CN102677958B - Building site greening ecological enclosing wall and construction method - Google Patents

Building site greening ecological enclosing wall and construction method Download PDF

Info

Publication number
CN102677958B
CN102677958B CN201210117144.6A CN201210117144A CN102677958B CN 102677958 B CN102677958 B CN 102677958B CN 201210117144 A CN201210117144 A CN 201210117144A CN 102677958 B CN102677958 B CN 102677958B
Authority
CN
China
Prior art keywords
enclosing
enclosure
purlin
construction
building site
Prior art date
Application number
CN201210117144.6A
Other languages
Chinese (zh)
Other versions
CN102677958A (en
Inventor
刘学应
包国钢
杜小平
王顺喜
Original Assignee
浙江水利水电专科学校
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 浙江水利水电专科学校 filed Critical 浙江水利水电专科学校
Priority to CN201210117144.6A priority Critical patent/CN102677958B/en
Publication of CN102677958A publication Critical patent/CN102677958A/en
Application granted granted Critical
Publication of CN102677958B publication Critical patent/CN102677958B/en

Links

Abstract

The invention discloses a building site greening ecological enclosing wall and a construction method. The enclosing wall comprises at least two H-shaped steel sheet piles, wherein the middle upper parts of the H-shaped steel sheet piles form the upright posts of the enclosing wall; an angle steel enclosing purlin is arranged between the adjacent upright posts, a flower trough is arranged on the angle steel enclosing purlin, and a top enclosing purlin is arranged at the top end of the upright post. A baffle plate is arranged on the surface of one side of the enclosing wall. The construction method comprises the following steps: locating the axial line of piles, punching the H-shaped steel sheet piles, and laying brick walls among the upright posts above the ground; mounting the angle steel enclosing purlins, mounting the top enclosing purlins, and mounting the baffle plate; and placing the flower trough, performing greening construction, and mounting bamboo fences. The enclosing wall disclosed by the invention can improve ecological environment, and has shortened construction period and improved working efficiency; and the construction method is simple and easy to operate and is convenient.

Description

Building site afforestation ecological enclosure wall and job practices
Technical field
The present invention relates to building structure technology field, especially relate to a kind of building site afforestation ecological enclosure wall and job practices.
Background technology
Civilization mark is turned to an important indicator of job site, is more and more subject to the attention of unit in charge of construction and supervision department.Building site is normally not only dirty but also random in people's impression.Along with the continuous standard of building trade, the requirement of building site " scenery external " improves constantly.Building enclosing, as building site and townie separator bar, is not only confined to space partition, also should contribute for landscaping.Therefore, in the urgent need to a kind of, can play the green ecological enclosure wall that enclosing effect can be beautified the environment again at present.
Chinese patent mandate publication number: CN102287072A, authorize open day on December 21st, 2011, a kind of Combined enclosing wall is disclosed, comprise two rhizosphere wall columns, be located at two cross band plates between two rhizosphere wall columns, be located at the curtain wall penel some arranged side by side between two cross band plates, snapping mutually between described adjacent curtain wall penel.The enclosure wall of this invention has quick detachable, easily the feature of carrying.Weak point is to play Greening functions.
Chinese patent mandate publication number: CN101906900A, authorize open day on December 8th, 2010, a kind of fence structure is disclosed, it is by connect two cylinders with building adhesive or connector on central post, the long cube that cylinder is comprised of polyphenyl plate, reinforcing mat, adhesive linkage or float coat, the height of cylinder is a little more than the height of wallboard; One side of cylinder is plane, and opposite side arranges two projections, and two protruding centres arrange depression; One side of wallboard is inserted in the groove after two cylinders merge, and the opposite side of wallboard inserts in the groove after two other cylinder merges, and the top of cylinder connects cap and forms.This invention has reusable, cost-saving, the feature of easy construction.Weak point is to play Greening functions.
Summary of the invention
The present invention can not play the deficiency of Greening functions in order to overcome enclosure wall of the prior art, and a kind of building site afforestation ecological enclosure wall and job practices are provided.
The building site afforestation ecological enclosure wall using, this enclosure wall adopts assembled structure, can reach and reuses and reduce the object of constructing enclosure wall required time, has saved social resources, has improved operating efficiency.
To achieve these goals, the present invention is by the following technical solutions:
An afforestation ecological enclosure wall, comprises at least two H shaped steel plate piles, and the middle and upper part of H shaped steel plate pile forms the column of enclosure wall; Between adjacent upright posts, be provided with angle steel enclosing purlin, angle steel enclosing purlin is provided with colored groove, and column upper end is provided with top and encloses purlin.
The present invention is the building site greening enclosing wall of quick detachable, the easy carrying used of a kind of Ke building site, different from common enclosure wall, can planting plants on enclosure wall, and plant can be beautified the environment, and reduces noise.Make green enclosure become a beautiful scenery in city.
Consider that building site need to solidly be gone along with sb. to guard him reliably and the requirement of enhancement of environment, afforestation ecological enclosure wall adopts steel work framing, and setting up cultivation has the colored groove of plant to fill, and is configured to solid reliable greening and environmental protection enclosure wall.
H shaped steel plate pile lower end is squeezed in soil, and the middle and upper part of H shaped steel plate pile is as the column of enclosure wall.Angle steel enclosing purlin forms the bracket of laying colored groove.Flower groove can adopt colored groove or other finished product flower groove of concreting, and flower rooved face is imitated woodworking and processed, and can reach better appearance effect.
Adopt inserted to play 250 * 250H shaped steel plate pile framing, 3.6 meters to 4.3 meters of steel sheet pile overall heights, steel sheet pile thickness 10mm.Wherein, squeeze in soil 1.8 meters-2.5 meters, foundation pile length Wei1.8 meter , top as column.Foundation pile and column can adopt the complete H shaped steel of integral type, then adopt connector connection segment.
As preferably, the surface of described enclosure wall one side is provided with baffle plate.Baffle plate has improved the enclosing buffer action of enclosure wall, and provides stable growing environment to plant.Baffle plate can be located at enclosure wall on the metope of building site one side.
As preferably, the surface of described enclosure wall one side is provided with rhombus bamboo fence.Rhombus bamboo fence both can be used as sealing enclosing, can be used as again the support of climbing up by holding on to of plant growth.Rhombus bamboo fence can be located on the metope of the outside side in building site.
As preferably, described colored groove is rectangle, and the height of the cell wall of flower groove one side is lower than the height of other cell wall; Flower trench bottom is provided with drain hole.Highly low cell wall is positioned at towards sunlight one side, is convenient to the irradiation that plant is accepted more sunlight.Drain hole is for getting rid of unnecessary moisture.
As preferably, described angle steel enclosing purlin consists of two angle steel between adjacent upright posts; It is the channel-section steel that Open Side Down that purlin is enclosed at described top.
A job practices for building site afforestation ecological enclosure wall, comprises the steps:
(1) stake position axis location, the wall of laying bricks between column more than inserted to play H shaped steel plate pile , ground;
(2) angle steel enclosing purlin is installed, top is installed and encloses purlin, baffle plate is installed;
(3) lay colored groove, greening construction, installs bamboo fence.
As preferably, described step (1) is replaced by following step:
Carry out stake position axis location, buried foundation built-in fitting in soil, is fixed on by H shaped steel plate pile the wall of laying bricks between column more than basic built-in fitting Shang, ground.Basis built-in fitting is concrete foundation built-in fitting.
Therefore, the present invention has following beneficial effect:
(1) adopt green plants wall surface construction, not only played the effect of enclosing, and can contribute for afforestation of city, reduce noise, improve the ecological environment;
(2) planting is in flower groove, and flower groove can carry out separated and combination with wall frame, reaches reusable object, can reduce the waste of resource;
(3) material using is material common on building site, as H shaped steel, angle steel etc., draws materials conveniently, and cost is low; Adopting reusable fabricated structure to construct can the reduction of erection time, increases work efficiency;
(4) spend groove to install from bottom to top, remove and carry out from top to bottom, flower groove good stability;
(5) building engineering method is simple, easy to operate, easy construction.
Accompanying drawing explanation
Fig. 1 is a kind of structural representation of embodiments of the invention 1;
Fig. 2 is a kind of structural representation of embodiments of the invention 2;
Fig. 3 is a kind of structural representation of angle steel enclosing purlin of the present invention;
Fig. 4 is a kind of structural representation of colored groove of the present invention.
In figure: purlin 4, rhombus bamboo fence 5, brick wall 6, basic built-in fitting 7, drain hole 8 are enclosed in H shaped steel plate pile 1, angle steel enclosing purlin 2, flower groove 3, top.
The specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention will be further described.
Embodiment 1
Embodiment is as shown in Figure 1 a kind of building site afforestation ecological enclosure wall, comprises two H shaped steel plate piles 1, and the middle and upper part of H shaped steel plate pile forms the column of enclosure wall; Between adjacent upright posts, be provided with angle steel enclosing purlin 2, angle steel enclosing purlin is provided with colored groove 3, and column upper end is provided with top and encloses purlin 4.Enclosure wall is provided with baffle plate near the surface of building site one side.The surface of enclosure wall one side in outside, close building site is provided with rhombus bamboo fence 5.
As shown in Figure 4, flower groove is rectangle, and the height of the cell wall of flower groove one side is lower than the height of other cell wall; Flower trench bottom is provided with drain hole 8.
As shown in Figure 3, angle steel enclosing purlin consists of two angle steel between adjacent upright posts; It is the channel-section steel that Open Side Down that purlin is enclosed at top.
Construction sequence is as described below:
Step 1, carries out a location for position axis; Then, determine baseline, set main shaft and control net, according to the main shaft of making, control net and determine enclosure wall baseline.
Step 2, fixed pile.The concrete stake position of indicating in order steel sheet pile, each position is separated by 3 meters, spills gray line and indicates.
Step 3, framying.
Steel sheet pile sets: adopt fluid pressure type steel sheet pile special-purpose machinery inserted to play.The stake machine forearm steel sheet pile of slinging, opens a head clamping plate and clamps pile crown, and at design attitude, the hydraulic vibration driver by pile driver is inserted into projected depth by steel sheet pile after vertical.Follow-up steel sheet pile inserted to play is carried out according to first steel sheet pile, and on the corner steel sheet pile adopts aluminium-plastic panel to carry out the processing of arc bound edge.In steel sheet pile construction, allowable error is: stake high deviation ± 100 millimeter of top mark, and steel sheet pile misalignment of axe ± 100 millimeter, steel sheet pile perpendicularity deviation is 1%; In setting process, whether should monitor within the scope of allowable error, while exceeding, correct in time.
Step 4, the wall of laying bricks.Body of wall adopts all-cis brick masonry, strictly presses the two-sided hanging wire of marked rod, and elevation control and mortar joint and degree of plainness for wall surface adopt shove method to guarantee that mortar joint mortar is full.While building by laying bricks or stones, mortar joint should be smooth vertical and horizontal, and mortar is full, between building block, should have good adhesion stress, spreads grey length and be generally no more than 1.5 meters.
Step 5, encloses purlin and installs.0.50 meter of H shaped steel absolute altitude ﹢ above every 30 centimetres in both sides edge of a wing bolt connect angle steel, specification ∠ 25 * 25 * 3, doublely make colored groove bracket.Top is enclosed purlin and is adopted 10# channel-section steel to be welded on steel sheet pile.
Step 6, spends fixedly laying of groove.6 colored grooves are embedded in the space of horizontal angle steel enclosing purlin formation, place from the bottom to top 8 layers of colored groove.Flower well width is 180 millimeters, and flower slot length is 460 millimeters, makes flower groove just block to be put in and encloses on purlin.
Step 7, the making of bamboo fence.Bamboo fence raw material adopts the conventional bamboo in building site to be processed into thin bamboo strips used for weaving, utilizes aperture Churn drill to punch on thin bamboo strips used for weaving, utilizes bolt and nut to connect.Bamboo fence form is diamond shaped, extensible, convenient installation, storage, transportation.
Embodiment 2
As shown in Figure 2, the structure division of embodiment 2 is in the same manner as in Example 1.
Construction sequence in embodiment 2 (1) is replaced by following step:
Carry out stake position axis location, buried foundation built-in fitting in soil, is fixed on by H shaped steel plate pile the wall of laying bricks between column more than basic built-in fitting Shang, ground.
Basis built-in fitting.As shown in Figure 2, ± 0.00 following enclosure wall basis adopts C15 concreting, wide 200 millimeters high 300 millimeters, H shaped steel plate pile lower end is fixedly connected to form to column by stone bolt and C15 concrete.
After the construction work in embodiment 2 Zhong, building sites, carry out pulling out of steel sheet pile.By laterally enclosing after purlin is removed, adopting crane to coordinate to carry out pulling out of steel sheet pile with vibrating hammer, the forced vibration disturbance soil property of utilizing vibrating hammer to produce, around destruction steel sheet pile, the cohesion of soil, to overcome pile extraction resistance, relies on the effect of additional hoisting machine that stake is pulled out.The stake hole that steel sheet pile stays after pulling out, must immediately do backfill and process, and backfill is generally with compacting method or insert method, and material therefor is medium sand.In embodiment 1, will laterally enclose after purlin is removed, directly bolt is unloaded dismountable.

Claims (2)

  1. The job practices of 1.Yi Zhong building site afforestation ecological enclosure wall, described building site afforestation ecological enclosure wall comprises at least two H shaped steel plate piles (1), the middle and upper part of H shaped steel plate pile forms the column of enclosure wall; Between adjacent upright posts, be provided with angle steel enclosing purlin (2), angle steel enclosing purlin is provided with colored groove (3), and column upper end is provided with top and encloses purlin (4); The surface of described enclosure wall one side is provided with baffle plate, and the surface of described enclosure wall one side is provided with rhombus bamboo fence (5); It is characterized in that, described job practices comprises the steps:
    (1) stake position axis location, the wall of laying bricks between column more than inserted to play H shaped steel plate pile , ground;
    (2) angle steel enclosing purlin is installed, top is installed and encloses purlin, baffle plate is installed;
    (3) lay colored groove, greening construction, installs bamboo fence.
  2. 2. the job practices of building site according to claim 1 afforestation ecological enclosure wall, is characterized in that, described step (1) is replaced by following step:
    Carry out stake position axis location, buried foundation built-in fitting in soil, is fixed on by H shaped steel plate pile the wall of laying bricks between column more than basic built-in fitting Shang, ground.
CN201210117144.6A 2012-04-20 2012-04-20 Building site greening ecological enclosing wall and construction method CN102677958B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210117144.6A CN102677958B (en) 2012-04-20 2012-04-20 Building site greening ecological enclosing wall and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210117144.6A CN102677958B (en) 2012-04-20 2012-04-20 Building site greening ecological enclosing wall and construction method

Publications (2)

Publication Number Publication Date
CN102677958A CN102677958A (en) 2012-09-19
CN102677958B true CN102677958B (en) 2014-01-15

Family

ID=46810474

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210117144.6A CN102677958B (en) 2012-04-20 2012-04-20 Building site greening ecological enclosing wall and construction method

Country Status (1)

Country Link
CN (1) CN102677958B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102723138A (en) * 2012-06-28 2012-10-10 特变电工(德阳)电缆股份有限公司 Coaxial data composite cable
CN106049668A (en) * 2016-07-19 2016-10-26 江西建工第二建筑有限责任公司 Greening and energy-saving type building outer wall structure and construction method thereof
CN108086787A (en) * 2017-12-05 2018-05-29 浙江易拓园林开发有限公司 A kind of building site afforestation ecological enclosure wall and its construction method
CN108360846A (en) * 2018-01-24 2018-08-03 河南工程学院 A kind of multifunctional ecological Landscape Architecture and its construction method

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001238544A (en) * 2000-02-28 2001-09-04 Tenryu Ind Co Ltd Vegetative frame and vegetative structure having the frame, and continuous vegetative structure comprising the vegetative structure and roadside vegetative structure
CN2460668Y (en) * 2001-01-20 2001-11-21 倪既民 Plant fence combined with grid
JP3642056B2 (en) * 2002-05-02 2005-04-27 良三 高野 Greening method using mesh wire mesh block on the wall of multi-story building.
CN101748823B (en) * 2010-01-01 2012-09-26 张宇顺 Ecological greening wall and constructing method thereof
CN201915688U (en) * 2010-12-22 2011-08-03 上海中卉生态科技有限公司 Combined ecological fence
CN102359112A (en) * 2011-07-22 2012-02-22 中铁第四勘察设计院集团有限公司 Method for bracing foundation pit by using steel box piles
CN202544489U (en) * 2012-04-20 2012-11-21 浙江水利水电专科学校 Construction site greening ecological enclosing wall

Also Published As

Publication number Publication date
CN102677958A (en) 2012-09-19

Similar Documents

Publication Publication Date Title
CN203834739U (en) End steel board connection, positioning and assembly type shear wall structure
CN101914925B (en) Basement by using optimized composite prefabricated arch wall as external wall
CN203394170U (en) Prefabricated enclosing wall
CN1948633A (en) Tray type excarvating contrary construction method
CN101831970A (en) Integrally assembled wallboard wall and construction method thereof
CN207160039U (en) A kind of Tenon prefabricated PC open caisson
CN103334439A (en) Long-span reinforced concrete inner support structure of rectangular deep foundation pit and construction method of structure
CN204258238U (en) A kind of prefabricated assembled irrigation canals and ditches device
CN202324323U (en) Outer wall plate
CN104878835B (en) Strip footing increases basement structure behind house
CN105401605B (en) Deformation joint structure and its construction method
CN105421470B (en) Assembled anchor pole arched framework combined type ecological revetment construction method
CN107268807B (en) A kind of Prefabricated concrete-filled steel tube superposed column
CN104727440B (en) Industrialized production efficiently-assembled type building frame column beam and manufacturing method
CN205894281U (en) Integral basement of coincide assembly of arch without beam system
CN101787710B (en) Integrally-assembled buttressed retaining wall and construction method thereof
CN206070562U (en) Subassembly formula underground structure
CN204510467U (en) A kind of cap node for basement flat slab structure
CN203383508U (en) One-sided formwork body structure backing onto brick concrete retaining wall
CN103603435B (en) A kind of assembly concrete antidetonation beam column frame and construction method thereof
CN204983662U (en) To drawing screw rod and steel pipe framed bent combination unilateral formwork device
CN204781441U (en) Assembled reinforced concrete wallboard frame construction
CN105113660B (en) A kind of construction method for the constructional column constructed simultaneously with frame structure filling wall
CN104878836B (en) A kind of prefabricated house and its construction method
CN103290952A (en) Integrated assembled concrete frame and shear wall connection structure and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
C10 Entry into substantive examination
GR01 Patent grant
C14 Grant of patent or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 310018 HANGZHOU, ZHEJIANG PROVINCE TO: 315400 NINGBO, ZHEJIANG PROVINCE

ASS Succession or assignment of patent right

Owner name: NINGBO DECHENG GARDEN CONSTRUCTION CO., LTD.

Free format text: FORMER OWNER: ZHEJIANG WATER CONSERVANCY + HYDROPOWER COLLEGE

Effective date: 20150225

TR01 Transfer of patent right

Effective date of registration: 20150225

Address after: Yu Jia Qiao Road Yuyao City, Zhejiang province 315400 Ningbo City No. 76 two floor

Patentee after: Ningbo Decheng Garden Construction Co., Ltd.

Address before: Hangzhou City, Zhejiang province 310018 Xuelin economic and Technological Development Zone Road No. 583

Patentee before: Zhejiang Hydraulic & Hydroelectric Junior School

C41 Transfer of patent application or patent right or utility model
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140115