CN102983617B - Solar photovoltaic power generation system with adaptive power control and method of operation thereof - Google Patents
Solar photovoltaic power generation system with adaptive power control and method of operation thereof Download PDFInfo
- Publication number
- CN102983617B CN102983617B CN201110259635.XA CN201110259635A CN102983617B CN 102983617 B CN102983617 B CN 102983617B CN 201110259635 A CN201110259635 A CN 201110259635A CN 102983617 B CN102983617 B CN 102983617B
- Authority
- CN
- China
- Prior art keywords
- unit
- solar photovoltaic
- control
- electric energy
- power
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E10/00—Energy generation through renewable energy sources
- Y02E10/50—Photovoltaic [PV] energy
- Y02E10/56—Power conversion systems, e.g. maximum power point trackers
Landscapes
- Charge And Discharge Circuits For Batteries Or The Like (AREA)
- Photovoltaic Devices (AREA)
Abstract
Description
技术领域 technical field
本发明为有关一种太阳光伏发电系统及其操作方法,尤指一种具有适应性电能控制的太阳光伏发电系统及其操作方法。The invention relates to a solar photovoltaic power generation system and its operating method, especially a solar photovoltaic power generation system with adaptive electric energy control and its operating method.
背景技术 Background technique
自从二次能源危机以来,替代能源的寻求与研究已经成为许多国家的主要政策之一。替代能源基本上是指煤、石油、天然气、核能等以外的能源,可包括风、太阳、地热、潮汐、黑潮等等的能源。由于太阳能具有无污染、无公害的特性,且又取之不尽用之不竭,因此,太阳能的应用具有相当发展的潜力。并且,由于近年来太阳能光伏电池的积极研究发展,已达到相当高的效率,因此逐渐受到欧、美、日等各国的重视,并制订政策鼓励推展应用。Since the second energy crisis, the search and research of alternative energy has become one of the main policies of many countries. Alternative energy basically refers to energy other than coal, oil, natural gas, nuclear energy, etc., and may include energy such as wind, sun, geothermal, tide, and Kuroshio. Since solar energy is non-polluting, non-pollution-free, and inexhaustible, the application of solar energy has considerable potential for development. Moreover, due to the active research and development of solar photovoltaic cells in recent years, they have reached a very high efficiency, so they have gradually attracted the attention of countries such as Europe, the United States, and Japan, and formulated policies to encourage their application.
太阳能光电系统主要是透过太阳能板进行光电转换而产生直流电源,再经由电力调节器将直流电源转换成交流电源以供负载使用或馈入市电的总线与市电同步并联运转。因此,就功能而言,小型分布式发电系统可区分为以下三种类型:(1)独立型(stand-alonesystem)、(2)市电并联型(grid-connectionsystem)以及(3)混合型(hybridsystem)。独立型系统所指的是太阳能光电系统没有与其它电源连结运转,只能直接供给系统所接的负载,所以此系统较适合用于偏远地区或海上孤岛等没有市电供应的地方。负载所有电力来源均为风力或太阳能,太阳能除了能提供负载用电外,则可将多余能量对蓄电池(battery)充电;当太阳能电力瞬间不足以提供负载所需电力时,则由蓄电池提供。市电并聯型系统所指的是太阳能光电系统与电力公司网络并联,只要市电电力可正常送达的任何地点均适用此类系统。若太阳能光电系统发电量大于负载需求,则可将多余电力逆潮流馈入市电,反之,当太阳能光电系统发电量不足负载使用时,市电将可供应不足的部分。此外,为了顺应电力质量不稳定的问题,而发展出混合型系统。太阳能光电系统于市电停止供电时,透过搭配蓄电池组使用,可立即与市电隔离,形成独立运转供电,以提供短暂电力。等到市电恢复供电时,太阳能光电系统则恢复与市电并联,同时也对蓄电池组进行充电。The solar photovoltaic system mainly generates DC power through the photoelectric conversion of solar panels, and then converts the DC power into AC power through the power conditioner for use by loads or feeds into the mains bus to run in parallel with the mains synchronously. Therefore, in terms of function, small-scale distributed generation systems can be divided into the following three types: (1) stand-alone system, (2) grid-connection system, and (3) hybrid ( hybrid system). The independent system refers to the solar photovoltaic system that is not connected to other power sources and can only directly supply the load connected to the system. Therefore, this system is more suitable for remote areas or isolated islands on the sea where there is no mains power supply. All power sources for the load are wind power or solar power. In addition to providing power for the load, the solar power can charge the battery with excess energy. The mains parallel system refers to the parallel connection between the solar photovoltaic system and the power company network, as long as the mains power can be delivered to any place, this type of system is applicable. If the power generated by the solar photovoltaic system is greater than the demand of the load, the excess power can be fed into the city power against the current flow. Conversely, when the power generated by the solar photovoltaic system is insufficient for the load to use, the city power will be able to supply the insufficient part. In addition, in order to cope with the problem of unstable power quality, hybrid systems have been developed. When the mains power supply stops, the solar photovoltaic system can be immediately isolated from the mains by using a battery pack to form an independent power supply to provide short-term power. When the mains power is restored, the solar photovoltaic system will be connected in parallel with the mains, and the battery pack will also be charged at the same time.
请参见图1,为先前技术的太阳光伏发电系统的方块图。如图所示,该太阳光伏发电系统为透过一太阳光伏电池板(photovoltaicpanel)10A产生一直流电压(未标示)与一直流电流(未标示),利用控制该直流电压与该直流电流所提供的一电能,对一负载50A供电。该太阳光伏发电系统为包含一充电控制单元20A、一开关单元Sw、一充电电池单元30A以及一电源调节单元40A。Please refer to FIG. 1 , which is a block diagram of a prior art solar photovoltaic power generation system. As shown in the figure, the solar photovoltaic power generation system generates a DC voltage (not shown) and a DC current (not shown) through a solar photovoltaic panel (photovoltaic panel) 10A, and controls the DC voltage and the DC current to provide A power of 50A is supplied to a load. The solar photovoltaic power generation system includes a charge control unit 20A, a switch unit Sw, a rechargeable battery unit 30A and a power regulation unit 40A.
该充电控制单元20A为电性连接该太阳光伏电池板10A。该开关单元Sw为电性连接该充电控制单元20A。该充电电池单元30A为电性连接该太阳光伏电池板10A与该开关单元Sw。该电源调节单元40A为电性连接该开关单元Sw以及该充电电池单元30A。其中,该充电控制单元20A为根据该太阳光伏电池板10A所产生的该直流电压与该直流电流所提供的该电能,控制该开关单元Sw的导通与截止。The charging control unit 20A is electrically connected to the solar photovoltaic panel 10A. The switch unit Sw is electrically connected to the charging control unit 20A. The rechargeable battery unit 30A is electrically connected to the solar photovoltaic panel 10A and the switch unit Sw. The power regulating unit 40A is electrically connected to the switch unit Sw and the rechargeable battery unit 30A. Wherein, the charging control unit 20A controls the switching on and off of the switching unit Sw according to the electric energy provided by the DC voltage and the DC current generated by the solar photovoltaic cell panel 10A.
当该太阳光伏电池板10A能够提供该电能输出时,该充电控制单元20A为导通该开关单元Sw,并透过该电源调节单元40A提供该电能对该负载50A供电与对该充电电池单元30A充电的调节。此外,当该太阳光伏电池板10A无法提供该电能输出时,该电源调节单元40A为提供该充电电池单元30A所储存的该电能对该负载50A供电的调节。When the solar photovoltaic panel 10A can provide the electric energy output, the charging control unit 20A is to turn on the switch unit Sw, and provide the electric energy through the power regulation unit 40A to supply power to the load 50A and the rechargeable battery unit 30A Charging regulation. In addition, when the solar photovoltaic cell panel 10A cannot provide the electric energy output, the power regulation unit 40A regulates the electric energy stored in the rechargeable battery unit 30A to power the load 50A.
当该太阳光伏电池板10A能够提供该电能输出时,需透过该电源调节单元40A提供该电能对该负载50A供电与对该充电电池单元30A充电的调节。亦即,无论是该太阳光伏电池板10A直接对该负载50A供电或能将多余的该电能储存于该充电电池单元30A中,都需经过该充电控制单元20A的调节,使该太阳光伏电池板10A所提供的电能对该负载50A供电的路径以及该太阳光伏电池板10A所提供的电能对该充电电池单元30A充电的路径都需经过该充电控制单元20A。When the solar photovoltaic panel 10A can provide the electric energy output, the electric energy needs to be provided through the power regulation unit 40A to regulate the power supply to the load 50A and the charging of the rechargeable battery unit 30A. That is, whether the solar photovoltaic panel 10A directly supplies power to the load 50A or stores the excess electric energy in the rechargeable battery unit 30A, it needs to be adjusted by the charging control unit 20A so that the solar photovoltaic panel The path of the electric energy provided by 10A to supply power to the load 50A and the path of electric energy provided by the solar photovoltaic panel 10A to charge the rechargeable battery unit 30A need to go through the charging control unit 20A.
由于该充电控制单元20A的开关组件操作,存在着开关导通损失(conductionlosses)与开关切换损失(switchinglosses),使该充电控制单元20A本身的转换效率降低,也使得在转换的过程中造成能量消耗。因此,当该太阳光伏电池板10A对该负载50A供电或对该充电电池单元30A充电,每次皆需经由该充电控制单元20A的操作,如此,将大大地影响该太阳光伏发电系统整体效率。Due to the operation of the switch components of the charging control unit 20A, there are conduction losses and switching losses of the switches, which reduces the conversion efficiency of the charging control unit 20A itself, and also causes energy consumption during the conversion process. . Therefore, when the solar photovoltaic panel 10A supplies power to the load 50A or charges the rechargeable battery unit 30A, the charging control unit 20A needs to be operated each time, which will greatly affect the overall efficiency of the solar photovoltaic power generation system.
因此,如何设计出一种具有适应性电能控制的太阳光伏发电系统及其操作方法,针对该太阳光伏发电系统的一太阳光伏电池板能够提供电能输出以及无法提供电能输出的操作状况下,透过控制不同开关单元的导通与截止,进而对负载供电以及对充电电池单元充电,以能够提升该太阳光伏发电系统的整体效率,乃为本案创作人所欲行克服并加以解决的一大课题。Therefore, how to design a solar photovoltaic power generation system with adaptive power control and its operation method, for the operating conditions that a solar photovoltaic panel of the solar photovoltaic power generation system can provide electric energy output and cannot provide electric energy output, through Controlling the on and off of different switching units, and then supplying power to the load and charging the rechargeable battery unit, so as to improve the overall efficiency of the solar photovoltaic power generation system, is a major problem that the creators of this project want to overcome and solve.
发明内容 Contents of the invention
为解决上述问题,本发明的一目的在于提供一种具有适应性电能控制的太阳光伏发电系统,以克服已知技术的问题。To solve the above problems, an object of the present invention is to provide a solar photovoltaic power generation system with adaptive power control, so as to overcome the problems of the known technology.
因此本发明的具有适应性电能控制的太阳光伏发电系统,为透过一太阳光伏电池板产生一直流电压与一直流电流,利用控制该直流电压与该直流电流所提供的一电能,对一负载供电。该具有适应性电能控制的太阳光伏发电系统为包含一充电控制单元、一充电电池单元、一第一开关单元、一第二开关单元、一电源调控单元以及一开关控制单元。Therefore, the solar photovoltaic power generation system with adaptive power control of the present invention generates a DC voltage and a DC current through a solar photovoltaic cell panel, and uses an electric energy provided by controlling the DC voltage and the DC current to control a load. powered by. The solar photovoltaic power generation system with adaptive power control includes a charge control unit, a rechargeable battery unit, a first switch unit, a second switch unit, a power regulation unit and a switch control unit.
该充电控制单元为电性连接该太阳光伏电池板。该充电电池单元为电性连接该太阳光伏电池板与该充电控制单元。该第一开关单元为电性连接该太阳光伏电池板。该第二开关单元为电性连接该充电控制单元与该充电电池单元。该电源调控单元为电性连接该太阳光伏电池板、该第一开关单元以及该第二开关单元。该开关控制单元为电性连接该太阳光伏电池板、该第一开关单元以及该第二开关单元。该开关控制单元为根据该太阳光伏电池板所产生的该直流电压与该直流电流所提供的该电能,控制该第一开关单元与该第二开关单元的导通与截止。The charging control unit is electrically connected to the solar photovoltaic panel. The charging battery unit is electrically connected to the solar photovoltaic panel and the charging control unit. The first switch unit is electrically connected to the solar photovoltaic battery panel. The second switch unit is electrically connected to the charge control unit and the rechargeable battery unit. The power regulation unit is electrically connected to the solar photovoltaic cell panel, the first switch unit and the second switch unit. The switch control unit is electrically connected to the solar photovoltaic cell panel, the first switch unit and the second switch unit. The switch control unit controls the on and off of the first switch unit and the second switch unit according to the electric energy provided by the direct voltage generated by the solar photovoltaic cell panel and the direct current.
当该太阳光伏电池板能够提供该电能输出时,该开关控制单元为导通该第一开关单元并截止该第二开关单元,使该太阳光伏电池板所输出的该电能为能透过该电源调控单元的调节,进而对该负载供电,以提供所需的能量;同时,该太阳光伏电池板所输出的该电能为能透过该充电控制单元的控制,进而对该充电电池单元充电。When the solar photovoltaic cell panel can provide the electric energy output, the switch control unit turns on the first switch unit and turns off the second switch unit, so that the electric energy output by the solar photovoltaic cell panel can pass through the power supply The adjustment of the regulating unit provides power to the load to provide the required energy; at the same time, the electric energy output by the solar photovoltaic panel can be controlled by the charging control unit to charge the rechargeable battery unit.
当该太阳光伏电池板无法提供该电能输出时,该开关控制单元为截止该第一开关单元并导通该第二开关单元,使该充电电池单元能输出所储存的该电能为能透过该电源调控单元的调节,进而对该负载供电。When the solar photovoltaic cell panel cannot provide the electric energy output, the switch control unit turns off the first switch unit and turns on the second switch unit, so that the rechargeable battery unit can output the stored electric energy through the The adjustment of the power regulation unit, and then supply power to the load.
本发明的另一目的在于提供一种具有适应性电能控制的太阳光伏发电系统的操作方法,以克服已知技术的问题。Another object of the present invention is to provide an operation method of a solar photovoltaic power generation system with adaptive power control, so as to overcome the problems of the known technology.
因此本发明的具有适应性电能控制的太阳光伏发电系统的操作方法,为透过一太阳光伏电池板产生一直流电压与一直流电流,利用控制该直流电压与该直流电流所提供的一电能,对一负载供电。该具有适应性电能控制的太阳光伏发电系统操作方法的步骤包含:提供一充电控制单元与一充电电池单元;提供一第一开关单元与一第二开关单元;提供一电源调控单元;以及提供一开关控制单元,该开关控制单元为根据该太阳光伏电池板所产生的该直流电压与该直流电流所提供的该电能,控制该第一开关单元与该第二开关单元的导通与截止。Therefore, the operating method of the solar photovoltaic power generation system with adaptive power control of the present invention is to generate a DC voltage and a DC current through a solar photovoltaic panel, and utilize an electric energy provided by controlling the DC voltage and the DC current, supply power to a load. The steps of the operating method of the solar photovoltaic power generation system with adaptive power control include: providing a charge control unit and a rechargeable battery unit; providing a first switch unit and a second switch unit; providing a power regulation unit; and providing a A switch control unit, the switch control unit controls the on and off of the first switch unit and the second switch unit according to the electric energy provided by the direct voltage generated by the solar photovoltaic cell panel and the direct current.
为了能更进一步了解本发明为达成预定目的所采取的技术、手段及功效,请参阅以下有关本发明的详细说明与附图,相信本发明的目的、特征与特点,当可由此得一深入且具体的了解,然而所附附图仅提供参考与说明用,并非用来对本发明加以限制者。In order to further understand the technology, means and effects that the present invention adopts to achieve the predetermined purpose, please refer to the following detailed description and accompanying drawings of the present invention. It is believed that the purpose, characteristics and characteristics of the present invention can be obtained from this For specific understanding, however, the accompanying drawings are only for reference and illustration, and are not intended to limit the present invention.
为让本发明的上述特征和优点能更明显易懂,下文特举实施例,并配合附图作详细说明如下。In order to make the above-mentioned features and advantages of the present invention more comprehensible, the following specific embodiments are described in detail with reference to the accompanying drawings.
附图说明 Description of drawings
图1为现有技术的太阳光伏发电系统的方块图;Fig. 1 is the block diagram of the solar photovoltaic power generation system of prior art;
图2为本发明具有适应性电能控制的太阳光伏发电系统的方块图;Fig. 2 is the block diagram of the solar photovoltaic power generation system with adaptive power control of the present invention;
图3为本发明该太阳光伏发电系统一种电能控制的方块示意图;Fig. 3 is a schematic block diagram of a kind of electric energy control of the solar photovoltaic power generation system of the present invention;
图4为本发明该太阳光伏发电系统另一种电能控制的方块示意图;及Fig. 4 is a schematic block diagram of another electric energy control of the solar photovoltaic power generation system of the present invention; and
图5为本发明具有适应性电能控制的太阳光伏发电系统操作方法的流程图。FIG. 5 is a flow chart of the operating method of the solar photovoltaic power generation system with adaptive power control according to the present invention.
附图标识Reference sign
10A太阳光伏电池板10A Solar Photovoltaic Panel
20A充电控制单元20A charging control unit
30A充电电池单元30A rechargeable battery unit
40A电源调节单元40A power conditioning unit
50A负载50A load
Sw开关单元SW switch unit
10太阳光伏电池板10 solar photovoltaic panels
20充电控制单元20 charging control unit
30充电电池单元30 rechargeable battery units
40电源调控单元40 power regulation unit
50负载50 load
60开关控制单元60 switch control unit
Sw1第一开关单元Sw1 first switch unit
Sw2第二开关单元Sw2 second switch unit
Vpv太阳光伏电池板直流电压Vpv Solar Photovoltaic Panel DC Voltage
Ipv太阳光伏电池板直流电流Ipv Solar Photovoltaic Panel DC Current
S1第一控制信号S1 first control signal
S2第二控制信号S2 second control signal
L1第一供电路径L1 first power supply path
L2第二供电路径L2 second power supply path
L3第三供电路径L3 third power supply path
S100~S400步骤Steps from S100 to S400
具体实施方式 detailed description
兹有关本发明的技术内容及详细说明,配合附图说明如下:Hereby, the technical content and detailed description of the present invention are described as follows in conjunction with the accompanying drawings:
请参见图2,为本发明具有适应性电能控制的太阳光伏发电系统的方块图。如图所示,该具有适应性电能控制的太阳光伏发电系统透过一太阳光伏电池板(photovoltaicpanel)10产生一直流电压Vpv与一直流电流Ipv,利用控制该直流电压Vpv与该直流电流Ipv所提供的一电能,对一负载50供电。该具有适应性电能控制的太阳光伏发电系统包含一充电控制单元20、一充电电池单元30、一第一开关单元Sw1、一第二开关单元Sw2、一电源调控单元40以及一开关控制单元60。Please refer to FIG. 2 , which is a block diagram of a solar photovoltaic power generation system with adaptive power control according to the present invention. As shown in the figure, the solar photovoltaic power generation system with adaptive power control generates a DC voltage Vpv and a DC current Ipv through a solar photovoltaic panel (photovoltaic panel) 10, and utilizes the control of the DC voltage Vpv and the DC current Ipv. The provided electric energy supplies power to a load 50 . The solar photovoltaic power generation system with adaptive power control includes a charge control unit 20 , a rechargeable battery unit 30 , a first switch unit Sw1 , a second switch unit Sw2 , a power regulation unit 40 and a switch control unit 60 .
该充电控制单元20电性连接该太阳光伏电池板10。该充电电池单元30电性连接该太阳光伏电池板10与该充电控制单元20。其中,该充电控制单元20以控制该充电电池单元30所需的充电电压与充电电流大小,并调节该太阳光伏电池板10所产生该直流电压Vpv与该直流电流Ipv的工作点(operatingpoint),以提供最大功率点追踪(maximumpowerpointtracing,MPPT)控制。该第一开关单元Sw1为电性连接该太阳光伏电池板10。该第二开关单元Sw2为电性连接该充电控制单元20与该充电电池单元30。该电源调控单元40为电性连接该太阳光伏电池板10、该第一开关单元Sw1以及该第二开关单元Sw2。其中,该电源调控单元40为一直流转交流的变流器(inverter)。此外,该电源调控单元40为能调节该太阳光伏电池板10所产生该直流电压Vpv与该直流电流Ipv的工作点(operatingpoint),以提供最大功率点追踪(maximumpowerpointtracing,MPPT)控制。惟,该电源调控单元40的功能与电路架构(topology),端视应用场合与使用者需求而有所不同,不以上述的架构为限。该开关控制单元60为电性连接该太阳光伏电池板10、该第一开关单元Sw1以及该第二开关单元Sw2。该开关控制单元60为根据该太阳光伏电池板10所产生的该直流电压Vpv与该直流电流Ipv所提供的该电能,控制该第一开关单元Sw1与该第二开关单元Sw2的导通与截止。The charging control unit 20 is electrically connected to the solar photovoltaic panel 10 . The rechargeable battery unit 30 is electrically connected to the solar photovoltaic panel 10 and the charging control unit 20 . Wherein, the charging control unit 20 controls the charging voltage and charging current required by the rechargeable battery unit 30, and adjusts the operating point (operating point) of the DC voltage Vpv and the DC current Ipv generated by the solar photovoltaic cell panel 10, To provide maximum power point tracking (maximum power point tracing, MPPT) control. The first switch unit Sw1 is electrically connected to the solar photovoltaic panel 10 . The second switch unit Sw2 is electrically connected to the charging control unit 20 and the rechargeable battery unit 30 . The power regulation unit 40 is electrically connected to the solar photovoltaic cell panel 10 , the first switch unit Sw1 and the second switch unit Sw2 . Wherein, the power regulating unit 40 is a converter (inverter) for converting DC to AC. In addition, the power regulation unit 40 is capable of regulating the operating point of the DC voltage Vpv and the DC current Ipv generated by the solar photovoltaic panel 10 to provide maximum power point tracking (MPPT) control. However, the function and circuit topology of the power regulation unit 40 are different depending on the application and user requirements, and are not limited to the above-mentioned topology. The switch control unit 60 is electrically connected to the solar photovoltaic cell panel 10 , the first switch unit Sw1 and the second switch unit Sw2 . The switch control unit 60 controls the on and off of the first switch unit Sw1 and the second switch unit Sw2 according to the electric energy provided by the DC voltage Vpv and the DC current Ipv generated by the solar photovoltaic cell panel 10 .
至于该太阳光伏发电系统的适应性电能控制的详细操作,将如下文所述。请参见图3,为本发明该太阳光伏发电系统一种电能控制的方块示意图。当该太阳光伏电池板10能够提供该电能输出时,该开关控制单元60为导通该第一开关单元Sw1并截止该第二开关单元Sw2,使该太阳光伏电池板10所输出的该电能为能透过该电源调控单元40调节,进而对该负载50供电,以提供所需的能量,此时,该太阳光伏电池板10所提供的电能对该负载50供电的路径,参见图上所绘的一第一供电路径L1所示。As for the detailed operation of the adaptive power control of the solar photovoltaic power generation system, it will be described as follows. Please refer to FIG. 3 , which is a schematic block diagram of an electric energy control of the solar photovoltaic power generation system of the present invention. When the solar photovoltaic cell panel 10 can provide the electric energy output, the switch control unit 60 is to turn on the first switch unit Sw1 and turn off the second switch unit Sw2, so that the electric energy output by the solar photovoltaic cell panel 10 is It can be regulated by the power regulation unit 40, and then the load 50 is powered to provide the required energy. At this time, the path of the electric energy provided by the solar photovoltaic panel 10 to supply power to the load 50 is shown in the figure A first power supply path L1 is shown.
同时,该太阳光伏电池板10所输出的该电能为能透过该充电控制单元20的控制,进而对该充电电池单元30充电,以储存该电能,此时,该太阳光伏电池板10所提供的电能对该充电电池单元30充电的路径,参见图上所绘的一第二供电路径L2所示。At the same time, the electric energy output by the solar photovoltaic cell panel 10 can be controlled by the charging control unit 20 to charge the rechargeable battery unit 30 to store the electric energy. At this time, the solar photovoltaic cell panel 10 provides The path of electric energy charging the rechargeable battery unit 30 is shown as a second power supply path L2 drawn on the figure.
值得一提,该开关控制单元60为电性连接该太阳光伏电池板10,以接收该太阳光伏电池板10所输出的该直流电压Vpv与该直流电流Ipv。并且,该开关控制单元60为根据该太阳光伏电池板10所输出的该直流电压Vpv与该直流电流Ipv大小判断,该太阳光伏电池板10是否提供该电能的输出。亦即,当该直流电压Vpv与该直流电流Ipv皆不为零时,则该太阳光伏电池板10所提供的该电能大小为该直流电压Vpv与该直流电流Ipv的乘积。因此,在实际应用的实例中,该太阳光伏电池板10能够提供该电能输出的时机,通常为当该太阳光伏发电系统操作于白天或晴天(气候条件良好)时。换言之,当该太阳光伏发电系统操作于白天或晴天(气候条件良好)时,该太阳光伏电池板10所输出的该电能为能透过该电源调控单元40的调节,进而对该负载50供电,以提供所需的能量。同时,该太阳光伏电池板10所输出的该电能为能透过该充电控制单元20的控制,进而对该充电电池单元30充电,以储存该电能。亦即,该太阳光伏电池板10为可直接对该负载50供电,亦同时能将多余的该电能储存于该充电电池单元30中。It is worth mentioning that the switch control unit 60 is electrically connected to the solar photovoltaic panel 10 to receive the DC voltage Vpv and the DC current Ipv output by the solar photovoltaic panel 10 . Moreover, the switch control unit 60 judges whether the solar photovoltaic panel 10 provides the output of electric energy according to the magnitude of the DC voltage Vpv and the DC current Ipv output by the solar photovoltaic panel 10 . That is, when the DC voltage Vpv and the DC current Ipv are not zero, the electric energy provided by the solar photovoltaic cell panel 10 is the product of the DC voltage Vpv and the DC current Ipv. Therefore, in an example of practical application, the timing when the solar photovoltaic cell panel 10 can provide the electric energy output is usually when the solar photovoltaic power generation system operates in daytime or sunny (good weather conditions). In other words, when the solar photovoltaic power generation system operates in the daytime or on a sunny day (good weather conditions), the electric energy output by the solar photovoltaic cell panel 10 can be regulated by the power regulation unit 40 to supply power to the load 50, to provide the required energy. At the same time, the electric energy output by the solar photovoltaic panel 10 can be controlled by the charging control unit 20 to charge the rechargeable battery unit 30 to store the electric energy. That is, the solar photovoltaic panel 10 can directly supply power to the load 50 , and at the same time, can store the excess electric energy in the rechargeable battery unit 30 .
当该太阳光伏电池板10能够提供该电能输出时,该电源调控单元40为提供该电能对该负载50供电与对该充电电池单元30充电的调节,亦即,该电源调控单元40能够根据该负载50所需的能量大小,以调节该太阳光伏电池板10所输出的该电能提供给该负载50使用,另外,调节该太阳光伏电池板10所输出的该电能其余部分给该充电电池单元30储存。When the solar photovoltaic cell panel 10 can provide the electric energy output, the power regulation unit 40 is to provide the electric energy to regulate the power supply to the load 50 and the charging of the rechargeable battery unit 30, that is, the power regulation unit 40 can adjust according to the The amount of energy required by the load 50 is to adjust the electric energy output by the solar photovoltaic cell panel 10 to be used by the load 50 , and to adjust the remaining part of the electric energy output by the solar photovoltaic cell panel 10 to the rechargeable battery unit 30 store.
在上述该第一开关单元Sw1与该第二开关单元Sw2的控制中,该开关控制单元60为产生一第一控制信号S1以控制该第一开关单元Sw1的导通,并且,该开关控制单元60为产生一第二控制信号S2以控制该第二开关单元Sw2的截止。此外,该第一控制信号S1与该第二控制信号S2为互补信号,亦即,当该第一控制信号S1为高准位导通该第一开关单元Sw1,而该第二控制信号S2为低准位截止该第二开关单元Sw2。In the above control of the first switch unit Sw1 and the second switch unit Sw2, the switch control unit 60 generates a first control signal S1 to control the conduction of the first switch unit Sw1, and the switch control unit 60 is to generate a second control signal S2 to control the cut-off of the second switch unit Sw2. In addition, the first control signal S1 and the second control signal S2 are complementary signals, that is, when the first control signal S1 is at a high level, the first switch unit Sw1 is turned on, and the second control signal S2 is The low level turns off the second switch unit Sw2.
请参见图4,为本发明该太阳光伏发电系统另一种电能控制的方块示意图。当该太阳光伏电池板10无法提供该电能输出时,该开关控制单元60为截止该第一开关单元Sw1并导通该第二开关单元Sw2,使该充电电池单元30能输出所储存的该电能为能透过该电源调控单元40的调节,进而对该负载50供电,以提供所需的能量,此时,该充电电池单元30所储存的该电能对该负载50供电的路径,参见图上所绘的一第三供电路径L3所示。Please refer to FIG. 4 , which is a schematic block diagram of another electric energy control of the solar photovoltaic power generation system of the present invention. When the solar photovoltaic panel 10 cannot provide the electric energy output, the switch control unit 60 is to turn off the first switch unit Sw1 and turn on the second switch unit Sw2, so that the rechargeable battery unit 30 can output the stored electric energy In order to supply power to the load 50 through the adjustment of the power regulation unit 40 to provide the required energy, at this time, the path of the electric energy stored in the rechargeable battery unit 30 to supply power to the load 50 is shown in the figure A third power supply path L3 is drawn.
值得一提,该开关控制单元60为电性连接该太阳光伏电池板10,以接收该太阳光伏电池板10所输出的该直流电压Vpv与该直流电流Ipv。并且,该开关控制单元60为根据该太阳光伏电池板10所输出的该直流电压Vpv与该直流电流Ipv大小判断,该太阳光伏电池板10是否提供该电能的输出。亦即,当该直流电压Vpv与该直流电流Ipv皆为零时,则该太阳光伏电池板10所提供的该电能大小(为该直流电压Vpv与该直流电流Ipv的乘积)亦即为零。因此,在实际应用的实例中,该太阳光伏电池板10无法提供该电能输出的时机,通常为当该太阳光伏发电系统操作于晚上时。换言之,当该太阳光伏发电系统操作于晚上时,该充电电池单元30能输出所储存的该电能为能透过该电源调控单元40的调节,进而对该负载50供电,以提供所需的能量。亦即,该充电电池单元30为可当该太阳光伏电池板10无法提供该负载50所需的该电能时,将所储存的该电能提供给该负载50使用。此外,当该太阳光伏电池板10无法提供该电能输出时,该电源调控单元40为提供该充电电池单元30所储存的该电能对该负载50供电的调节,亦即,该电源调控单元40能够根据该负载50所需的能量大小,以调节该充电电池单元30所储存的该电能对该负载50供电。It is worth mentioning that the switch control unit 60 is electrically connected to the solar photovoltaic panel 10 to receive the DC voltage Vpv and the DC current Ipv output by the solar photovoltaic panel 10 . Moreover, the switch control unit 60 judges whether the solar photovoltaic panel 10 provides the output of electric energy according to the magnitude of the DC voltage Vpv and the DC current Ipv output by the solar photovoltaic panel 10 . That is, when the DC voltage Vpv and the DC current Ipv are both zero, the electric energy provided by the solar photovoltaic cell panel 10 (which is the product of the DC voltage Vpv and the DC current Ipv) is also zero. Therefore, in practical examples, the solar photovoltaic cell panel 10 cannot provide the power output, which is usually when the solar photovoltaic power generation system operates at night. In other words, when the solar photovoltaic power generation system operates at night, the rechargeable battery unit 30 can output the stored electric energy through the adjustment of the power regulation unit 40, and then supply power to the load 50 to provide the required energy . That is, the rechargeable battery unit 30 can provide the stored electric energy to the load 50 when the solar photovoltaic panel 10 cannot provide the electric energy required by the load 50 . In addition, when the solar photovoltaic panel 10 cannot provide the electric energy output, the power regulation unit 40 provides the regulation of the electric energy stored in the rechargeable battery unit 30 to power the load 50, that is, the power regulation unit 40 can According to the energy required by the load 50 , the electric energy stored in the rechargeable battery unit 30 is adjusted to supply power to the load 50 .
在上述该第一开关单元Sw1与该第二开关单元Sw2的控制中,该开关控制单元60为产生该第一控制信号S1以控制该第一开关单元Sw1的截止,并且,该开关控制单元60为产生该第二控制信号S2以控制该第二开关单元Sw2的导通。此外,该第一控制信号S1与该第二控制信号S2为互补信号,亦即,当该第一控制信号S1为低准位截止该第一开关单元Sw1,而该第二控制信号S2为高准位导通该第二开关单元Sw2。In the above control of the first switch unit Sw1 and the second switch unit Sw2, the switch control unit 60 generates the first control signal S1 to control the cut-off of the first switch unit Sw1, and the switch control unit 60 To generate the second control signal S2 to control the conduction of the second switch unit Sw2. In addition, the first control signal S1 and the second control signal S2 are complementary signals, that is, when the first control signal S1 is at a low level, the first switch unit Sw1 is turned off, and the second control signal S2 is at a high level. The level turns on the second switch unit Sw2.
请参见图5,为本发明具有适应性电能控制的太阳光伏发电系统操作方法的流程图。该具有适应性电能控制的太阳光伏发电系统的操作方法,为透过一太阳光伏电池板产生一直流电压与一直流电流,利用控制该直流电压与该直流电流所提供的一电能,对一负载供电。该具有适应性电能控制的太阳光伏发电系统操作方法的步骤为包含:提供一充电控制单元与一充电电池单元(S100)。提供一第一开关单元与一第二开关单元(S200)。提供一电源调控单元(S300)。其中,该电源调控单元为一直流转交流的变流器(inverter)。此外,该电源调控单元为能调节该太阳光伏电池板所产生该直流电压与该直流电流的工作点(operatingpoint),以提供最大功率点追踪(maximumpowerpointtracing,MPPT)控制。提供一开关控制单元。该开关控制单元为根据该太阳光伏电池板所产生的该直流电压与该直流电流所提供的该电能,控制该第一开关单元与该第二开关单元的导通与截止(S400)。其中,该开关控制单元为产生一第一控制信号与一第二控制信号,以分别控制该第一开关单元与该第二开关单元的导通与截止。并且,该第一控制信号与该第二控制信号为互补信号,亦即,当该第一控制信号为高准位导通该第一开关单元,而该第二控制信号为低准位截止该第二开关单元;或者,当该第一控制信号为低准位截止该第一开关单元,而该第二控制信号为高准位导通该第二开关单元。Please refer to FIG. 5 , which is a flow chart of the operating method of the solar photovoltaic power generation system with adaptive power control according to the present invention. The operation method of the solar photovoltaic power generation system with adaptive power control is to generate a direct current voltage and a direct current through a solar photovoltaic panel, and use an electric energy provided by controlling the direct current voltage and the direct current to control a load powered by. The steps of the operating method of the solar photovoltaic power generation system with adaptive power control include: providing a charge control unit and a rechargeable battery unit ( S100 ). A first switch unit and a second switch unit are provided (S200). Provide a power regulation unit (S300). Wherein, the power regulation unit is a DC-to-AC converter (inverter). In addition, the power regulation unit is capable of regulating the operating point of the DC voltage and the DC current generated by the solar photovoltaic cell panel, so as to provide maximum power point tracking (MPPT) control. A switch control unit is provided. The switch control unit controls the turn-on and turn-off of the first switch unit and the second switch unit according to the electric energy provided by the direct voltage generated by the solar photovoltaic cell panel and the direct current ( S400 ). Wherein, the switch control unit generates a first control signal and a second control signal to respectively control the on and off of the first switch unit and the second switch unit. Moreover, the first control signal and the second control signal are complementary signals, that is, when the first control signal is at a high level, the first switch unit is turned on, while the second control signal is at a low level, the switch unit is turned off. A second switch unit; or, when the first control signal is at a low level, the first switch unit is turned off, and the second control signal is at a high level, and the second switch unit is turned on.
在步骤(S400)中,当该太阳光伏电池板能够提供该电能输出时,该开关控制单元导通该第一开关单元并截止该第二开关单元,使该太阳光伏电池板所输出的该电能为能透过该电源调控单元调节,进而对该负载供电,以提供所需的能量;同时,该太阳光伏电池板所输出的该电能为能透过该充电控制单元的控制,进而对该充电电池单元充电,以储存该电能。亦即,当该太阳光伏电池板能够提供该电能输出时,该电源调控单元为提供该电能对该负载供电与对该充电电池单元充电的调节。同时,该充电控制单元为以控制该充电电池单元所需的充电电压与充电电流大小,并调节该太阳光伏电池板所产生该直流电压与该直流电流的工作点,以提供最大功率点追踪控制。In step (S400), when the solar photovoltaic cell panel can provide the electric energy output, the switch control unit turns on the first switch unit and turns off the second switch unit, so that the electric energy output by the solar photovoltaic cell panel In order to be able to adjust through the power regulation unit, and then supply power to the load to provide the required energy; at the same time, the electric energy output by the solar photovoltaic panel can be controlled by the charging control unit, and then charge the load The battery cells are charged to store this electrical energy. That is, when the solar photovoltaic panel can provide the electric energy output, the power regulating unit provides the electric energy for powering the load and regulating the charging of the rechargeable battery unit. At the same time, the charging control unit is to control the charging voltage and charging current required by the rechargeable battery unit, and adjust the operating point of the DC voltage and the DC current generated by the solar photovoltaic panel to provide maximum power point tracking control .
同样地,在步骤(S400)中,当该太阳光伏电池板无法提供该电能输出时,该开关控制单元为截止该第一开关单元并导通该第二开关单元,使该充电电池单元能输出所储存的该电能为能透过该电源调控单元的调节,进而对该负载供电,以提供所需的能量。亦即,当该太阳光伏电池板无法提供该电能输出时,该电源调控单元为提供该充电电池单元所储存的该电能对该负载供电的调节。Similarly, in step (S400), when the solar photovoltaic panel cannot provide the electric energy output, the switch control unit is to turn off the first switch unit and turn on the second switch unit, so that the rechargeable battery unit can output The stored electric energy can be regulated by the power regulation unit to supply power to the load to provide the required energy. That is, when the solar photovoltaic cell panel cannot provide the electric energy output, the power regulation unit provides regulation of the electric energy stored in the rechargeable battery unit to supply power to the load.
综上所述,本发明具有以下的优点:In summary, the present invention has the following advantages:
1、可根据早晚时间或气候条件,利用该开关控制单元控制该第一开关单元与该第二开关单元的导通与截止,以提供具有适应性电能控制功能;1. The switch control unit can be used to control the on and off of the first switch unit and the second switch unit according to the morning and evening time or weather conditions, so as to provide an adaptive power control function;
2、当该太阳光伏电池板能够提供该电能输出时,可提供该太阳光伏电池板对该负载供电或对该充电电池单元充电的不同路径,使得当该太阳光伏电池板对该负载直接供电时,不需要经由该充电控制单元的操作,如此,可大大地提升该太阳光伏发电系统的整体效率。2. When the solar photovoltaic panel can provide the electric energy output, it can provide different paths for the solar photovoltaic panel to supply power to the load or to charge the rechargeable battery unit, so that when the solar photovoltaic panel directly supplies power to the load , does not need to operate through the charging control unit, so that the overall efficiency of the solar photovoltaic power generation system can be greatly improved.
本发明的技术内容及技术特点已如上公开,在不背离本发明精神及其实质的情况下,熟悉本领域的技术人员可根据本发明作出各种相应的改变和变形,但这些相应的改变和变形都应属于本发明所附的权利要求的保护范围。The technical content and technical characteristics of the present invention have been disclosed above. Without departing from the spirit and essence of the present invention, those skilled in the art can make various corresponding changes and deformations according to the present invention, but these corresponding changes and All deformations should belong to the protection scope of the appended claims of the present invention.
Claims (18)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201110259635.XA CN102983617B (en) | 2011-09-05 | 2011-09-05 | Solar photovoltaic power generation system with adaptive power control and method of operation thereof |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201110259635.XA CN102983617B (en) | 2011-09-05 | 2011-09-05 | Solar photovoltaic power generation system with adaptive power control and method of operation thereof |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102983617A CN102983617A (en) | 2013-03-20 |
| CN102983617B true CN102983617B (en) | 2016-01-20 |
Family
ID=47857431
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201110259635.XA Active CN102983617B (en) | 2011-09-05 | 2011-09-05 | Solar photovoltaic power generation system with adaptive power control and method of operation thereof |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102983617B (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105141023A (en) * | 2014-05-30 | 2015-12-09 | 宁波保税区绿光能源科技有限公司 | Solar power supply processing system in area without mains supply or with instable mains supply output |
| CN105322868A (en) * | 2014-08-01 | 2016-02-10 | 高平唐一新能源科技有限公司 | Solar synergistic energy system and method |
| CN108964100B (en) * | 2018-06-26 | 2022-03-25 | 江门云天电力设计咨询有限公司 | Photovoltaic circuit control method and device based on circuit current |
Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2552232Y (en) * | 2002-04-19 | 2003-05-21 | 深圳键桥通讯技术有限公司 | Solar charger |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2000004544A (en) * | 1998-06-11 | 2000-01-07 | Nippon Telegr & Teleph Corp <Ntt> | Independent photovoltaic power supply control method and system device |
| US7830038B2 (en) * | 2007-12-17 | 2010-11-09 | Shay-Ping Thomas Wang | Single chip solution for solar-based systems |
-
2011
- 2011-09-05 CN CN201110259635.XA patent/CN102983617B/en active Active
Patent Citations (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2552232Y (en) * | 2002-04-19 | 2003-05-21 | 深圳键桥通讯技术有限公司 | Solar charger |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102983617A (en) | 2013-03-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| TWI460963B (en) | Photovoltaic powered system with adaptive power control and method of operating the same | |
| US6914418B2 (en) | Multi-mode renewable power converter system | |
| US7830038B2 (en) | Single chip solution for solar-based systems | |
| US20170201098A1 (en) | Photovoltaic microstorage microinverter | |
| US20050006958A1 (en) | Grid-connected power systems having back-up power sources and methods of providing back-up power in grid-connected power systems | |
| GB2622726A (en) | Electric vehicle solar charging system | |
| AU2009329554B2 (en) | A photovoltaic system | |
| Doshi et al. | Analysis of a wind-PV battery hybrid renewable energy system for a dc microgrid | |
| CN103441674A (en) | Bi-directional dual-input CUK/BUCKBOOST DC converter and its power distribution method | |
| CN103269157A (en) | Bi-Directional Dual-Input SEPIC DC Converter and Its Power Distribution Method | |
| WO2025097784A1 (en) | Hybrid energy storage system and control method therefor | |
| Jie et al. | Nanogrid for energy aware buildings | |
| CN104701877A (en) | Novel building photovoltaic power generation maximum power point tracking and grid connection control device | |
| CN104953927A (en) | Novel solar and diesel hybrid power generation system | |
| CN103296879A (en) | Bi-directional double-input CUK DC converter and its power distribution method | |
| CN102983617B (en) | Solar photovoltaic power generation system with adaptive power control and method of operation thereof | |
| CN103401419A (en) | Bi-directional double-input BUCK/BUCKBOOST DC converter and its power distribution method | |
| CN103441671A (en) | Bidirectional Double Input ZETA/BUCKBOOST DC Converter and Its Power Distribution Method | |
| Nayar | Control and interfacing of bi-directional inverters for off-grid and weak grid photovoltaic power systems | |
| CN103166303A (en) | Power management device and method of operation thereof | |
| CN103187794A (en) | Compound invertion device | |
| Das et al. | A novel control strategy for stand-alone solar PV systems with enhanced battery life | |
| CN202513586U (en) | Intelligent micro-grid using renewable energy for generating power | |
| Samith et al. | Controller for integrating small scale power generation to hybrid AC/DC grid | |
| Gawande et al. | Design and development of cost-effective solar PV based DC microgrid for rural applications |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant |