CN102733589A - Mobile operating platform and construction method thereof - Google Patents

Mobile operating platform and construction method thereof Download PDF

Info

Publication number
CN102733589A
CN102733589A CN2012102337383A CN201210233738A CN102733589A CN 102733589 A CN102733589 A CN 102733589A CN 2012102337383 A CN2012102337383 A CN 2012102337383A CN 201210233738 A CN201210233738 A CN 201210233738A CN 102733589 A CN102733589 A CN 102733589A
Authority
CN
China
Prior art keywords
platform
move
operating platform
cable
junction plates
Prior art date
Application number
CN2012102337383A
Other languages
Chinese (zh)
Inventor
朱继华
何辉
李森
郑伟盛
蒋礼
郐国雄
徐聪
Original Assignee
中建钢构有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中建钢构有限公司 filed Critical 中建钢构有限公司
Priority to CN2012102337383A priority Critical patent/CN102733589A/en
Publication of CN102733589A publication Critical patent/CN102733589A/en

Links

Abstract

The invention relates to a mobile operating platform, comprising a cable, an operating platform and a hanging part; the hanging part hangs the operating platform below the cable; the operating platform comprises a plurality of cage units which are detachably connected together. In the operating platform and a construction method of the operating platform, provided by the invention, cage units can be detachably connected together, is suitable for installation of ceiling in large area, and can be recycled to install ceilings in the other areas.

Description

A kind of move operation platform and job practices thereof
Technical field
The present invention relates to building field, particularly a kind of move operation platform and job practices thereof.
Background technology
At present, often adopt of the interior decoration of aluminium sheet ceiling system in the building as building.In work progress, often adopt high empty wagons or simple and easy hanging basket etc. measure to be installed as the architecture indoor furred ceiling.Common high empty wagons can only be not suitable for large-area furred ceiling and install as the installation of point type ceiling system, and measure cost is high, thereby strengthens construction costs, causes the engineering material waste, and, be unfavorable for that like this building-site installation will certainly extend installation period.
Summary of the invention
Technical problem to be solved by this invention is, a kind of move operation platform and job practices thereof that solves problem in the prior art is provided.
The present invention is achieved in that provides a kind of move operation platform, comprises cable, operating platform and hanging piece; Said hanging piece is hung in said operating platform extension below the said cable; Said operating platform comprises a plurality of cages unit, and said cage unit removably links together.
Further, connect through bolt between the said cage unit.
Further, said operating platform is made up of two platforms, and each platforms is formed by six cage unit combination; The long 6m of each platforms, the about 200mm of spacing between said two platforms.
Further; Two second junction plates that said hanging piece comprises two first junction plates, be installed in roller bearing between said two first junction plates, be separately positioned on said two first junction plates and be provided with at interval with said roller bearing, and wear and be fixed on said two second junction plates in order to connect the bolt on the said operating platform; Wherein, said cable is arranged in the space by said roller bearing, said two first junction plates and said two second junction plates besieged city.
Further, said hanging piece comprises a plurality of bolts, and said a plurality of bolts are arranged on said two second junction plates according to predetermined space.
Further, said move operation platform comprises that also power supports square tube, electric block and brake gear; Said power supports between second junction plate that square tube is installed in two hanging pieces that are provided with at interval along said length of warping winch direction; Said electric block and said brake gear are installed in said power and support on the square tube, and are connected with haulage cable.
Further, said brake gear is a safety lock.
Further, said operating platform adopts the welding of steel square tube to form.
Further, said operating platform also comprises the reinforcing rib that is installed in said operating platform middle part.
The present invention also provides a kind of move operation platform construction method, and it may further comprise the steps:
Fixing said cable: said cable is walked around steel structure girder the screens cuff is installed and is tighted a bolt and fix, in kind be fixed in the drag-line cuff on the main drag-line and carry out bolt and tighten fixing;
Hang said operating platform and be hung in below the said cable: utilize said hanging piece that said operating platform is hung and be hung in below the said cable; With
Move the arrival workman to said operating platform the furred ceiling desired position is installed: start said electric block and make said operating platform move along the length direction of said cable; When the said workman of arrival installs the furred ceiling desired location, utilize said brake gear to make said operating platform stop to move.
Compared with prior art, move operation platform among the present invention and the cage unit in the job practices thereof removably link together, and are fit to large-area furred ceiling and install, and can in other section furred ceilings are installed, recycle.
Above-mentioned explanation only is the general introduction of technical scheme of the present invention; Understand technological means of the present invention in order can more to know; And can implement according to the content of manual, and for let of the present invention above-mentioned with other purposes, feature and advantage can be more obviously understandable, below special act preferred embodiment; And conjunction with figs., specify as follows.
Description of drawings
Sketch map when Fig. 1 is used for the furred ceiling installation for the move operation platform in one embodiment of the invention.
Fig. 2 is the elevation of move operation platform among Fig. 1;
Fig. 3 is the axle side sketch map after the move operation platform amplifies among Fig. 1;
Fig. 4 is the electric device of move operation platform among Fig. 1 and the sketch map of security lock arrangement;
Fig. 5 is the sketch map of hanging piece among Fig. 4;
Fig. 6 is the sketch map of another angle of hanging piece among Fig. 5.
The specific embodiment
In order to make technical problem to be solved by this invention, technical scheme and beneficial effect clearer,, the present invention is further elaborated below in conjunction with accompanying drawing and embodiment.Should be appreciated that specific embodiment described herein only in order to explanation the present invention, and be not used in qualification the present invention.
Sketch map when Fig. 1 is used for the furred ceiling installation for the move operation platform 100 in one embodiment of the invention.Fig. 2 is the elevation of move operation platform among Fig. 1.Shown in Fig. 1-2, move operation platform 100 comprises cable 120, operating platform 150 and hanging piece 160 (shown in Fig. 5-6).Wherein, operating platform 150 is hung through hanging piece 160 and is hung in below the cable 120.
Cable 120 is the main stress structure, and its diameter can be confirmed according to actual needs.
Operating platform 150 is hung and is hung in below the cable 120, can flatly or have certain low-angle translation to arrive the workman furred ceiling desired position is installed.Operating platform 150 can adopt steel square tube welded construction.
In one embodiment, operating platform 150 adopts the steel square tube to be welded into the form of cage, and it comprises a plurality of cages unit 152.Each cage unit 152 is a unit with 1m.Removably link together between the adjacent cage unit 152, thereby operating platform 150 can be shortened with the change width of environment for use or extend, install with the furred ceiling that is suitable for different in width.Wherein, can connect through bolt 154 between the adjacent cage unit 152, to be easy for installation and removal.For example, each the cage unit 152 in the operating platform 150 can adopt the steel square tube welding of mouthful 40x3 to process, and can connect through 8 M12 bolts 154 between two adjacent cage unit 152.
In another embodiment, as shown in fig. 1, whole operation platform 150 can be made up of two platforms, and each platforms is combined by six cage unit 152 again.The long 6m of each platforms, the about 200mm of spacing between two platforms.Adjacent cage unit 152 in each platforms is through the high-strength bolt combination, and construction is convenient in detachable assembling.
In order to improve the intensity of operating platform 150, operating platform 150 can comprise further that the reinforcing rib 159 that is installed in operating platform 150 middle parts is like round steel, shown in Fig. 2-3.
As shown in Figure 2, operating platform 150 can further comprise the baseboard 155 that is provided with along the periphery of operating platform 150, and is laid on operating platform 150 ground bottom backing plates, with the safety that improves whole device and easy to use.
Hanging piece 160 is used for operating platform 150 hung and is hung in below the cable 120.Shown in Fig. 4-6, hanging piece 160 comprises two first junction plates 162, roller bearing 163, two second junction plates 165 and bolts 167.Two first junction plate 162 almost parallel settings, against each other and keep at a certain distance away in order to roller bearing 163 to be installed.Roller bearing 163 is installed between two first junction plates 162.Two second junction plates 165 are separately positioned on first junction plate 162, and are provided with at interval with roller bearing 163, thus by roller bearing 163, two spaces of first junction plate 162 and two second junction plates 165 besieged cities in order to pass cable 120.In the embodiment shown in fig. 4, each second junction plate 165 is respectively perpendicular to two first junction plates 162.Two second junction plate 165 almost parallel settings, against each other and keep at a certain distance away in order to accommodate the square tube on the operating platform 150, this square tube can become hanging basket square tube 158.Bolt 167 wears and is fixed on each second junction plate 165 in order to carry hanging basket square tube 158.
In one embodiment, the bolt of a plurality of bolts 167 as 3 M16 is arranged on second junction plate 165 according to predetermined space (as equidistantly).Like this, hanging basket square tube 158 can be arranged between two second junction plates 165 and optionally contact with a bolt 167, thereby can regulate the height of operating platform 150 according to actual conditions.
In one embodiment, operating platform 150 can be connected through 4 hanging pieces 160 with cable 120, and contacts to reduce friction through roller bearing 163 between hanging piece 160 and the cable 120.
In addition, move operation platform 100 can further adopt power set 180.In one embodiment, power set 180 comprise that power supports square tube 182, electric block 183 and brake gear such as safety lock 185.Power supports between second junction plate 165 that square tube 182 is installed in two hanging pieces 160 that are provided with at interval along cable 120 length directions.Electric block 183 is installed in power with safety lock 185 and supports on the square tube 182, and is connected with haulage cable.Wherein, the roller of safety lock 185 is towards operating platform 150 inboards.
Above-mentioned is the concrete structure of the move operation platform 100 in one embodiment of the invention, and brief description is used the method for its construction.
As shown in Figure 1; When move operation platform 100 is used for the furred ceiling installation; Fixed cable 120: cable 120 is walked around steel structure girder 200 the screens cuffs are installed and are tighted a bolt and fix; Stretch-draw reaches after the designing requirement, in kind is fixed in the drag-line cuff on the main drag-line and carries out bolt and tighten fixing; Hang operating platform 150 and be hung in below the cable 120: utilize hanging piece 160 that operating platform 150 is hung and be hung in below the cable 120; Move the arrival workman to operating platform 150 the furred ceiling desired position is installed: start electric block 183 and make operating platform 150 move along the length direction of cable 120; When the arrival workman installs the furred ceiling desired location, utilize brake gear such as safety lock 185 to make operating platform 150 stop to move.
As stated, the move operation platform in one embodiment of the invention adopts the ordinary steel structure, can not cause big waste to material; The move operation platform is convenient to install and dismounting, is fit to large-area furred ceiling and installs, and can in other section furred ceilings are installed, recycle; The use of move operation platform does not receive the restriction of agent structure moulding, and use face is more extensive.In addition, use each stage detachable at any time, and solving constructor's problem with material delivery on and off duty.Safety when in sum, the move operation platform in one embodiment of the invention can improve the ceiling board installation, saving construction costs, shortening construction period.
The above is merely preferred embodiment of the present invention, not in order to restriction the present invention, all any modifications of within spirit of the present invention and principle, being done, is equal to and replaces and improvement etc., all should be included within protection scope of the present invention.

Claims (10)

1. a move operation platform is characterized in that, it comprises cable, operating platform and hanging piece; Said hanging piece is hung in said operating platform extension below the said cable; Said operating platform comprises a plurality of cages unit, and said cage unit removably links together.
2. move operation platform as claimed in claim 1 is characterized in that, connects through bolt between the said cage unit.
3. move operation platform as claimed in claim 1 is characterized in that, said operating platform is made up of two platforms, and each platforms is formed by six cage unit combination; The long 6m of each platforms, the about 200mm of spacing between said two platforms.
4. move operation platform as claimed in claim 1; It is characterized in that; Two second junction plates that said hanging piece comprises two first junction plates, be installed in roller bearing between said two first junction plates, be separately positioned on said two first junction plates and be provided with at interval with said roller bearing, and wear and be fixed on said two second junction plates in order to connect the bolt on the said operating platform; Wherein, said cable is arranged in the space by said roller bearing, said two first junction plates and said two second junction plates besieged city.
5. move operation platform as claimed in claim 4 is characterized in that said hanging piece comprises a plurality of bolts, and said a plurality of bolts are arranged on said two second junction plates according to predetermined space.
6. like any one described move operation platform in the claim 1 to 5, it is characterized in that said move operation platform comprises that also power supports square tube, electric block and brake gear; Said power supports between second junction plate that square tube is installed in two hanging pieces that are provided with at interval along said length of warping winch direction; Said electric block and said brake gear are installed in said power and support on the square tube, and are connected with haulage cable.
7. move operation platform as claimed in claim 6 is characterized in that, said brake gear is a safety lock.
8. like any one described move operation platform in the claim 1 to 5, it is characterized in that said operating platform adopts the welding of steel square tube to form.
9. like any one described move operation platform in the claim 1 to 5, it is characterized in that said operating platform also comprises the reinforcing rib that is installed in said operating platform middle part.
10. move operation platform construction method as claimed in claim 6 is characterized in that it may further comprise the steps:
Fixing said cable: said cable is walked around steel structure girder the screens cuff is installed and is tighted a bolt and fix, in kind be fixed in the drag-line cuff on the main drag-line and carry out bolt and tighten fixing;
Hang said operating platform and be hung in below the said cable: utilize said hanging piece that said operating platform is hung and be hung in below the said cable; With
Move the arrival workman to said operating platform the furred ceiling desired position is installed: start said electric block and make said operating platform move along the length direction of said cable; When the said workman of arrival installs the furred ceiling desired location, utilize said brake gear to make said operating platform stop to move.
CN2012102337383A 2012-06-26 2012-06-26 Mobile operating platform and construction method thereof CN102733589A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012102337383A CN102733589A (en) 2012-06-26 2012-06-26 Mobile operating platform and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012102337383A CN102733589A (en) 2012-06-26 2012-06-26 Mobile operating platform and construction method thereof

Publications (1)

Publication Number Publication Date
CN102733589A true CN102733589A (en) 2012-10-17

Family

ID=46989834

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012102337383A CN102733589A (en) 2012-06-26 2012-06-26 Mobile operating platform and construction method thereof

Country Status (1)

Country Link
CN (1) CN102733589A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104358393A (en) * 2014-10-24 2015-02-18 中铁航空港建设集团北京有限公司 Horizontal moving platform hung at high altitude
CN105155832A (en) * 2015-06-17 2015-12-16 中建钢构有限公司 Hanging basket device and moving method thereof
CN105197845A (en) * 2015-09-19 2015-12-30 山东德建集团有限公司 Lifting hanging type hanging basket roof cornice construction device and use method
CN109025234A (en) * 2018-07-28 2018-12-18 北京建工集团有限责任公司 A kind of building high-altitude vacantly construct with can level, vertically the track crane ship that walk

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201265254Y (en) * 2008-12-29 2009-07-01 中铁建工集团有限公司 Movable operating platform system
CN201865321U (en) * 2010-11-23 2011-06-15 中铁建工集团有限公司 Multifunctional movable protecting and isolating operating platform
CN102409838A (en) * 2011-08-22 2012-04-11 中国建筑第八工程局有限公司 Moveable operating platform and method for constructing suspended ceiling of roof by using same

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201265254Y (en) * 2008-12-29 2009-07-01 中铁建工集团有限公司 Movable operating platform system
CN201865321U (en) * 2010-11-23 2011-06-15 中铁建工集团有限公司 Multifunctional movable protecting and isolating operating platform
CN102409838A (en) * 2011-08-22 2012-04-11 中国建筑第八工程局有限公司 Moveable operating platform and method for constructing suspended ceiling of roof by using same

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104358393A (en) * 2014-10-24 2015-02-18 中铁航空港建设集团北京有限公司 Horizontal moving platform hung at high altitude
CN105155832A (en) * 2015-06-17 2015-12-16 中建钢构有限公司 Hanging basket device and moving method thereof
CN105197845A (en) * 2015-09-19 2015-12-30 山东德建集团有限公司 Lifting hanging type hanging basket roof cornice construction device and use method
CN109025234A (en) * 2018-07-28 2018-12-18 北京建工集团有限责任公司 A kind of building high-altitude vacantly construct with can level, vertically the track crane ship that walk

Similar Documents

Publication Publication Date Title
CN103061506B (en) Construction method of steel structure dome
CN203201175U (en) Integrated aluminium alloy villa
CN103628680B (en) Large steel space truss hanging layer construction method
CN203809870U (en) Supporting and fixing tool for level pump pipe on concrete floor
CN104453197B (en) High Large Cantilever concrete structural steel shape supports platform
CN201221193Y (en) High altitude packway ceiling construction operating platform
CN201635379U (en) Safety platform for installation and construction of roof contour plate hang ceiling
EP2434188A2 (en) Structural duct bearing system
CN203821720U (en) High-altitude large roof panel installing tool trolley
CN101787796B (en) Suspended formwork bracing system for steel structure concrete floor slab construction
CN202755634U (en) Suspension type operational platform
CN101892736B (en) High altitude moving hanging basket construction method
CN103711323A (en) Construction method of sprung roof plates by use of movable type pipe truss platform
CN108396749B (en) Installation system and installation method of steel support in foundation pit
CN204057851U (en) Performance stage booth lifting mechanism
CN203820287U (en) Composite steel carrying pole for hoisting roof tiles of steel structure workshops
CN204401997U (en) A kind of suspension type ceiling construction scaffold
CN202810173U (en) Mounting and construction platform for steel lining bracket and circular crane track girder of nuclear power plant
CN101974974A (en) Support device for template for construction of steel structure concrete floor slab
CN103334579B (en) Slipping platform used for mounting arched roof truss with steel structure
CN105298099A (en) Modular suspension type steel tube fastener scaffold operating platform and erecting method thereof
KR101076562B1 (en) Supporting structure of slab form
CN103711301A (en) Construction method and device for two-track movable electric basket and lifting hoist
CN205171975U (en) Tuber pipe mounting platform based on BIM technique
CN103726421A (en) Height and span adjustable track paver for metro construction

Legal Events

Date Code Title Description
PB01 Publication
C06 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20121017

C12 Rejection of a patent application after its publication