CN102930141A - Quick calculation method for controlling power grid complicated monitoring section tidal current - Google Patents
Quick calculation method for controlling power grid complicated monitoring section tidal current Download PDFInfo
- Publication number
- CN102930141A CN102930141A CN2012103797030A CN201210379703A CN102930141A CN 102930141 A CN102930141 A CN 102930141A CN 2012103797030 A CN2012103797030 A CN 2012103797030A CN 201210379703 A CN201210379703 A CN 201210379703A CN 102930141 A CN102930141 A CN 102930141A
- Authority
- CN
- China
- Prior art keywords
- section
- matrix
- monitoring
- limit
- trend
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
The invention discloses a quick calculation method for controlling power grid complicated monitoring section tidal current. The method is simplified and abstracted according to an actual power grid structure, and a monitoring section topological graph based on a directed picture is constructed. The overload of a monitoring section can be gradually eliminated according to a rule from bottom to top; node adjustment values are quickly distributed by using a coefficient matrix; and an algorithm is realized according to an adjacent matrix and a path matrix in a graph theory. The simulation result of an example shows that the method provided by the invention is feasible and effective in complicated section monitoring.
Description
Technical field
The invention belongs to electrical equipment and electrical engineering technical field, be applicable to the quick control of the complicated monitoring of electrical network section tidal current after out-of-limit, significant to guaranteeing power grid security.
Technical background
In recent years, repeatedly large area blackout occurs in electric system, add such as " 814 " U.S.A have a power failure on a large scale, " 114 " Europe has a power failure on a large scale, " 730 ", " 731 " India have a power failure on a large scale etc., the economic loss that causes and social influence are extremely serious.
China's electric power networks structure is relatively weaker, and the energy and economic development are uneven, and electric power resource and power load distributed pole are inhomogeneous, and the electric power more than needed of repository needs to be transported to load center by long distance transmission line.Expect the year two thousand twenty, will have every year 100000MW electric power to be sent to the east by many AC/DC parallel circuits from western part.
Power plant generally accesses electrical network according to electric pressure according to nearby principle, a plurality of concentrating again after sending passage and compiling sent, and so often has a plurality of power plant and shares one and send passage, causes some areas electric power to be sent and is obstructed, send passage and press for a long time limit operation, stabilization of power grids problem is very outstanding.The limit of transmission cross-section is restricted by angle stability, thermally-stabilised, voltage stabilization mainly, and when the circuit transmission power surpasses stability limit, in case disturbance occurs, the stabilization of power grids is very likely destroyed, thereby causes large area blackout, the serious threat power grid security.
Compound section for single section, refer to one group electric have contact directly, interactional section set.A plurality of control section Relations Amongs in the compound section are complicated, each control section has compiled a plurality of subordinates section, the fluctuation of the inconsistent and regional earth mat load on power plant's generating capacity time that subordinate's section is incorporated into the power networks, space, the capital has influence on the trend of higher level's section, the section reason of over-load is complicated, therefore also brings difficulty for the regulation and control of scheduling at different levels.When guaranteeing the passway for transmitting electricity utilization factor, a plurality of sections of sending on the passage are carried out real time monitoring, when the generation section is out-of-limit, according to open, fair and impartial " three public affairs " principle, regulation and control are transshipped to eliminate fast, and are for ensureing electricity net safety stable, significant.
Summary of the invention
Purpose of the present invention is just for can be after complexity is monitored section and transshipped, the section tidal current control program is calculated fast, for Dispatchers on duty or the automatic control system of electric system provides the control strategy reference, with the overload of all monitoring sections of quick elimination, thereby guarantee power grid security.
The objective of the invention is to realize by following technical solution.
The quick calculation method of the complicated monitoring of a kind of electrical network section tidal current control, feature of the present invention is:
(1) set up based on the complicated section topological model of monitoring of the electrical network of graph theory; The section that needs in the actual electric network to monitor comprises main transformer, transmission line of electricity element, and each section is in respectively the superior and the subordinate of passway for transmitting electricity, and connection type is various, sends trend and interacts.Each section that mainly comprises the needs monitoring in the monitoring section topological diagram of setting up, all the other uncorrelated factory stations, circuit are simplified in topological diagram; Substation bus bar is abstract to be summit V in the digraph, and needing the elements such as main transformer, circuit of monitoring abstract is limit E in the digraph;
(2). set up the regulation and control allocation proportion that matrix of coefficients K reflects each section; K is the square formation (k on n * n rank
Ij)
N * n, n is the summit number of monitoring section topological diagram; If section l
IjTrend need to adjust Δ p
Ij, the capable vector that the resize ratio that then all nodes be should bear in the network forms is K
i, K
iMiddle all elements sum is 1; What matrix of coefficients K reflected is the percentage contribution that each node is regulated and control section, can calculate according to proportional sharing principle, can require arrange according to the regulation and control in the production reality;
(3). set up the adjustment vector M
tThe trend size that the reflection moment each node of t should be adjusted; M
tBe the row vector of 1 * n dimension, (to carry out size be m to the section tidal current of sending of 1≤i≤n) to node i
iRegulation and control after, the constantly out-of-limit whole eliminations of all monitoring sections of t;
(4). using formula Δ P
t=P'-P
tCalculate the constantly nargin matrix Δ P of t
tΔ P
tSquare formation (Δ p for n * n rank
Ij)
N * n, P ' is the limit value matrix of this monitor network, consists of P by the monitoring limit value of each section
tBe the trend matrix of moment t, by the SCADA system acquisition in the electric system.Nargin matrix Δ P
tEach section is in the section nargin size of moment t, if Δ p in the reflection monitor network
Ij<0, section l then
IjOut-of-limit, if Δ p
Ij0, section l then
IjNot out-of-limit;
(5) if. a certain section l
IjTrend is out-of-limit, according to the principle of " from bottom to top ", eliminates first the out-of-limit of its all subordinate's sections, then upgrades the nargin matrix, if this section still transships, then according to matrix of coefficients K, determines the adjustment trend size that each node be should bear, to eliminate this section overload;
(6). travel through all and monitor section, and the overload section is carried out the measure of eliminating overload, until all section overloads are eliminated, obtain the constantly adjustment vector M of t
t
Because electric network composition changes little, need the section of monitoring relatively fixing, the structure of therefore monitoring the section topological model can carry out by off-line, adjusts vector M
tCalculating mainly be matrix operation, can satisfy the requirement of online rapid calculation; The Dispatchers on duty of electric system or automatic control system are according to adjusting vector M
tThe monitoring section is controlled fast, can when guaranteeing channel utilization index, " three public affairs " dispatching principle, effectively be eliminated fast the out-of-limit of all monitoring sections of moment t, thereby guarantee the safety of electrical network.
If a certain section l
IjOut-of-limit, all eliminate but all sections of its subordinate are out-of-limit, then for eliminating this section overload, the adjustment amount that each node is born is by the vector of the i every trade among matrix of coefficients K K
iDetermine.Matrix of coefficients K can arrange according to producing actual needs, also can adjust principle according to equal proportion and calculate, and computing method are:
(1) initialization K=P
t, with all are set to 0 less than 0 element among the K, revise complete after, each row of K are carried out normalization;
(2) make K=K
T, i=1;
(3) make j=1;
(4) if k
Ij≠ 0, then travel through h=1 ~ n, step-length is 1, to each h, such as k
Jh≠ 0, then make k
Ih=k
Ij* k
JhTraversal makes k after finishing
Ij=0;
(5) j=j+1, execution in step (4) is until j〉n;
(6) i=i+1, execution in step (3) is until i〉n;
(7) if the row vector of traversal matrix of coefficients K is K
x=0, then make k
Xx=1, calculate and finish.
Below in conjunction with the drawings and specific embodiments the present invention is done further explanation.
Description of drawings
Fig. 1 is policing algorithm schematic flow sheet of the present invention;
Fig. 2 is the electric network wiring scheme of an embodiment of the present invention;
Fig. 3 is the monitoring section topological diagram of an embodiment of the present invention.
Embodiment
Embodiment
If total n the summit of a certain monitoring section topology, the trend matrix is P
t, the limit value matrix is P ', nargin matrix Δ P
t=P '-P
t, path matrix T, matrix of coefficients K adjusts vector M
tAdjust vector M
tFind the solution flow process as shown in Figure 1, concrete derivation algorithm is as follows:
(1) vector M is adjusted in initialization
t=0;
(2) traversal Δ P
tMiddle all elements is such as Δ p
Ij<0, then represent section l
IjOut-of-limit, enter step (3);
(3) traversal x=1 ~ n, step-length is 1, if t
Xi≠ 0, show that node x is positioned at section l
IjSubordinate, execution in step (4) then; Traversal finishes, and shows that subordinate's section is all without overload, execution in step (5);
(4) traversal y=1 ~ n, step-length is 1, if
The section of sending that shows node x transships then recursive call step (3); Traversal finishes, and returns step (3);
(5) the overload section of establishing current search is l
Xy, then
K wherein
xX every trade vector for matrix of coefficients;
(6) upgrade nargin matrix Δ P
t, section l
XyAll superior nodes send section nargin and all increase
(7) if all section overloads are eliminated, then computing stops, otherwise, continue step (2).
According to adjusting vector M
tEach node is regulated and control to eliminate constantly all section overloads of t, if m
iBe negative value, then exerting oneself of node i adjusted and reduced | m
i|, if m
iFor on the occasion of, then with the increase of exerting oneself of node i | m
i|.
Take the area power grid of From Western Yunnan as example, feasibility and the validity of regulation and control algorithm is described.The From Western Yunnan hydroelectric resources is abundant, and total installed capacity reaches 1,420 ten thousand kilowatts, and a large amount of small power stations send and are obstructed in flood season, send passage and press for a long time limit operation.The area power grid wiring as shown in Figure 2, the method according to this invention has made up corresponding monitoring section topological diagram, as shown in Figure 3.If a certain moment, section l
21, l
2,l
75Simultaneously out-of-limit, regulation and control algorithm according to the present invention is tried to achieve matrix of coefficients K as the formula (1),
Try to achieve the adjustment vector M
t=[0,0,0,0,0 ,-1,0 ,-6 ,-2,-10], namely to node 6,8,9,10 on send power and adjust and reduce respectively 1MW, 6MW, 2MW, 10MW after, can eliminate fast the out-of-limit of all monitoring sections, and each passage is regulated and control according to the equal proportion principle, satisfy " three public affairs " scheduling requirement, regulating effect is as shown in table 1.
The table 1 regulating effect table of comparisons
Claims (1)
1. an electrical network complexity is monitored the quick calculation method that section tidal current is controlled, and it is characterized in that:
(1). set up the complicated monitoring of the electrical network section topological model based on graph theory; The section that needs in the actual electric network to monitor comprises main transformer, transmission line of electricity element, and each section is in respectively the superior and the subordinate of passway for transmitting electricity, and connection type is various, sends trend and interacts; Each section that mainly comprises the needs monitoring in the monitoring section topological diagram of setting up, all the other uncorrelated factory stations, circuit are simplified in topological diagram; Substation bus bar is abstract to be summit V in the digraph, and needing the elements such as main transformer, circuit of monitoring abstract is limit E in the digraph;
(2). set up the regulation and control allocation proportion that matrix of coefficients K reflects each section; K is the square formation (k on n * n rank
Ij)
N * n, n is the summit number of monitoring section topological diagram; If section l
IjTrend need to adjust Δ p
Ij, the capable vector that the resize ratio that then all nodes be should bear in the network forms is K
i, K
iMiddle all elements sum is 1; What matrix of coefficients K reflected is the percentage contribution that each node is regulated and control section, calculates according to proportional sharing principle, requires to arrange according to the regulation and control in the production reality;
(3). set up the adjustment vector M
tThe trend size that the reflection moment each node of t should be adjusted; M
tBe the row vector of 1 * n dimension, (to carry out size be m to the section tidal current of sending of 1≤i≤n) to node i
iRegulation and control after, the constantly out-of-limit whole eliminations of all monitoring sections of t;
(4). using formula Δ P
t=P '-P
tCalculate the constantly nargin matrix Δ P of t
tΔ P
tSquare formation (Δ p for n * n rank
Ij)
N * n, P ' is the limit value matrix of this monitor network, consists of P by the monitoring limit value of each section
tBe the trend matrix of moment t, by the SCADA system acquisition in the electric system; Nargin matrix Δ P
tEach section is in the section nargin size of moment t, if Δ p in the reflection monitor network
Ij<0, section l then
IjOut-of-limit, if Δ p
Ij0, section l then
IjNot out-of-limit;
(5) if. a certain section l
IjTrend is out-of-limit, according to the principle of " from bottom to top ", eliminates first the out-of-limit of its all subordinate's sections, then upgrades the nargin matrix, if this section still transships, then according to matrix of coefficients K, determines the adjustment trend size that each node be should bear, to eliminate this section overload;
(6). travel through all and monitor section, and the overload section is carried out the measure of eliminating overload, until all section overloads are eliminated, obtain the constantly adjustment vector M of t
t
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210379703.0A CN102930141B (en) | 2012-10-09 | 2012-10-09 | The quick calculation method that a kind of electrical network complexity monitoring section tidal current controls |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210379703.0A CN102930141B (en) | 2012-10-09 | 2012-10-09 | The quick calculation method that a kind of electrical network complexity monitoring section tidal current controls |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102930141A true CN102930141A (en) | 2013-02-13 |
CN102930141B CN102930141B (en) | 2015-11-25 |
Family
ID=47644938
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210379703.0A Expired - Fee Related CN102930141B (en) | 2012-10-09 | 2012-10-09 | The quick calculation method that a kind of electrical network complexity monitoring section tidal current controls |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102930141B (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103077484A (en) * | 2013-02-20 | 2013-05-01 | 华东电网有限公司 | Multi-dimensional power flow evaluation index method based on statistic analysis of historical information of power grid |
CN103632052A (en) * | 2013-11-27 | 2014-03-12 | 国网上海市电力公司 | Power distribution network load flow calculation method |
CN104102830A (en) * | 2014-07-09 | 2014-10-15 | 西南交通大学 | Complex network building method |
CN106600136A (en) * | 2016-12-08 | 2017-04-26 | 国网浙江省电力公司 | Electric power section off-limit control efficiency evaluation method |
CN106712056A (en) * | 2016-12-30 | 2017-05-24 | 国网山东省电力公司泰安供电公司 | Power grid section power adjusting method and device |
CN107181284A (en) * | 2017-04-24 | 2017-09-19 | 中国电力科学研究院 | The method of adjustment and device of a kind of out-of-limit electricity of circuit |
CN108199364A (en) * | 2016-12-08 | 2018-06-22 | 中国电力科学研究院 | A kind of stability checking method for planning method of operation transmission cross-section |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101330205A (en) * | 2008-04-29 | 2008-12-24 | 天津大学 | Method for controlling section power based on tidal current pursuit and train rescheduling |
US20100094477A1 (en) * | 2006-10-05 | 2010-04-15 | Abb Research Ltd | Determination and use of power system sensitivities |
-
2012
- 2012-10-09 CN CN201210379703.0A patent/CN102930141B/en not_active Expired - Fee Related
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100094477A1 (en) * | 2006-10-05 | 2010-04-15 | Abb Research Ltd | Determination and use of power system sensitivities |
CN101330205A (en) * | 2008-04-29 | 2008-12-24 | 天津大学 | Method for controlling section power based on tidal current pursuit and train rescheduling |
Non-Patent Citations (2)
Title |
---|
谢开贵 等: "基于有向通路的潮流跟踪新方法", 《中国电机工程学报》, 30 November 2001 (2001-11-30), pages 87 - 88 * |
赵恒亮 等: "地区电网潮流越限处理的研究", 《浙江电力》, 31 January 2012 (2012-01-31), pages 1 - 5 * |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103077484A (en) * | 2013-02-20 | 2013-05-01 | 华东电网有限公司 | Multi-dimensional power flow evaluation index method based on statistic analysis of historical information of power grid |
CN103077484B (en) * | 2013-02-20 | 2016-08-24 | 华东电网有限公司 | Various dimensions trend evaluation index method based on historical information of power grid statistical analysis |
CN103632052A (en) * | 2013-11-27 | 2014-03-12 | 国网上海市电力公司 | Power distribution network load flow calculation method |
CN104102830A (en) * | 2014-07-09 | 2014-10-15 | 西南交通大学 | Complex network building method |
CN106600136A (en) * | 2016-12-08 | 2017-04-26 | 国网浙江省电力公司 | Electric power section off-limit control efficiency evaluation method |
CN108199364A (en) * | 2016-12-08 | 2018-06-22 | 中国电力科学研究院 | A kind of stability checking method for planning method of operation transmission cross-section |
CN106600136B (en) * | 2016-12-08 | 2021-04-09 | 国网浙江省电力公司 | Power section out-of-limit control efficiency evaluation method |
CN108199364B (en) * | 2016-12-08 | 2023-02-07 | 中国电力科学研究院 | Stability checking method for power transmission section in planned operation mode |
CN106712056A (en) * | 2016-12-30 | 2017-05-24 | 国网山东省电力公司泰安供电公司 | Power grid section power adjusting method and device |
CN107181284A (en) * | 2017-04-24 | 2017-09-19 | 中国电力科学研究院 | The method of adjustment and device of a kind of out-of-limit electricity of circuit |
CN107181284B (en) * | 2017-04-24 | 2021-04-16 | 中国电力科学研究院 | Method and device for adjusting out-of-limit electric quantity of circuit |
Also Published As
Publication number | Publication date |
---|---|
CN102930141B (en) | 2015-11-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102930141B (en) | The quick calculation method that a kind of electrical network complexity monitoring section tidal current controls | |
Wang et al. | A fully distributed power dispatch method for fast frequency recovery and minimal generation cost in autonomous microgrids | |
Li et al. | A distributed coordination control based on finite-time consensus algorithm for a cluster of DC microgrids | |
Bhatti | AGC of two area power system interconnected by AC/DC links with diverse sources in each area | |
Hafiz et al. | Optimal use of kinetic energy for the inertial support from variable speed wind turbines | |
Hosseini et al. | Delay compensation of demand response and adaptive disturbance rejection applied to power system frequency control | |
Zhang et al. | Distributed estimation and secondary control of autonomous microgrid | |
Wu et al. | A multi-agent-based energy-coordination control system for grid-connected large-scale wind–photovoltaic energy storage power-generation units | |
Ranamuka et al. | Flexible AC power flow control in distribution systems by coordinated control of distributed solar-PV and battery energy storage units | |
CN104992009B (en) | Active distribution network distributed voltage control method based on multi-agent system | |
Xi et al. | A wolf pack hunting strategy based virtual tribes control for automatic generation control of smart grid | |
CN103928940A (en) | Active power control device and control method for distributed photovoltaic power station | |
CN107579543A (en) | A kind of isolated island micro-capacitance sensor distributed and coordinated control method based on muti-layer control tactics | |
CN104362648A (en) | Reactive phase modulation method for photovoltaic power station | |
Huang et al. | Bi-level decentralized active and reactive power control for large-scale wind farm cluster | |
Seuss et al. | Advanced inverter controls to dispatch distributed PV systems | |
CN103001219A (en) | Optimal coordination control method of multiple flexible alternative current transmission systems (FACTSs) based on trend entropy | |
CN103151795A (en) | Scattered-type wind power plant reactive power optimization control method capable of reducing fan losses and system | |
CN104538953A (en) | TCSC optimal configuration method based on probabilistic load flow control | |
Xi et al. | A novel automatic generation control method based on the ecological population cooperative control for the islanded smart grid | |
Elgammal et al. | Optimal model predictive frequency control management of grid integration PV/wind/FC/storage battery based smart grid using multi objective particle swarm optimization MOPSO | |
CN105900308B (en) | The method for keeping electrical network stable by load break | |
CN108536917A (en) | A kind of distributed computing method of transmission and distribution network overall situation Voltage Stability Control | |
CN105337290A (en) | Reactive adjustment method applicable to low-frequency oscillation aid decision of electric system | |
CN102709955A (en) | Multi-section-based power flow control method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20151125 Termination date: 20161009 |
|
CF01 | Termination of patent right due to non-payment of annual fee |