CN103015280A - 轨道交通轮轴移动荷载模拟加载方法及装置 - Google Patents

轨道交通轮轴移动荷载模拟加载方法及装置 Download PDF

Info

Publication number
CN103015280A
CN103015280A CN2012105737744A CN201210573774A CN103015280A CN 103015280 A CN103015280 A CN 103015280A CN 2012105737744 A CN2012105737744 A CN 2012105737744A CN 201210573774 A CN201210573774 A CN 201210573774A CN 103015280 A CN103015280 A CN 103015280A
Authority
CN
China
Prior art keywords
rail
actuator
sleeper
load
wheel shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012105737744A
Other languages
English (en)
Inventor
边学成
蒋红光
徐翔
陈仁朋
陈云敏
蒋建群
程翀
金皖锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University ZJU
Original Assignee
Zhejiang University ZJU
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University ZJU filed Critical Zhejiang University ZJU
Priority to CN2012105737744A priority Critical patent/CN103015280A/zh
Publication of CN103015280A publication Critical patent/CN103015280A/zh
Priority to PCT/CN2013/080321 priority patent/WO2014101405A1/zh
Priority to US14/298,507 priority patent/US9747395B2/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B35/00Applications of measuring apparatus or devices for track-building purposes
    • E01B35/12Applications of measuring apparatus or devices for track-building purposes for measuring movement of the track or of the components thereof under rolling loads, e.g. depression of sleepers, increase of gauge

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Train Traffic Observation, Control, And Security (AREA)

Abstract

本发明公开了一种轨道交通轮轴移动荷载模拟加载方法及装置。多个作动器在沿轨道方向的轨枕正上方布置,每个作动器底部在分配梁跨中处连接,分配梁两端底部安装在两侧钢轨正上方,两条连续的钢轨铺设在轨枕上,分别在轨枕位置正上方切断成相互独立的分段钢轨,每对分段钢轨和轨枕用扣件系统连接。防脱套件实现作动器竖向压力、上拔力的施加。根据列车-轨道-路基理论模型确定在不同移动速度下轮轴移动作用的单个扣件系统的受力荷载时程曲线,作为每个作动器的荷载激励曲线,相邻作动器沿轮轴移动方向以相同时间间隔依次进行动态激振,实现不同速度下轮轴移动荷载的模拟加载。本发明为开展轨道交通动力学模型试验研究提供了可靠便捷的加载平台。

Description

轨道交通轮轴移动荷载模拟加载方法及装置
技术领域
本发明涉及一种荷载加载方法及装置,尤其是涉及一种轨道交通轮轴移动荷载模拟加载方法及装置。
背景技术
我国正处于轨道交通快速发展的阶段,无论是城际普通铁路和高速铁路,还是城市地铁和轻轨,都处于快速建设过程中。伴随着轨道交通设施的建设和投入运营,越来越多的工程问题凸显出来。在列车高速通过时荷载通过轮轴与钢轨的相互作用传递至线下结构,与传统的定点循环加载相比,轮轴与钢轨的作用具有典型的移动效应和速度效应,随着轮轴的移动,轨下各结构层沿着列车行进方向经历相同的加载过程。这种不同于固定点加载的受力方式,导致了轨道结构和路基结构呈现出不同的动力性能。因此,实现列车轮轴荷载移动过程的有效模拟,对研究轨道交通基础设施真实的动力性能至关重要。目前,轮轴荷载模拟的试验手段主要有室内模型试验和现场原位测试两种。室内模型试验受到场地尺寸和行车速度的限制,不易实现真车的高速移动加载;现场原位测试虽然可以采用真实的轮轴移动过程,但所处的环境比较复杂不易控制,可重复性较差。现有的轮轴动荷载模拟装置,如可调频调幅SBZ30动态激振器,采用偏心块的快速转动产生竖向激振力,可以实现固定位置的高频激振,不足之处是:无法实现轮轴荷载的移动性;模拟高速交通移动荷载作用的试验系统,采用由离心旋转电机控制的正反向移动加载器,带动竖向激振器实现轮轴荷载的移动加载,但由于尺寸限制,无法实现轮轴荷载的以较高的速度匀速移动。
发明内容
为了克服现有室内模型试验和现场原位测试的不足,本发明的目的在于提供一种轨道交通轮轴移动荷载模拟加载方法及装置,实现轮轴荷载高速移动。
为实现上述目的,本发明采用的技术方案是:
一、一种轨道交通轮轴移动荷载模拟加载方法,包括以下步骤:
步骤1)通过列车-轨道-路基理论模型计算确定不同移动速度                                               
Figure 2012105737744100002DEST_PATH_IMAGE002
下轮轴移动荷载作用的单个扣件系统的受力荷载时程曲线; 
步骤2)按高速铁路设计规范轨枕沿轨道方向的间距为,通过扣件系统将钢轨与轨枕进行连接,两条连续的钢轨分别在轨枕位置正上方处切断为多对相互独立的分段钢轨,钢轨与轨枕之间的连接特性保持不变;
步骤3)在步骤2)中的每一对分段钢轨正上方均布置一条分配梁,分配梁跨中处上方连接一个作动器,将步骤1)得到的单个扣件系统的受力荷载时程曲线,作为每个作动器的荷载激励曲线;
步骤4)步骤3)中每个作动器的荷载激励曲线均相同,每个作动器开始激振存在时间间隔,相邻作动器激振的时间间隔
Figure 2012105737744100002DEST_PATH_IMAGE006
由轨枕的间距
Figure 729107DEST_PATH_IMAGE004
和移动速度确定:  
Figure 2012105737744100002DEST_PATH_IMAGE008
步骤5)沿轮轴移动方向相邻作动器通过按照步骤4)所述的时间间隔依次进行动态激振,即实现不同移动速度轮轴移动荷载的模拟加载。
二、一种轨道交通轮轴移动荷载模拟加载装置:
多个作动器在按照高速铁路每条轨枕沿轨道方向的正上方布置,每个作动器底部用高强螺栓在分配梁跨中处连接,分配梁两端底部固定安装在两侧钢轨正上方,两条连续的钢轨铺设在轨枕上,分别在轨枕位置正上方切断成相互独立的分段钢轨,每对分段钢轨和轨枕用扣件系统连接,轨枕下方为道床、道床下方为地基。
所述的每个作动器顶部连接在反力横梁跨中处,每根反力横梁两端固定在两根反力纵梁上,每根反力纵梁的两端连接在两根支撑柱上,每根支撑柱底部固定在地面上。 
所述的分配梁两端底部固定安装在每对分段钢轨正上方的装置是防脱套件,其实现作动器竖向压力的施加,也实现作动器上拔力的施加。
本发明具有的有益效果是:
(1)两条钢轨分段后,相邻作动器以单个扣件系统的受力荷载时程曲线为荷载激励曲线,并沿轮轴移动方向以相同时间依次动态激振,从而代替实体列车轮轴模型实现不同速度下的轮轴荷载的移动加载;(2)防脱套件实现作动器竖向压力的施加,也实现作动器上拔力的施加。(3)避免了行车速度提高所需要的长距离加速路段,大大缩小了室内试验模型的尺寸,为开展轨道交通动力学模型试验研究提供了可靠便捷的加载平台。
附图说明
图1是本发明装置横向示意图。
图2是本发明装置纵向示意图。
图3是一段钢轨连接横向示意图。
图4是一段钢轨连接纵向示意图。
图5是轮轴移动下列车-轨道-路基理论模型原理图。
图6是作动器荷载激励曲线。
图中:1、作动器,2、分配梁,3、防脱套件,4、高强螺栓,5、扣件结构,6、钢轨,7、轨枕,8、道床,9、地基,10、反力横梁,11、反力纵梁,12、支撑柱。
具体实施方式
下面结合附图和实施例对本发明作进一步说明。
本实施例在图1和图2所示轨道交通轮轴移动荷载模拟加载装置上进行,选用有砟轨道结构,扣件系统5选用WJ-7型,钢轨6型号选用CHN60,轨枕7选用III型钢筋混凝土轨枕,道床8分为道床表层和道床底层,道床表层选用级配碎石,道床底层选用A/B填料,每条轨枕7沿轨道方向的间距为
Figure 2012105737744100002DEST_PATH_IMAGE010
,共设置8条轨枕7, 8个作动器1在每条轨枕7位置处上方布置,每个作动器1底部用高强螺栓4在分配梁2跨中处连接,分配梁2两端底部固定安装在每对分段钢轨6正上方的装置是防脱套件3,其实现作动器1竖向压力的施加,也实现作动器1上拔力的施加。两条连续的钢轨6铺设在轨枕7上,分别在轨枕7位置正上方切断成相互独立的0.3m长的分段钢轨6,每对分段钢轨6和轨枕7用扣件系统5连接,如图3和图4所示,轨枕7下方为道床8、道床8下方为地基9,每个作动器1顶部连接在反力横梁10跨中处,每根反力横梁10两端固定在两根反力纵梁11上,每根反力纵梁11的两端连接在两根支撑柱12上,每根支撑柱12底部固定在地面上。
图5所示轮轴移动下列车-轨道-路基理论模型为平面结构假设,依次由轮轴、钢轨6、扣件结构5、轨枕7、道床8和地基9组成,钢轨6采用欧拉梁假设,假设为简支梁,离散分布的轨枕7假设为质量块。扣件系统5、道床8均采用粘弹性弹簧假设,其中道床8为分布弹簧和阻尼,列车运行过程中轮轴与钢轨6相互作用,产生的作用力通过钢轨6下方离散支撑的扣件系统5承担。
取轮轴移动速度
Figure 2012105737744100002DEST_PATH_IMAGE012
,由于该模型为研究结构移动质量系的问题,不同于一般的定点加载的动力问题,采用的基本控制方程为偏微分方程组,使用模态分解的方法,将列车子系统的平衡方程、钢轨的平衡方程和轨枕的平衡方程转化为常微分方程组,根据NEWMARK方法进行求解,得到在轮轴移动速度
Figure 573249DEST_PATH_IMAGE002
为13.5km/h时单个扣件系统的受力荷载时程曲线如图6所示,将其作为每个作动器的荷载激励曲线。
所有作动器的荷载激励曲线均相同,每个作动器开始激振存在时间间隔,相邻作动器的激振时间间隔由轨枕的间距和列车速度确定, 
Figure 2012105737744100002DEST_PATH_IMAGE014
沿轮轴移动方向相邻作动器按照时间间隔
Figure 2012105737744100002DEST_PATH_IMAGE016
依次进行动态激振,即实现不同速度下轮轴移动荷载的模拟加载。

Claims (4)

1.一种轨道交通轮轴移动荷载模拟加载方法,其特征在于包括以下步骤:
步骤1)通过列车-轨道-路基理论模型计算确定不同移动速度                                                
Figure 2012105737744100001DEST_PATH_IMAGE001
下轮轴移动荷载作用的单个扣件系统的受力荷载时程曲线; 
步骤2)按高速铁路轨枕沿轨道方向的间距为
Figure 815498DEST_PATH_IMAGE002
,通过扣件系统将钢轨与轨枕进行连接,两条连续的钢轨分别在轨枕位置正上方处切断为多对相互独立的分段钢轨,钢轨与轨枕之间的连接特性保持不变;
步骤3)在步骤2)中的每一对分段钢轨正上方均布置一条分配梁,分配梁跨中处上方连接一个作动器,将步骤1)得到的单个扣件系统的受力荷载时程曲线,作为每个作动器的荷载激励曲线;
步骤4)步骤3)中每个作动器的荷载激励曲线均相同,每个作动器开始激振存在时间间隔,相邻作动器激振的时间间隔
Figure 2012105737744100001DEST_PATH_IMAGE003
由轨枕的间距
Figure 700277DEST_PATH_IMAGE002
和移动速度
Figure 780360DEST_PATH_IMAGE001
确定:  
Figure 979260DEST_PATH_IMAGE004
步骤5)沿轮轴移动方向相邻作动器通过按照步骤4)所述的时间间隔依次进行动态激振,即实现不同移动速度
Figure 703819DEST_PATH_IMAGE001
轮轴移动荷载的模拟加载。
2.根据权利要求1所述的加载方法的一种轨道交通轮轴移动荷载模拟加载装置,其特征在于:多个作动器(1)在按照高速铁路每条轨枕(7)沿轨道方向的正上方布置,每个作动器(1)底部用高强螺栓(4)在分配梁(2)跨中处连接,分配梁(2)两端底部固定安装在两侧钢轨(6)正上方,两条连续的钢轨(6)铺设在轨枕(7)上,分别在轨枕(7)位置正上方切断成相互独立的分段钢轨(6),每对分段钢轨(6)和轨枕(7)用扣件系统(5)连接,轨枕(7)下方为道床(8)、道床(8)下方为地基(9)。
3.根据权利要求2所述的一种轨道交通轮轴移动荷载模拟加载装置,其特征在于:所述的每个作动器(1)顶部连接在反力横梁(10)跨中处,每根反力横梁(10)两端固定在两根反力纵梁(11)上,每根反力纵梁(11)的两端连接在两根支撑柱(12)上,每根支撑柱(12)底部固定在地面上。
4.根据权利要求2所述的一种轨道交通轮轴移动荷载模拟加载装置,其特征在于:所述的分配梁(2)两端底部固定安装在每对分段钢轨(6)正上方的装置是防脱套件(3),其实现作动器(1)竖向压力的施加,也实现作动器(1)上拔力的施加。
CN2012105737744A 2012-12-26 2012-12-26 轨道交通轮轴移动荷载模拟加载方法及装置 Pending CN103015280A (zh)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN2012105737744A CN103015280A (zh) 2012-12-26 2012-12-26 轨道交通轮轴移动荷载模拟加载方法及装置
PCT/CN2013/080321 WO2014101405A1 (zh) 2012-12-26 2013-07-29 轨道交通轮轴移动荷载模拟加载方法及装置
US14/298,507 US9747395B2 (en) 2012-12-26 2014-06-06 Simulated loading method and apparatus for moving load of wheel axle in rail transportation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012105737744A CN103015280A (zh) 2012-12-26 2012-12-26 轨道交通轮轴移动荷载模拟加载方法及装置

Publications (1)

Publication Number Publication Date
CN103015280A true CN103015280A (zh) 2013-04-03

Family

ID=47964344

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012105737744A Pending CN103015280A (zh) 2012-12-26 2012-12-26 轨道交通轮轴移动荷载模拟加载方法及装置

Country Status (3)

Country Link
US (1) US9747395B2 (zh)
CN (1) CN103015280A (zh)
WO (1) WO2014101405A1 (zh)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103674598A (zh) * 2013-12-18 2014-03-26 西南交通大学 模拟移动荷载的轨道结构疲劳试验方法及装置
WO2014101405A1 (zh) * 2012-12-26 2014-07-03 浙江大学 轨道交通轮轴移动荷载模拟加载方法及装置
WO2014101407A1 (zh) * 2012-12-26 2014-07-03 浙江大学 轨道交通列车整车移动荷载模拟加载方法及装置
CN104062134A (zh) * 2014-06-19 2014-09-24 西南交通大学 模拟往复滚动荷载的结构疲劳试验方法及其试验装置
CN104390629A (zh) * 2014-11-18 2015-03-04 上海交通大学 一种确定地铁运营列车动荷载与隧道长期沉降的方法
CN104458224A (zh) * 2014-10-23 2015-03-25 西南交通大学 铁路轨道扣件胶垫动参数实验装置
CN104631241A (zh) * 2015-01-26 2015-05-20 西南交通大学 一种铁路无砟轨道走行式落轴试验台
CN105133449A (zh) * 2015-09-14 2015-12-09 北京航华星金属结构厂 轨道调轨机
CN106289819A (zh) * 2016-08-17 2017-01-04 太仓中博铁路紧固件有限公司 用于检测轨下基板复合载荷的检测工装及其检测方法
CN108982139A (zh) * 2018-06-19 2018-12-11 福建农林大学 一种时变损伤桥梁实验装置及其实验方法
CN109297698A (zh) * 2018-11-23 2019-02-01 中南大学 一种大型结构疲劳试验加载装置
CN109990967A (zh) * 2019-04-30 2019-07-09 上海材料研究所 一种钢轨组装扣件系统的动态和疲劳性能检测装置及方法
CN110926979A (zh) * 2019-11-26 2020-03-27 西南交通大学 滚动荷载模拟试验装置及方法
CN112161766A (zh) * 2020-09-22 2021-01-01 温州大学 一种铁路减振试验装置
CN113310628A (zh) * 2021-07-29 2021-08-27 南昌大学 一种重载列车荷载作用下铁路轨枕结构平衡性能测试设备
CN113656899A (zh) * 2021-07-02 2021-11-16 西南交通大学 一种基于车轨耦合理论的轨道扣件参数优化方法
CN114462126A (zh) * 2022-01-20 2022-05-10 西南交通大学 无砟轨道结构缝位置路基面列车荷载分布模式确定方法

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108956964A (zh) * 2017-05-19 2018-12-07 中国科学院寒区旱区环境与工程研究所 一种用于模拟行车荷载的模型试验系统
CN107829451A (zh) * 2017-11-11 2018-03-23 广州环保投资集团有限公司 基于模型箱的水平双向循环荷载加载装置及试验方法
CN108733904B (zh) * 2018-05-08 2022-03-08 同济大学 一种轨道交通小比例试验模拟加载方法
CN109932245B (zh) * 2019-04-18 2024-08-13 天津铁路信号有限责任公司 一种钢轨压力试验平台
CN110409518A (zh) * 2019-07-12 2019-11-05 河南理工大学 一种高速铁路采空区地基拟动力加载模型试验装置及方法
CN110569549B (zh) * 2019-08-07 2023-09-19 宁波大学 一种基于区间摄动的桁架结构的动载荷识别方法
CN113405783A (zh) * 2020-03-16 2021-09-17 中南大学 一种基于桥墩变形的无砟轨道几何形位变化模拟试验台

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4023745A1 (de) * 1990-07-26 1992-01-30 Pfister Gmbh Schwelle zur auflage von eisenbahnschienen
CN102109419B (zh) * 2010-12-18 2013-04-03 浙江大学 高速铁路列车运行荷载的模拟加载系统
CN102650574A (zh) * 2011-08-19 2012-08-29 高速铁路建造技术国家工程实验室 一种高速铁路动力荷载模拟装置
CN203096538U (zh) * 2012-12-26 2013-07-31 浙江大学 一种轨道交通轮轴移动荷载模拟加载装置
CN103015280A (zh) * 2012-12-26 2013-04-03 浙江大学 轨道交通轮轴移动荷载模拟加载方法及装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王启云,等: "高速铁路轨道路基模型及动力加载研究", 《铁道学报》 *

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2014101405A1 (zh) * 2012-12-26 2014-07-03 浙江大学 轨道交通轮轴移动荷载模拟加载方法及装置
WO2014101407A1 (zh) * 2012-12-26 2014-07-03 浙江大学 轨道交通列车整车移动荷载模拟加载方法及装置
US9747395B2 (en) 2012-12-26 2017-08-29 Zhejiang University Simulated loading method and apparatus for moving load of wheel axle in rail transportation
US9785730B2 (en) 2012-12-26 2017-10-10 Zhejiang University Simulated loading method and apparatus for moving load of whole train in rail transportation
CN103674598A (zh) * 2013-12-18 2014-03-26 西南交通大学 模拟移动荷载的轨道结构疲劳试验方法及装置
CN103674598B (zh) * 2013-12-18 2016-08-17 西南交通大学 模拟移动荷载的轨道结构疲劳试验方法及装置
CN104062134A (zh) * 2014-06-19 2014-09-24 西南交通大学 模拟往复滚动荷载的结构疲劳试验方法及其试验装置
CN104062134B (zh) * 2014-06-19 2017-06-13 西南交通大学 模拟往复滚动荷载的结构疲劳试验方法
CN104458224A (zh) * 2014-10-23 2015-03-25 西南交通大学 铁路轨道扣件胶垫动参数实验装置
CN104458224B (zh) * 2014-10-23 2017-01-18 西南交通大学 铁路轨道扣件胶垫动参数实验装置
CN104390629B (zh) * 2014-11-18 2016-11-30 上海交通大学 一种确定地铁运营列车动荷载与隧道长期沉降的方法
CN104390629A (zh) * 2014-11-18 2015-03-04 上海交通大学 一种确定地铁运营列车动荷载与隧道长期沉降的方法
CN104631241A (zh) * 2015-01-26 2015-05-20 西南交通大学 一种铁路无砟轨道走行式落轴试验台
CN104631241B (zh) * 2015-01-26 2016-06-22 西南交通大学 一种铁路无砟轨道走行式落轴试验台
CN105133449A (zh) * 2015-09-14 2015-12-09 北京航华星金属结构厂 轨道调轨机
CN105133449B (zh) * 2015-09-14 2017-03-22 北京航华星轨道设备制造有限公司 轨道调轨机
CN106289819A (zh) * 2016-08-17 2017-01-04 太仓中博铁路紧固件有限公司 用于检测轨下基板复合载荷的检测工装及其检测方法
CN106289819B (zh) * 2016-08-17 2018-10-23 太仓中博铁路紧固件有限公司 用于检测轨下基板复合载荷的检测工装及其检测方法
CN108982139B (zh) * 2018-06-19 2019-08-13 福建农林大学 一种时变损伤桥梁实验装置及其实验方法
CN108982139A (zh) * 2018-06-19 2018-12-11 福建农林大学 一种时变损伤桥梁实验装置及其实验方法
CN109297698A (zh) * 2018-11-23 2019-02-01 中南大学 一种大型结构疲劳试验加载装置
CN109990967A (zh) * 2019-04-30 2019-07-09 上海材料研究所 一种钢轨组装扣件系统的动态和疲劳性能检测装置及方法
CN109990967B (zh) * 2019-04-30 2024-04-30 上海材料研究所有限公司 一种钢轨组装扣件系统的动态和疲劳性能检测装置及方法
CN110926979A (zh) * 2019-11-26 2020-03-27 西南交通大学 滚动荷载模拟试验装置及方法
CN112161766A (zh) * 2020-09-22 2021-01-01 温州大学 一种铁路减振试验装置
CN113656899A (zh) * 2021-07-02 2021-11-16 西南交通大学 一种基于车轨耦合理论的轨道扣件参数优化方法
CN113656899B (zh) * 2021-07-02 2023-06-23 西南交通大学 一种基于车轨耦合理论的轨道扣件参数优化方法
CN113310628A (zh) * 2021-07-29 2021-08-27 南昌大学 一种重载列车荷载作用下铁路轨枕结构平衡性能测试设备
CN113310628B (zh) * 2021-07-29 2021-10-01 南昌大学 一种重载列车荷载作用下铁路轨枕结构平衡性能测试设备
CN114462126A (zh) * 2022-01-20 2022-05-10 西南交通大学 无砟轨道结构缝位置路基面列车荷载分布模式确定方法

Also Published As

Publication number Publication date
US20140288902A1 (en) 2014-09-25
US9747395B2 (en) 2017-08-29
WO2014101405A1 (zh) 2014-07-03

Similar Documents

Publication Publication Date Title
CN103015280A (zh) 轨道交通轮轴移动荷载模拟加载方法及装置
CN103063451B (zh) 轨道交通列车整车移动荷载模拟加载方法及装置
Xia et al. Dynamic interaction of train-bridge systems in high-speed railways
CN102109419B (zh) 高速铁路列车运行荷载的模拟加载系统
Yang et al. An iterative interacting method for dynamic analysis of the maglev train–guideway/foundation–soil system
CN102650574A (zh) 一种高速铁路动力荷载模拟装置
CN104048880A (zh) 一种机场跑道三向载荷实验系统
Manalo et al. Analysis of a typical railway turnout sleeper system using grillage beam analogy
CN203096538U (zh) 一种轨道交通轮轴移动荷载模拟加载装置
CN112082780B (zh) 地震作用下高速列车桥上行车系统测试试验段装置
Ju 3D analysis of high-speed trains moving on bridges with foundation settlements
Shi et al. A theoretical investigation on influences of slab tracks on vertical dynamic responses of railway viaducts
Yang et al. Numerical studies of vibration of four-span continuous plate with rails excited by moving car with experimental validation
Gao et al. Vibration of subgrade and evaluation of derailment coefficient of train under combined earthquake-moving train load
CN201901828U (zh) 一种高速铁路列车运行荷载的模拟加载系统
CN203101071U (zh) 一种轨道交通列车整车移动荷载模拟加载装置
CN110320061B (zh) 一种用于桥梁模型试验的列车加载模拟装置
CN210243222U (zh) 一种用于桥梁模型试验的列车加载模拟装置
Yang et al. Dynamic analysis on the stiffness enhancement measure of the slab end for a discontinuous floating slab track
CN102539313B (zh) 模拟高速交通移动荷载作用的试验系统
CN113624319B (zh) 一种轨道交通环形振动模拟试验装置
Yang et al. Propagation characteristics of vibration induced by medium-low-speed maglev train running on subgrade
CN113884320A (zh) 一种模拟列车荷载动力试验的装置及方法
Feng et al. In-situ Measurement of Metro-Induced Building Vibrations over a Metro Station
Cheng et al. Model testing on dynamic behaviors of the slab track of high-speed railway

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130403