CN103133011A - Construction device and construction method of hydraulic pressure steel mould trolley monolithic conduit pipe body - Google Patents

Construction device and construction method of hydraulic pressure steel mould trolley monolithic conduit pipe body Download PDF

Info

Publication number
CN103133011A
CN103133011A CN2011103836755A CN201110383675A CN103133011A CN 103133011 A CN103133011 A CN 103133011A CN 2011103836755 A CN2011103836755 A CN 2011103836755A CN 201110383675 A CN201110383675 A CN 201110383675A CN 103133011 A CN103133011 A CN 103133011A
Authority
CN
China
Prior art keywords
oil cylinder
chassis
side direction
interior
hydraulic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011103836755A
Other languages
Chinese (zh)
Other versions
CN103133011B (en
Inventor
王五奇
王登武
王同生
卢春亭
卢相云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Original Assignee
China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Bureau Installation Engineering Co Ltd filed Critical China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Priority to CN201110383675.5A priority Critical patent/CN103133011B/en
Publication of CN103133011A publication Critical patent/CN103133011A/en
Application granted granted Critical
Publication of CN103133011B publication Critical patent/CN103133011B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a construction device and a construction method of a hydraulic pressure steel mould trolley monolithic conduit pipe body. The construction device comprises a trolley and an internal mould arranged outside the trolley. Walking wheels are arranged at the bottom of the trolley, the walking wheels are matched with walking tracks, a top hydro-cylinder and a side hydro-cylinder are connected with a hydraulic control device, and a rotary lead screw is arranged at the bottom of the trolley. According to the construction device and the construction method of the hydraulic pressure steel mould trolley monolithic conduit pipe body, a plurality of hydro-cylinders are arranged on the trolley, thus integral installation and removal of an internal top mould and an internal side mould are guaranteed. Compared with a general template, the construction device of the hydraulic pressure steel mould trolley monolithic conduit pipe body is good in integral rigidity, strength and stability, a wallboard and a roof can be formed by one-time-pouring, and evenness and perpendicularity of the surface of concrete can be ensured. In addition, the construction device of the hydraulic pressure steel mould trolley monolithic conduit pipe body can be used repeatedly, labor is saved, and overall benefit is good.

Description

Whole closed conduit pipe shaft construction equipment and the construction of watering of hydraulic steel form carrier
Technical field
The present invention relates to building field, be specifically related to transportable steel form carrier and job practices thereof used in a kind of closed conduit construction process.
Background technology
Steel form carrier is the indispensable non-device for mark of secondary lining in the constructing tunnel process.Conventional steel form carrier in use, the wall body of closed conduit and concrete roof are not that one-time-concreting is completed, and also have constuction joint between wall body and top board, need to process constuction joint, it is consuming time longer, makes the duration long.
Summary of the invention
The technical problem to be solved in the present invention be existing steel form carrier when building closed conduit labour intensity large, long in time limit, provide that a kind of hydraulic steel form carrier that can reduce labour intensity, reduction of erection time is whole waters closed conduit pipe shaft construction equipment, and introduced the construction that uses this device to revise closed conduit.
technical scheme of the present invention realizes in the following manner: the whole construction equipment that waters the closed conduit pipe shaft of a kind of hydraulic steel form carrier, comprise chassis and be arranged on the outer internal mold of chassis, chassis and internal mold are all hinged with connecting rod, described internal mold comprises interior backform and interior side form, interior backform and interior side form all are hinged and connected with oblique mould, the chassis top is provided with top oil cylinder and rotary-top leading screw, the top oil cylinder is connected with hanger on interior backform, be provided with hydraulic pressure support between top oil cylinder and chassis top, the chassis sidepiece is provided with side direction oil cylinder and side direction rotating threaded shaft, the side direction oil cylinder is connected with hanger on interior side form, be provided with hydraulic pressure support between side direction oil cylinder and chassis sidepiece, pallet bottom is provided with road wheel, road wheel matches with the walking track, the top oil cylinder, the side direction oil cylinder is connected with hydraulic control device, pallet bottom is provided with the bottom rotating threaded shaft.
Described chassis comprises side template and top template, is provided with studdle between two side templates.
The whole construction that waters the closed conduit pipe shaft of a kind of hydraulic steel form carrier, carry out according to following step:
A, laying walking track, assembling trolley connect internal mold, each rotating threaded shaft, top oil cylinder and side direction oil cylinder are installed, and are installed hydraulic pressure support, and the top oil cylinder is connected with hydraulic control device with the side direction oil cylinder;
B, adopt hoist engine traction chassis, make chassis along rail moving to the section of building design attitude, adjust the pallet bottom screw, make leading screw hold out against the chassis bottom girder, and it is fastening to be plugged pin;
C, primer fluid pressure control device, make backform in the synchronous slowly jack-up of top oil cylinder, after interior backform approaches requirement, opening single or multiple tops oil cylinder finely tunes, lock top oil cylinder, regulating platform roof screw after making interior top template elevation meet design, the top screw supports in place, is plugged lead screw peg and is fixed;
After D, interior backform are adjusted, start the side direction oil cylinder, make the side direction oil cylinder synchronously slowly back down interior side form, open single or multiple side direction oil cylinder hydraulic system, finely tune, interior side form meets locking side direction oil cylinder after design, then regulate the side direction screw, make it in place, hold out against the inside wall mould, and be plugged fixator pins;
F, set up external mold outside internal mold, fluid concrete outside external mold;
After G, concrete casting injection forming, lay down the side direction screw, synchronously start the side hydraulic oil cylinder, regain in side form, lay down top screw, synchronous firing platform roof hydraulic jack, regain interior top punching block, unload the bottom screw, utilize hoist engine with spud carriage shifting, dismounting external wall punching block;
H, dismounting outer side mold get final product.
The present invention arranges several hydraulic jacks on chassis, integral installation and the dismounting of backform and interior side form in guaranteeing, compare with conventional template, integral rigidity of the present invention, strength and stability are good, strong wallboard and top board can one-time-concretings, and can guarantee planeness and the verticality of concrete surface.In addition, use can be repeatedly had enough to meet the need in the present invention, saves the labour, and its overall benefit is good.
Description of drawings
Fig. 1 is that the present invention uses view.
Fig. 2 is the chassis side schematic view.
The specific embodiment
as shown in drawings, the whole closed conduit pipe shaft construction equipment that waters of hydraulic steel form carrier of the present invention comprises chassis 6 and is arranged on the outer internal mold of chassis, chassis 6 and internal mold are all hinged with connecting rod 10, described internal mold comprises interior backform 1 and interior side form 2, interior backform 1 and interior side form 2 all are hinged and connected with oblique mould 3, chassis 6 tops are provided with top oil cylinder 4 and rotary-top leading screw, top oil cylinder 4 is connected with hanger on interior backform 1, be provided with hydraulic pressure support 11 between top oil cylinder 4 and chassis 6 tops, chassis 6 sidepieces are provided with side direction oil cylinder 5 and side direction rotating threaded shaft, side direction oil cylinder 5 is connected with hanger on interior side form 2, be provided with hydraulic pressure support between side direction oil cylinder 5 and chassis 6 sidepieces, chassis 6 bottoms are provided with road wheel 7, road wheel 7 matches with walking track 8, top oil cylinder 4, side direction oil cylinder 5 is connected with hydraulic control device, chassis 6 bottoms are provided with the bottom rotating threaded shaft.
Chassis 6 comprises side template 6-1 and top template 6-2, connects between a side template 6-1 to be provided with studdle 6-3.Top oil cylinder 4 and rotary-top leading screw one end are connected on side template 6-1, the quantity of rotary-top leading screw is more than the quantity of top oil cylinder 4, like this, can guarantee the top oil cylinder with interior backform strut after, the intensity of several rotary-top leading screws is higher, so that support interior backform and concrete.In like manner, being connected on the template 6-2 of top with side direction oil cylinder side one end of side direction rotating threaded shaft, the quantity of side direction rotating threaded shaft is also more than the side direction oil cylinder.
Utilize hydraulic steel form carrier that the method for closed conduit pipe shaft construction is carried out according to following step in the present invention:
A, laying walking track, assembling trolley, connect interior backform and interior side form, rotary-top leading screw, side direction rotating threaded shaft, bottom rotating threaded shaft, top oil cylinder and side direction oil cylinder are installed, and are installed hydraulic pressure support, the top oil cylinder is connected with hydraulic control device with the side direction oil cylinder; In the present invention, need to debug after the chassis assembling, and debug the folding and unfolding of each hydraulic jack, rotating threaded shaft and interior backform, interior side form.
B, adopt the hoist engine traction chassis of 5t, make chassis along rail moving to the section of building design attitude, adjust the bottom screw of chassis, make leading screw hold out against the chassis bottom girder, and it is fastening to be plugged pin, namely fixed the position of chassis;
C, primer fluid pressure control device, make backform 1 in the synchronous slowly jack-up of top oil cylinder 4, after interior backform 1 approaches requirement, opening single or multiple tops oil cylinder finely tunes, lock top oil cylinder, regulating platform roof screw after making interior backform elevation meet design, the top screw supports in place, being plugged lead screw peg is fixed, namely fix interior backform 1, after fixing interior backform, adopt ceiling hammer check top board center line whether consistent with base plate center line, if any error, can carry out the top board WidFin, until the top board center line meets design.
After D, interior backform are adjusted, start side direction oil cylinder 5, make the side direction oil cylinder synchronously slowly back down interior side form, open afterwards single or multiple side direction oil cylinder hydraulic system, finely tune, interior side form locks the side direction oil cylinder after meeting design, then regulate the side direction screw, make it in place, hold out against the inside wall mould, and be plugged fixator pins, namely fix interior side form;
F, set up external mold 9 outside internal mold, fluid concrete outside external mold; External mold adopts manually sets up scaffold, moving door frame lifting moving die plate, and artificial the cooperation installs.
After G, concrete casting injection forming, lay down the side direction screw, synchronous side hydraulic oil cylinder 5, the interior side form of withdrawal of starting, lay down top screw, synchronous firing platform roof hydraulic jack 4, regain interior top punching block, unload the bottom screw, utilize afterwards hoist engine with spud carriage shifting, dismounting external wall punching block;
H, dismounting outer side mold get final product, and adopt the artificial moving door machine that coordinates to remove external mold 9 from top to bottom.
In the present invention, hydraulic steel form carrier has enough intensity, rigidity and stability, so, wall body and top board one-time-concreting, the wall body is with top board constuction joint less, save the operation of processing constuction joint, in addition, adopted the thick steel plate of 5mm as the inner and outer template of steel form carrier, surface finish is fairly good, the ability of resistance to deformation is also fine, and therefore, the concrete surface planeness is guaranteed.

Claims (3)

1. whole construction equipment that waters the closed conduit pipe shaft of hydraulic steel form carrier, comprise chassis (6) and be arranged on the outer internal mold of chassis, chassis (6) and internal mold are all hinged with connecting rod (10), it is characterized in that: described internal mold comprises interior backform (1) and interior side form (2), interior backform (1) and interior side form (2) all are hinged and connected with oblique mould (3), chassis (6) top is provided with top oil cylinder (4) and rotary-top leading screw, top oil cylinder (4) is connected with hanger on interior backform (1), be provided with hydraulic pressure support (11) between top oil cylinder (4) and chassis (6) top, chassis (6) sidepiece is provided with side direction oil cylinder (5) and side direction rotating threaded shaft, side direction oil cylinder (5) is connected with hanger on interior side form (2), be provided with hydraulic pressure support (11) between side direction oil cylinder (5) and chassis (6) sidepiece, chassis (6) bottom is provided with road wheel (7), road wheel (7) matches with walking track (8), top oil cylinder (4), side direction oil cylinder (5) is connected with hydraulic control device, chassis (6) bottom is provided with the bottom rotating threaded shaft.
2. the whole construction equipment that waters the closed conduit pipe shaft of hydraulic steel form carrier according to claim 1, it is characterized in that: described chassis (6) comprises side template (6-1) and top template (6-2), is provided with studdle (6-3) between two side templates (6-1).
3. whole construction that waters the closed conduit pipe shaft of hydraulic steel form carrier it is characterized in that carrying out according to following step:
A, laying walking track, assembling trolley connect internal mold, each rotating threaded shaft, top oil cylinder and side direction oil cylinder are installed, and are installed hydraulic pressure support, and the top oil cylinder is connected with hydraulic control device with the side direction oil cylinder;
B, adopt hoist engine traction chassis, make chassis along rail moving to the section of building design attitude, adjust the pallet bottom screw, make leading screw hold out against the chassis bottom girder, and it is fastening to be plugged pin;
C, primer fluid pressure control device, make backform in the synchronous slowly jack-up of top oil cylinder, after interior backform approaches requirement, opening single or multiple tops oil cylinder finely tunes, lock top oil cylinder, regulating platform roof screw after making interior top template elevation meet design, the top screw supports in place, is plugged lead screw peg and is fixed;
After D, interior backform are adjusted, start the side direction oil cylinder, make the side direction oil cylinder synchronously slowly back down interior side form, open single or multiple side direction oil cylinder hydraulic system, finely tune, interior side form meets locking side direction oil cylinder after design, then regulate the side direction screw, make it in place, hold out against the inside wall mould, and be plugged fixator pins;
F, set up external mold outside internal mold, fluid concrete outside external mold;
After G, concrete casting injection forming, lay down the side direction screw, synchronously start the side hydraulic oil cylinder, regain in side form, lay down top screw, synchronous firing platform roof hydraulic jack, regain interior top punching block, unload the bottom screw, utilize hoist engine with spud carriage shifting, dismounting external wall punching block;
H, dismounting outer side mold get final product.
CN201110383675.5A 2011-11-28 2011-11-28 Hydraulic pressure steel mould trolley monolithic conduit pipe body construction equipment and construction Active CN103133011B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110383675.5A CN103133011B (en) 2011-11-28 2011-11-28 Hydraulic pressure steel mould trolley monolithic conduit pipe body construction equipment and construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110383675.5A CN103133011B (en) 2011-11-28 2011-11-28 Hydraulic pressure steel mould trolley monolithic conduit pipe body construction equipment and construction

Publications (2)

Publication Number Publication Date
CN103133011A true CN103133011A (en) 2013-06-05
CN103133011B CN103133011B (en) 2015-11-18

Family

ID=48493391

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110383675.5A Active CN103133011B (en) 2011-11-28 2011-11-28 Hydraulic pressure steel mould trolley monolithic conduit pipe body construction equipment and construction

Country Status (1)

Country Link
CN (1) CN103133011B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103603678A (en) * 2013-11-26 2014-02-26 华北水利水电大学 One-step pouring type steel mould trolley and pouring method for concealed channels in deserts
CN104895584A (en) * 2015-04-28 2015-09-09 金中天集团港航有限公司 Modularization steel die trolley and construction process thereof
CN105220626A (en) * 2015-10-27 2016-01-06 安徽水安建设集团股份有限公司 Steel form device and the construction method that combines with outer steel mould plate thereof in a kind of self-propelled
CN105908752A (en) * 2016-04-22 2016-08-31 广州比艾莫信息科技有限公司 Formwork assembling and disassembling system for side wall concrete pouring and working process thereof
CN105922209A (en) * 2016-05-04 2016-09-07 中车青岛四方机车车辆股份有限公司 Vehicle body large part replacement method
CN106894828A (en) * 2017-04-28 2017-06-27 武汉科技大学 A kind of adjustable piping lane mould bases chassis wide
CN107023032A (en) * 2017-02-27 2017-08-08 贾登忠 A kind of cast-in-place method of pipe gallery
CN107514011A (en) * 2017-09-21 2017-12-26 杭州华诚机械有限公司 A kind of gang form and piping lane construction method for piping lane construction
CN107905254A (en) * 2017-11-16 2018-04-13 中铁四局集团有限公司 A construction method of integrated hydraulic inner formwork trolley for comprehensive pipe gallery support and formwork
CN107956490A (en) * 2017-12-29 2018-04-24 中国铁道科学研究院铁道建筑研究所 A kind of intelligent tunnel lining trolley
CN109137976A (en) * 2018-09-14 2019-01-04 中交二公局东萌工程有限公司 Municipal administration synthesis pipe gallery hydraulic jumbo and its construction method
CN114837706A (en) * 2022-05-30 2022-08-02 中电建十一局工程有限公司 Underground assembling device for oversized rectangular jacking pipe joints and using method
CN116356726A (en) * 2023-05-17 2023-06-30 中国水利水电第三工程局有限公司 Box culvert side wall template mobile trolley structure and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1448255A (en) * 2003-04-25 2003-10-15 广东水电二局股份有限公司 Construction method of in-situ concrete prestressed round pipe
CN1858404A (en) * 2006-05-24 2006-11-08 杨秋利 Full automatic hydraulic lining trolley
CN201474704U (en) * 2009-09-02 2010-05-19 广汉金达隧道机械有限公司 Needle beam type hydraulic steel mould carrier
CN201614939U (en) * 2010-03-15 2010-10-27 中国葛洲坝集团股份有限公司 Three-dimensional space curved surface steel mould trolley
CN201982108U (en) * 2010-12-03 2011-09-21 中铁五局(集团)有限公司 Single-track railway tunnel integral type full-hydraulic lining trolley
CN202381104U (en) * 2011-11-28 2012-08-15 中建七局安装工程有限公司 Integrally cast culvert pipe body construction device for hydraulic steel form carrier

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1448255A (en) * 2003-04-25 2003-10-15 广东水电二局股份有限公司 Construction method of in-situ concrete prestressed round pipe
CN1858404A (en) * 2006-05-24 2006-11-08 杨秋利 Full automatic hydraulic lining trolley
CN201474704U (en) * 2009-09-02 2010-05-19 广汉金达隧道机械有限公司 Needle beam type hydraulic steel mould carrier
CN201614939U (en) * 2010-03-15 2010-10-27 中国葛洲坝集团股份有限公司 Three-dimensional space curved surface steel mould trolley
CN201982108U (en) * 2010-12-03 2011-09-21 中铁五局(集团)有限公司 Single-track railway tunnel integral type full-hydraulic lining trolley
CN202381104U (en) * 2011-11-28 2012-08-15 中建七局安装工程有限公司 Integrally cast culvert pipe body construction device for hydraulic steel form carrier

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103603678B (en) * 2013-11-26 2016-02-24 华北水利水电大学 Desert secret tunnel one-time-concreting formula steel form carrier and casting method
CN103603678A (en) * 2013-11-26 2014-02-26 华北水利水电大学 One-step pouring type steel mould trolley and pouring method for concealed channels in deserts
CN104895584A (en) * 2015-04-28 2015-09-09 金中天集团港航有限公司 Modularization steel die trolley and construction process thereof
CN105220626A (en) * 2015-10-27 2016-01-06 安徽水安建设集团股份有限公司 Steel form device and the construction method that combines with outer steel mould plate thereof in a kind of self-propelled
CN105908752B (en) * 2016-04-22 2020-03-31 广州比艾莫信息科技有限公司 Formwork supporting and stripping system for pouring concrete on side wall and working process of formwork supporting and stripping system
CN105908752A (en) * 2016-04-22 2016-08-31 广州比艾莫信息科技有限公司 Formwork assembling and disassembling system for side wall concrete pouring and working process thereof
CN105922209A (en) * 2016-05-04 2016-09-07 中车青岛四方机车车辆股份有限公司 Vehicle body large part replacement method
CN105922209B (en) * 2016-05-04 2018-02-02 中车青岛四方机车车辆股份有限公司 A kind of method that car body big parts are changed
CN107023032A (en) * 2017-02-27 2017-08-08 贾登忠 A kind of cast-in-place method of pipe gallery
CN106894828A (en) * 2017-04-28 2017-06-27 武汉科技大学 A kind of adjustable piping lane mould bases chassis wide
CN107514011A (en) * 2017-09-21 2017-12-26 杭州华诚机械有限公司 A kind of gang form and piping lane construction method for piping lane construction
CN107905254A (en) * 2017-11-16 2018-04-13 中铁四局集团有限公司 A construction method of integrated hydraulic inner formwork trolley for comprehensive pipe gallery support and formwork
CN107956490A (en) * 2017-12-29 2018-04-24 中国铁道科学研究院铁道建筑研究所 A kind of intelligent tunnel lining trolley
CN109137976A (en) * 2018-09-14 2019-01-04 中交二公局东萌工程有限公司 Municipal administration synthesis pipe gallery hydraulic jumbo and its construction method
CN114837706A (en) * 2022-05-30 2022-08-02 中电建十一局工程有限公司 Underground assembling device for oversized rectangular jacking pipe joints and using method
CN116356726A (en) * 2023-05-17 2023-06-30 中国水利水电第三工程局有限公司 Box culvert side wall template mobile trolley structure and construction method thereof

Also Published As

Publication number Publication date
CN103133011B (en) 2015-11-18

Similar Documents

Publication Publication Date Title
CN103133011B (en) Hydraulic pressure steel mould trolley monolithic conduit pipe body construction equipment and construction
CN107119715B (en) A method of using the integral formwork of a comprehensive pipe gallery
CN103437782B (en) Hydraulic pressure automatic moving type steel form carrier and construction method thereof
CN104453949B (en) A kind of narrow transition telescoping steel form construction method of tunnel bundle
CN102704949A (en) No-pull rod side wall construction method for underground tunnel and formwork trolley for construction
CN109968521A (en) A kind of packaged type bridges prefabricated components production method and industrial production line
CN107700533B (en) A kind of construction technology of box-type quick assembly and disassembly mould pipe gallery
CN105736016A (en) Tunnel secondary lining steel bar framework construction equipment and application thereof
CN103726511B (en) A kind of template system for large-area tunnel immersed tube monobloc cast
CN105220626A (en) Steel form device and the construction method that combines with outer steel mould plate thereof in a kind of self-propelled
CN206800451U (en) A kind of piping lane top board construction chassis and chassis group
CN107059920B (en) Construction technology of loess layer pipe gallery
CN102022123B (en) Integral lining method for tunnel with altered diameter by model board trolley
CN105909278A (en) Combined automatic control mold rack and use method
CN105370298A (en) Loess tunnel one-off lining hydraulic formwork trolley
CN202596743U (en) Formwork trolley for underground tunnel pull-rod-free side wall construction
CN204436411U (en) A kind of for the large lining trolley across section tunnel
CN102286932B (en) Construction method for off-site assembling and automatic mounting on bridge of mobile mould bridge abutment
CN205112063U (en) Integral hydraulic pressure exterior sheathing of precast box girder
CN106223983A (en) A kind of diversion tunnel inclined shaft, flat section tunneling boring primary steel mould trolley
CN103306463A (en) Metal liner concrete air channel construction method
CN100429375C (en) A kind of high-rise building elevator shaft formwork and its construction method
CN202381104U (en) Integrally cast culvert pipe body construction device for hydraulic steel form carrier
CN202401753U (en) Sliding die device
CN106522542B (en) A kind of light engine position hydraulic climbing die block system and its method of climbing

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant