CN102817326A - Construction method of bridge construction super-small space double limb pier stud - Google Patents
Construction method of bridge construction super-small space double limb pier stud Download PDFInfo
- Publication number
- CN102817326A CN102817326A CN2012103511071A CN201210351107A CN102817326A CN 102817326 A CN102817326 A CN 102817326A CN 2012103511071 A CN2012103511071 A CN 2012103511071A CN 201210351107 A CN201210351107 A CN 201210351107A CN 102817326 A CN102817326 A CN 102817326A
- Authority
- CN
- China
- Prior art keywords
- bridge construction
- pier stud
- limb pier
- extra small
- small spacing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 56
- 230000001680 brushing effect Effects 0.000 claims abstract description 4
- 238000009415 formwork Methods 0.000 claims description 8
- 238000009434 installation Methods 0.000 claims description 5
- 238000000034 method Methods 0.000 claims description 4
- GNFTZDOKVXKIBK-UHFFFAOYSA-N 3-(2-methoxyethoxy)benzohydrazide Chemical compound COCCOC1=CC=CC(C(=O)NN)=C1 GNFTZDOKVXKIBK-UHFFFAOYSA-N 0.000 claims description 2
- 229910000831 Steel Inorganic materials 0.000 abstract description 2
- 239000010959 steel Substances 0.000 abstract description 2
- 230000000903 blocking effect Effects 0.000 abstract 1
- 238000004519 manufacturing process Methods 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 2
- 241001074085 Scophthalmus aquosus Species 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000001514 detection method Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 238000011900 installation process Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- 239000000725 suspension Substances 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210351107.1A CN102817326B (en) | 2012-09-20 | 2012-09-20 | Construction method of bridge construction super-small space double limb pier stud |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210351107.1A CN102817326B (en) | 2012-09-20 | 2012-09-20 | Construction method of bridge construction super-small space double limb pier stud |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102817326A true CN102817326A (en) | 2012-12-12 |
CN102817326B CN102817326B (en) | 2015-01-28 |
Family
ID=47301743
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210351107.1A Expired - Fee Related CN102817326B (en) | 2012-09-20 | 2012-09-20 | Construction method of bridge construction super-small space double limb pier stud |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102817326B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108277737A (en) * | 2018-01-29 | 2018-07-13 | 中国建筑第五工程局有限公司 | A kind of cross-saddle single-track traffic continuous rigid frame system pier stud construction method and mold |
CN108867398A (en) * | 2018-08-14 | 2018-11-23 | 魏浩峰 | A kind of construction method of bridge construction super-small space double limb pier stud |
CN110042743A (en) * | 2019-05-05 | 2019-07-23 | 陕西路桥集团有限公司 | The hydraulic climbing die block system of twin legged thin wall hollow pier with synchronize climb construction technology |
CN110863432A (en) * | 2019-11-26 | 2020-03-06 | 上海市基础工程集团有限公司 | Rapid and accurate positioning method for steel structure tower column installation construction |
CN112012109A (en) * | 2020-08-25 | 2020-12-01 | 华恒建设集团有限公司 | Construction process of ultra-small-spacing double-limb pier stud |
CN112160589A (en) * | 2020-09-24 | 2021-01-01 | 中国五冶集团有限公司 | Synchronous pouring rapid construction method for small-spacing square frame column |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100766888B1 (en) * | 2006-04-15 | 2007-10-18 | (주)스틸엔콘크리트 | Prefabricated bridge and construction method using pier coping part by connecting pile column with pillar connecting member |
CN101302742A (en) * | 2008-07-04 | 2008-11-12 | 敬忠诚 | Method for building bridge abutment on water |
CN101429752A (en) * | 2007-11-05 | 2009-05-13 | 中交一航局第一工程有限公司 | Pier column prefabrication splicing building technology |
JP2010242315A (en) * | 2009-04-01 | 2010-10-28 | Sumitomo Mitsui Construction Co Ltd | Bridge erection method |
-
2012
- 2012-09-20 CN CN201210351107.1A patent/CN102817326B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100766888B1 (en) * | 2006-04-15 | 2007-10-18 | (주)스틸엔콘크리트 | Prefabricated bridge and construction method using pier coping part by connecting pile column with pillar connecting member |
CN101429752A (en) * | 2007-11-05 | 2009-05-13 | 中交一航局第一工程有限公司 | Pier column prefabrication splicing building technology |
CN101302742A (en) * | 2008-07-04 | 2008-11-12 | 敬忠诚 | Method for building bridge abutment on water |
JP2010242315A (en) * | 2009-04-01 | 2010-10-28 | Sumitomo Mitsui Construction Co Ltd | Bridge erection method |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108277737A (en) * | 2018-01-29 | 2018-07-13 | 中国建筑第五工程局有限公司 | A kind of cross-saddle single-track traffic continuous rigid frame system pier stud construction method and mold |
CN108867398A (en) * | 2018-08-14 | 2018-11-23 | 魏浩峰 | A kind of construction method of bridge construction super-small space double limb pier stud |
CN108867398B (en) * | 2018-08-14 | 2021-02-02 | 桂林建安建设集团有限公司 | Construction method of bridge construction ultra-small-space double-limb pier stud |
CN110042743A (en) * | 2019-05-05 | 2019-07-23 | 陕西路桥集团有限公司 | The hydraulic climbing die block system of twin legged thin wall hollow pier with synchronize climb construction technology |
CN110863432A (en) * | 2019-11-26 | 2020-03-06 | 上海市基础工程集团有限公司 | Rapid and accurate positioning method for steel structure tower column installation construction |
CN112012109A (en) * | 2020-08-25 | 2020-12-01 | 华恒建设集团有限公司 | Construction process of ultra-small-spacing double-limb pier stud |
CN112160589A (en) * | 2020-09-24 | 2021-01-01 | 中国五冶集团有限公司 | Synchronous pouring rapid construction method for small-spacing square frame column |
Also Published As
Publication number | Publication date |
---|---|
CN102817326B (en) | 2015-01-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102817326B (en) | Construction method of bridge construction super-small space double limb pier stud | |
CN204753844U (en) | Circular steel tube concrete column sleeve connected node | |
CN204024679U (en) | Buried water stop fastening devices in a kind of tunnel lining hoop | |
CN105888078A (en) | U-shaped building embedded part and construction method of anchoring component of U-shaped building embedded part | |
CN104912191B (en) | Prefabricated concrete prefabricated column splicing device and using method | |
CN104153573B (en) | V-type cylinder concrete pour mould and construction method | |
CN117364656A (en) | Hydraulic climbing formwork construction method for highway bridge high pier | |
CN202830773U (en) | Bridge construction super-small space double limb pier stud integral template | |
CN204282225U (en) | For the length of side rapid adjustment template of unidirectional closing slope rectangular pier construction | |
CN204608825U (en) | A kind of three-chip type stone bolt locating rack | |
CN115012641A (en) | Scaffold construction method based on embedded wall connecting piece | |
CN112627034A (en) | Synchronous construction method for turning over mold of high pier of bridge | |
CN104695332A (en) | Hollow thin-walled pier internal mold bolt ejection removal technology | |
CN209868938U (en) | Prefabricated piping lane forming die | |
CN103850266A (en) | Multipurpose positioning template device for foundation bolt of iron tower and positioning method | |
CN103669831B (en) | A kind of transformer station's cast-in-situ wall combined steel and construction method thereof | |
CN206600005U (en) | The positioning component and positioner of reserved joint bar in shear wall | |
CN103981893B (en) | Gas Turbine Foundation Embedded Bolt Suspension Reinforcing Device and Method | |
CN108374350A (en) | A kind of the spelling moulding bed and installation method of steel anchor beam and steel corbel unit | |
CN104481142B (en) | The construction method of the chain support system of coupled columns template synchronous | |
CN202755674U (en) | Positioning installation component for embedded bolts | |
CN220058829U (en) | Circular column wood formwork reinforcing apparatus | |
CN217813511U (en) | Steel supporting assembly suitable for shield tunnel construction | |
CN114277849B (en) | Construction method of post-cast strip disassembly-free composite water stop template | |
CN204212445U (en) | Lift protects door fastening device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
ASS | Succession or assignment of patent right |
Owner name: CHONGQING CONSTRUCTION ENGINEERING GROUP CO., LTD. Effective date: 20131113 Owner name: CHONGQING CITY CONSTRUCTION GROUP CO., LTD. Free format text: FORMER OWNER: CHONGQING CONSTRUCTION BRIDGE ENGINEERING CO., LTD. Effective date: 20131113 |
|
C41 | Transfer of patent application or patent right or utility model | ||
C53 | Correction of patent of invention or patent application | ||
CB03 | Change of inventor or designer information |
Inventor after: Yang Shouzhong Inventor after: Zhu Guanghua Inventor after: Tang Jizhong Inventor after: Liang Chuan Inventor after: Liu Jianping Inventor before: Yang Shouzhong |
|
COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: YANG SHOUZHONG TO: YANG SHOUZHONG ZHU GUANGHUA TANG JIZHONG LIANG CHUAN LIU JIANPING Free format text: CORRECT: ADDRESS; FROM: 400060 NANAN, CHONGQING TO: 400013 YUBEI, CHONGQING |
|
TA01 | Transfer of patent application right |
Effective date of registration: 20131113 Address after: 400013 No. 8, defending Road, Chongqing, Yubei District Applicant after: Chongqing Urban Construction Holdings Group Co., Ltd. Applicant after: Chongqing Construction Engineering Group Co., Ltd. Address before: 400060 No. 56 Industrial Park, jade horse pond, Nan'an District, Chongqing Applicant before: CHONGQING CONSTRUCTION BRIDGE ENGINEERING CO., LTD. |
|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20150128 Termination date: 20180920 |