CN102839657A - Cast-in-place pedestal tubular pile and construction method thereof - Google Patents

Cast-in-place pedestal tubular pile and construction method thereof Download PDF

Info

Publication number
CN102839657A
CN102839657A CN 201210334334 CN201210334334A CN102839657A CN 102839657 A CN102839657 A CN 102839657A CN 201210334334 CN201210334334 CN 201210334334 CN 201210334334 A CN201210334334 A CN 201210334334A CN 102839657 A CN102839657 A CN 102839657A
Authority
CN
China
Prior art keywords
tubular pile
pile
concrete
perfusion
pile tube
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201210334334
Other languages
Chinese (zh)
Inventor
彭新生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU XINGPENG FONDATION ENGINEERING Co Ltd
Original Assignee
JIANGSU XINGPENG FONDATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU XINGPENG FONDATION ENGINEERING Co Ltd filed Critical JIANGSU XINGPENG FONDATION ENGINEERING Co Ltd
Priority to CN 201210334334 priority Critical patent/CN102839657A/en
Publication of CN102839657A publication Critical patent/CN102839657A/en
Pending legal-status Critical Current

Links

Images

Abstract

The invention relates to a cast-in-place pedestal tubular pile and a construction method thereof. A concrete loading plate with an enlarged cross section is additionally arranged at the bottom of the traditional prestress tubular pile to increase the bearing surface of the bottom of the tubular pile, so that the tip resistance of the tubular pile is increased, and the bearing capacity of the tubular pile is improved greatly. The specific construction method comprises the steps of sinking the tubular pile to a designed elevation, inserting a high-pressure rotary jet grouting construction equipment in a hollow part in the prestress tubular pile to the bottom of the tubular pile, switching on the rotary jet grouting equipment, inputting air, water and mud, conducting rotary jet grouting and pore forming so as to forming a cylinder which is 1000-1400mm in diameter and 500-1500mm in height, lifting the rotary jet grouting equipment, putting in a special central grouting conduit to a position 0.3 m above a pore bottom, inputting grout into the conduit for grout exchanging, discharging slurry from a pore, concreting to form the loading plate (cavity) at the bottom of the tubular pile, concerting to the top of the tubular pile, and inserting anchor bars according to requirements of collective drawings. With the adoption of the method, the carrying capacity of the tubular pile can be improved greatly, and a supporting layer at the upper part can be made full use, so that the length of the tubular pile is reduced, the construction cost is lowered greatly, the engineering quality is improved, and the method is suitable for comprehensive popularization and application.

Description

Bottom tube stake and job practices thereof are expanded in a kind of perfusion
Technical field
The present invention relates to a kind of pile foundation, refer more particularly to a kind of perfusion and expand bottom tube stake and job practices thereof.
Background technology
Existing pipe pile foundation when adopting the top bearing stratum, exists bearing capacity, settling amount big, can not adapt to the situation that the highrise building load is big, deflection is little, when adopting the bottom bearing stratum, has that pile tube length is big, construction requirement is high, the uneconomic situation of cost.
Summary of the invention
The present invention relates to a kind of perfusion and expand bottom tube stake and job practices thereof; It is a kind of concrete bearing block that increases an enlarged cross section in traditional pile for prestressed pipe bottom; With the bearing surface of increase pile tube bottom, thereby increase the pile tube end resistance, make the significantly raising of the bearing capacity of pile tube.Concrete job practices is: 1, with pile for prestressed pipe 1 pile sinking to design elevation; 2, hollow parts inserts high-pressure rotary-spray construction facility to pile tube bottom in pile for prestressed pipe 1, opens churning equipment, input air-flow, current, slurry flows, and the churning pore-forming, the formation diameter is 1000-1400mm, the cylinder of height 500-1500mm; 3, promote the churning facility, be lowered at the bottom of special-purpose center perfusion cannula to the hole on 0.3m place, in conduit, import cement paste, change slurry, the interior mud of tap.The perfusion concrete forms concrete in pile for prestressed pipe 1 bottom and expands end load dish 2; 4, hollow part pours into concrete 3 to the pile tube top in pile for prestressed pipe 1, and requires to insert anchor bar 4 according to atlas; This method can significantly improve the pile tube supporting capacity, and to shorten the pile tube stake long thereby can make full use of the top bearing stratum, greatly reduces construction cost, improved workmanship, is fit to popularize in an all-round way and uses.Description of drawings:
Below in conjunction with accompanying drawing and instance the present invention is described further.
Fig. 1 is the structural representation of one embodiment of the invention.
The specific embodiment:
The residential quarters, Nantong City are positioned at the clock show south of road, Nantong City side, north side, new bridge residential district, the west of a river, Xin Shi street, totally 4 building residential buildings, 28~29 layers of floor heights, underground 2 layers.PHC-600 (130) AB type pile tube is adopted in former design, and effective length 45m, pile-base supporting layer are the 15th layer of flour sand folder fine sand layer, and the vertical ultimate bearing capacity of single pile eigenvalue requirements reaches 5100KN.
My company adopts perfusion expansion bottom tube stake scheme, adopts PHC-600 (130) AB type pile tube, and effective length 26m, pile-base supporting layer are 11th layer flour sand folder silt, and during practical implementation, the construction pile tube designs stake end absolute altitude with pile tube according to designing requirement pile sinking to bearing stratum earlier.In the pile tube of the end of constructing is hollow, insert high-pressure rotary-spray facility to pile tube bottom then, open the high-pressure rotary-spray pump valve, import clear water, air and mud earlier; Downwards the rotary-spraying construction pore-forming gets into bearing stratum 1.0~1.5m, will be up and down during rotary-spraying construction 2 times repeatedly, to guarantee drilling diameter; The formation diameter is the cylindrical cavity of 1400mm, height 1500mm, and high-pressure whirl jet man-hour, range of pressure values generally is controlled at 20~80MPa; After promoting the churning drilling tool, be lowered at the bottom of special-purpose centre pipe to the hole on the 0.3m position, in cylindrical cavity, import cement paste through centre pipe; Mud changes slurry and handles in the tap, and the cement paste water/binder ratio is 1:1, after changing slurry and finishing; Connect hopper and conduit, perfusion label C30 concrete forms enlarged footing load dish.Continue the perfusion concrete to the pile tube top, and require to insert anchor bar according to the pile tube atlas, the completion pile tube was irritated the core operation 24 hours and can be reached 5500KN after detect the vertical ultimate bearing capacity of single pile characteristic value.
This project is as adopting the pile for prestressed pipe scheme, and 13500 yuan/root of single stake cost adopts perfusion to expand 9900 yuan/root of bottom tube stake scheme single stake cost; Can practice thrift cost 26.7% relatively; This method significantly improves the pile tube supporting capacity, and to shorten the pile tube stake long thereby can make full use of the top bearing stratum, greatly reduces construction cost; Improved workmanship, be fit to popularize in an all-round way and use.

Claims (4)

1. bottom tube stake and job practices thereof are expanded in a perfusion, are by pile for prestressed pipe 1, and concrete expands end load dish 2, and perfusion concrete 3 is formed with anchor bar 4; Job practices is the pile tube bottom of constructing; Adopt high-pressure rotary spraying method to expand the bottom application worker, form the cylinder of a diameter 1000-1400mm height 500-1500mm, and adopt the centre pipe method to change slurry and perfusion concrete; Form pile tube bottom load dish (enlarged footing); Simultaneously, the perfusion concrete replaces the tradition of pile tube to irritate the core working procedure to pile tube top and joint bar.
2. bottom tube stake and job practices thereof are expanded in said a kind of perfusion according to claim 1, it is characterized in that: pile body combination top is pile tube, and the bottom is that concrete expands end load dish.
3. bottom tube stake and job practices thereof are expanded in said a kind of perfusion according to claim 1, it is characterized in that: in the bearing stratum of pile tube bottom, form enlarged footing through high-pressure rotary-spray, change slurry and perfusion concrete through the centre pipe method, form concrete bearing block.
4. bottom tube stake and job practices thereof are expanded in a perfusion according to claim 1; It is characterized in that: after enlarged cavity is formed on the pile tube bottom, change slurry and perfusion concrete through the centre pipe method, the cement paste water/binder ratio is 1:0.6~1:1; Change slurry and finish perfusion concrete formation concrete bearing block; Pour into concrete simultaneously to the pile tube top, and require joint bar, accomplished pile for prestressed pipe simultaneously and irritated the core working procedure according to atlas.
CN 201210334334 2012-09-12 2012-09-12 Cast-in-place pedestal tubular pile and construction method thereof Pending CN102839657A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201210334334 CN102839657A (en) 2012-09-12 2012-09-12 Cast-in-place pedestal tubular pile and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201210334334 CN102839657A (en) 2012-09-12 2012-09-12 Cast-in-place pedestal tubular pile and construction method thereof

Publications (1)

Publication Number Publication Date
CN102839657A true CN102839657A (en) 2012-12-26

Family

ID=47367359

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201210334334 Pending CN102839657A (en) 2012-09-12 2012-09-12 Cast-in-place pedestal tubular pile and construction method thereof

Country Status (1)

Country Link
CN (1) CN102839657A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362120A (en) * 2013-07-05 2013-10-23 山东科技大学 Hollow hemispheric expanded-base cast-in-place pile and construction method thereof
CN105672307A (en) * 2016-01-12 2016-06-15 四川华西管桩工程有限公司 Expanded-base combination end pile bearing foundation
CN106351222A (en) * 2016-08-30 2017-01-25 中国建筑西南勘察设计研究院有限公司 Construction method of soft rock foundation bedding mortar implantation tube pile
CN107023002A (en) * 2016-08-30 2017-08-08 北京荣创岩土工程股份有限公司 Down-the-hole impacts churning composite pile pile making method
CN115305912A (en) * 2022-02-14 2022-11-08 高云飞 Tubular pile grouting, tamping and vibrating bottom expanding construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362120A (en) * 2013-07-05 2013-10-23 山东科技大学 Hollow hemispheric expanded-base cast-in-place pile and construction method thereof
CN105672307A (en) * 2016-01-12 2016-06-15 四川华西管桩工程有限公司 Expanded-base combination end pile bearing foundation
CN106351222A (en) * 2016-08-30 2017-01-25 中国建筑西南勘察设计研究院有限公司 Construction method of soft rock foundation bedding mortar implantation tube pile
CN107023002A (en) * 2016-08-30 2017-08-08 北京荣创岩土工程股份有限公司 Down-the-hole impacts churning composite pile pile making method
CN115305912A (en) * 2022-02-14 2022-11-08 高云飞 Tubular pile grouting, tamping and vibrating bottom expanding construction method

Similar Documents

Publication Publication Date Title
CN102839657A (en) Cast-in-place pedestal tubular pile and construction method thereof
CN2866602Y (en) Long-auger drill reaming bottom stirring and in-hole reaming concrete pile-grouting piling apparatus
CN111364532B (en) Existing pile foundation reinforcement method based on slurry control
CN106996104A (en) Injection forming club-footed pile and its construction method
CN104563147A (en) Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
CN204551430U (en) A kind of pre-buried floral tube grouting and reinforcing device on soft foundation
CN103911989B (en) A kind of underwater casting base type foundation with retaining wall and construction method thereof
CN102877466A (en) Rotary expansion cast-in-place pile and construction method thereof
CN2673944Y (en) Prestressed pipe pile with large end filled with sand
CN204139190U (en) A kind of Liftable preformed bricks fetal membrane
CN202298605U (en) Cast-in-place concrete and sand filling compound pile
CN111676963A (en) Steel pipe upright post positioning device and positioning construction method thereof
CN203361138U (en) Rear implantation pile of expanded-base pier pit underpinning
CN206486890U (en) Concrete cylindrical structure
CN102817381A (en) Construction method of rear-embedded pile foundation
CN205259175U (en) Lower part enlarges compound foundation pile of diameter section
CN203808066U (en) PHA anchor rod
CN101135156B (en) Mechanical pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN101130957A (en) Mixed pile-forming method for multilevel expanding bottom pile with high bearing capacity
CN212452268U (en) Connecting structure of prefabricated cylinder and pile foundation
CN100580187C (en) Pile forming method for one-stage bottom expanding steel pipe composite pile body
CN100580186C (en) Pile forming method for high-bearing two-stage bottom expanding prefabricated pile body
CN205314092U (en) A miniature steel pipe pressure bored concrete pile for limit for height place
CN203808120U (en) Penetrating steeping condensate strengthening member formed in combination with existing underground concrete member
CN117306527A (en) Annular grouting method suitable for pile foundation underlying goaf treatment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20121226