CN103125296B - Plant water retention pit and water retention method of Yunnan phosphorite refuse dumps - Google Patents
Plant water retention pit and water retention method of Yunnan phosphorite refuse dumps Download PDFInfo
- Publication number
- CN103125296B CN103125296B CN201310083438.6A CN201310083438A CN103125296B CN 103125296 B CN103125296 B CN 103125296B CN 201310083438 A CN201310083438 A CN 201310083438A CN 103125296 B CN103125296 B CN 103125296B
- Authority
- CN
- China
- Prior art keywords
- water
- hole
- pit
- filled
- layer
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A40/00—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production
- Y02A40/10—Adaptation technologies in agriculture, forestry, livestock or agroalimentary production in agriculture
- Y02A40/22—Improving land use; Improving water use or availability; Controlling erosion
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P60/00—Technologies relating to agriculture, livestock or agroalimentary industries
- Y02P60/40—Afforestation or reforestation
Landscapes
- Cultivation Of Plants (AREA)
Abstract
Description
技术领域 technical field
本发明涉及一种植物保水坑穴及保水方法,具体地说是一种在云南磷矿排土场进行植树造林时,使用的植物保水坑穴及保水方法,属于种植技术领域。 The invention relates to a plant water retention pit and a water retention method, in particular to a plant water retention pit and a water retention method used in afforestation at a phosphate dump in Yunnan, and belongs to the technical field of planting.
背景技术 Background technique
云南滇池流域是我国重要的磷矿集中分布区域。磷矿开采过程中剥离的废石堆积地称为排土场。对滇池流域磷矿排土场开展植被恢复,既可以减少滇池磷污染压力,又可以改善生态环境,增加土地使用经济效益。但由于滇池流域的雨季和旱季较为分明,且旱季土壤缺水严重,要在干燥的磷矿排土场尽快恢复植被,其首要任务就是要提高种植坑穴的保水能力。但目前滇池流域磷矿排土场植被恢复没有有效的保水措施,制约着磷矿排土场植被恢复的进程。因此,在不使用化学物质,仅通过种植坑穴的改造来保持一定时间内的土壤水分,是尽快恢复磷矿排土场植被的重要措施。 The Dianchi Lake Basin in Yunnan is an important concentrated distribution area of phosphate rock in my country. The accumulation of waste rock stripped during the phosphate rock mining process is called a dump. Carrying out vegetation restoration on the phosphate mine dump in Dianchi Lake Basin can not only reduce the pressure of phosphorus pollution in Dianchi Lake, but also improve the ecological environment and increase the economic benefits of land use. However, since the rainy and dry seasons in the Dianchi Lake Basin are relatively distinct, and the soil water shortage is serious in the dry season, the first task of restoring vegetation in the dry phosphate dump is to improve the water retention capacity of the planting pits. However, at present, there are no effective water conservation measures for vegetation restoration of phosphate mine dumps in Dianchi Lake Basin, which restricts the process of vegetation restoration of phosphate mine dumps. Therefore, maintaining soil moisture for a certain period of time only through the transformation of planting pits without using chemicals is an important measure to restore vegetation in phosphate rock dumps as soon as possible.
发明内容 Contents of the invention
针对云南磷矿排土场植被恢复过程中,存在种植坑穴保水难的问题,本发明提供一种云南磷矿排土场植物保水坑穴及保水方法。以在植树造林后3年内的关键期内,有效保持土壤水分。 Aiming at the problem of difficult water retention in planting pits in the vegetation restoration process of the phosphate mine dump in Yunnan, the present invention provides a plant water retention pit and water retention method in the phosphate mine dump in Yunnan. To effectively maintain soil moisture during the critical period of 3 years after afforestation.
本发明提供的是这样一种云南磷矿排土场植物保水坑穴,包括其顶部敞开,中部为空腔,底部封闭的坑穴,其特征在于坑穴底水平设置敞口槽,该敞口槽的上方设置过滤层,过滤层上方设置基肥层,基肥层上方设置栽种土层,并在基肥层和栽种土层中设置多根倾斜的底部封闭,上部设通孔的盛水管,以通过底部敞口槽集水,再通过敞口上的过滤层的毛细作用,缓慢向土壤输送水分,同时通过过滤层上部放置的多根倾斜盛水管收集水后,再通过盛水管上部的通孔将水气送入土壤中,使种植在栽种土层中的树苗得到足够的水分。 The present invention provides such a water-retaining pit for plants in a phosphate rock dump in Yunnan, which includes an open top, a cavity in the middle, and a closed bottom. A filter layer is arranged above the tank, a base fertilizer layer is arranged above the filter layer, a planting soil layer is arranged above the base fertilizer layer, and a plurality of inclined bottoms are arranged in the base fertilizer layer and the planting soil layer to close, and a through-hole water holding pipe is arranged on the upper part to pass through the bottom The open trough collects water, and then slowly transports water to the soil through the capillary action of the filter layer on the open opening. At the same time, after collecting water through a number of inclined water pipes placed on the upper part of the filter layer, the water vapor is discharged through the through holes on the upper part of the water pipe. Send it into the soil, so that the saplings planted in the planting soil layer can get enough water.
所述坑穴底部水平设置的敞口槽至少设两根,呈斜交叉或十字交叉叠放在坑穴底部,以方便集水、盛水。 There are at least two open grooves horizontally arranged at the bottom of the pit, which are stacked on the bottom of the pit in an oblique or criss-cross manner to facilitate water collection and storage.
所述敞口槽下方设有由碎石和粘土夯实的底土层,其厚度为10~20cm,以阻止部分水分渗透至坑穴外。 A subsoil layer compacted by gravel and clay is arranged under the open tank, and its thickness is 10-20 cm, so as to prevent part of the water from penetrating out of the pit.
所述敞口槽上方的过滤层为枯枝杂草层,其厚度为5~10cm以便过滤自上而下的渗水,防止渣、泥进入敞口槽中,同时支撑基肥层。 The filter layer above the open tank is a layer of dead branches and weeds, with a thickness of 5-10 cm in order to filter water seepage from top to bottom, prevent slag and mud from entering the open tank, and support the base fertilizer layer at the same time.
所述基肥层为厚度为10~20cm的植物生长所需的常规基肥。 The base fertilizer layer is a conventional base fertilizer required for plant growth with a thickness of 10-20 cm.
所述栽种土层为厚度为25~35cm的土壤层。 The planting soil layer is a soil layer with a thickness of 25-35 cm.
所述栽种土层的上表面与坑穴顶面设凹槽,该凹槽的高度为3~7cm,以方便集水。 A groove is provided on the upper surface of the planting soil layer and the top surface of the pit, and the height of the groove is 3-7 cm to facilitate water collection.
所述多根倾斜的盛水管沿坑穴四周间隔设置,每一根盛水管的封闭底部位于坑穴中心部位,设通孔的上部位于坑穴壁面,且盛水管的封闭底部为低端,盛水管的设通孔的上部为高端,形成中心低、周边高的倾斜管,以便收集渗透水。 The plurality of inclined water pipes are arranged at intervals around the pit, the closed bottom of each water pipe is located at the center of the pit, the upper part of the through hole is located on the wall of the pit, and the closed bottom of the water pipe is at the lower end. The upper part of the through hole of the water pipe is set as a high end, forming an inclined pipe with a low center and a high periphery, so as to collect seepage water.
所述敞口槽及盛水管为竹筒,或者为木材制成,或者为塑料制成,或者为金属制成,优选竹筒。 The open tank and the water-holding pipe are bamboo tubes, or made of wood, or made of plastic, or made of metal, preferably bamboo tubes.
本发明提供的云南磷矿排土场植物保水方法,经过下列步骤: The plant water retention method of Yunnan phosphate mine dump site provided by the invention, through the following steps:
A、在植树造林的云南磷矿排土场挖掘出70~90cm×70~90cm的坑穴: A. A 70-90cm×70-90cm pit was excavated in the Yunnan Phosphate Mine Dump Site for afforestation:
B、在上述坑穴的穴底夯实厚度为10~20cm的由直径小于2cm的碎石和粘土组成的底土层,以阻止部分水分向坑穴外渗透; B. Tamping the subsoil layer composed of gravel and clay with a diameter of less than 2cm at the bottom of the above-mentioned pit with a thickness of 10-20 cm to prevent part of the water from penetrating out of the pit;
C、在底土层上水平放置两层敞口槽,每一层敞口槽至少设一根,呈斜交叉或十字交叉叠放在坑穴底部,以方便集水、盛水; C. Place two layers of open troughs horizontally on the subsoil layer, at least one open trough for each layer, and stack them on the bottom of the pit in an oblique or crossed manner to facilitate water collection and storage;
D、在敞口槽上铺设厚度为5~10cm的枯枝杂草过滤层,以过滤自上而下的渗水,防止渣、泥进入敞口槽中,同时支撑基肥层; D. Lay a filter layer of dead branches and weeds with a thickness of 5-10cm on the open tank to filter water seepage from top to bottom, prevent slag and mud from entering the open tank, and support the base fertilizer layer at the same time;
E、在枯枝杂草过滤层上铺放厚度为10~20cm的植物生长所需的常规基肥; E. Lay the conventional basal fertilizer required for plant growth with a thickness of 10 to 20 cm on the filter layer of dead branches and weeds;
F、将多根盛水管沿坑穴四周间隔倾斜设置,每一根盛水管的封闭底部位于坑穴中心部位,设通孔的上部位于坑穴壁面,且盛水管的封闭底部为低端,盛水管的设通孔的上部为高端,以形成中心低、周边高的倾斜管,以便收集渗透水; F. A plurality of water-holding pipes are arranged at intervals along the pit, and the closed bottom of each water-filling pipe is located in the center of the pit. The upper part of the through hole is located on the wall of the pit, and the closed bottom of the water-filled pipe is the The upper part of the through hole of the water pipe is set as a high end, so as to form an inclined pipe with a low center and a high periphery, so as to collect infiltrated water;
G、在多根盛水管之间的空隙处填充植物生长所需的土壤,以形成厚度为25~35cm的土壤层; G. Fill the gaps between multiple water pipes with the soil required for plant growth to form a soil layer with a thickness of 25-35cm;
H、将树苗按常规种植在土壤层中,该土壤层的上表面与坑穴顶面设凹槽,该凹槽的高度为3~7cm,以便集水; H, the sapling is planted in the soil layer as usual, the upper surface of the soil layer and the top surface of the pit are provided with grooves, and the height of the grooves is 3~7cm, so as to collect water;
I、按常规进行植树管理,直至树苗长大。 1. Carry out tree planting management as usual until the saplings grow up.
本发明具有下列优点和效果:采用上述方案,可通过底部敞口槽收集大量水,再通过敞口上的过滤层的毛细作用,缓慢向土壤输送水分,同时通过过滤层上部放置的多根倾斜盛水管收集水后,再通过盛水管上部的通孔将水气送入土壤中,使种植在栽种土层中的树苗得到足够的水分,并从基肥层中吸取营养成分,这样可在植树造林后3年内的关键期内,有效保持土壤水分。从根本上解决了磷矿排土场植被恢复过程中,种植坑穴保水差的难题,为滇池流域磷矿排土场植被的快速恢复提供可靠的技术保障,有利于加快磷矿排土场植被恢复的进程。本发明提供的植物保水坑穴适用于任何植物种植的保水要求,具有无污染,成本低,操作简单,保水效果好等特点。本方法特别适用于植树造林的植物保水需要。 The present invention has the following advantages and effects: adopting the above-mentioned scheme, a large amount of water can be collected through the bottom open tank, and then slowly transport water to the soil through the capillary action of the filter layer on the open opening, and at the same time, the water can be transported to the soil through a plurality of inclined roots placed on the upper part of the filter layer. After the water pipe collects water, the water vapor is sent into the soil through the through hole on the upper part of the water pipe, so that the saplings planted in the planting soil layer can get enough water and absorb nutrients from the base fertilizer layer, so that after afforestation Effectively maintain soil moisture during the critical period of 3 years. It fundamentally solves the problem of poor water retention in planting pits during the vegetation restoration process of phosphate rock dumps, provides reliable technical support for the rapid restoration of vegetation in phosphate rock dumps in the Dianchi Lake Basin, and is conducive to speeding up the vegetation of phosphate rock dumps recovery process. The plant water retention pit provided by the invention is suitable for the water retention requirements of any plant planting, and has the characteristics of no pollution, low cost, simple operation, good water retention effect and the like. The method is particularly suitable for plant water conservation needs of afforestation.
附图说明 Description of drawings
图1为本发明植物种植保水坑穴结构示意图。 Fig. 1 is a schematic diagram of the plant planting water retention pit structure of the present invention.
具体实施方式 Detailed ways
下面结合附图及实施例对本发明做进一步描述。 The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
如图1,本发明提供的云南磷矿排土场植物保水坑穴,包括其顶部敞开,其中部为空腔,其底部封闭的坑穴1,在坑穴1底部水平设置两层敞口槽3,每一层敞口槽3设一根,呈十字交叉叠放在坑穴1底部,敞口槽3的上方设置厚度为3cm的枯枝杂草过滤层4,过滤层4上方设置厚度为15cm的基肥层5,基肥层5上方设置厚度为30cm的栽种土层6,并在基肥层5和栽种土层6中设置四根倾斜的底部封闭,上部设通孔的盛水管7,四根倾斜的盛水管7沿坑穴1四周间隔设置,每一根盛水管7的封闭底部位于坑穴1中心部位,设通孔的上部位于坑穴1壁面,且盛水管7的封闭底部为低端,盛水管的设通孔的上部为高端,形成中心低、周边高的倾斜管,敞口槽3及盛水管7用竹制成,敞口槽3下方设有由碎石和粘土夯实的底土层2,其厚度为15cm,以阻止部分水分渗透至坑穴外,同时通过敞口槽3集水,再通过敞口上的过滤层4的毛细作用,缓慢向土壤输送水分,同时通过过滤层4上部放置的多根倾斜盛水管7收集水后,再通过盛水管7上部的通孔将水气送入土壤中,使种植在栽种土层中的树苗得到足够的水分及营养,栽种土层6的上表面与坑穴1顶面设凹槽8,该凹槽8的高度为5cm,以方便集水。 As shown in Fig. 1, the plant water retention pit of the Yunnan phosphate mine dump site provided by the present invention includes a pit 1 whose top is open, the middle part is a cavity, and the bottom is closed, and two layers of open grooves are horizontally arranged at the bottom of the pit 1 3, each layer of open groove 3 is provided with one, which is stacked on the bottom of the pit 1 in a cross, and a dead branch and weed filter layer 4 with a thickness of 3 cm is set above the open groove 3, and a thickness of 3 cm is set above the filter layer 4. The base fertilizer layer 5 of 15cm, the planting soil layer 6 with a thickness of 30cm is set above the base fertilizer layer 5, and four inclined bottoms are set in the base fertilizer layer 5 and the planting soil layer 6 to close, and the top is provided with through-hole water holding pipes 7, four The inclined water pipes 7 are arranged at intervals around the pit 1, the closed bottom of each water pipe 7 is located at the center of the pit 1, the upper part of the through hole is located on the wall of the pit 1, and the closed bottom of the water pipe 7 is the lower end. , the upper part of the through hole of the water pipe is set as a high end, forming an inclined pipe with a low center and a high periphery. The open groove 3 and the water pipe 7 are made of bamboo, and the bottom of the open groove 3 is provided with subsoil compacted by gravel and clay. Layer 2, its thickness is 15cm, to prevent part of the water from penetrating to the outside of the pit, and at the same time collect water through the open groove 3, and then through the capillary action of the filter layer 4 on the opening, slowly transport water to the soil, and at the same time pass through the filter layer 4 After the many inclined water holding pipes 7 placed on the top collect water, water vapor is sent into the soil through the through holes on the top of the water holding pipe 7, so that the saplings planted in the planting soil layer can get enough water and nutrition, and the planting soil layer 6 Groove 8 is established on the upper surface and pit 1 top surface, and the height of this groove 8 is 5cm, to facilitate water collection.
实施例 Example
本发明提供的云南磷矿排土场植物保水方法,经过下列步骤: The plant water retention method of Yunnan phosphate mine dump site provided by the invention, through the following steps:
A、在植树造林的磷矿排土场挖掘出80cm×80cm的坑穴1: A. Excavate a pit 1 of 80cm×80cm in the phosphate rock dump for afforestation:
B、在上述坑穴1的穴底夯实厚度为15cm的由直径小于2cm的碎石和粘土组成的底土层2,并将坑穴四周的壁面夯实,以阻止部分水分向坑穴外渗透; B, at the bottom of the hole of above-mentioned hole 1, tamping thickness is the subsoil layer 2 that the diameter is less than 2cm and the subsoil layer 2 that is made up of gravel and clay of 15cm, and the wall surface around the hole is tamped, to stop part moisture from penetrating outside the hole;
C、在底土层2上水平放置两层竹制敞口槽3,每一层竹制敞口槽3设一根,呈十字交叉叠放在坑穴1底部,以方便集水、盛水; C. Place two layers of bamboo open grooves 3 horizontally on the subsoil layer 2, and set one bamboo open groove 3 on each layer, which is stacked on the bottom of the pit 1 in a cross to facilitate water collection and water storage;
D、在竹制敞口槽3上铺设厚度为10cm的枯枝杂草过滤层4,以过滤自上而下的渗水,防止渣、泥进入敞口槽3中,同时支撑基肥层5; D, on the open groove 3 made of bamboo, lay a dead branch weed filter layer 4 with a thickness of 10cm, to filter the seepage from top to bottom, prevent slag and mud from entering the open groove 3, and support the base fertilizer layer 5 simultaneously;
E、在枯枝杂草过滤层4上铺放厚度为15cm的植物生长所需的常规基肥层5; E, on the litter weed filter layer 4, lay the conventional basal manure layer 5 that thickness is needed for the plant growth of 15cm;
F、将四根竹制盛水管7沿坑穴1四周间隔倾斜设置,每一根竹制盛水管7的封闭底部位于坑穴1中心部位,设通孔的上部位于坑穴1壁面,且竹制盛水管7的封闭底部为低端,竹制盛水管7的设通孔的上部为高端,以形成中心低、周边高的倾斜管,以便收集渗透水; F, the four bamboo water holding pipes 7 are arranged obliquely at intervals around the pit 1, the closed bottom of each bamboo water holding pipe 7 is located at the center of the pit 1, the upper part of the through hole is located at the wall of the pit 1, and the bamboo The closed bottom of the water holding pipe 7 is a low end, and the upper part of the through hole of the bamboo water holding pipe 7 is a high end, so as to form an inclined pipe with a low center and a high periphery, so as to collect infiltrated water;
G、在四根竹制盛水管7之间的空隙处填充植物生长所需的土壤,以形成厚度为30cm的土壤层6; G, fill the soil required for plant growth in the gaps between four bamboo water holding pipes 7, to form a soil layer 6 with a thickness of 30cm;
H、将树苗按常规种植在土壤层6中,该土壤层6的上表面与坑穴1顶面设高度为5cm的凹槽8,以形成集水层; H, sapling is conventionally planted in soil layer 6, and the upper surface of this soil layer 6 and pit 1 top surface establish the groove 8 that height is 5cm, to form catchment layer;
I、按常规进行植树管理,直至树苗长大。 1. Carry out tree planting management as usual until the saplings grow up.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310083438.6A CN103125296B (en) | 2013-03-16 | 2013-03-16 | Plant water retention pit and water retention method of Yunnan phosphorite refuse dumps |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201310083438.6A CN103125296B (en) | 2013-03-16 | 2013-03-16 | Plant water retention pit and water retention method of Yunnan phosphorite refuse dumps |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN103125296A CN103125296A (en) | 2013-06-05 |
| CN103125296B true CN103125296B (en) | 2015-05-20 |
Family
ID=48486246
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201310083438.6A Expired - Fee Related CN103125296B (en) | 2013-03-16 | 2013-03-16 | Plant water retention pit and water retention method of Yunnan phosphorite refuse dumps |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN103125296B (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103493665A (en) * | 2013-09-27 | 2014-01-08 | 北京东方园林股份有限公司 | Method for planting large-standard trees in clayed soil |
| CN104620891A (en) * | 2015-02-27 | 2015-05-20 | 黄丽玲 | Flower pot with oblique-opening air tubes |
| CN105484225B (en) * | 2015-12-25 | 2020-07-31 | 中国科学院、水利部成都山地灾害与环境研究所 | Gully head energy dissipation gully bank stabilizing method |
| CN105830859A (en) * | 2016-05-18 | 2016-08-10 | 四川九鼎智远知识产权运营有限公司 | Dry-land tree planting method |
| CN108617457A (en) * | 2018-04-04 | 2018-10-09 | 佛山市亚科恒远科技有限公司 | Nursery stock transplanting device |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1860845A (en) * | 2005-05-08 | 2006-11-15 | 陈建 | Equipment for growing plants |
| CN201809249U (en) * | 2010-06-25 | 2011-04-27 | 中国水利水电科学研究院 | Artificial filler underground infiltration domestic sewage treatment system |
| CN202222220U (en) * | 2011-09-20 | 2012-05-23 | 北京正和恒基滨水生态环境治理有限公司 | Tree hole suitable for planting seedlings in clay soil |
| CN202785811U (en) * | 2012-08-22 | 2013-03-13 | 山东大学 | Rip irrigation type soil infiltration system |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR2707451B1 (en) * | 1993-07-02 | 1995-10-13 | Barre Louis Jean Marie Joseph | Agricultural container for sowing / cutting and planting trees. |
| JPH1075669A (en) * | 1996-09-06 | 1998-03-24 | Ohbayashi Corp | Device for keeping or draining water in soil for greening |
| CN2531628Y (en) * | 2002-01-28 | 2003-01-22 | 北京科技大学 | Buried in type water storage apparatus |
| KR101225187B1 (en) * | 2012-06-22 | 2013-01-22 | 오준성 | Rooftop gardening structure |
-
2013
- 2013-03-16 CN CN201310083438.6A patent/CN103125296B/en not_active Expired - Fee Related
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1860845A (en) * | 2005-05-08 | 2006-11-15 | 陈建 | Equipment for growing plants |
| CN201809249U (en) * | 2010-06-25 | 2011-04-27 | 中国水利水电科学研究院 | Artificial filler underground infiltration domestic sewage treatment system |
| CN202222220U (en) * | 2011-09-20 | 2012-05-23 | 北京正和恒基滨水生态环境治理有限公司 | Tree hole suitable for planting seedlings in clay soil |
| CN202785811U (en) * | 2012-08-22 | 2013-03-13 | 山东大学 | Rip irrigation type soil infiltration system |
Also Published As
| Publication number | Publication date |
|---|---|
| CN103125296A (en) | 2013-06-05 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| US10405502B2 (en) | Water and soil conservation and ecological restoration method of high and steep, abandoned slag piles at high elevation with large temperature difference in dry, hot valley | |
| CN101485275B (en) | Sylvicultural method on argillaceous saline soil | |
| CN103262689B (en) | Coastal saline-alkali soil terrace type afforesting method for improvement of dredger fill | |
| CN106612692B (en) | A landscape greening method and landscape tree species planting structure of coastal saline-alkali land based on biochar interlayer | |
| CN104429215A (en) | Ecological restoration management method for coal spontaneous combustion fire potential areas | |
| CN108650924B (en) | Method for constructing saline-alkali soil body by classifying and disposing greening plant wastes | |
| CN204762460U (en) | Planting system in saline and alkaline land | |
| CN103125296B (en) | Plant water retention pit and water retention method of Yunnan phosphorite refuse dumps | |
| CN102138491A (en) | Soil and ecological control method for coastal beaches | |
| CN104652452A (en) | Water-collecting irrigation device for slope protection in karst regions | |
| CN112012229A (en) | Ecological restoration system for high steep slope rock slope of limestone mine stope | |
| CN107896548B (en) | A method and irrigation system suitable for ecological management of cliff sections in karst rocky mountainous areas | |
| CN104846912B (en) | Dune area water collection irrigation system | |
| CN104429802B (en) | Unirrigated vegetation planting method by Haloxylonammodendron for heavy clay lands of arid area | |
| CN101213925B (en) | Drought resisting method for man-made forest construction and foster | |
| CN106489465A (en) | A kind of in heavy salinized the method for recovering sheep's hay vegetation in the north | |
| CN103821131B (en) | The restorative procedure of development construction item soil and water conservation ecological | |
| CN203646005U (en) | Local collection permeation-enhancing evaporation-suppression saline-alkali land improvement system | |
| CN103141323B (en) | Season drought barren slope economic crop planting pit and planting method | |
| CN109673316A (en) | A kind of comprehensive greening system of exposed scar and method | |
| CN105200998B (en) | ecological slope protection structure | |
| CN211240745U (en) | Saline-alkali soil salt elimination and prevention ecological structure | |
| CN203618424U (en) | Structure suitable for vegetation recovery of high steep-hill waste slag slope | |
| CN106958224A (en) | A kind of method that wetland mud is administered | |
| CN115104396B (en) | Soil improvement and soil preparation forestation method for arid abrupt slope sandy soil |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150520 Termination date: 20190316 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |