CN103174093A - Mounting device and mounting method of steel box girder in support zone - Google Patents

Mounting device and mounting method of steel box girder in support zone Download PDF

Info

Publication number
CN103174093A
CN103174093A CN2013100808466A CN201310080846A CN103174093A CN 103174093 A CN103174093 A CN 103174093A CN 2013100808466 A CN2013100808466 A CN 2013100808466A CN 201310080846 A CN201310080846 A CN 201310080846A CN 103174093 A CN103174093 A CN 103174093A
Authority
CN
China
Prior art keywords
steel box
box girder
steel case
installation
platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100808466A
Other languages
Chinese (zh)
Inventor
张鸿
彭琳琳
唐衡
何承海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
Original Assignee
CCCC Second Harbor Engineering Co
CCCC SHEC Fourth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co, CCCC SHEC Fourth Engineering Co Ltd filed Critical CCCC Second Harbor Engineering Co
Priority to CN2013100808466A priority Critical patent/CN103174093A/en
Publication of CN103174093A publication Critical patent/CN103174093A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种支架区钢箱梁的安装装置及其安装方法,属于桥梁施工领域,装置包括搭设在桥梁的纵向中轴线上的临时支架平台,以及锚固在所述临时支架平台上的变幅式桥面吊机,还包括环绕所述临时支架平台布置的滑移支架平台,所述滑移支架平台顶部平台平面上铺设固定有相连接的横向滑移轨道及两纵向滑移轨道。安装方法,依次包括以下步骤:布置安装装置;变幅式桥面吊机起吊钢箱梁;将分块钢箱梁放置在滑移支架平台上;分块钢箱梁通过横纵向滑移轨道滑移至预定的钢箱梁安装位置;重复,完成支架区梁段的安装。本发明的目的在于:提出一种在不具备大型起重船或者起重吊车的驻位条件的情况下,进行支架区分幅式钢箱梁的安装施工的装置及其方法。

Figure 201310080846

The invention discloses an installation device and an installation method for a steel box girder in a support area, belonging to the field of bridge construction. The width-type bridge deck crane also includes a sliding support platform arranged around the temporary support platform, and the top platform plane of the sliding support platform is laid and fixed with a connected transverse sliding track and two longitudinal sliding tracks. The installation method includes the following steps in turn: arranging the installation device; hoisting the steel box girder by the luffing deck crane; placing the segmented steel box girder on the sliding support platform; Move to the predetermined steel box girder installation location; repeat to complete the installation of the beam section in the support area. The object of the present invention is to propose a device and method for installing and constructing a frame-dividing-width steel box girder without the parking conditions of a large-scale lifting ship or a lifting crane.

Figure 201310080846

Description

一种支架区钢箱梁的安装装置及其安装方法An installation device and installation method for a steel box girder in a support area

技术领域 technical field

本发明属于桥梁施工领域,尤其涉及桥梁建造过程中,支架区分幅式钢箱梁的安装施工。 The invention belongs to the field of bridge construction, and in particular relates to the installation and construction of a support section-width steel box girder in the bridge construction process.

背景技术 Background technique

1)传统支架区钢箱梁安装装置及其工艺: 1) Installation device and technology of steel box girder in traditional support area:

钢箱梁做为桥梁结构中承受桥面荷载的重要结构物,越来越多的被广泛采用。传统支架区整体式或分幅式钢箱梁往往采用大型起重船舶或者起重吊车,将运输至现场的钢箱梁起吊并抬升后,通过旋转起重大臂的方式将钢箱梁搁置在预先搭设的钢箱梁支架上。 Steel box girder, as an important structure bearing bridge deck load in bridge structure, is widely used more and more. Integral or segmented steel box girders in the traditional support area often use large-scale lifting ships or cranes to hoist and lift the steel box girders transported to the site, and then place the steel box girders on the pre-set by rotating the lifting boom. erected on steel box girder supports.

2)传统施工工艺的局限性: 2) Limitations of traditional construction techniques:

传统方法施工时,往往需要采用大型起重船或者起重吊车。当现场水文条件恶劣,不具备大型起重船或者起重吊车的驻位条件时,钢箱梁往往无法吊装。传统工艺受条件限制较大。 In the traditional method of construction, it is often necessary to use large cranes or cranes. When the on-site hydrological conditions are bad and there are no parking conditions for large-scale lifting ships or lifting cranes, steel box girders often cannot be hoisted. Traditional crafts are limited by conditions.

发明内容 Contents of the invention

本发明的目的在于:提出一种在不具备大型起重船或者起重吊车的驻位条件的情况下,进行支架区分幅式钢箱梁的安装施工的装置及其方法。 The object of the present invention is to propose a device and method for installing and constructing a frame-dividing-width steel box girder without the parking conditions of a large-scale lifting ship or a lifting crane.

本发明目的通过下述技术方案来实现: The object of the invention is achieved through the following technical solutions:

一种支架区钢箱梁的安装装置,包括搭设在桥梁的纵向中轴线上的临时支架平台,且所述临时支架平台位于左右幅钢箱梁的分幅的中间空档,以及锚固在所述临时支架平台上的变幅式桥面吊机,且所述变幅式桥面吊机也驻位于桥梁的纵向中轴线上,还包括环绕所述临时支架平台布置的滑移支架平台,所述滑移支架平台顶部平台平面上铺设固定有相连接的横向滑移轨道及两纵向滑移轨道,且所述两纵向滑移轨道位置分别对应左右幅钢箱梁位置。 An installation device for a steel box girder in a support area, comprising a temporary support platform erected on the longitudinal central axis of the bridge, and the temporary support platform is located in the middle space of the framing of the left and right steel box girders, and is anchored on the The luffing bridge deck crane on the temporary support platform, and the luffing bridge deck crane is also located on the longitudinal central axis of the bridge, and also includes a sliding support platform arranged around the temporary support platform, the A horizontal sliding track and two longitudinal sliding tracks connected to each other are laid and fixed on the top platform plane of the sliding support platform, and the positions of the two longitudinal sliding tracks correspond to the positions of the left and right steel box girders respectively.

一种使用前述安装装置安装支架区钢箱梁的安装方法,依次包括以下步骤: An installation method for installing a steel box girder in a support area by using the aforementioned installation device, comprising the following steps in sequence:

1)布置所述安装装置; 1) arrange the installation device;

2)运输分块钢箱梁至设计位置,变幅式桥面吊机变幅下勾、连接,起吊钢箱梁; 2) Transport the segmented steel box girder to the design position, and the luffing bridge deck crane lowers the hook and connects to lift the steel box girder;

3)通过变幅式桥面吊机的变幅功能,将分块钢箱梁放置在滑移支架平台上; 3) Through the luffing function of the luffing deck crane, place the segmented steel box girder on the sliding support platform;

4)分块钢箱梁通过滑移支架平台上的横向滑移轨道横向滑移至纵向滑移轨道,再通过纵向滑移轨道纵向滑移至预定的钢箱梁安装位置; 4) The segmented steel box girder slides horizontally to the longitudinal sliding track through the horizontal sliding track on the sliding support platform, and then slides longitudinally to the predetermined steel box girder installation position through the longitudinal sliding track;

5)重复第2-4步,完成多片分块钢箱梁的起吊和滑移工作; 5) Repeat steps 2-4 to complete the lifting and sliding work of multi-piece steel box girders;

6)重复第5步,完成对称一片梁段的安装; 6) Repeat step 5 to complete the installation of a symmetrical beam segment;

7)重复第6步,完成支架区梁段的安装。 7) Repeat step 6 to complete the installation of the beam section in the support area.

作为优选方式,所述变幅式桥面吊机锚固位置的高度超过安装完成后的钢箱梁高度。 As a preferred manner, the height of the anchoring position of the luffing deck crane exceeds the height of the steel box girder after installation.

上述方案中,避免钢箱梁在滑移过程中受到阻碍。 In the above scheme, the steel box girder is prevented from being hindered during the sliding process.

工作过程为:单片钢箱梁通过变幅式桥面吊机起吊后,通过预设的横、纵向滑移轨道,横移和纵移两次滑移到位。该方法既适用于索塔支架区钢箱梁安装,也适用于边跨支架区钢箱梁安装。 The working process is as follows: After the single-piece steel box girder is hoisted by the luffing deck crane, it slides into place twice through the preset horizontal and vertical sliding tracks. This method is not only applicable to the steel box girder installation in the tower support area, but also suitable for the steel box girder installation in the side span support area.

本发明的有益效果:桥面吊机跨中一次就位无需挪位即可实现支架区全部钢箱梁安装。安装方便,无需大型的起重船舶和起重吊车。变幅式桥面吊机安装完支架区钢箱梁后,可就地周转至悬臂钢箱梁安装,不额外增加桥面吊机购买成本,施工费用大幅降低。 The beneficial effect of the present invention is that the bridge deck crane can be installed in the mid-span at one time without displacement, and all the steel box girders in the support area can be installed. It is easy to install and does not require large lifting ships and cranes. After the steel box girder in the support area is installed by the luffing deck crane, it can be transferred to the cantilever steel box girder on the spot for installation, without additional purchase cost of the deck crane, and the construction cost is greatly reduced.

附图说明 Description of drawings

图1是本发明实施例支架区钢箱梁安装装置的结构示意图; Fig. 1 is the structural representation of the installation device of the steel box girder in the support area of the embodiment of the present invention;

图2是本发明实施例支架区钢箱梁安装方法的步骤1的示意图; Fig. 2 is the schematic diagram of step 1 of the steel box girder installation method in the support area of the embodiment of the present invention;

图3是图2的俯视图; Fig. 3 is the top view of Fig. 2;

图4是本发明实施例支架区钢箱梁安装方法的步骤2的示意图; Fig. 4 is the schematic diagram of step 2 of the steel box girder installation method in the support area of the embodiment of the present invention;

图5是图4的俯视图; Figure 5 is a top view of Figure 4;

图6是本发明实施例支架区钢箱梁安装方法的步骤3的示意图; Fig. 6 is a schematic diagram of step 3 of the installation method of the steel box girder in the support area of the embodiment of the present invention;

图7是图6的俯视图; Figure 7 is a top view of Figure 6;

图8是本发明实施例支架区钢箱梁安装方法的步骤4的示意图; Fig. 8 is a schematic diagram of step 4 of the installation method of the steel box girder in the support area of the embodiment of the present invention;

图9是图8的俯视图; Figure 9 is a top view of Figure 8;

图10是本发明实施例支架区钢箱梁安装方法的步骤5的示意图; Fig. 10 is a schematic diagram of step 5 of the method for installing a steel box girder in the support area according to an embodiment of the present invention;

图11是图10的俯视图; Figure 11 is a top view of Figure 10;

图12是本发明实施例支架区钢箱梁安装方法的步骤6的示意图; Fig. 12 is a schematic diagram of step 6 of the method for installing a steel box girder in the support area according to an embodiment of the present invention;

图13是图12的俯视图; Figure 13 is a top view of Figure 12;

图14是本发明实施例支架区钢箱梁安装方法的步骤7的示意图; Fig. 14 is a schematic diagram of step 7 of the method for installing a steel box girder in the bracket area according to an embodiment of the present invention;

图15是图14的俯视图; Figure 15 is a top view of Figure 14;

其中1为变幅式桥面吊机、2为临时支架平台、3为滑移支架平台、4为纵向滑移轨道、5为横向滑移轨道、6为桥梁的纵向中轴线、7为钢箱梁。 Among them, 1 is the luffing bridge deck crane, 2 is the temporary support platform, 3 is the sliding support platform, 4 is the longitudinal sliding track, 5 is the horizontal sliding track, 6 is the longitudinal axis of the bridge, and 7 is the steel box beam.

具体实施方式 Detailed ways

下列非限制性实施例用于说明本发明。 The following non-limiting examples illustrate the invention.

如图1至15所示,一种支架区钢箱梁的安装装置,包括搭设在桥梁的纵向中轴线6上的临时支架平台2,且临时支架平台2位于左右幅钢箱梁7的分幅的中间空档,以及锚固在临时支架平台2上的变幅式桥面吊机1,且变幅式桥面吊机1也驻位于桥梁的纵向中轴线6上,还包括环绕临时支架平台2布置的滑移支架平台3,滑移支架平台3顶部平台平面上铺设固定有相连接的横向滑移轨道5及两纵向滑移轨道4,且两纵向滑移轨道4位置分别对应左右幅钢箱梁7位置。 As shown in Figures 1 to 15, an installation device for a steel box girder in the support area includes a temporary support platform 2 erected on the longitudinal central axis 6 of the bridge, and the temporary support platform 2 is located at the framing of the left and right steel box girders 7 and the luffing deck crane 1 anchored on the temporary support platform 2, and the luffing deck crane 1 is also located on the longitudinal central axis 6 of the bridge, and also includes the temporary support platform 2 Arranged sliding support platform 3, the top platform of the sliding support platform 3 is laid and fixed with a connected horizontal sliding track 5 and two longitudinal sliding tracks 4, and the positions of the two longitudinal sliding tracks 4 correspond to the left and right steel boxes respectively Beam 7 position.

如图2至15所示,一种使用前述安装装置安装支架区钢箱梁的安装方法,依次包括以下步骤: As shown in Figures 2 to 15, an installation method for installing the steel box girder in the bracket area using the aforementioned installation device includes the following steps in sequence:

1)布置所述安装装置,其中变幅式桥面吊机1锚固位置的高度超过安装完成后的钢箱梁7高度,如图2、3所示; 1) Arrange the installation device, wherein the height of the anchorage position of the luffing deck crane 1 exceeds the height of the steel box girder 7 after installation, as shown in Figures 2 and 3;

2)运输分块钢箱梁7至设计位置,变幅式桥面吊机1变幅下勾、连接,起吊钢箱梁7,如图4、5所示; 2) Transport the segmented steel box girder 7 to the design position, hook and connect the luffing deck crane 1 to lift the steel box girder 7, as shown in Figures 4 and 5;

3)通过变幅式桥面吊机1的变幅功能,将分块钢箱梁7放置在滑移支架平台3上,如图6、7所示; 3) Through the luffing function of the luffing deck crane 1, the segmented steel box girder 7 is placed on the sliding support platform 3, as shown in Figures 6 and 7;

4)分块钢箱梁7通过滑移支架平台3上的横向滑移轨道5横向滑移至纵向滑移轨道4,再通过纵向滑移轨道4纵向滑移至预定的钢箱梁安装位置,如图8、9所示; 4) The segmented steel box girder 7 slides horizontally to the longitudinal sliding track 4 through the horizontal sliding track 5 on the sliding support platform 3, and then slides longitudinally to the predetermined steel box girder installation position through the longitudinal sliding track 4, As shown in Figures 8 and 9;

5)重复第2-4步,完成多片分块钢箱梁7的起吊和滑移工作,如图10、11所示; 5) Repeat steps 2-4 to complete the lifting and sliding work of the multi-piece steel box girder 7, as shown in Figures 10 and 11;

6)重复第5步,完成对称一片梁段的安装,如图12、13所示; 6) Repeat step 5 to complete the installation of a symmetrical beam section, as shown in Figures 12 and 13;

7)重复第6步,完成支架区梁段的安装,如图14、15所示。 7) Repeat step 6 to complete the installation of the beam section in the support area, as shown in Figures 14 and 15.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。 The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principles of the present invention should be included in the protection of the present invention. within range.

Claims (3)

1. the erecting device of a rack area steel case beam, it is characterized in that: comprise the falsework platform of setting up on the longitudinal central axis line of bridge, and described falsework platform is positioned at the middle neutral gear of the framing of left and right width steel case beam, and be anchored at amplitude variation type erection crane on described falsework platform, and described amplitude variation type erection crane is also stayed and is positioned on the longitudinal central axis line of bridge, also comprise the slippage bracket platform of arranging around described falsework platform, lay on described slippage bracket table top platform plane and be fixed with horizontal sliding track and the two straight skidding tracks that are connected, and described two straight skidding orbital positions are width steel case beam position, corresponding left and right respectively.
2. a right to use requires the mounting method of 1 described erecting device mounting bracket district steel case beam, it is characterized in that comprising the following steps successively:
1) arrange described erecting device;
2) transportation piecemeal steel case beam to design attitude, hooks under amplitude variation type erection crane luffing, connects hoisting steel case beam;
3) by the luffing function of amplitude variation type erection crane, piecemeal steel case beam is placed on the slippage bracket platform;
4) piecemeal steel case beam by the horizontal sliding track horizontal sliding on the slippage bracket platform to the straight skidding track, then by straight skidding track straight skidding to predetermined steel pile equipment position;
5) repeat the 2-4 step, complete lifting and the slippage work of multi-disc piecemeal steel case beam;
6) repeated for the 5th step, complete the installation of symmetrical a slice beam section;
7) repeated for the 6th step, complete the installation of support beam section.
3. the mounting method of rack area steel case beam as claimed in claim 2, it is characterized in that: the height of described amplitude variation type erection crane anchorage point surpasses the steel case depth of beam after installation.
CN2013100808466A 2013-03-14 2013-03-14 Mounting device and mounting method of steel box girder in support zone Pending CN103174093A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100808466A CN103174093A (en) 2013-03-14 2013-03-14 Mounting device and mounting method of steel box girder in support zone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100808466A CN103174093A (en) 2013-03-14 2013-03-14 Mounting device and mounting method of steel box girder in support zone

Publications (1)

Publication Number Publication Date
CN103174093A true CN103174093A (en) 2013-06-26

Family

ID=48634248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100808466A Pending CN103174093A (en) 2013-03-14 2013-03-14 Mounting device and mounting method of steel box girder in support zone

Country Status (1)

Country Link
CN (1) CN103174093A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442451A (en) * 2015-11-11 2016-03-30 中铁大桥局集团第一工程有限公司 Incremental launching construction device and method for plane-bending steel channel beams
CN105648913A (en) * 2015-12-17 2016-06-08 浙江大学 Temporary reinforcement method for transverse partitioning construction of steel box girder bridge
CN106522097A (en) * 2016-11-02 2017-03-22 中交第二航务工程局有限公司 Self-adaptive cable cranes for extra large space-cross cable face suspension bridge girder erection
CN106544956A (en) * 2016-10-09 2017-03-29 浙江大学 A kind of horizontal block construction shoveing of steel box-girder is longitudinally arranged method
CN110318344A (en) * 2019-06-28 2019-10-11 中交二航局第四工程有限公司 A kind of No. 0 block bracket of novel steel box-girder and No. 0 block erection construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1800498A (en) * 2005-07-12 2006-07-12 上海市第二市政工程有限公司 Large scale concrete box girder hoisting method
CN102182147A (en) * 2011-03-31 2011-09-14 中铁港航局集团第二工程有限公司 Steel box girder erection method
CN102277825A (en) * 2011-05-23 2011-12-14 江苏沪宁钢机股份有限公司 Steel truss bridge and method for fabricating same
KR20120103300A (en) * 2011-03-10 2012-09-19 주식회사 아모텍 A nfc antenna module

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1800498A (en) * 2005-07-12 2006-07-12 上海市第二市政工程有限公司 Large scale concrete box girder hoisting method
KR20120103300A (en) * 2011-03-10 2012-09-19 주식회사 아모텍 A nfc antenna module
CN102182147A (en) * 2011-03-31 2011-09-14 中铁港航局集团第二工程有限公司 Steel box girder erection method
CN102277825A (en) * 2011-05-23 2011-12-14 江苏沪宁钢机股份有限公司 Steel truss bridge and method for fabricating same

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
李传习等: ""嘉绍大桥斜拉桥边跨钢箱梁架设方法及支架的受力分析",李传习等,中外公路,第6期,第129~133页,2012年12月31日", 《中外公路》, no. 6, 31 December 2012 (2012-12-31), pages 129 - 133 *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105442451A (en) * 2015-11-11 2016-03-30 中铁大桥局集团第一工程有限公司 Incremental launching construction device and method for plane-bending steel channel beams
CN105648913A (en) * 2015-12-17 2016-06-08 浙江大学 Temporary reinforcement method for transverse partitioning construction of steel box girder bridge
CN106544956A (en) * 2016-10-09 2017-03-29 浙江大学 A kind of horizontal block construction shoveing of steel box-girder is longitudinally arranged method
CN106544956B (en) * 2016-10-09 2018-03-20 浙江大学 A kind of steel box-girder transverse direction block construction shoveing is longitudinally arranged method
CN106522097A (en) * 2016-11-02 2017-03-22 中交第二航务工程局有限公司 Self-adaptive cable cranes for extra large space-cross cable face suspension bridge girder erection
CN106522097B (en) * 2016-11-02 2018-12-04 中交第二航务工程局有限公司 The adaptive deck unit erection gantry of super-span Spatial Cable face suspension cable bridge stand beam
CN110318344A (en) * 2019-06-28 2019-10-11 中交二航局第四工程有限公司 A kind of No. 0 block bracket of novel steel box-girder and No. 0 block erection construction method
CN110318344B (en) * 2019-06-28 2024-04-19 中交二航局第四工程有限公司 Novel steel box girder No. 0 block support and No. 0 block erection construction method

Similar Documents

Publication Publication Date Title
CN103911956B (en) A kind of large span stayed-cable bridge steel truss girder mounting method
CN104674668B (en) A kind of method by cable-hoisting construction girder section
CN110374008A (en) A method of the erection of cable-stayed bridge steel truss is carried out in marine environment
CN106939707A (en) A kind of restricted clearance large-scale steel structure supporting platform from method for improving
CN105484162B (en) Suspension bridge construction stiff girder secondary on the bank swings moving device and method
CN103523665B (en) A kind of transport device and method of high pedestal jib crane
CN103882812A (en) Construction method for midspan main beams of cable-stayed bridge
CN102653938B (en) Offshore dismantling construction method for descending movable formwork
CN103174093A (en) Mounting device and mounting method of steel box girder in support zone
CN108049666B (en) A kind of echelon installation method of super plane multilayer steel truss electronic workshop steel construction
CN103967284B (en) The steel column installation method of reserved stigma docking
CN110255395A (en) A kind of side crossbeam, girder erection crane and girder erection crane hanging method
CN106245919A (en) A prefabricated building automation assembly platform
CN103964300B (en) Jacking type increases equipment
CN202658590U (en) Integral assembled drilling platform
CN205474862U (en) Wet seam template operation platform of portable case roof beam
CN113106866B (en) Counterweight type mounting method of main beam
CN202689016U (en) Cofferdam assembling and lifting platform for double-wall steel cofferdam construction of deep-water bridge pier
CN102041779A (en) Erection crane and construction method thereof
CN202416191U (en) Lifting device of main girder for offshore demolition of downward mobile formwork
CN208009277U (en) A kind of short sliding installation system of land-based area large-tonnage steel box beam
CN102071646A (en) Large-tonnage box girder sea system and construction method
CN102776840B (en) Mal-position assembly in-position method of truss bridge
CN112982183A (en) Counterweight type mounting system of main beam
CN102041781A (en) Enclosed lake beam type steel bridge installation method based on portal crane

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Zhang Hong

Inventor after: Peng Linlin

Inventor after: Tang Heng

Inventor after: He Chenghai

Inventor after: Yang Yanhua

Inventor before: Zhang Hong

Inventor before: Peng Linlin

Inventor before: Tang Heng

Inventor before: He Chenghai

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: ZHANG HONG PENG LINLIN TANG HENG HE CHENGHAI TO: ZHANG HONG PENG LINLIN TANG HENG HE CHENGHAI YANG YANHUA

C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130626