CN102912720B - A kind of frame bridge attractive joint structure - Google Patents
A kind of frame bridge attractive joint structure Download PDFInfo
- Publication number
- CN102912720B CN102912720B CN201210393483.7A CN201210393483A CN102912720B CN 102912720 B CN102912720 B CN 102912720B CN 201210393483 A CN201210393483 A CN 201210393483A CN 102912720 B CN102912720 B CN 102912720B
- Authority
- CN
- China
- Prior art keywords
- frame
- attractive joint
- steel
- joint
- framework
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域 technical field
本发明涉及一种框架桥诱导缝结构,具体是一种设置在框架桥中改善长箱体顶进框架混凝土应力裂缝及框架节接缝处渗水现象的诱导缝结构,属于顶进施工技术领域。The invention relates to an induced joint structure of a frame bridge, in particular to an induced joint structure arranged in a frame bridge to improve the concrete stress cracks in the jacking frame of a long box body and water seepage at the joint joints of the frame, and belongs to the technical field of jacking construction.
背景技术 Background technique
框架顶进施工时,如果顶进框架长度比较长,通常是分多节预制后采取中继间法顶进,这样需要较长的施工工期,且顶进次数增加后则顶进累计偏差增多;或者采用框架整个通长的预制,这样虽可缩短施工工期,但框架结构因混凝土应力影响会出现较多裂缝,质量不能保证。以往在框架上每隔约5~10m设沉降缝一道,这样虽能改善结构裂缝,但框架节接缝处止水效果不好,无法彻底解决漏水问题,时间久了就会出现渗水现象。During frame jacking construction, if the length of the jacking frame is relatively long, it is usually prefabricated in multiple sections and then jacked by the intermediate method, which requires a longer construction period, and the cumulative deviation of jacking will increase after the number of jackings increases; Or use the prefabrication of the entire length of the frame, although the construction period can be shortened in this way, but there will be more cracks in the frame structure due to the influence of concrete stress, and the quality cannot be guaranteed. In the past, settlement joints were set every 5-10m on the frame. Although this can improve structural cracks, the water-stop effect at the joints of the frame joints is not good, and the problem of water leakage cannot be completely solved. Water seepage will occur after a long time.
发明内容 Contents of the invention
针对现有技术中存在的上述缺陷,本发明提供了一种框架桥诱导缝结构,可有效解决框架分多段预制施工工期长、多次顶进造成顶进累计偏差增多、因混凝土应力影响会出现较多裂缝、框架节接缝止水效果差的问题。Aiming at the above-mentioned defects existing in the prior art, the present invention provides an induced joint structure of a frame bridge, which can effectively solve the problem of long construction period for multi-stage prefabrication of the frame, increased accumulative deviation of jacking caused by multiple jackings, and problems caused by concrete stress. There are many cracks and poor sealing effect of frame joints.
本发明是通过如下技术方案来实现的:一种框架桥诱导缝结构,其包括设置在框架桥中的诱导缝,所述诱导缝内设有填缝板,在所述诱导缝处的框架两侧边墙内沿框架高度方向间隔设有若干沿框架长度方向设置的钢剪销,所述钢剪销穿过所述填缝板,在所述诱导缝处的框架的顶板外侧、两侧边墙外侧及框架的内侧分别设有防水层。The present invention is achieved through the following technical solutions: a frame bridge induced joint structure, which includes an induced joint arranged in the frame bridge, a caulking plate is provided in the induced joint, and the two sides of the frame at the induced joint are A number of steel shear pins arranged along the length direction of the frame are arranged at intervals in the side wall along the height direction of the frame. The outer side of the wall and the inner side of the frame are respectively provided with waterproof layers.
本发明中,设在缝中的钢剪销可以保证框架在顶进中诱导缝结构的稳定性,并可控制框架桥竖向的剪切变形,防水层的设计可有效保证诱导缝不漏水。框架桥通过设置上述诱导缝结构,可以有效防止因混凝土应力影响而出现的裂缝。In the present invention, the steel shear pins arranged in the joints can ensure the stability of the induced joint structure during the jacking of the frame, and can control the vertical shear deformation of the frame bridge, and the design of the waterproof layer can effectively ensure that the induced joints do not leak. The frame bridge can effectively prevent cracks caused by the influence of concrete stress by setting the above-mentioned induced joint structure.
为了提高诱导缝处的止水效果,所述诱导缝处在框架钢筋的外侧还埋设有沿诱导缝处形成闭环的钢边止水带,在所述导缝处的框架混凝土中埋设有沿诱导缝处形成闭环的橡胶止水带。In order to improve the water-stop effect at the induced joint, a steel edge waterstop strip forming a closed loop along the induced joint is buried outside the frame steel bar at the induced joint, and a water stop along the induced joint is embedded in the frame concrete at the induced joint. A rubber waterstop that forms a closed loop at the seam.
进一步的方案是,所述钢边止水带为GSE5型钢边止水带,所述橡胶止水带为GRE7型橡胶止水带。A further solution is that the steel edge waterstop is a GSE5 steel edge waterstop, and the rubber waterstop is a GRE7 rubber waterstop.
为了提高防水效果,所述防水层包括在框架的顶板外侧和两侧边墙外侧由内至外依次设置的聚氨酯防水涂料层和氯化聚乙烯防水卷材层,以及在框架的内侧涂刷的M1500防水剂层。In order to improve the waterproof effect, the waterproof layer includes a polyurethane waterproof coating layer and a chlorinated polyethylene waterproof membrane layer arranged sequentially from the inside to the outside on the outside of the top plate of the frame and the outside of the side walls on both sides, and the inside of the frame. M1500 waterproofing agent layer.
所述钢剪销由内径为30mm的铁套管和直径为φ28mm的圆钢构成,所述圆钢插装在所述铁套管内,所述铁套管内填充有沥青油膏。The steel shear pin is composed of an iron sleeve with an inner diameter of 30 mm and a round steel with a diameter of φ28 mm. The round steel is inserted in the iron sleeve, and the iron sleeve is filled with asphalt ointment.
所述填缝板为固定设置在诱导缝中间的硬质锯末板。The caulking board is a hard sawdust board fixedly arranged in the middle of the induced seam.
所述钢剪销的设置间距是20cm。The setting interval of the steel shear pins is 20cm.
本发明的有益效果是:本发明结构简单,操作简单,其设置在框架中,有效改善了框架结构因受混凝土应力影响出现较多裂缝的现象,大大减小了多节框架分次顶进产生的累计顶进偏差,提高了工程质量,并可大大缩短工期,降低施工成本。The beneficial effects of the present invention are: the present invention is simple in structure and easy to operate, and it is arranged in the frame, which effectively improves the phenomenon of many cracks in the frame structure due to the influence of concrete stress, and greatly reduces the occurrence of multi-section frame jacking in stages. The accumulative jacking deviation improves the quality of the project, and can greatly shorten the construction period and reduce the construction cost.
附图说明 Description of drawings
图1是本发明实施例1中的结构示意图;Fig. 1 is the structural representation among the embodiment 1 of the present invention;
图2是图1中的A-A示意图;Fig. 2 is A-A schematic diagram in Fig. 1;
图3是图1中的C部放大示意图;Fig. 3 is an enlarged schematic diagram of part C in Fig. 1;
图4是本发明实施例2中的结构示意图;Fig. 4 is a schematic structural diagram in Embodiment 2 of the present invention;
图5是图4中的D-D示意图;Fig. 5 is a D-D schematic diagram in Fig. 4;
图6是图4中的B部放大示意图;Fig. 6 is an enlarged schematic diagram of part B in Fig. 4;
图中:1、氯化聚乙烯防水卷材层,2、聚氨酯防水涂料层,3、钢边止水带,4、橡胶止水带,5、钢剪销,6、防水剂层,7、填缝板,8、铁套管,9、沥青油膏,10、圆钢,11、框架身。In the figure: 1. Chlorinated polyethylene waterproof coiled material layer, 2. Polyurethane waterproof coating layer, 3. Steel edge waterstop, 4. Rubber waterstop, 5. Steel shear pin, 6. Waterproof agent layer, 7. caulking board, 8, iron casing, 9, asphalt ointment, 10, round steel, 11, frame body.
具体实施方式 Detailed ways
下面结合附图对本发明作进一步的说明:Below in conjunction with accompanying drawing, the present invention will be further described:
实施例1Example 1
如附图1-3所示,一种框架桥诱导缝结构,诱导缝设置在框架内,所述诱导缝内设有填缝板7,在所述诱导缝处的框架两侧边墙内沿框架高度方向间隔设有若干沿框架长度方向设置的钢剪销5,钢剪销5由内径为30mm的铁套管8和直径为φ28mm的圆钢10构成,圆钢10穿过填缝板7插装在铁套管8内,铁套管8的另一端为封闭端,其内填充有沥青油膏9,铁套管8的非封闭端与填缝板7的表面平齐。所述诱导缝处在框架钢筋的外侧还埋设有沿诱导缝处形成闭环的钢边止水带3,在所述导缝处的框架混凝土中埋设有沿诱导缝处形成闭环的橡胶止水带4。本实施例中的钢边止水带3为GSE5型钢边止水带,橡胶止水带4为GRE7型橡胶止水带。在框架的顶板外侧和两侧边墙外侧由内至外依次设置有聚氨酯防水涂料层2和氯化聚乙烯防水卷材层1,在框架的内侧涂刷有M1500防水剂层6。As shown in accompanying drawings 1-3, a frame bridge induced joint structure, the induced joint is arranged in the frame, the joint is provided with a caulking plate 7 inside the induced joint, and the inner edges of the side walls on both sides of the frame at the induced joint are There are several steel shear pins 5 arranged along the length direction of the frame at intervals in the height direction of the frame. The steel shear pins 5 are composed of an iron sleeve 8 with an inner diameter of 30 mm and a round steel 10 with a diameter of φ28 mm. The round steel 10 passes through the caulking plate 7 Inserted in the iron sleeve 8, the other end of the iron sleeve 8 is a closed end, which is filled with asphalt ointment 9, and the non-closed end of the iron sleeve 8 is flush with the surface of the caulking plate 7. The induced seam is also embedded with a steel edge waterstop 3 forming a closed loop along the induced joint on the outside of the frame reinforcement, and a rubber waterstop forming a closed loop along the induced joint is embedded in the frame concrete at the induced joint 4. The steel edge waterstop 3 in this embodiment is a GSE5 steel edge waterstop, and the rubber waterstop 4 is a GRE7 rubber waterstop. A polyurethane waterproof coating layer 2 and a chlorinated polyethylene waterproof coiled material layer 1 are sequentially arranged on the outside of the top plate of the frame and the outside of the side walls on both sides from inside to outside, and an M1500 waterproofing agent layer 6 is painted on the inside of the frame.
本实施例中,钢剪销5的设置间距为20cm,填缝板7为硬质锯末板,填缝板7的厚度为2cm。In this embodiment, the distance between the steel shear pins 5 is 20 cm, the caulking board 7 is a hard sawdust board, and the thickness of the caulking board 7 is 2 cm.
本实施例的诱导缝结构适用于不带沉降缝的框架,主要用于顶进框架中设置。The induction joint structure of this embodiment is suitable for frames without settlement joints, and is mainly used for setting in jacking frames.
在框架预制过程中,绑扎框架底板钢筋时,埋设GSE5型钢边止水带3和GRE7型橡胶止水带4及填缝板7,浇筑底板混凝土,然后在绑扎框架边墙、顶板钢筋过程中依次先埋设GRE7型橡胶止水带4,安设填缝板7,两种均用螺纹钢筋固定,再埋设铁套管8和圆钢10组成钢剪销5,钢剪销5穿过填缝板7,待框架边墙、顶板钢筋绑扎完毕,在框架钢筋网上焊接固定GSE5型钢边止水带3,浇筑混凝土,最后待框架混凝土养护期结束后在框架边墙、顶板外混凝土面先刷两层聚氨酯防水涂料,再铺设氯化聚乙烯防水卷材,并在框架内诱导缝处混凝土面上涂刷M1500防水剂。During the prefabrication process of the frame, when tying the steel bars of the frame bottom plate, the GSE5 steel edge waterstop 3, the GRE7 rubber waterstop 4 and the caulking plate 7 are buried, the bottom slab concrete is poured, and then the frame side walls and roof steel bars are bound in sequence First bury the GRE7 rubber waterstop 4, install the caulking plate 7, both of which are fixed with threaded steel bars, then bury the iron sleeve 8 and round steel 10 to form the steel shear pin 5, and the steel shear pin 5 passes through the caulking plate 7. After the frame side wall and roof steel bars are bound, weld and fix the GSE5 steel edge waterstop 3 on the frame steel bar net, pour concrete, and finally paint two layers on the frame side wall and roof outer concrete surface after the frame concrete curing period is over Polyurethane waterproof coating, then lay chlorinated polyethylene waterproof membrane, and paint M1500 waterproofing agent on the concrete surface at the induced joint in the frame.
GSE5型钢边止水带和GRE7型橡胶止水带设置在框架四周,用钢筋横向、竖向固定,使其在混凝土浇筑时不至移位或变形后影响止水作用;钢剪销设置在框架两侧边墙处,点焊固定在框架钢筋上;填缝板使用前根据需要尺寸锯成两块板,在钢剪销位置取洞,组拼使用,需用钢筋将其固定在框架钢筋上,在浇筑混凝土时保证其不移位。GSE5 steel edge waterstop and GRE7 rubber waterstop are set around the frame, fixed horizontally and vertically with steel bars, so that they will not be displaced or deformed during concrete pouring and affect the waterstop effect; steel shear pins are set on the frame The side walls on both sides are spot-welded and fixed on the frame reinforcement; before use, the caulking board is sawed into two boards according to the required size, and holes are made at the positions of the steel shear pins for assembly. It needs to be fixed on the frame reinforcement with reinforcement. , to ensure that it does not shift when pouring concrete.
本发明通过设“缝”改善了结构内部混凝土应力影响下产生裂缝,通过“缝”内设止水带、钢剪销保证了框架在顶进中诱导缝结构的稳定性,又能保证在框架节接缝处不漏水。The present invention improves the cracks generated under the influence of concrete stress inside the structure by setting "seams", and ensures the stability of the induced joint structure of the frame during jacking by setting waterstops and steel shear pins in the "seams", and can also ensure the stability of the structure in the frame. Watertight joints.
本实施例中的其他部分采用现有技术,在此不再赘述。Other parts in this embodiment adopt the prior art, and will not be repeated here.
实施例2Example 2
如附图4-6所示,本实施例与实施例1基本相同,不同之处是,本实施例中不设钢边止水带和橡胶止水带。其包括设置在框架桥中的诱导缝,所述诱导缝内设有填缝板7。在所述诱导缝处的框架两侧边墙内沿框架高度方向间隔设有若干沿框架长度方向设置的钢剪销5,钢剪销5由内径为30mm的铁套管8和直径为φ28mm的圆钢10构成,圆钢10穿过填缝板7插装在铁套管8内,铁套管8的另一端为封闭端,其内填充有沥青油膏9,铁套管8的非封闭端与填缝板7的表面平齐。在框架的顶板外侧和两侧边墙外侧由内至外依次设置有聚氨酯防水涂料层2和氯化聚乙烯防水卷材层1,在框架的内侧涂刷有M1500防水剂层6。As shown in accompanying drawings 4-6, this embodiment is basically the same as Embodiment 1, the difference is that no steel edge waterstop and rubber waterstop are provided in this embodiment. It includes induction joints arranged in the frame bridge, and caulking plates 7 are arranged in the induction joints. In the side walls on both sides of the frame at the induction joint, several steel shear pins 5 arranged along the length direction of the frame are arranged at intervals along the height direction of the frame. The round steel 10 is composed of round steel 10, which passes through the caulking plate 7 and is inserted into the iron sleeve 8. The other end of the iron sleeve 8 is a closed end, which is filled with asphalt ointment 9, and the non-closed end of the iron sleeve 8 The end is flush with the surface of caulking plate 7. A polyurethane waterproof coating layer 2 and a chlorinated polyethylene waterproof membrane layer 1 are sequentially arranged on the outside of the top plate of the frame and the outside of the side walls on both sides from inside to outside, and an M1500 waterproofing agent layer 6 is painted on the inside of the frame.
本实施例中,填缝板7为硬质锯末板,填缝板7的厚度为2cm。In this embodiment, the caulking board 7 is a hard sawdust board, and the thickness of the caulking board 7 is 2 cm.
本实施例中的其他部分采用现有技术,在此不再赘述。Other parts in this embodiment adopt the prior art, and will not be repeated here.
本实施例的诱导缝结构适用于带沉降缝的框架,主要是用于顶进框架就位后与现浇框架间的接缝处。The induced joint structure of this embodiment is suitable for the frame with settlement joints, mainly used for the joint between the jacked frame and the cast-in-place frame after it is in place.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201210393483.7A CN102912720B (en) | 2012-10-16 | 2012-10-16 | A kind of frame bridge attractive joint structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201210393483.7A CN102912720B (en) | 2012-10-16 | 2012-10-16 | A kind of frame bridge attractive joint structure |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102912720A CN102912720A (en) | 2013-02-06 |
| CN102912720B true CN102912720B (en) | 2015-08-26 |
Family
ID=47611270
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201210393483.7A Expired - Fee Related CN102912720B (en) | 2012-10-16 | 2012-10-16 | A kind of frame bridge attractive joint structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102912720B (en) |
Families Citing this family (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103397600B (en) * | 2013-08-15 | 2015-01-28 | 中铁六局集团天津铁路建设有限公司 | Method for arranging water stops in box body jacking process |
| CN104563163A (en) * | 2014-12-16 | 2015-04-29 | 成都绿迪科技有限公司 | Induced crack used for basement outer wall |
| CN109594663B (en) * | 2018-12-29 | 2024-05-31 | 云南省建设投资控股集团有限公司 | Reinforced concrete induction belt structure used for post-casting belt position and construction method thereof |
| CN113774961B (en) * | 2021-06-01 | 2022-09-16 | 中国二十冶集团有限公司 | Waterproof method for underground gallery type structure jacking relay room |
| CN116971345B (en) * | 2023-06-05 | 2025-11-14 | 甘肃省水利水电工程局有限责任公司 | A high-flow-rate stilling basin structure |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101761096A (en) * | 2009-12-14 | 2010-06-30 | 山东万鑫建设有限公司 | Anti-crack and anti-leak construction method of arranging tower crane foundation below waterproof baseplate |
| CN202265801U (en) * | 2011-10-09 | 2012-06-06 | 中国水电顾问集团西北勘测设计研究院 | Exhaust system for joint grouting of induced joints of rolled concrete dam |
| CN202830739U (en) * | 2012-10-16 | 2013-03-27 | 中铁十局集团有限公司 | Frame bridge inducing joint structure |
Family Cites Families (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP4428304B2 (en) * | 2005-06-29 | 2010-03-10 | 鹿島建設株式会社 | Plastic hinge part of RC structure |
| JP2012026228A (en) * | 2010-07-27 | 2012-02-09 | Kumagai Gumi Co Ltd | Crack-inducing joint |
-
2012
- 2012-10-16 CN CN201210393483.7A patent/CN102912720B/en not_active Expired - Fee Related
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101761096A (en) * | 2009-12-14 | 2010-06-30 | 山东万鑫建设有限公司 | Anti-crack and anti-leak construction method of arranging tower crane foundation below waterproof baseplate |
| CN202265801U (en) * | 2011-10-09 | 2012-06-06 | 中国水电顾问集团西北勘测设计研究院 | Exhaust system for joint grouting of induced joints of rolled concrete dam |
| CN202830739U (en) * | 2012-10-16 | 2013-03-27 | 中铁十局集团有限公司 | Frame bridge inducing joint structure |
Non-Patent Citations (2)
| Title |
|---|
| "下穿式立交桥的防水技术";张献;《浙江建筑》;20120430;第29卷(第4期);第58~60页 * |
| "海棠路下穿陇海铁路立交桥设计";罗海兵等;《中国市政工程》;20080228(第4期);第23~27页 * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102912720A (en) | 2013-02-06 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107326940B (en) | A kind of basement structure and construction method | |
| CN102373715B (en) | Advance water stop construction method of post poured band of fundamental plane part and external wall of underground part | |
| CN209339466U (en) | A prefabricated parapet construction structure | |
| CN110761322B (en) | Cast-in-place pipe gallery side wall horizontal construction joint reinforcing structure and construction method thereof | |
| CN104790970B (en) | A kind of method that use combining structure carries out shield tunnel reinforcing | |
| CN107165185A (en) | A prefabricated concrete column foot node with outsourcing steel plate and its construction method | |
| CN206189455U (en) | a corridor | |
| CN103225285B (en) | A kind of steel membrane rock | |
| CN102912720B (en) | A kind of frame bridge attractive joint structure | |
| CN208280185U (en) | A kind of post-cast strip advanced water-stopping construction | |
| CN102251540A (en) | Construction installation method for fast-easy setback grid of bottom plate construction joint | |
| CN108166531A (en) | Basic alter-pouring strips mould plate and the construction method for pouring post-cast strip | |
| CN203947498U (en) | Poured band of outer wall of basement wall Side Template | |
| CN206189870U (en) | Improves construction quality, | |
| CN110593320A (en) | A pre-closed structure and construction method of post-pouring belt on exterior wall | |
| CN105113535A (en) | Joint structure and construction method of a prefabricated assembled tunnel | |
| CN206189454U (en) | Piping lane | |
| CN204475379U (en) | Shorten the basement post-pouring zone in Dewatering cycle | |
| CN204326100U (en) | The Preserved node of covered back-digging side wall bar splice | |
| CN207794133U (en) | Precast assembly tunnel | |
| CN103161181B (en) | Underground outer wall construction joint water-stopping structure and construction method thereof | |
| CN110644538A (en) | Basement side wall extra front and back pouring belt periphery protection structure | |
| CN202830739U (en) | Frame bridge inducing joint structure | |
| CN212248328U (en) | Raft foundation and tower crane foundation's linking structure | |
| CN108560585B (en) | Fully assembled structure of basement exterior wall and its construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150826 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |