described post boots.
Described post boots external surface is coated with anti-corrosion material.
Described anti-corrosion material is silicon rubber emulsion, polyurea elastomer or fluorocarbon resin coating.
The wall thickness of described post boots is 20cm~35cm.
Described post boots end face is positioned at the above 1m~1.5m of salt pond peak level.
The clear distance of described post boots and described pier stud body is 1cm~5cm.
The invention has the beneficial effects as follows:
(1) the present invention isolates high salt concentration solution corrosion pier stud with post boots, the rain cover anti-corrosion protection member as pier stud, prevents from destroying agent structure, guarantees agent structure safety, prolongs the application life of bridge pier column, reduces its later stage maintenance difficulties;
(2) post boots of the present invention are concrete structure, easy construction, and the later maintenance workload is little, and the engineering comprehensive cost is low;
(3) post boots of the present invention can be controlled its anticorrosion time limit by the design of thickness, can either reach the effect of permanent protection in the application life of bridge pier column, the material that avoids waste again, anticorrosion ability reliability height;
(4) post boots of the present invention and pier stud are the separate type member, and participation structure is not stressed, reduce bridge pier column antidetonation plastic hinge design difficulty, particularly after geological process is destroyed, repair easily.
Description of drawings
Fig. 1 is the structural representation of bridge pier column provided by the present invention;
Fig. 2 is the profile of pier stud;
Fig. 3 is the profile of post boots.
Among the figure: 1: the pier stud body; 2: the post boots; 3: cushion cap; 4: pile foundation; 5: rain cover; 6: sealing compound.
The specific embodiment
The present invention is described in further detail below by specific embodiment, and following examples can make those skilled in the art more fully understand the present invention, but do not limit the present invention in any way.
As shown in Figure 1 to Figure 3, present embodiment discloses the bridge pier column under a kind of high salt concentration solution corrosion environment, comprises the pier stud body 1 that is arranged on the cushion cap 3, and pier stud body 1 pier stud routinely carries out force analysis and sectional reinforcement.Pier stud body 1 bottom is positioned at fluctuation of water table district, salt pond, this position is owing to contact with atmosphere, and alternation of wetting and drying, the saline solution repeated crystallization, corrosion situation for structure is the most serious, therefore in above 1m~1.5m scope post boots 2 is set to the salt pond peak level by cushion cap 3 end faces in the periphery of pier stud body 1 bottom.Post boots 2 are the reinforced concrete structure of tubular, by constructing configuration reinforcement, build simultaneously with pier stud body 1, make post boots 2 and cushion cap 3 seams closely knit, guarantee pouring quality, improve protection effect, and the post boots 2 of monobloc cast are convenient to later stage inspection maintenance simultaneously.
Clear distance between post boots 2 and pier stud body 1 external surface is 2cm, and is perfused with HM99 sealing compound 6 in post boots 2, and sealing compound 6 can prevent effectively that corrosive medium from entering in the space between pier stud body 1 and the post boots 2, prevents that pier stud body 1 is corroded.
Generally, the clear distance of post boots 2 and pier stud body 1 is in 1cm~5cm scope, and the pier stud body 1 stressed post boots 2 that are not subjected to of bridge influence, and pier stud body 1 anti-seismic construction requires design routinely.Post boots 2 wall thickness in 20cm~35cm scope, its concrete quantity is by the control of the anticorrosion time limit of design.
Post boots 2 tops are provided with rain cover 5, and rain cover 5 is fixed in pier stud body 1 by stirrup.Rain cover 5 has low domatic of the high outer rim of inner edge, and its external diameter stretches out in post boots outside, avoids rainwater to infiltrate in the post boots 2 wall chambeies, thereby influences the durability of member.
On the basis of above measure; further to being exposed to salt pond water and being subjected to post boots 2 external surfaces of salt pond water alternation of wetting and drying effect to carry out the outer processing that is coated with anti-corrosion material; to resist the abominable corrosive environment in saltern; prolong the post boots 2 protection time limits; reduce later stage engineering maintenance work amount, the agent structure external surface of pier stud body 1 adopts the protection of silane impregnation process simultaneously.Anti-corrosion material can be selected silicon rubber emulsion, polyurea elastomer, fluorocarbon resin coating etc. for use, and every have good alkali resistance, tack and corrosion proof anti-corrosion material and all can be used for the present invention.
The above-mentioned bridge substructure of high salt concentration solution corrosion that prevents is implemented by the Integratively casting method, i.e. simultaneously colligation pier stud body 1 cage of reinforcement and post boots 2 cage of reinforcement, the hard plastic plate is set as the template between pier stud body 1 and the post boots 2 between two cage of reinforcement, post boots 2 cage of reinforcement arrange exterior sheathing outward.Build the concrete of pier stud body 1 and post boots 2 simultaneously, treat concrete curing after, perfusion sealing compound 6 is installed rain cover 5 again, easy construction, quality is good.
Although by reference to the accompanying drawings the preferred embodiments of the present invention are described above; but the present invention is not limited to the above-mentioned specific embodiment; the above-mentioned specific embodiment only is schematic; be not restrictive; those of ordinary skill in the art is under enlightenment of the present invention; not breaking away under the scope situation that aim of the present invention and claim protect, can also make the concrete conversion of a lot of forms, these all belong within protection scope of the present invention.