CN103161484A - Pasty fluid fixed-length anchoring supporting method - Google Patents

Pasty fluid fixed-length anchoring supporting method Download PDF

Info

Publication number
CN103161484A
CN103161484A CN2013100939068A CN201310093906A CN103161484A CN 103161484 A CN103161484 A CN 103161484A CN 2013100939068 A CN2013100939068 A CN 2013100939068A CN 201310093906 A CN201310093906 A CN 201310093906A CN 103161484 A CN103161484 A CN 103161484A
Authority
CN
China
Prior art keywords
lotion
slurries
anchoring
flexible pipe
rope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100939068A
Other languages
Chinese (zh)
Other versions
CN103161484B (en
Inventor
张农
薛飞
阚甲广
赵一鸣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201310093906.8A priority Critical patent/CN103161484B/en
Publication of CN103161484A publication Critical patent/CN103161484A/en
Priority to PCT/CN2013/081725 priority patent/WO2014146392A1/en
Application granted granted Critical
Publication of CN103161484B publication Critical patent/CN103161484B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/028Devices or accesories for injecting a grouting liquid in a bore-hole
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/00715Uses not provided for elsewhere in C04B2111/00 for fixing bolts or the like
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/00724Uses not provided for elsewhere in C04B2111/00 in mining operations, e.g. for backfilling; in making tunnels or galleries
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/70Grouts, e.g. injection mixtures for cables for prestressed concrete

Abstract

Disclosed is a pasty fluid fixed-length anchoring supporting method. Pasty fluid size prefabricated on site is adopted as an anchoring agent, a plastic flexible pipe is inserted in a drill hole, and the well collocated pasty fluid size is injected in the drill hole by an injection pump through the plastic flexible pipe. An anchor rod/anchor cable is inserted in the drill hole, a tray, a spherical cushion, an anti-attrition gasket, and a nut/ground tackle are installed on an exposed part of the anchor rod/anchor cable in sequence, and pre-tightening and repeated twisting are carried out on the anchor rod/anchor cable through a stretch-draw device after the pasty fluid size is solidified. The adopted pasty fluid size has good thixotropy and pumping performance. Compared with a traditional packaging type resin anchoring agent, by means of the pasty fluid size, the anchoring problem of breaking surrounding rock can be solved, and requirements on jacking force of construction equipment is low. The needed anchoring length can be selected flexibly according to requirements of a project at the same time, and the overall-length anchoring of the anchor rod/anchor cable can be achieved, so that the anchor rod/anchor cable is enabled to be sensitive to deformation and layer separation of the surrounding rock, and layer separation and sliding of the surrounding rock can be hampered in time. Adaptability of an anchor rod supporting system to the surrounding rock with large deformation is improved, and the problem of heavily stressed roadway supporting in a deep position is solved.

Description

A kind of lotion fixed length anchoring support method
Technical field
The present invention relates to a kind of anchoring support method, especially a kind of lotion fixed length anchoring support method that is applicable to roadway surrounding rock.
Background technology
Bolt support is as a kind of important support form of colliery tunnel support, compare with traditional shed ding support the supporting effect that has significantly improved the tunnel, reduced the roadway support cost, alleviated labor strength, the Bolt System development that comprises monomer anchor pole, anchor beam (band), anchor beam (band) net and bolting and rope support take anchor pole as the basic supporting form rapidly, be widely used in home and abroad colliery roadway support, become the colliery and realize one of requisite key technology of high-yield and high-efficiency.
in recent years along with adopting dark increase, roadway surrounding rock stress increases, make a lot of roadway surrounding rocks become the engineering soft rock, show strong dilatation and strain softening or lasting rheology characteristic, roadway deformation speed is fast, deflection is large, and present Bolt System is usually to hold anchor or to lengthen anchor as main, anchorage length is limited, thereby be difficult to suitable for surrounding rock large deformation characteristics, surrouding rock deformation begins when above over 200mm to lose efficacy, destroy, surrouding rock deformation can not get effective control, cause the part repair of laneway to reach more than 90%, greatly increased support cost, have a strong impact on the safe and efficient production of mine.
Traditional Bolt System adopts resin anchoring agent as main anchorage style, has adhesion strength large, quick solidifying, security reliability advantages of higher.But its anchoring effect depends on stirring resistance that rig can provide and the time of stirring, and anchorage length limits to some extent, can't realize growing the anchoring of scope, is difficult to simultaneously install when rock crusher.And exist the problems such as hole-sealing technology complexity, easily races, spillage when adopting the cement injection method to realize full length fastening, therefore can't realize the especially interior anchoring of anchor cable length range of anchor pole.Above-mentioned phenomenon has a strong impact on the Surrounding Rock Control effect of Bolt System, particularly can't solve the supporting difficult problem of deep large deformation soft-rock tunnel.
Summary of the invention
Technical problem: the objective of the invention is to overcome the weak point in prior art, provide that a kind of method is simple, easily construction, effective lotion fixed length anchoring support method.
Technical scheme: lotion fixed length anchoring support method of the present invention, be included in boring on the scar of tunnel, clear hole, also comprise the steps:
A, prepare the lotion slurries at the scene;
Insert plastic flexible pipe in b, the boring on the scar of described tunnel, and plastic flexible pipe is inserted the bottom of boring;
C, according to boring, anchor pole/rope diameter and the design anchorage length calculate required lotion slurries injection rate, starting grouting pump injects by plastic flexible pipe the lotion slurries that configure in boring, lotion slurries injection rate is controlled by the metering device on grouting pump, while injecting, plastic flexible pipe is slowly extracted out, so that the lotion slurries fill up the space of extracting plastic flexible pipe out;
D, anchor pole/rope is inserted in boring, the lotion slurries of extruding are filled in annulus around anchor pole/rope, install successively pallet, ball pad, anti-attrition pad, nut/ground tackle at the revealed section of anchor pole/rope;
E, solidify rear use stretch-draw instrument to anchor pole/Suo Jinhang pretension until the lotion slurries.
Described lotion slurries are to be configured in mass ratio and formed by water, cement, anchoring additive, accelerating admixture, and wherein water, cement ratio are 0.25 ~ 0.35, and the anchoring additive is 3% ~ 5% of cement amount, and accelerating admixture is 2% ~ 3% of cement amount.
beneficial effect: the lotion injection slurry that adopts in the present invention is different from the ordinary Portland cement slurries, have thixotropy and mobility preferably, its Marsh funnel viscosity value can reach the 50s left and right, can stream pendant phenomenon not appear because of gravity effect, thereby the anchor that is particularly suitable for deep hole is annotated, do not need extra hole-sealing technology, can effectively avoid the ordinary Portland cement slurries easily to run leakage problem, can arbitrarily adjust anchorage length by controlling grouting amount, realize the fixed length anchoring, especially can realize the anchoring in anchor pole/rope length range in the high stress tunnel of deep, effectively improved the compliance of anchor pole/rope to large deformation, strengthened the system stiffness of bolt support.The working resistance that lotion slurries of the present invention need not to stir construction equipment requires low, can be according to requirement of engineering, the anchorage length that flexible choice is fit to, and can realize the full length fastening of anchor pole/rope, make anchor pole/rope very sensitive to surrouding rock deformation and absciss layer, can in time suppress absciss layer and the slip of country rock, strengthened the compliance of Bolt System to the large deformation country rock, can effectively improve the supporting effect in tunnel, solve a deep high stress tunnel supporting difficult problem.The present invention both can be used for the anchoring of bottom, tunnel and the boring of section of side, also can be used for the anchoring of top plate drilling, also was applicable in the surrounding rock supporting of other geotechnical engineerings.Can effectively solve the problem that the anchorage length that has the bolt support technology existence now is limited, can not adapt to the deformation of the surrounding rock in tunnel under the condition of high ground stress of deep.Its method is simple, easy to operate, effective, has practicality widely.
Description of drawings
Fig. 1 is slip casting process schematic diagram of the present invention;
Fig. 2 is anchor pole/rope scheme of installation.
In figure: 1. tunnel scar, 2. boring, 3. plastic flexible pipe, 4. lotion slurries, 5. anchor pole/rope, 6. pallet, 7. ball pad, 8. anti-attrition pad, 9. nut/ground tackle.
The specific embodiment
Below in conjunction with accompanying drawing, embodiments of the invention are further described:
Embodiment 1,
(1) preparing at the scene lotion slurries 4, is 0.25 to mix slurry by water, cement quality ratio, gets cement 2000 grams, water 500 grams, by FLOWCABLE anchoring additive 60 grams that BASF AG produces, accelerating admixture 40 grams namely get required lotion slurries 4 after stirring fully;
(2) at tunnel scar 1 construction drill 2, bore diameter is 28mm, and drilling depth is 2750mm, and clear hole;
(3) with internal diameter 15mm external diameter be the bottom that 22mm plastic flexible pipe 3 inserts boring 2;
(4) according to diameter and the anchorage length of boring 2, anchor pole/rope 5, calculate required lotion slurries injection rate by following formula,
In formula s-lotion slurries injection rate;
D-bore diameter;
d-anchor pole/rope diameter;
l—Anchorage length
Getting bore diameter is that 28mm, anchor pole/rope diameter are 22mm, the design anchorage length is 1800mm, can get lotion slurries injection rate and be about 0.42L, starting grouting pump passes through the lotion slurries 4 that configure in plastic flexible pipe 3 injection holes 2, lotion slurries 4 injection rates are controlled by the metering device on grouting pump, while injecting, plastic flexible pipe 3 is slowly extracted out, so that lotion slurries 4 fill up the space of extracting plastic flexible pipe 3 out;
(5) be that 22mm length is that anchor pole/rope 5 of 2800mm inserts in boring 2 with diameter, the lotion slurries 4 of extruding just are filled in annulus around anchor pole/rope 5, install successively pallet 6, ball pad 7, anti-attrition pad 8, nut 9 at the revealed section of anchor pole/rope 5;
(6) after solidifying rear approximately 30min, lotion slurries 4 with pneumatic impact wrench or stretch-draw instrument, anchor pole/rope is applied pretightning force again.
Embodiment 2,
Substantially the same manner as Example 1, exist together mutually slightly.Difference: be 0.3 to mix slurry by water ash mass ratio, get cement 2000 grams, water 600 grams, by FLOWCABLE anchoring additive 60 grams that BASF AG produces, accelerating admixture 40 grams namely get required lotion slurries 4 after stirring fully.
Embodiment 3,
Substantially the same manner as Example 1, exist together mutually slightly.Difference: be 0.35 to mix slurry by water ash mass ratio, get cement 2000 grams, water 700 grams, by FLOWCABLE anchoring additive 60 grams that BASF AG produces, accelerating admixture 40 grams namely get required lotion slurries 4 after stirring fully.

Claims (2)

1. a lotion fixed length anchoring support method, be included in the upper boring of tunnel scar (1) (2), clear hole, it is characterized in that:
A, prepare lotion slurries (4) at the scene;
Insert plastic flexible pipe (3) in b, the boring on described tunnel scar (1), and plastic flexible pipe (3) is inserted the bottom of boring (2);
C, calculate required lotion slurries (4) injection rate according to boring (2), anchor pole/rope (5) diameter and design anchorage length, starting grouting pump passes through the lotion slurries (4) that configure in plastic flexible pipe (3) injection hole (2), lotion slurries (4) injection rate is controlled by the metering device on grouting pump, while injecting, plastic flexible pipe (3) is slowly extracted out, so that lotion slurries (4) fill up the space of extracting plastic flexible pipe (3) out;
D, anchor pole/rope (5) is inserted in boring, the lotion slurries (4) of extruding are filled in anchor pole/rope (5) annulus on every side, install successively pallet (6), ball pad (7), anti-attrition pad (8), nut/ground tackle (9) at the revealed section of anchor pole/rope (5);
E, solidify rear use stretch-draw instrument until lotion slurries (4) anchor pole/rope (5) is carried out pretension.
2. a kind of lotion fixed length anchoring support method according to claim 1, it is characterized in that: described lotion slurries are to be configured in mass ratio and formed by water, cement, anchoring additive, accelerating admixture, wherein water, cement ratio are 0.25 ~ 0.35, the anchoring additive is 3% ~ 5% of cement amount, and accelerating admixture is 2% ~ 3% of cement amount.
CN201310093906.8A 2013-03-22 2013-03-22 A kind of lotion fixed length anchoring support method Active CN103161484B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201310093906.8A CN103161484B (en) 2013-03-22 2013-03-22 A kind of lotion fixed length anchoring support method
PCT/CN2013/081725 WO2014146392A1 (en) 2013-03-22 2013-08-19 Paste fixed-length anchoring supporting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310093906.8A CN103161484B (en) 2013-03-22 2013-03-22 A kind of lotion fixed length anchoring support method

Publications (2)

Publication Number Publication Date
CN103161484A true CN103161484A (en) 2013-06-19
CN103161484B CN103161484B (en) 2015-08-19

Family

ID=48584979

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310093906.8A Active CN103161484B (en) 2013-03-22 2013-03-22 A kind of lotion fixed length anchoring support method

Country Status (2)

Country Link
CN (1) CN103161484B (en)
WO (1) WO2014146392A1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103758549A (en) * 2014-01-09 2014-04-30 中国矿业大学 Sequential filling-anchoring prestress full-length anchorage supporting method on basis of paste materials
WO2014146392A1 (en) * 2013-03-22 2014-09-25 中国矿业大学 Paste fixed-length anchoring supporting method
CN105257325A (en) * 2015-11-02 2016-01-20 新汶矿业集团有限责任公司协庄煤矿 Anchor rod anchoring device for surrounding rock of roadway and anchoring method of anchor rod anchoring device
CN105863693A (en) * 2016-05-09 2016-08-17 美亚高新材料股份有限公司 Full-length anchoring supporting method for deep high-stress roadway
CN112922651A (en) * 2021-04-23 2021-06-08 辽宁工程技术大学 Anchor rod supporting process for driving face

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111022848B (en) * 2019-12-03 2021-10-26 北京中科富海低温科技有限公司 Fixing device and cold box

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4140429A (en) * 1977-02-19 1979-02-20 Dyckerhoff & Widmann Aktiengesellschaft Corrosion protected tensioning member for a prestressable anchor in solid rock
CN101200904A (en) * 2007-12-10 2008-06-18 山西建筑工程(集团)总公司 Anti-floating construction method by combination of bar-planting and anchoring-bolt
CN102003194A (en) * 2010-10-30 2011-04-06 中国矿业大学 Rapid installation process of resin anchor bar and device thereof

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FI79597C (en) * 1985-11-07 1990-01-10 Tampella Oy Ab Method and apparatus for feeding concrete in a borehole during concrete aeration of rock.
AU664186B2 (en) * 1991-08-30 1995-11-09 Technological Resources Pty Limited Rock bolt load sensor
CN1448363A (en) * 2003-05-01 2003-10-15 东南大学 High-strength anchor grouting agent
CA2504058A1 (en) * 2005-04-11 2006-10-11 Mansour Mining Inc. Mine roof support system having torque indicating washer
CN1830882A (en) * 2006-04-17 2006-09-13 张京泉 Roofbolt anchoring agent and roofbolt pin-timbering method therewith
CN101949294A (en) * 2010-08-13 2011-01-19 山西潞安环保能源开发股份有限公司常村煤矿 Prestressed full-length anchorage support method
CN102503324B (en) * 2011-11-22 2014-07-09 中建材中岩科技有限公司 Anchoring grouting material as well as preparation method and application thereof
CN103161484B (en) * 2013-03-22 2015-08-19 中国矿业大学 A kind of lotion fixed length anchoring support method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4140429A (en) * 1977-02-19 1979-02-20 Dyckerhoff & Widmann Aktiengesellschaft Corrosion protected tensioning member for a prestressable anchor in solid rock
CN101200904A (en) * 2007-12-10 2008-06-18 山西建筑工程(集团)总公司 Anti-floating construction method by combination of bar-planting and anchoring-bolt
CN102003194A (en) * 2010-10-30 2011-04-06 中国矿业大学 Rapid installation process of resin anchor bar and device thereof

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
徐永明等: "向家坝水电站尾水洞出口预应力锚杆施工技术", 《人民长江》, vol. 42, no. 01, 14 January 2011 (2011-01-14) *
田源等: "向家坝电站地下厂房岩壁梁锚杆施工技术与工艺", 《四川水力发电》, vol. 28, no. 04, 15 August 2009 (2009-08-15) *
苏智光: "两河口水电站锚杆锚固质量控制与无损检测总结", 《云南水力发电》, vol. 27, no. 05, 15 October 2011 (2011-10-15) *
邓良超: "溪洛渡水电站右岸泄洪洞预应力锚杆施工", 《人民长江》, vol. 39, no. 07, 5 April 2008 (2008-04-05) *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014146392A1 (en) * 2013-03-22 2014-09-25 中国矿业大学 Paste fixed-length anchoring supporting method
CN103758549A (en) * 2014-01-09 2014-04-30 中国矿业大学 Sequential filling-anchoring prestress full-length anchorage supporting method on basis of paste materials
WO2015103862A1 (en) * 2014-01-09 2015-07-16 中国矿业大学 Method for supporting by means of full-length pre-stressed anchorage with paste material being first poured and last anchored
CN103758549B (en) * 2014-01-09 2016-09-28 中国矿业大学 Anchor prestressing force full-length anchorage support method after a kind of first filling based on ointment material
CN105257325A (en) * 2015-11-02 2016-01-20 新汶矿业集团有限责任公司协庄煤矿 Anchor rod anchoring device for surrounding rock of roadway and anchoring method of anchor rod anchoring device
CN105863693A (en) * 2016-05-09 2016-08-17 美亚高新材料股份有限公司 Full-length anchoring supporting method for deep high-stress roadway
CN112922651A (en) * 2021-04-23 2021-06-08 辽宁工程技术大学 Anchor rod supporting process for driving face

Also Published As

Publication number Publication date
WO2014146392A1 (en) 2014-09-25
CN103161484B (en) 2015-08-19

Similar Documents

Publication Publication Date Title
CN103161484B (en) A kind of lotion fixed length anchoring support method
CN205689230U (en) A kind of recyclable pressure grouting anchor cable that allows
CN102493821B (en) Support method for high stress roadway coal-rock mass
CN104500115B (en) A kind of prestressing force Bolt method for protecting support
CN206592139U (en) A kind of external poured is segmented anchoring rod
CN103758549A (en) Sequential filling-anchoring prestress full-length anchorage supporting method on basis of paste materials
CN105840221B (en) It rotatably can quick anchoring installation binding type hollow bolt
CN103711507A (en) Method for controlling deformation of large broken rock zone roadway by using multi-steel stranded wire combined supporting device
CN205689228U (en) A kind of pressure-release anchor cable
CN205370613U (en) Utilize biliquid slip casting medicated roll to realize high prestressing force total length anchored stock
CN106567722A (en) Novel composite type groutable anchor rod
CN103147777B (en) Pumping paste prestress full bolting anchor rod/cable supporting method
CN102865088A (en) Tension and compression coupling type high-strength and high-deformation anchor rod and method for using same
CN105840222B (en) Push-press type can quick anchoring installation binding type hollow bolt
CN201650323U (en) Grouting anchor rope
CN204568493U (en) A kind of colliery coal pocket dredger
CN103573280A (en) Method for supporting porous ooze invasion compound roof roadway
CN203257442U (en) Anchor rod/anchor rope with leakproof plug of rubber for anchoring
CN202866841U (en) Pull and press coupling type high, strong and big deformation anchor rod
CN202132060U (en) Anchoring structure for liquid-filled corrosion resistant anchor rod or anchor rope
CN204804863U (en) From formula of boring joinable prestressing force slip casting stock
CN105626109B (en) It is a kind of that there is the method for repeating to apply prestressed cable bolting
CN102748048A (en) Hole wall grouting anchor cable
CN202768031U (en) Hollow grouting anchor rod
CN205876364U (en) Cavity intelligence slip casting stock

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant