CN102691415B - Bridge embedded part and method for mounting bridge using bridge embedded part - Google Patents

Bridge embedded part and method for mounting bridge using bridge embedded part Download PDF

Info

Publication number
CN102691415B
CN102691415B CN201210163726.8A CN201210163726A CN102691415B CN 102691415 B CN102691415 B CN 102691415B CN 201210163726 A CN201210163726 A CN 201210163726A CN 102691415 B CN102691415 B CN 102691415B
Authority
CN
China
Prior art keywords
crane span
span structure
fitting
threaded connection
connection hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210163726.8A
Other languages
Chinese (zh)
Other versions
CN102691415A (en
Inventor
周强
廖晓东
谢惠庆
康清泉
戴纪文
吴贵君
杨火安
黄义龙
马驰
田川
汪华双
刘宏
曾俊卿
何贤敏
郭建
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu No4 Construction Engineering Co
Original Assignee
Chengdu No4 Construction Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu No4 Construction Engineering Co filed Critical Chengdu No4 Construction Engineering Co
Priority to CN201410067383.4A priority Critical patent/CN103806651B/en
Priority to CN201210163726.8A priority patent/CN102691415B/en
Publication of CN102691415A publication Critical patent/CN102691415A/en
Application granted granted Critical
Publication of CN102691415B publication Critical patent/CN102691415B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention relates to a bridge embedded part which comprises four plates. The four plates extend longitudinally and form a rectangular frame. A bridge threaded connecting hole is reserved on at least one plate. A bending part is disposed on the bottom of at least one plate. The bending part transversely extends outwardly. By the aid of the structure, the bending part of the bridge embedded part is fixed onto a construction formwork before hole pouring of the bridge embedded part, the formwork does not need to be removed after concrete pouring, a bridge mounting hole is integrated with the concrete, construction of the bridge mounting hole is facilitated, the inner wall of the bridge mounting hole is neat, and the bridge mounting hole is fine in construction quality.

Description

A kind of crane span structure built-in fitting and utilize the method for this crane span structure installation of embedded parts crane span structure
Technical field
The present invention relates to the apparatus and method that a kind of crane span structure is installed, especially a kind of for having assisted the crane span structure built-in fitting that crane span structure installs in vertical shaft hole and the method for utilizing this crane span structure installation of embedded parts crane span structure.
Background technology
The mounting method of cable testing bridge be mainly divided into along mounting of roof plate, along wall level install, along vertical shaft installation etc.
In engineering house and office main building, every layer is provided with distribution well, and each layer of distribution well location put unification, in distribution well, there are some buses and cable testing bridge, due to limited space in distribution well, and all need through-flooring to lay, conventionally need to adopt the method installing cables crane span structure of installing along vertical shaft.
Existing method is: make after hole reservation mould by bamboo offset plate or woodwork plate, build the rest size reserving hole of adaptation mutually forming with cable testing bridge, and the manual hole reservation mould of removing, and crane span structure is bolted together in reserving hole, mainly comprise following step: determine hole to be provided size → make formwork for placing → concreting → stripping → cleaning hole → erection bridge → crane span structure perforate → crane span structure distribution (i.e. installing wire, cable in crane span structure) according to the size of reserving hole.
Above-mentioned cable testing bridge, along vertical shaft mounting method, mainly has the following disadvantages:
1, use bamboo offset plate or woodwork plate to make hole reservation mould, after concreting, need to remove separately, complex operation and increased construction cost.
2, after crane span structure installs, enter the perforate of crane span structure corresponding site at spool, be convenient to electrical line setting, but workman is cumbersome in the time of operation, easily occurs irregular hole.And the later stage when threading electric wire or cable easily pull open insulated hull at crane span structure perforate position, cause unnecessary doing over again.
Summary of the invention
The technical problem that the present invention solves is to overcome the above-mentioned deficiency of prior art, provide a kind of: easy for installation, speed of application is fast, construction quality is better, and built after concrete without the disposable reserved crane span structure built-in fitting construction method of form removal separately, and one makes, and crane span structure is easy for installation, crane span structure built-in fitting efficiently.
For solving the problems of the technologies described above, the invention provides following technical scheme:
A kind of crane span structure built-in fitting, comprises four plate bodys, and described four plate bodys all longitudinally extend, described four plate bodys enclose formation rectangle frame, on at least one plate body, be provided with crane span structure threaded connection hole, the bottom of at least one plate body is provided with bending, and described bending is along laterally extending laterally.Adopt such structure, crane span structure built-in fitting is before hole is built, be fixed in civil engineering template by the bending that is arranged at bottom, after concreting without remove, with concrete shape all-in-one-piece crane span structure install hole, be convenient to crane span structure the construction of hole is installed, and crane span structure is installed, and hole inner wall shape is regular, construction quality good.
Preferably, in described bending, be vertically arranged with threaded connection hole.Be connected with the bottom thread of civil engineering template by the threaded connection hole in bending, can further ensure the verticality of hole, improve crane span structure installation accuracy and qualification rate.
Preferably, be provided with the entrance hole for cross-under cable therein on a plate body, described entrance hole runs through plate body.Adopt such structure, be conducive to the layout of cable.
Preferably, the inside of described rectangle frame is provided with at least one support bar, and the two ends of described support bar and the inwall of plate body are closely connected.Support bar props up plate body at crane span structure built-in fitting as liner, and can prevent from building time, the distortion of crane span structure built-in fitting, improves construction precision and yield rate.
Preferably, the quantity of described support bar is two, and the two ends of the described two support bars respectively plate body relative with two of rectangle frame connect.By prop up plate body with support bar in crane span structure built-in fitting, can prevent from building time, the distortion of crane span structure built-in fitting, improves construction precision and yield rate.
A method of utilizing above-mentioned crane span structure installation of embedded parts crane span structure, comprises the following steps:
A, making crane span structure built-in fitting:
B, crane span structure built-in fitting location and installation: pass threaded connection hole with bolt crane span structure built-in fitting and cast-in-place structural template are fixed;
C, concreting; At the peripheral concreting of crane span structure built-in fitting, and form reserving hole herein;
D, connection crane span structure and crane span structure built-in fitting: pass crane span structure threaded connection hole with bolt crane span structure built-in fitting and crane span structure are fixed.
Adopt such method, construction technology is easy, progress is fast, reserving hole disposal molding gets final product erection bridge, reduce the past when adopting plank Mold Making reserved opening, that the operations such as form removal cause is artificial, material and the loss in man-hour, and can cut off concrete by crane span structure built-in fitting, make hole there is the more regular inwall of shape, construction quality is better, can avoid follow-up threading time, electric wire or cable scratch at hole inwall, and without manually picking separately the mouth that burrows, reduce labour intensity, and improved efficiency of construction after concrete is fixed.
Preferably, before described step c, two support bars are set in the inside of crane span structure built-in fitting, the two ends of the two support bars respectively plate body relative with two of rectangle frame connect.
As preferably, in above-mentioned crane span structure built-in fitting, on described crane span structure threaded connection hole, be provided with seal, described seal and crane span structure threaded connection hole removably connect.Adopt such structure, before building, crane span structure threaded connection hole is crammed, can avoid concrete to pour into crane span structure threaded connection hole, be convenient to follow-up being threaded, improve and connect precision and joint efficiency; Before building, entrance hole is crammed, can be avoided spillage, make that the inner duct of entrance hole is level and smooth, burr is few, inner spool is difficult for scratching when mobile.
Preferably, described seal comprises filler and sealing adhesive plaster, and described filler is arranged in crane span structure threaded connection hole, and described fluid sealant cloth is arranged at the both sides of crane span structure threaded connection hole.Before building, crane span structure threaded connection hole is crammed and sealed, can avoid concrete to pour into crane span structure threaded connection hole, be convenient to follow-up being threaded, improve and connect precision and joint efficiency; Before building, entrance hole is crammed and sealed, can avoid spillage, make that the inner duct of entrance hole is level and smooth, burr is few, inner spool is difficult for scratching when mobile.
A method of utilizing above-mentioned crane span structure installation of embedded parts crane span structure, comprises the following steps:
A, making crane span structure built-in fitting;
B, crane span structure built-in fitting location and installation: pass threaded connection hole with bolt crane span structure built-in fitting and cast-in-place structural template are fixed;
C, cram crane span structure threaded connection hole with filler, and seal at the two ends of crane span structure threaded connection hole sticking cloth.
D, concreting;
E, cleaning filler and sealing adhesive plaster;
F, connection crane span structure and crane span structure built-in fitting: pass crane span structure threaded connection hole with bolt crane span structure built-in fitting and crane span structure are fixed.
Adopt such method, before building, crane span structure threaded connection hole is crammed and sealed, can avoid concrete to pour into crane span structure threaded connection hole, be convenient to follow-up being threaded, improve and connect precision and joint efficiency; Before building, entrance hole is crammed and sealed, can avoid spillage, make that the inner duct of entrance hole is level and smooth, burr is few, inner spool is difficult for scratching when mobile.
Preferably, after step f, in crane span structure built-in fitting, fire barrier is installed, and at the upper filling fire prevention calking of fire barrier, fire prevention calking is positioned at the At The Height of crane span structure built-in fitting inside, cast-in-place structural template.In crane span structure built-in fitting, set up one deck fireproof partition similar to cast-in-place structural template thickness.
Compared with prior art, beneficial effect of the present invention is as follows:
1, while adopting above-mentioned crane span structure installation of embedded parts crane span structure, construction technology is easy, progress is fast, reserving hole disposal molding gets final product erection bridge, reduce the past when adopting plank Mold Making reserved opening, that the operations such as form removal cause is artificial, material and the loss in man-hour, after concrete is fixed, without manually picking separately the mouth that burrows, reduces labour intensity, and improved efficiency of construction;
2, construction quality is better, cuts off concrete by crane span structure built-in fitting, makes hole have the more regular inwall of shape, and can avoid follow-up threading time, electric wire or cable scratch at hole inwall.
Brief description of the drawings
Fig. 1 is construction method flow chart of the present invention;
Fig. 2 is the connection diagram of crane span structure built-in fitting in the present invention;
Fig. 3 is the structural representation of crane span structure built-in fitting in the present invention;
Fig. 4 is the front view of crane span structure built-in fitting in the present invention.
Fig. 5 is the lateral view of crane span structure built-in fitting in the present invention;
Fig. 6 is the structural representation of fire barrier in the present invention.
Wherein Reference numeral is as follows: crane span structure-1; Plate body-2; Bending-3; Threaded connection hole-4; Crane span structure threaded connection hole-5; Cast-in-place structural template-6; Entrance hole-7; Fire barrier-8; Fire prevention calking-9; Cable-10; Winding displacement hole-11.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the present invention is further illustrated.
Embodiments of the present invention are not limited to following examples, within the various variations of making under the prerequisite that does not depart from aim of the present invention all belong to protection scope of the present invention.
embodiment 1
As shown in Figure 1 to Figure 3, the present embodiment crane span structure built-in fitting comprises four plate bodys 2, four plate bodys 2 all longitudinally extend, described four plate bodys 2 enclose formation rectangle frame, four plate bodys 2 be mutually alternately connected to form square-section, the frame shaped body that stretches longitudinally, be the hollow cavity of rectangle at rectangle frame middle part, the support shape adaptation of the cavity shape of rectangle frame and crane span structure 1.
In the present embodiment, four plate bodys 2 link together by the mode of welding, in all the other embodiments, also can adopt snapping or the mode that is threaded is fixed.
On a plate body 2, be provided with crane span structure threaded connection hole 5 therein, be provided with bending 3 in the bottom of two opposed plate bodys 2, bending 3 is along laterally extending laterally, form wing limit, in two bendings 3, be all vertically arranged with threaded connection hole 4, be threaded connection hole 4 bending 3 is connected with the bottom thread of civil engineering template, realize the fixing of crane span structure built-in fitting.
In the time of subsequent installation, can be directly between crane span structure threaded connection hole 5 and the screwed hole on crane span structure 1 erection bolt be fixed.
On a pair of non-conterminous two plate bodys 2, be provided with several crane span structure threaded connection holes 5 therein, the quantity of crane span structure threaded connection hole 5 and position and to be arranged at quantity and the position of the installing hole on the support of crane span structure 1 mutually adaptive, in the time of subsequent installation, can be directly between crane span structure threaded connection hole 5 and the installing hole on crane span structure 1 erection bolt be fixed.On a plate body 2, be provided with the entrance hole 7 for cross-under cable 10 therein, described entrance hole 7 runs through plate body 2.
In all the other embodiments, also can only on a plate body 2, crane span structure threaded connection hole 5 be set.
In the manufacturing process of crane span structure built-in fitting, determined in advance size and bore size and the quantity of built-in fitting according to the size of cast-in-place structural template 6 thickness, crane span structure 1, spool model, ensure disposable reserved the putting in place of built-in fitting.
A method of utilizing the present embodiment crane span structure installation of embedded parts crane span structure, comprises the following steps:
A, making crane span structure built-in fitting:
B, crane span structure built-in fitting location and installation: pass threaded connection hole 4 with bolt crane span structure built-in fitting and cast-in-place structural template 6 are fixed;
Refer to Fig. 2 and Fig. 4, the interior erection bolt of threaded connection hole 4 in each bending 3, is fixedly connected with crane span structure built-in fitting with cast-in-place structural template 6.Before installation in position, first hang the method for vertical line by perforate, guarantee the installation verticality of crane span structure built-in fitting.
Behind location, spool can be penetrated in crane span structure built-in fitting; On one of them plate body 2 of crane span structure built-in fitting, offer entrance hole 7, cable 10, spool penetrate to crane span structure built-in fitting by entrance hole 7;
C, concreting;
Concreting, forms the pre-buried hole of crane span structure.After concreting completes, crane span structure built-in fitting is not removed, and fixes the connector of crane span structure as subsequent installation, has reduced the operation of making, stripping in standard practice, and has promoted regularity and the fineness of hole, improves crane span structure positioning precision.
D, connection crane span structure 1 and crane span structure built-in fitting: pass crane span structure threaded connection hole 5 with bolt crane span structure built-in fitting and crane span structure 1 are fixed;
Crane span structure 1 is packed in hole, on the support of crane span structure 1, be provided with installation screwed hole, pass by bolt after the support and crane span structure threaded connection hole 5 of crane span structure 1, crane span structure 1 and crane span structure built-in fitting and concrete hole are fixed;
If if the curtailment of its support when erection bridge 1 can adopt lengthening brace tabular, that two ends are provided with screwed hole to lengthen connection, guarantee that the crane span structure 1 of levels vertical shaft all can be installed and fix.
After crane span structure 1 installation in position, the cable 10 that is positioned at crane span structure built-in fitting inside is entered to crane span structure 1.
Adopt the method erection bridge 1 of the present embodiment, construction technology is easy, progress is fast, after reserving hole disposal molding, get final product direct erection bridge 1, reduce the past when adopting plank Mold Making reserved opening, that the operations such as form removal cause is artificial, material and the loss in man-hour, and can cut off concrete by crane span structure built-in fitting, make hole there is the more regular inwall of shape, fixed later without manually picking separately the mouth that burrows at concrete, reduce labour intensity, construction quality is better, and can avoid follow-up threading time, electric wire or cable scratch at hole inwall.
In all the other embodiments, crane span structure built-in fitting can adopt remaining structure and cast-in-place structural template 6 to reinforce the connection, for example, can indirectly connect crane span structure built-in fitting and cast-in-place structural template 6 by suspension bracket.
In addition, in all the other embodiments, the quantity that is arranged at the threaded connection hole 4 in bending 3 also one, three or more, all can play a part the bottom stable connection of crane span structure built-in fitting and cast-in-place structural template 6, the quantity of threaded connection hole 4 can increase and decrease according to the actual conditions of construction.
embodiment 2
Refer to Fig. 2 to Fig. 4, in the present embodiment crane span structure built-in fitting, the inside of described rectangle frame is provided with support bar, the inwall of the two ends of described support bar and plate body 2 is closely connected, the quantity of described support bar is two, the two ends of the two support bars respectively plate body 2 relative with two of rectangle frame connect, and two non-conterminous plate bodys 2 are shored and propped, in the criss-cross structure of shoring of the inner formation of crane span structure built-in fitting, in order to support crane span structure built-in fitting, while preventing from building, the distortion of crane span structure built-in fitting, improves construction precision and yield rate.
All the other structures refer to embodiment 1.
A method of utilizing the present embodiment crane span structure installation of embedded parts crane span structure, comprises the following steps:
A, making crane span structure built-in fitting:
B, crane span structure built-in fitting location and installation: pass threaded connection hole 4 with bolt the cast-in-place structural template in crane span structure built-in fitting and distribution wellhole hole 6 is fixed; Again cable 10 is penetrated in crane span structure built-in fitting;
C, two support bars are set in the inside of crane span structure built-in fitting, the two ends of the two support bars respectively plate body 2 relative with two of rectangle frame connect.
D, concreting;
E, connection crane span structure 1 and crane span structure built-in fitting: pass crane span structure threaded connection hole 5 with bolt crane span structure built-in fitting and crane span structure 1 are fixed, and crane span structure 1 is carried out to distribution, at the interior installing wire of crane span structure 1, cable.
All the other steps in the method for employing the present embodiment crane span structure installation of embedded parts crane span structure refer to embodiment 1.
embodiment 3
As shown in Figures 1 to 4, in the present embodiment crane span structure built-in fitting, on described crane span structure threaded connection hole 5, be provided with seal, described seal and crane span structure threaded connection hole 5 removably connect.By crane span structure threaded connection hole 5 being crammed before building, avoid concrete to pour into crane span structure threaded connection hole 5, be convenient to follow-up being threaded, improve and connect precision and joint efficiency; Described seal comprises filler and sealing adhesive plaster, and described filler is arranged in crane span structure threaded connection hole 5, and described fluid sealant cloth is arranged at the both sides of crane span structure threaded connection hole 5.
Simultaneously, on entrance hole 7, be provided with seal, described seal and entrance hole 7 removably connect, and seal comprises filler and sealing adhesive plaster, described filler is arranged in crane span structure threaded connection hole 5, and described fluid sealant cloth is arranged at the both sides of crane span structure threaded connection hole 5.Before building, entrance hole 7 is crammed and sealed, can avoid spillage, make that the inner duct of entrance hole 7 is level and smooth, burr is few, inner spool is difficult for scratching when mobile.
In all the other embodiments, the seal being arranged in crane span structure threaded connection hole 5 or entrance hole 7 can be also to have double-screw bolt or the bolt suitable with crane span structure threaded connection hole 5 internal threads, fills sealing before concreting; Or fill in the mode of foam stuffing, and can play equally the effect of spillage while preventing concreting, just repeat no more at this.
A method of utilizing the present embodiment crane span structure installation of embedded parts crane span structure, comprises the following steps:
A, making crane span structure built-in fitting;
B, crane span structure built-in fitting location and installation: pass threaded connection hole 4 with bolt crane span structure built-in fitting and cast-in-place structural template 6 are fixed, cast-in-place structural template 6 is floor, crane span structure built-in fitting is fixed on behind the bottom of floor with bolt, then cable 10 is penetrated in crane span structure built-in fitting;
C, cram crane span structure threaded connection hole 5 with filler, and seal at the two ends of crane span structure threaded connection hole 5 sticking cloth.
D, concreting;
E, cleaning filler and sealing adhesive plaster;
F, connection crane span structure 1 and crane span structure built-in fitting: crane span structure built-in fitting and crane span structure 1 are fixed through crane span structure threaded connection hole 5 with bolt, finally carried out crane span structure 1 distribution, at the interior installing wire of crane span structure 1, cable.
G, as shown in Figure 5, fire barrier 8 is installed in crane span structure built-in fitting, the quantity of fire barrier 8 is two, on in the inner chamber of crane span structure built-in fitting, lower each fire barrier 8 that arranges, one of them fire barrier 8 is arranged in the inner chamber of crane span structure built-in fitting bottom, fire barrier 8 is secured by bolts in the inside of crane span structure built-in fitting, play the effect of carrying fire prevention calking 9 weight, upper surface at this fire barrier 8 is filled the fire prevention calking 9 roughly the same with cast-in-place structural template 6 thickness, another fire barrier 8 is fixed on crane span structure built-in fitting inside with identical connected mode, and maintain an equal level with the apical side height of cast-in-place structural template 6, can make structure more attractive in appearance, avoid other people to dismantle.
The connected mode of fire barrier 8 and crane span structure built-in fitting inwall, is not limited to bolt and connects, and also can, using inside the sidewall of crane span structure built-in fitting bending or installation angle steel etc. as support, all can play the effect of fixing fire barrier 8.
After filling completes, fire prevention calking 9 is positioned at the At The Height of crane span structure built-in fitting inside, cast-in-place structural template 6, form fireproof partition, crane span structure built-in fitting interior fire protection performance better, more safe and reliable.
As shown in Figure 6, a side of fire barrier 8 is provided with several winding displacement holes 11 to the structure of fire barrier 8, by the winding displacement hole 11 on fire barrier 8, the vertical cable 10 in crane span structure built-in fitting is pressed to the inwall of crane span structure built-in fitting, plays the effect of winding displacement.
Adopt such method, before building, crane span structure threaded connection hole 5 is crammed and sealed, can avoid concrete to pour into crane span structure threaded connection hole 5, be convenient to follow-up being threaded, improve and connect precision and joint efficiency;
Separately, also can adopt and cram the method that sealing crane span structure threaded connection hole 5 is identical before building, entrance hole 7 is crammed and sealed, can avoid spillage, make that the inner duct of entrance hole 7 is level and smooth, burr is few, inner spool is difficult for scratching when mobile.
Disposable reserved crane span structure built-in fitting construction method described in employing the present embodiment detects construction quality after constructing, and the statistical conditions of the disposable reserved crane span structure hole installation and measuring point of hoistway are as shown in table 1:
Table 1: the disposable reserved crane span structure hole installation and measuring point qualification rate statistical form of hoistway
All the other steps in the method for employing the present embodiment crane span structure installation of embedded parts crane span structure refer to embodiment 1.
By reference to the accompanying drawings embodiments of the invention are described in detail above; but the present invention is not limited to above-described embodiment; in the ken possessing those of ordinary skill in the art, can also make various variations, within these variations all belong to protection scope of the present invention.

Claims (5)

1. a crane span structure built-in fitting, it is characterized in that: comprise four plate bodys (2), described four plate bodys (2) all longitudinally extend, described four plate bodys (2) enclose formation rectangle frame, on at least one plate body (2), be provided with crane span structure threaded connection hole (5), the bottom of at least one plate body (2) is provided with bending (3), described bending (3) is along laterally extending laterally, in described bending (3), be vertically arranged with threaded connection hole (4), on a plate body (2), be provided with therein the entrance hole (7) for cross-under cable (10), described entrance hole (7) runs through plate body (2).
2. crane span structure built-in fitting according to claim 1, is characterized in that: the inside of described rectangle frame is provided with at least one support bar, the inwall of the two ends of described support bar and plate body (2) is closely connected.
3. crane span structure built-in fitting according to claim 1 and 2, is characterized in that: on described crane span structure threaded connection hole (5), be provided with seal, described seal and crane span structure threaded connection hole (5) removably connect.
4. crane span structure built-in fitting according to claim 3, is characterized in that: described seal comprises filler and sealing adhesive plaster, and described filler is arranged in crane span structure threaded connection hole (5), and described fluid sealant cloth is arranged at the both sides of crane span structure threaded connection hole (5).
5. a method of utilizing crane span structure installation of embedded parts crane span structure as claimed in claim 1 or 2, is characterized in that, comprises the following steps:
A, making crane span structure built-in fitting;
B, crane span structure built-in fitting location and installation: pass threaded connection hole (4) with bolt crane span structure built-in fitting and cast-in-place structural template (6) are fixed;
C, concreting;
D, connection crane span structure (1) and crane span structure built-in fitting: pass crane span structure threaded connection hole (5) with bolt crane span structure built-in fitting and crane span structure (8) are fixed ;
Before described step c, two support bars are set in the inside of crane span structure built-in fitting, the two ends of the two support bars respectively plate body (2) relative with two of rectangle frame connect.
CN201210163726.8A 2012-05-24 2012-05-24 Bridge embedded part and method for mounting bridge using bridge embedded part Active CN102691415B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201410067383.4A CN103806651B (en) 2012-05-24 2012-05-24 A kind of method utilizing crane span structure installation of embedded parts crane span structure
CN201210163726.8A CN102691415B (en) 2012-05-24 2012-05-24 Bridge embedded part and method for mounting bridge using bridge embedded part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210163726.8A CN102691415B (en) 2012-05-24 2012-05-24 Bridge embedded part and method for mounting bridge using bridge embedded part

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201410067383.4A Division CN103806651B (en) 2012-05-24 2012-05-24 A kind of method utilizing crane span structure installation of embedded parts crane span structure

Publications (2)

Publication Number Publication Date
CN102691415A CN102691415A (en) 2012-09-26
CN102691415B true CN102691415B (en) 2014-09-24

Family

ID=46857139

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201410067383.4A Active CN103806651B (en) 2012-05-24 2012-05-24 A kind of method utilizing crane span structure installation of embedded parts crane span structure
CN201210163726.8A Active CN102691415B (en) 2012-05-24 2012-05-24 Bridge embedded part and method for mounting bridge using bridge embedded part

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201410067383.4A Active CN103806651B (en) 2012-05-24 2012-05-24 A kind of method utilizing crane span structure installation of embedded parts crane span structure

Country Status (1)

Country Link
CN (2) CN103806651B (en)

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106911110A (en) * 2017-02-14 2017-06-30 山西省工业设备安装有限公司 A kind of distribution box support component and the utilization direct pre-embedded construction method of the component
CN107268991A (en) * 2017-08-18 2017-10-20 中国水利水电第六工程局有限公司 A kind of electrically pre-buried pipeline goes out clear-water concrete built-in fitting and its construction method
CN107989201A (en) * 2017-11-29 2018-05-04 北京城建北方设备安装有限责任公司 Finished product crane span structure built-in fitting
CN109252662B (en) * 2018-09-22 2021-09-24 陕西建工第十建设集团有限公司 One-step forming construction method for vertical shaft bridge frame through cast-in-place concrete floor
CN109763579A (en) * 2018-12-18 2019-05-17 中铁广州工程局集团有限公司 A kind of manufacture installation method of gantry standard knot formula fire barrier
CN109707160A (en) * 2019-02-14 2019-05-03 广东腾安机电安装工程有限公司 The pre-buried set of gantry and the method for utilizing the pre-buried set erection bridge of the gantry
CN110750828B (en) * 2019-10-14 2022-06-07 中国能源建设集团江苏省电力设计院有限公司 Method and system for automatically selecting embedded part of thermal power plant and storage medium
CN111810715B (en) * 2020-06-18 2021-09-24 中铁工程装备集团有限公司 Trenchless pipeline updating method and construction system
CN111896892B (en) * 2020-08-19 2023-04-18 山东空天网安科技发展有限公司 Multi-mode detection equipment for computer network engineering line
CN112376906A (en) * 2020-09-18 2021-02-19 广东汇盈电力工程有限公司 Cable hole fireproof blocking method and device
CN113471901B (en) * 2021-05-26 2022-06-28 烟建集团有限公司 Self-adjusting building embedded joint and embedding method thereof
CN113675800B (en) * 2021-08-30 2022-11-08 中天建设集团有限公司 Vertical metal wire groove embedded part and installation method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1100487A (en) * 1993-05-21 1995-03-22 陈毓权 A plastic pipe sleeve and its method of installation
CN2835440Y (en) * 2005-10-25 2006-11-08 吴锡禄 Dedicated mould for pre-molded hole of construction pipe
CN101131042A (en) * 2007-07-17 2008-02-27 莱西市建筑总公司 Shaping mold for reserved hole in concrete wall
CN201292667Y (en) * 2008-10-17 2009-08-19 中国建筑第六工程局有限公司 Composite mould for pre-arranged hole for installation work pipe
CN201292665Y (en) * 2008-11-10 2009-08-19 郑州市第一建筑工程集团有限公司 Concrete floor pre-arranged hole apparatus
CN202596173U (en) * 2012-05-24 2012-12-12 成都市第四建筑工程公司 Embedded part for cable bridge

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3487797B2 (en) * 2000-01-07 2004-01-19 昭和スプリング株式会社 Bracket for frame assembly and frame assembly method
JP2001254573A (en) * 2000-03-08 2001-09-21 Izumo Keikinzoku Kk Outside frame of vent adjusting door
JP4636995B2 (en) * 2005-10-26 2011-02-23 鹿島建設株式会社 Composite concrete structure
JP4598028B2 (en) * 2007-07-19 2010-12-15 タカムラ総業株式会社 Residual form for rubber impact resistance
CN201473892U (en) * 2009-09-08 2010-05-19 中铁九局集团有限公司 Supporting device for pouring of concrete of No.0 block of continuous beam cantilever

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1100487A (en) * 1993-05-21 1995-03-22 陈毓权 A plastic pipe sleeve and its method of installation
CN2835440Y (en) * 2005-10-25 2006-11-08 吴锡禄 Dedicated mould for pre-molded hole of construction pipe
CN101131042A (en) * 2007-07-17 2008-02-27 莱西市建筑总公司 Shaping mold for reserved hole in concrete wall
CN201292667Y (en) * 2008-10-17 2009-08-19 中国建筑第六工程局有限公司 Composite mould for pre-arranged hole for installation work pipe
CN201292665Y (en) * 2008-11-10 2009-08-19 郑州市第一建筑工程集团有限公司 Concrete floor pre-arranged hole apparatus
CN202596173U (en) * 2012-05-24 2012-12-12 成都市第四建筑工程公司 Embedded part for cable bridge

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JP特开2001-193365A 2001.07.17
JP特开2001-254573A 2001.09.21

Also Published As

Publication number Publication date
CN103806651A (en) 2014-05-21
CN103806651B (en) 2015-10-07
CN102691415A (en) 2012-09-26

Similar Documents

Publication Publication Date Title
CN102691415B (en) Bridge embedded part and method for mounting bridge using bridge embedded part
CN104060629B (en) The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo
CN103410317A (en) Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part
CN104790302B (en) A kind of high pier continuous rigid frame bridge end bay straightway Hanging Basket coordinates bent cap support integral construction method
CN103485537A (en) Construction method and structure of embedded reinforcement of super high-rise horizontal secondary structure
CN110777983A (en) Synchronous construction structure and method for concrete filled wall and cast-in-place structure
CN102758451A (en) Concrete cable channel construction process
CN204983662U (en) To drawing screw rod and steel pipe framed bent combination unilateral formwork device
CN107443566A (en) The preparation method of prefabricated constructional column formwork
CN107558603A (en) A kind of assembled arthitecutral structure system and its construction method
CN106499070A (en) The construction method of connecting sewing between assembled architecture component and component
CN106120870A (en) The advanced enclosed construction of poured band of outer wall of basement and construction method
CN106245817A (en) A kind of fabricated shear wall vertical connection structure and installation method thereof
CN110552370A (en) Reverse construction method based annular lining wall integral single-side formwork construction method
CN107288263A (en) The construction method of prefabricated constructional column
CN202596173U (en) Embedded part for cable bridge
CN206233560U (en) Wall formwork erecting structure
CN105347142B (en) A kind of building hoist is mounted on the threading installation method on basement roof
CN208121808U (en) Die body system is hung in bottom plate and side wall one-time-concreting molding pond
CN205954707U (en) Leading enclosed construction in basement outer wall post -cast strip
CN204475714U (en) A kind of ready-package precast stair
CN106049665A (en) Lightweight blockwork cast-in-place core and construction method
CN203429798U (en) Embedded bar structure for horizontal secondary structure of super high-rise
CN105421725B (en) Exempt from formwork one-shot forming construction method in reserved residential ventilation road
CN207469433U (en) A kind of assembled arthitecutral structure system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant