CN103015519A - Pipe-jacking construction of drain pipe - Google Patents

Pipe-jacking construction of drain pipe Download PDF

Info

Publication number
CN103015519A
CN103015519A CN 201210575945 CN201210575945A CN103015519A CN 103015519 A CN103015519 A CN 103015519A CN 201210575945 CN201210575945 CN 201210575945 CN 201210575945 A CN201210575945 A CN 201210575945A CN 103015519 A CN103015519 A CN 103015519A
Authority
CN
China
Prior art keywords
jacking
pipe
head
jack
iron
Prior art date
Application number
CN 201210575945
Other languages
Chinese (zh)
Inventor
朱奎
Original Assignee
朱奎
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 朱奎 filed Critical 朱奎
Priority to CN 201210575945 priority Critical patent/CN103015519A/en
Publication of CN103015519A publication Critical patent/CN103015519A/en

Links

Abstract

The invention discloses a pipe-jacking construction of a drain pipe, which is characterized by comprising the following steps of: (1) surveying and setting out; (2) constructing a working well, wherein a cover of the inner wall of the working well is coated by two layers; (3) installing a fabricated back wall; (4) installing guide rails; (5) installing a main jack; (6) installing an oil pump; (7) installing an ejector iron; (8) constructing and sealing an inlet and an outlet; (9) jacking the pipe, wherein a buffer material pad is arranged between the ejector iron and the pipe port, a ring ejector iron is additionally arranged on the end of the pipe when the jacking force is close to the allowable compressive strength of a pipe section material; and (10) unearthing.

Description

The gutter jacking construction

Technical field

The present invention relates to the gutter construction, particularly a kind of gutter jacking construction.

Background technology

Construction by pipeline jacking method and the construction of fluting method are compared, and pipeline not soil excavation and the backfilling working amount of slot grooving reduces a lot; Needn't remove ground obstacle; Can not affect traffic above-ground; Can not increase the earth excavation amount because of the embedding degree of depth of pipeline; Pipeline needn't arrange basis and base; Can reduce pipeline environment pollution along the line etc.But larger to the soil disturbance around the body in the drain pipe jacking construction process, be difficult to keep the stable of excavation surface.

Summary of the invention

For the deficiencies in the prior art, the object of the present invention is to provide a kind of gutter jacking construction.

When the present invention worked at development machine, cutterhead was close to the soil body section that is cut by predefined pressure, and the one side rotary cutting soil body under the effect of top power is pushed ahead the balance of keeping the soil body on the one hand in the wings.If soil body hardness increases in the jacking, push up fastly when constant, cutterhead is subject to head resistance greater than the cutterhead pressure that presets, and cutterhead is retracted gradually backward, keeps cutterhead constant to the pressure of the soil body.When cutterhead was retracted, the Tu Kou that cuts of cutterhead increased automatically, and the amount of the cutting soil body increases, and the soil body reduces the pressure of cutterhead, and soil pressure increases, and cutterhead still keeps balance with soil pressure and the soil body that presets at reposition.Cooperate the manual adjustments cutterhead to cut the regulatory function of Tu Kou and preset pressure size, make soil body lateral pressure obtain point-device balance.Manual-lock is cut Tu Kou during shutdown, and cutterhead still keeps predetermined pressure to be close to the soil body, and with muddy water storehouse and Excavation isolation.No matter the soil body is crossed softly or really up to the mark, and when automatic adjustable range value of reaching the limit of, the cutterhead warning device is reported to the police, and reminds operating personnel to note, by regulating top speed, resets the means such as cutterhead pressure, makes the soil body keep new balance.

The present invention injects the mud of certain pressure to the excavation storehouse, this mud by the size of control mud extraction flow, thereby simply and is exactly controlled water pressure in the muddy water storehouse, balance underground water except the particle in the soil layer can being taken away.

Construction sequence comprises:

(1) measures unwrapping wire

Lay temporary bench mark and conduit axis control stake, during the construction line-putting, establish Center stake every 20m, the place arranges Center stake at manhole.

(2) construction of working shaft

In active well reservation notch suitable for reading, steel bar concrete precast slab is installed, is wanted the seat slurry full in the notch.The wall of laying bricks at precast plate reserved opening place, all bricks are wanted saturated with water, and Ying Manpu, full squeezing are taken up and down block when building by laying bricks or stones, and thickness of mortarat bed joint and perpends width should be even, and vertical straight joint must not be arranged.When building manhole by laying bricks or stones, should install synchronously and mark time, want accurately the position, must not trample before masonry mortar reaches regulation compressive strength after the installation of marking time.Well inwall front cover should divide two-layer smearing into, strikes off and make the surface to cause coarse line after first is smeared into; After the second mortar dries, compacting troweling at twice.Slurry and the interlayer of the basic unit close and firm that should bond must not have the phenomenons such as hollowing and crackle.The planeness of wiping one's face should be greater than 15mm.After plastering mortar solidifies, should keep moist curing, curing time is no less than 14d.

(3) parados is installed behind the assembling

The parados back soil body must be evenly closely knit behind the assembling, and wall should be smooth, and with pipeline jacking perpendicular direction; Back soil body wall should be close to rear parados, should adopt the sand material filling closely knit when hole is arranged.The bottom of parados following 500mm at the bottom of working pit behind the assembling, thus make rear jack center of effort highly be not less than 1/3 of back lumps of wood height, the point of making a concerted effort of being broken ground behind origin of force and the wall is consistent.Parados verticality allowable variation is parados height behind 0.1% assembling behind the assembling, and horizontal torsion degree allowable variation is parados length behind 0.1% assembling.

(4) guide rails assembling

During guide rails assembling and active well base plate pre-embedded steel slab weld, and enclose the jail with type steel support.To check first the pipeline center position before the guide rails assembling, guarantee that the elevation of guide rail, axial location are accurate.The rail axis position deviation is no more than 3mm, and the elevation of top surface deviation is no more than 3mm, is no more than 2mm apart from deviation in two rails.The guide rail end can not be too far away apart from the work wall, should be controlled at about 500mm, and reserving seam during guide rails assembling highly is 100~150mm.

(5) main top jack installation

Jack will be arranged take pipe centerline as axial symmetry.Main top oil cylinder frame is installed and is wanted accurate positioning, guarantees the correct position of cylinder force point, and its elevation and plane alignment error should be controlled in the 3mm.The oil cylinder errors of centration that is installed on the oil cylinder frame is controlled in the 3mm.Jack is fixed on the support, and its central point of making a concerted effort is on pipe centerline; The oil circuit of jack should be in parallel, and every jack should have oil-feed, move back oily control system.The position of jack is positioned at 1/3~1/4 place of pipeline perpendicular diameter, makes jack make a concerted effort the position of position and jacking drag on same axis, avoids producing the top couple, makes pipeline generation vertical error.

(6) oil pump is installed

Oil pump is arranged near the jack, and oil pipe is straight, corner is few; Oil pump should be complementary with jack, and emergency bearing oil pump is arranged; Oil pump installs, and carries out test running.When beginning, jacking slowly carries out, after each contact site driving fit, again by normal move speed jacking; If find in the jacking that oil pressure increases suddenly, stop immediately jacking, check reason and continue after treatment jacking; When jack piston was return, oil pressure was not too much, and speed must not be too fast.

(7) top iron is installed

Top iron adopts the cast-steel integral casting or adopts the shaped steel welding fabrication.The vertical top of single file iron center line is consistent with conduit axis; Two center lines of the vertical top of duplicate rows iron are parallel, and equate with the tubular axis linear distance, and will be perpendicular to the pipe end plane.The adjacent surface of top iron is orthogonal, on the iron of top locking device is arranged, and top iron should be able to keep stable when placing.When vertically top iron contacts with end surfaces, must make vertical top iron origin of force height and position be positioned at external diameter 1/3~1/4 place, cause front pipe to bow to prevent that origin of force is too high.When top power was larger, end surfaces should add arched top iron steel plate, to increase the lifting surface area of pipe end, improved its stressing conditions, prevented that pipe from damaging when top power is excessive.When changing top iron, use first the large top iron of length, should lock after the iron assembly unit of top.Should adopt the padded coaming liner between top iron and the mouth of pipe, when top power during near the permission compressive strength of tube coupling material, pipe end should increase circular top iron.During jacking, the staff must not be above the iron of top and the side stop, and observe at any time top iron and have or not unusual sign.

(8) construction of turnover hole and sealing

Equipment installs a complete set of jacking device of rear reply and does the primary system debugging, after definite jacking device service behavior is good, and beginning jacking work.When growing apart from jacking, be to reduce the jacking resistance, make sealing ring at the portal place so that the thixotropic slurry performance drag-reduction effect that pours into.

(9) pipeline jacking

After dismounting is sealed up a door, should begin immediately the jacking head, after the jacking 300mm, unlatching adds the mud system and injects mud, in order to regulate the creeping of dregs and keep earth pressure balance.When head just buries, because head does not have enough resisting moment in orbit, head easily produced rotation when cutterhead was rotated, so when the initial 2m that buries, move speed is controlled at below the 5mm/min, in case the rotation of stop machine head, and incessantly observation airplane head inclination angle and the anglec of rotation, the inclination angle changes with the levelling of correction jack, and the anglec of rotation is greater than ± 50 degree, and cutterhead is opened the counter-rotating levelling; In the non-rotary situation of head behind the jacking 2m, strengthen gradually move speed.When head buried not yet fully, support pressure was controlled at 0.1~0.15MPa.After head all buried, lower the first pipe joint was done rear enclosed.After rear enclosed is complete, annotate the space of cement mortar filling head outside backbreaking at 1: 2 to the head shell injected hole, grouting pressure is controlled at 0.4MPa.The hole soil property is unstable when preventing that head from just appearing produces landslide, locates built-in rigidity piston ring at the hole.Rear enclosed adopts the ring-shaped rubber plate to be close to the soil body, and the hole side wall covers pressure with doughnut-shaped steel plate, and the running pulp phenomenon occurs when preventing from annotating thixotropic slurry.Control support pressure according to predefined parameter during jacking, meet sand gravel layer, when nearer apart from building, soil pressure is set suitably and is strengthened, and improves safety factor.The thixotropic slurry drag reduction is the drag reduction mode that long-distance pipe-jacking construction often adopts, and can effectively reduce resistance, lengthens to greatest extent apex distance.Be provided with the thixotropic slurry injected hole at the head afterbody, every joint concrete reinforced pipe is established injected hole, at any time slip casting during jacking.Move speed is controlled at 30~50mm/min, uses low speed when front 30m and correction, and looking afterwards is unearthed stirs, the cutterhead torque condition is suitably accelerated move speed.During lower pipe, stop under the jacking state at head, cutterhead idle running 3~5min closes conveying worm spoil disposal hydraulic pressure door when shutting down, and outage is to guarantee soil pressure storehouse soil pressure.

If center, height variation then will stop jacking immediately greater than ± 20mm, correction is proofreaied and correct and should slowly be carried out, and tube coupling is resetted gradually, must not suddenly entangle vigour.When wherein rectifying a deviation elevation, the pipe on the track will add counterweight; During the correction center, the pipe on the track will add supported on both sides.After head all enters the hole, and elevation, centre deviation will in time adopt the head correcting device to rectify a deviation during greater than 10mm, and the center is controlled in the 5mm, elevation is controlled at ± 10mm in, tool heads self straightening method is adopted in bearing calibration.The effective control tool head of this method for correcting error is the state of four direction up and down, and the amplitude of at every turn rectifying a deviation is measured the off normal judgement take 5mm as a unit according to inclinometer and the laser transit of tool heads, if when trend does not reduce, increases the correction dynamics; If when trend stability or minimizing, should keep this correction dynamics, continue jacking; When off normal trend is opposite, then need the correction dynamics is reduced gradually.In the pipeline jack-in process, if move speed is on the low side in fine silty layer, turn down the concentration of hydraulic mixture into mud, reduce move speed.When running into the different soil layer of soft or hard degree, judge geological conditions by the torque of cutterhead.If suddenly hardening then should add entry or mud in native storehouse.

(10) be unearthed

The soil that excavates in the push-bench course of work is transported on the belt conveyer through conveying worm first, is transported in the battery truck through belt conveyer again, and battery truck is transported to active well, and Tu Chang is deposited on last vertical handling to ground, regularly outward transport.

The present invention has that construction speed is fast, the significant advantage of social benefit.

The specific embodiment

The present embodiment construction sequence comprises:

(1) measures unwrapping wire

Lay temporary bench mark and conduit axis control stake, during the construction line-putting, establish Center stake every 20m, the place arranges Center stake at manhole.

(2) construction of working shaft

In active well reservation notch suitable for reading, steel bar concrete precast slab is installed, is wanted the seat slurry full in the notch.The wall of laying bricks at precast plate reserved opening place, all bricks are wanted saturated with water, and Ying Manpu, full squeezing are taken up and down block when building by laying bricks or stones, and thickness of mortarat bed joint and perpends width should be even, and vertical straight joint must not be arranged.When building manhole by laying bricks or stones, should install synchronously and mark time, want accurately the position, must not trample before masonry mortar reaches regulation compressive strength after the installation of marking time.Well inwall front cover should divide two-layer smearing into, strikes off and make the surface to cause coarse line after first is smeared into; After the second mortar dries, compacting troweling at twice.Slurry and the interlayer of the basic unit close and firm that should bond must not have the phenomenons such as hollowing and crackle.The planeness of wiping one's face should be greater than 15mm.After plastering mortar solidifies, should keep moist curing, curing time is no less than 14d.

(3) parados is installed behind the assembling

The parados back soil body must be evenly closely knit behind the assembling, and wall should be smooth, and with pipeline jacking perpendicular direction; Back soil body wall should be close to rear parados, should adopt the sand material filling closely knit when hole is arranged.The bottom of parados following 500mm at the bottom of working pit behind the assembling, thus make rear jack center of effort highly be not less than 1/3 of back lumps of wood height, the point of making a concerted effort of being broken ground behind origin of force and the wall is consistent.

(4) guide rails assembling

During guide rails assembling and active well base plate pre-embedded steel slab weld, and enclose the jail with type steel support.To check first the pipeline center position before the guide rails assembling, guarantee that the elevation of guide rail, axial location are accurate.The rail axis position deviation is no more than 3mm, and the elevation of top surface deviation is no more than 3mm, is no more than 2mm apart from deviation in two rails.The guide rail end can not be too far away apart from the work wall, should be controlled at about 500mm, and reserving seam during guide rails assembling highly is 120mm.

(5) main top jack installation

Jack will be arranged take pipe centerline as axial symmetry.Main top oil cylinder frame is installed and is wanted accurate positioning, guarantees the correct position of cylinder force point, and its elevation and plane alignment error should be controlled in the 3mm.The oil cylinder errors of centration that is installed on the oil cylinder frame is controlled in the 3mm.Jack is fixed on the support, and its central point of making a concerted effort is on pipe centerline; The oil circuit of jack should be in parallel, and every jack should have oil-feed, move back oily control system.The position of jack is positioned at 7/24 place of pipeline perpendicular diameter, makes jack make a concerted effort the position of position and jacking drag on same axis, avoids producing the top couple, makes pipeline generation vertical error.

(6) oil pump is installed

Oil pump is arranged near the jack, and oil pipe is straight, corner is few; Oil pump should be complementary with jack, and emergency bearing oil pump is arranged; Oil pump installs, and carries out test running.When beginning, jacking slowly carries out, after each contact site driving fit, again by normal move speed jacking; If find in the jacking that oil pressure increases suddenly, stop immediately jacking, check reason and continue after treatment jacking; When jack piston was return, oil pressure was not too much, and speed must not be too fast.

(7) top iron is installed

Top iron adopts the cast-steel integral casting or adopts the shaped steel welding fabrication.The vertical top of single file iron center line is consistent with conduit axis; Two center lines of the vertical top of duplicate rows iron are parallel, and equate with the tubular axis linear distance, and will be perpendicular to the pipe end plane.The adjacent surface of top iron is orthogonal, on the iron of top locking device is arranged, and top iron should be able to keep stable when placing.When vertically top iron contacts with end surfaces, must make vertical top iron origin of force height and position be positioned at external diameter 7/24 place.When top power was larger, end surfaces should add arched top iron steel plate.When changing top iron, use first the large top iron of length, should lock after the iron assembly unit of top.Should adopt the padded coaming liner between top iron and the mouth of pipe, when top power during near the permission compressive strength of tube coupling material, pipe end should increase circular top iron.During jacking, the staff must not be above the iron of top and the side stop, and observe at any time top iron and have or not unusual sign.

(8) construction of turnover hole and sealing

Equipment installs a complete set of jacking device of rear reply and does the primary system debugging, after definite jacking device service behavior is good, and beginning jacking work.When growing apart from jacking, make sealing ring so that the thixotropic slurry performance drag-reduction effect that pours at the portal place.

(9) pipeline jacking

After dismounting is sealed up a door, should begin immediately the jacking head, after the jacking 300mm, unlatching adds the mud system and injects mud, in order to regulate the creeping of dregs and keep earth pressure balance.When head just buries, because head does not have enough resisting moment in orbit, head easily produced rotation when cutterhead was rotated, so when the initial 2m that buries, move speed is controlled at below the 5mm/min, and incessantly observation airplane head inclination angle and the anglec of rotation, and the inclination angle changes with the levelling of correction jack, the anglec of rotation is greater than ± 50 degree, and cutterhead is opened the counter-rotating levelling; In the non-rotary situation of head behind the jacking 2m, strengthen gradually move speed.When head buried not yet fully, support pressure was controlled to be 0.1MPa.After head all buried, lower the first pipe joint was done rear enclosed.After rear enclosed is complete, annotate the space of cement mortar filling head outside backbreaking at 1: 2 to the head shell injected hole, grouting pressure is controlled to be 0.4MPa.Locate built-in rigidity piston ring at the hole.Rear enclosed adopts the ring-shaped rubber plate to be close to the soil body, and the hole side wall covers pressure with doughnut-shaped steel plate.Control support pressure according to predefined parameter during jacking, meet sand gravel layer, when nearer apart from building, soil pressure is set suitably and is strengthened.Be provided with the thixotropic slurry injected hole at the head afterbody, every joint concrete reinforced pipe is established injected hole, at any time slip casting during jacking.Move speed is controlled at 40mm/min, uses low speed when front 30m and correction, and looking afterwards is unearthed stirs, the cutterhead torque condition is suitably accelerated move speed.During lower pipe, stop under the jacking state at head, cutterhead idle running 3~5min closes conveying worm spoil disposal hydraulic pressure door when shutting down, and outage is to guarantee soil pressure storehouse soil pressure.

If center, height variation then will stop jacking immediately greater than ± 20mm, correction is proofreaied and correct and should slowly be carried out, and tube coupling is resetted gradually, must not suddenly entangle vigour.When wherein rectifying a deviation elevation, the pipe on the track will add counterweight; During the correction center, the pipe on the track will add supported on both sides.After head all enters the hole, and elevation, centre deviation will in time adopt the head correcting device to rectify a deviation during greater than 10mm, and the center is controlled in the 5mm, elevation is controlled at ± 10mm in, tool heads self straightening method is adopted in bearing calibration.The effective control tool head of this method for correcting error is the state of four direction up and down, and the amplitude of at every turn rectifying a deviation is measured the off normal judgement take 5mm as a unit according to inclinometer and the laser transit of tool heads, if when trend does not reduce, increases the correction dynamics; If when trend stability or minimizing, should keep this correction dynamics, continue jacking; When off normal trend is opposite, then need the correction dynamics is reduced gradually.In the pipeline jack-in process, if move speed is on the low side in fine silty layer, turn down the concentration of hydraulic mixture into mud, reduce move speed.When running into the different soil layer of soft or hard degree, judge geological conditions by the torque of cutterhead.If suddenly hardening then should add entry or mud in native storehouse.

(10) be unearthed

The soil that excavates in the push-bench course of work is transported on the belt conveyer through conveying worm first, is transported in the battery truck through belt conveyer again, and battery truck is transported to active well, and Tu Chang is deposited on last vertical handling to ground, regularly outward transport.

Claims (3)

1. gutter jacking construction is characterized in that construction sequence comprises:
(1) measures unwrapping wire
Lay temporary bench mark and conduit axis control stake, during the construction line-putting, establish Center stake every 20m, the place arranges Center stake at manhole;
(2) construction of working shaft
In active well reservation notch suitable for reading, steel bar concrete precast slab is installed, is wanted the seat slurry full in the notch; The wall of laying bricks at precast plate reserved opening place, all bricks are wanted saturated with water, and Ying Manpu, full squeezing are taken up and down block when building by laying bricks or stones, and thickness of mortarat bed joint and perpends width should be even, and vertical straight joint must not be arranged; When building manhole by laying bricks or stones, should install synchronously and mark time, want accurately the position, must not trample before masonry mortar reaches regulation compressive strength after the installation of marking time;
(3) parados is installed behind the assembling
The parados back soil body must be evenly closely knit behind the assembling, and wall should be smooth, and with pipeline jacking perpendicular direction; Back soil body wall should be close to rear parados, should adopt the sand material filling closely knit when hole is arranged; The bottom of parados following 500mm at the bottom of working pit behind the assembling, thus make rear jack center of effort highly be not less than 1/3 of back lumps of wood height, the point of making a concerted effort of being broken ground behind origin of force and the wall is consistent; Parados verticality allowable variation is parados height behind 0.1% assembling behind the assembling, and horizontal torsion degree allowable variation is parados length behind 0.1% assembling;
(4) guide rails assembling
During guide rails assembling and active well base plate pre-embedded steel slab weld, and enclose the jail with type steel support; To check first the pipeline center position before the guide rails assembling, guarantee that the elevation of guide rail, axial location are accurate; The rail axis position deviation is no more than 3mm, and the elevation of top surface deviation is no more than 3mm, is no more than 2mm apart from deviation in two rails; The guide rail end can not be too far away apart from the work wall, should be controlled at about 500mm, and reserving seam during guide rails assembling highly is 100~150mm;
(5) main top jack installation
Jack will be arranged take pipe centerline as axial symmetry; Main top oil cylinder frame is installed and is wanted accurate positioning, guarantees the correct position of cylinder force point, and its elevation and plane alignment error should be controlled in the 3mm; The oil cylinder errors of centration that is installed on the oil cylinder frame is controlled in the 3mm; Jack is fixed on the support, and its central point of making a concerted effort is on pipe centerline; The oil circuit of jack should be in parallel, and every jack should have oil-feed, move back oily control system; The position of jack is positioned at 1/3~1/4 place of pipeline perpendicular diameter, makes jack make a concerted effort the position of position and jacking drag on same axis, avoids producing the top couple, makes pipeline generation vertical error;
(6) oil pump is installed
Oil pump is arranged near the jack, and oil pipe is straight, corner is few; Oil pump should be complementary with jack, and emergency bearing oil pump is arranged; Oil pump installs, and carries out test running; When beginning, jacking slowly carries out, after each contact site driving fit, again by normal move speed jacking; If find in the jacking that oil pressure increases suddenly, stop immediately jacking, check reason and continue after treatment jacking; When jack piston was return, oil pressure was not too much, and speed must not be too fast;
(7) top iron is installed
Top iron adopts the cast-steel integral casting or adopts the shaped steel welding fabrication; The vertical top of single file iron center line is consistent with conduit axis; Two center lines of the vertical top of duplicate rows iron are parallel, and equate with the tubular axis linear distance, and will be perpendicular to the pipe end plane;
(8) construction of turnover hole and sealing
Equipment installs a complete set of jacking device of rear reply and does the primary system debugging, after definite jacking device service behavior is good, and beginning jacking work; When growing apart from jacking, make sealing ring so that the thixotropic slurry performance drag-reduction effect that pours at the portal place;
(9) pipeline jacking
After dismounting is sealed up a door, should begin immediately the jacking head, after the jacking 300mm, unlatching adds the mud system and injects mud, in order to regulate the creeping of dregs and keep earth pressure balance; When head just buries, because head does not have enough resisting moment in orbit, head easily produced rotation when cutterhead was rotated, so when the initial 2m that buries, move speed is controlled at below the 5mm/min, and incessantly observation airplane head inclination angle and the anglec of rotation, and the inclination angle changes with the levelling of correction jack, the anglec of rotation is greater than ± 50 degree, and cutterhead is opened the counter-rotating levelling; In the non-rotary situation of head behind the jacking 2m, strengthen gradually move speed; When head buried not yet fully, support pressure was controlled at 0.1~0.15MPa; After head all buried, lower the first pipe joint was done rear enclosed; After rear enclosed is complete, annotate the space of cement mortar filling head outside backbreaking at 1: 2 to the head shell injected hole, grouting pressure is controlled at 0.4MPa; Locate built-in rigidity piston ring at the hole; Rear enclosed adopts the ring-shaped rubber plate to be close to the soil body, and the hole side wall covers pressure with doughnut-shaped steel plate; Control support pressure according to predefined parameter during jacking, meet sand gravel layer, when nearer apart from building, soil pressure is set suitably and is strengthened; Be provided with the thixotropic slurry injected hole at the head afterbody, every joint concrete reinforced pipe is established injected hole, at any time slip casting during jacking; Move speed is controlled at 30~50mm/min, uses low speed when front 30m and correction, and looking afterwards is unearthed stirs, the cutterhead torque condition is suitably accelerated move speed; During lower pipe, stop under the jacking state at head, cutterhead idle running 3~5min closes conveying worm spoil disposal hydraulic pressure door when shutting down, and outage is to guarantee soil pressure storehouse soil pressure;
If center, height variation then will stop jacking immediately greater than ± 20mm, correction is proofreaied and correct and should slowly be carried out, and tube coupling is resetted gradually, must not suddenly entangle vigour; When wherein rectifying a deviation elevation, the pipe on the track will add counterweight; During the correction center, the pipe on the track will add supported on both sides; After head all enters the hole, and elevation, centre deviation will in time adopt the head correcting device to rectify a deviation during greater than 10mm, and the center is controlled in the 5mm, elevation is controlled at ± 10mm in, tool heads self straightening method is adopted in bearing calibration; The effective control tool head of this method for correcting error is the state of four direction up and down, and the amplitude of at every turn rectifying a deviation is measured the off normal judgement take 5mm as a unit according to inclinometer and the laser transit of tool heads, if when trend does not reduce, increases the correction dynamics; If when trend stability or minimizing, should keep this correction dynamics, continue jacking; When off normal trend is opposite, then need the correction dynamics is reduced gradually; In the pipeline jack-in process, if move speed is on the low side in fine silty layer, turn down the concentration of hydraulic mixture into mud, reduce move speed; When running into the different soil layer of soft or hard degree, judge geological conditions by the torque of cutterhead; If suddenly hardening then should add entry or mud in native storehouse;
(10) be unearthed
The soil that excavates in the push-bench course of work is transported on the belt conveyer through conveying worm first, is transported in the battery truck through belt conveyer again, and battery truck is transported to active well, and Tu Chang is deposited on last vertical handling to ground, regularly outward transport.
2. gutter jacking construction according to claim 1 is characterized in that active well inwall front cover should divide two-layer smearing into, strikes off and make the surface to cause coarse line after first is smeared into; After the second mortar dries, compacting troweling at twice; Slurry and the interlayer of the basic unit close and firm that should bond must not have the phenomenons such as hollowing and crackle; The planeness of wiping one's face should be greater than 15mm; After plastering mortar solidifies, should keep moist curing, curing time is no less than 14d.
3. gutter jacking construction according to claim 1 is characterized in that should adopting the padded coaming liner between top iron and the mouth of pipe, and when top power during near the permission compressive strength of tube coupling material, pipe end should increase circular top iron; During jacking, the staff must not be above the iron of top and the side stop, and observe at any time top iron and have or not unusual sign.
CN 201210575945 2011-04-28 2011-04-28 Pipe-jacking construction of drain pipe CN103015519A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201210575945 CN103015519A (en) 2011-04-28 2011-04-28 Pipe-jacking construction of drain pipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201210575945 CN103015519A (en) 2011-04-28 2011-04-28 Pipe-jacking construction of drain pipe

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN 201110119467 Division CN102277898B (en) 2011-04-28 2011-04-28 Drain pipe jacking construction method

Publications (1)

Publication Number Publication Date
CN103015519A true CN103015519A (en) 2013-04-03

Family

ID=47964578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201210575945 CN103015519A (en) 2011-04-28 2011-04-28 Pipe-jacking construction of drain pipe

Country Status (1)

Country Link
CN (1) CN103015519A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103557026A (en) * 2013-10-28 2014-02-05 煤科集团沈阳研究院有限公司 Method for removing upper corner gas based on pipe-jacking tunneling device
CN103822016A (en) * 2013-07-02 2014-05-28 天津市天联滨海复合材料有限公司 Glass-reinforced plastic pipe jacking construction method applied during pipe body breaking in jacking
CN103994277A (en) * 2014-06-06 2014-08-20 中国科学院武汉岩土力学研究所 Round jacking pipe correction adjusting pipe
CN105570534A (en) * 2016-02-22 2016-05-11 中国水利水电第十一工程局有限公司 Shallow-burial-depth pipe-jacking equipment capable of controlling ground structural deformation and construction method
CN108662284A (en) * 2018-06-01 2018-10-16 成都金玉雄辉建筑工程有限公司 The construction method of small-bore push pipe
CN108662283A (en) * 2018-06-01 2018-10-16 成都金玉雄辉建筑工程有限公司 earth pressure balance pipe jacking construction method
CN108915698A (en) * 2018-08-14 2018-11-30 中铁十四局集团有限公司 A kind of complex condition large diameter pipe curtain construction method
CN108930323A (en) * 2018-07-23 2018-12-04 中国市政工程中南设计研究总院有限公司 A kind of pipe jacking construction method
CN109630151A (en) * 2018-11-07 2019-04-16 中衡设计集团工程咨询有限公司 Rectangular top pipe tunneling construction method
CN109798396A (en) * 2019-02-28 2019-05-24 青岛瑞源工程集团有限公司 A kind of artificial jacking technique of the long-distance large-caliber pipe of concrete of bad ground

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103822016A (en) * 2013-07-02 2014-05-28 天津市天联滨海复合材料有限公司 Glass-reinforced plastic pipe jacking construction method applied during pipe body breaking in jacking
CN103557026A (en) * 2013-10-28 2014-02-05 煤科集团沈阳研究院有限公司 Method for removing upper corner gas based on pipe-jacking tunneling device
CN103557026B (en) * 2013-10-28 2015-12-30 煤科集团沈阳研究院有限公司 A kind of method solving gas at upper corner based on push pipe mole
CN103994277A (en) * 2014-06-06 2014-08-20 中国科学院武汉岩土力学研究所 Round jacking pipe correction adjusting pipe
CN105570534A (en) * 2016-02-22 2016-05-11 中国水利水电第十一工程局有限公司 Shallow-burial-depth pipe-jacking equipment capable of controlling ground structural deformation and construction method
CN105570534B (en) * 2016-02-22 2019-07-12 中国水利水电第十一工程局有限公司 Shallow overburden push pipe controls the equipment and construction method of ground structure deformation
CN108662284A (en) * 2018-06-01 2018-10-16 成都金玉雄辉建筑工程有限公司 The construction method of small-bore push pipe
CN108662283A (en) * 2018-06-01 2018-10-16 成都金玉雄辉建筑工程有限公司 earth pressure balance pipe jacking construction method
CN108930323A (en) * 2018-07-23 2018-12-04 中国市政工程中南设计研究总院有限公司 A kind of pipe jacking construction method
CN108930323B (en) * 2018-07-23 2020-08-25 中国市政工程中南设计研究总院有限公司 Pipe jacking construction method
CN108915698A (en) * 2018-08-14 2018-11-30 中铁十四局集团有限公司 A kind of complex condition large diameter pipe curtain construction method
CN109630151A (en) * 2018-11-07 2019-04-16 中衡设计集团工程咨询有限公司 Rectangular top pipe tunneling construction method
CN109798396A (en) * 2019-02-28 2019-05-24 青岛瑞源工程集团有限公司 A kind of artificial jacking technique of the long-distance large-caliber pipe of concrete of bad ground

Similar Documents

Publication Publication Date Title
CN101644160B (en) High ground stress soft rock stress-relief construction method
CN102493822B (en) Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN101963061B (en) Construction method for underground box culvert of existing railway line
CN202337983U (en) Ejector, drill combination structure and combination drilling tools
CN100410485C (en) Construction method for push pipe by cooperation of horizontal auger driller and horizontal directional driller
CN104088647B (en) Shield tube push bench with super-large rectangular cross section
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN101936167B (en) Construction method for crossing bridge pile foundation by combining bridge underpinning with shield construction
CN102758635B (en) Construction method for tool changing under pressure in shield of water-rich silty soil and silty sand stratum under station tracks of railways
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN102094650B (en) Construction method for shield entry under complicated working conditions
CN101761083B (en) Underground continuous wall obstacle clearing construction method for traversing ultra-thick obstacle
CN100497841C (en) Supporting leg type underground continuous wall construction method
CN101666081B (en) Abrupt slope bare rock drilling platform and technology in huge reservoir
CN103276639B (en) Roadbed structure for deep soft soil region
CN104343455B (en) Long-distance curved jacking pipe and pipe roof construction technique
CN104594348B (en) Enlarged footing bellows anchor pole and construction method thereof
CN1215276C (en) Earth pressure balancing technology for laying rectangular top pipe
CN103850249B (en) Long spire is squeezed into rock filling pile construction technology
CN104846810A (en) Self-circulating posterior grouting bored pile construction method
Wang et al. Jet grouting for mitigation of installation disturbance
CN100501124C (en) Construction method for tunnel contact passage in shield section of underground railway
CN104612695A (en) Repairing and reinforcing method for vertical shaft wall collapsed fiercely
CN104120716A (en) Slurry wall protection construction method for bored pile
CN102537517B (en) Construction technology for jacking pipe in river or lake

Legal Events

Date Code Title Description
PB01 Publication
C06 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130403

C02 Deemed withdrawal of patent application after publication (patent law 2001)