CN102661057A - 电力转角塔拉腿主材更换方法以及专用主材卡具 - Google Patents

电力转角塔拉腿主材更换方法以及专用主材卡具 Download PDF

Info

Publication number
CN102661057A
CN102661057A CN2012101732188A CN201210173218A CN102661057A CN 102661057 A CN102661057 A CN 102661057A CN 2012101732188 A CN2012101732188 A CN 2012101732188A CN 201210173218 A CN201210173218 A CN 201210173218A CN 102661057 A CN102661057 A CN 102661057A
Authority
CN
China
Prior art keywords
main material
remove
bolts
install
defective
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012101732188A
Other languages
English (en)
Other versions
CN102661057B (zh
Inventor
刘明亮
王荣阁
李树平
李卫红
张留岗
王继双
梁河雷
何义良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Hengshui Power Supply Co
Original Assignee
Hengshui Power Supply Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hengshui Power Supply Co filed Critical Hengshui Power Supply Co
Priority to CN201210173218.8A priority Critical patent/CN102661057B/zh
Publication of CN102661057A publication Critical patent/CN102661057A/zh
Application granted granted Critical
Publication of CN102661057B publication Critical patent/CN102661057B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

本发明属于电力塔维护方法技术领域,特别公开了一种电力转角塔拉腿主材更换方法以及专用主材卡具。其技术方案为:该方法包括下列步骤:第一步,安装地锚和临时拉线;第二步,拉紧临时拉线;第三步,拆除基础保护帽;第四步,安装塔脚卡具;第五步,安装主材卡具;第六步,装好两套拉紧工具;第七步,拆除主材上端8条防盗接头螺栓;第八步,继续拆除主材上端其它8条防盗接头螺栓;第九步,拆除缺陷主材的其他螺栓;第十步,更换新主材;第十一步,拆除更换工具。在更换缺陷主材时,不需要停电,避免了因停电对电网和用电客户生产生活造成的影响,而且减少了落线、紧线等工序,更换时间大大缩短。

Description

电力转角塔拉腿主材更换方法以及专用主材卡具
技术领域
本发明属于电力塔维护方法技术领域,特别涉及一种电力转角塔拉腿主材更换方法以及专用主材卡具。
背景技术
电力转角塔拉腿主材在使用过程中,由于受到风力、锈蚀、线路结冰等原因的影响,使得电力转角塔拉腿主材容易断裂,必须及时更换,如果不及时更换,会对线路运行造成安全隐患。目前更换电力转角塔拉腿主材的主要方法就是先将线路停电;将耐张塔两侧直线塔进行锚线,然后将耐张塔的导、地线全部从空中松至地面,对原铁塔塔材进行拆除,更换新塔材后在挂线才能完成塔材更换任务。这样约需2天的停电时间,停电时间长,工作量大,需要耗费大量的人力、物力,电网可靠性也大受影响。
发明内容
本发明解决的第一个技术问题就是提供一种可以在不停电的情况下进行更换、工作效率高的电力转角塔拉腿主材更换方法。
为解决上述技术问题,本发明采用的技术方案为:
电力转角塔拉腿主材更换方法,其特征在于:该方法包括下列步骤:
第一步,安装地锚和临时拉线
在缺陷主材基础周围外沿5m—7m处,对称均布埋设4个7t—8 t级地锚,在所述地锚上方要堆放300mm以上土堆并踩压实,在缺陷主材上方的主材内侧绑扎稍径不小于110mm、长度1.3—1.8m左右的杉杆,在铁塔主材的内侧设置四条临时拉线,临时拉线上端绑扎在杉杆上,操作人员必须站在铁塔主材的内侧,传递绳也从铁塔内侧上下;
第二步,拉紧临时拉线
临时拉线用6t链条葫芦调节向下施压,临时拉线的下端固定10t级卸扣,卸扣中穿过第一钢绳,该第一钢绳一端固定在地锚上,另一端连接在6t链条葫芦上;
第三步,拆除基础保护帽
去掉损伤拉腿基础保护帽;
第四步,安装塔脚卡具
拆除损伤拉腿外侧两对称地脚螺栓,并将带有挂环的塔脚卡具固定在地脚螺栓位置;
第五步,安装主材卡具
在缺陷主材上端的抱铁上部安装带有挂钩的主材卡具;
第六步,装好两套拉紧工具
在主材卡具的挂钩上穿过钢绳套,在钢绳套下方挂上链条葫芦,该链条葫芦的下端挂在塔脚卡具的挂环上;
第七步,拆除主材上端8条防盗接头螺栓
拉紧链条葫芦至合适张紧度后,逐根拆除缺陷主材最上端8条防盗接头螺栓,在拆除同时替换成普通接头螺栓并紧固好;
第八步,继续拆除主材上端其它8条防盗接头螺栓
继续拆除缺陷主材上端剩余的8条防盗接头螺栓,同时替换成普通接头螺栓,该普通接头螺栓不紧固,此时慢慢放松已经紧固的好的8条螺栓,并随时观察上方主材的相对运动情况,防止其向上滑动,必要时调整链条葫芦;
第九步,拆除缺陷主材的其他螺栓
待缺陷主材上端接头螺栓全部松开后,且缺陷主材上端的主材位置未发生变化,并观察各受力点均稳定后,开始拆除连接在缺陷主材上的其它防盗螺栓;
第十步,更换新主材
在缺陷主材上方的合适位置悬挂起重钢绳,卸下缺陷主材后,安装新主材及斜材,并将所有螺栓紧固到扭矩标准;
第十一步,拆除更换工具
拆除主材卡具、钢绳套、链条葫芦、塔脚卡具、地锚和临时拉线。
本发明解决的第二个技术问题就是提供一种实现电力转角塔拉腿主材更换方法的主材卡具。
为解决上述技术问题,本发明采用的技术方案为:包括前角板和与该前角板形状相同的后角板,在所述前角板和所述后角板上带有螺孔,在所述前角板前端设置有与所述前角板垂直的挂钩板,在所述挂钩板的顶端设置有挂钩。
本发明所提供的电力转角塔拉腿主材更换方法以及专用主材卡具,同现有技术相比具有以下优点:
其一,由于该方法包括下列步骤:
第一步,安装地锚和临时拉线
在缺陷主材基础周围外沿5m—7m处,对称均布埋设4个7t—8 t级地锚,在所述地锚上方要堆放300mm以上土堆并踩压实,在缺陷主材上方的主材内侧绑扎稍径不小于110mm、长度1.3—1.8m左右的杉杆,在铁塔主材的内侧设置四条临时拉线,临时拉线上端绑扎在杉杆上,操作人员必须站在铁塔主材的内侧,传递绳也从铁塔内侧上下;
第二步,拉紧临时拉线
临时拉线用6t链条葫芦调节向下施压,临时拉线的下端固定10t级卸扣,卸扣中穿过第一钢绳,该第一钢绳一端固定在地锚上,另一端连接在6t链条葫芦上;
第三步,拆除基础保护帽
去掉损伤拉腿基础保护帽;
第四步,安装塔脚卡具
拆除损伤拉腿外侧两对称地脚螺栓,并将带有挂环的塔脚卡具固定在地脚螺栓位置;
第五步,安装主材卡具
在缺陷主材上端的抱铁上部安装带有挂钩的主材卡具;
第六步,装好两套拉紧工具
在主材卡具的挂钩上穿过钢绳套,在钢绳套下方挂上链条葫芦,该链条葫芦的下端挂在塔脚卡具的挂环上;
第七步,拆除主材上端8条防盗接头螺栓
拉紧链条葫芦至合适张紧度后,逐根拆除缺陷主材最上端8条防盗接头螺栓,在拆除同时替换成普通接头螺栓并紧固好;
第八步,继续拆除主材上端其它8条防盗接头螺栓
继续拆除缺陷主材上端剩余的8条防盗接头螺栓,同时替换成普通接头螺栓,该普通接头螺栓不紧固,此时慢慢放松已经紧固的好的8条螺栓,并随时观察上方主材的相对运动情况,防止其向上滑动,必要时调整链条葫芦;
第九步,拆除缺陷主材的其他螺栓
待缺陷主材上端接头螺栓全部松开后,且缺陷主材上端的主材位置未发生变化,并观察各受力点均稳定后,开始拆除连接在缺陷主材上的其它防盗螺栓;
第十步,更换新主材
在缺陷主材上方的合适位置悬挂起重钢绳,卸下缺陷主材后,安装新主材及斜材,并将所有螺栓紧固到扭矩标准;
第十一步,拆除更换工具
拆除主材卡具、钢绳套、链条葫芦、塔脚卡具、地锚和临时拉线,
在更换缺陷主材时,不需要停电,避免了因停电对电网和用电客户生产生活造成的影响,而且减少了落线、紧线等工序,更换时间大大缩短;
其二,由于主材卡具包括前角板和与该前角板形状相同的后角板,在所述前角板和所述后角板上带有螺孔,在所述前角板前端设置有与所述前角板垂直的挂钩板,在所述挂钩板的顶端设置有挂钩,将前角板和后角板通过螺杆固定在主材上,固定更加牢固。
附图说明
图1为更换缺陷主材方法的示意图;
图2为主材卡具的结构示意图。
具体实施方式
下面结合附图和具体实施例对本发明所提供的电力转角塔拉腿主材更换方法以及专用卡具做进一步的详细说明。
如图1所示,为更换缺陷主材方法的示意图,本发明提供的电力转角塔拉腿主材更换方法,该方法包括下列步骤:
第一步,安装地锚和临时拉线
在缺陷主材1基础周围外沿5m—7m处,对称均布埋设4个7t—8 t级地锚2,在地锚2的上方要堆放300mm以上土堆并踩压实,在缺陷主材1上方的主材3内侧绑扎稍径不小于110mm、长度1.3—1.8m左右的杉杆4,在铁塔主材的内侧设置四条临时拉线5,临时拉线5上端绑扎在杉杆4上,操作人员必须站在铁塔主材的内侧,传递绳也从铁塔内侧上下;
第二步,拉紧临时拉线
临时拉线5用6t链条葫芦调节向下施压,临时拉线的下端固定10t级卸扣10,卸扣中穿过第一钢绳11,该第一钢绳11的一端固定在地锚2上,另一端连接在6t链条葫芦12上;
第三步,拆除基础保护帽
去掉损伤拉腿基础保护帽;
第四步,安装塔脚卡具
拆除损伤拉腿外侧两对称地脚螺栓,并将带有挂环6的塔脚卡具7固定在地脚螺栓位置;
第五步,安装主材卡具
在缺陷主材1上端的抱铁上部安装带有挂钩8的主材卡具9;
第六步,装好两套拉紧工具
在主材卡具9的挂钩8上穿过钢绳套13,在钢绳套13的下方挂上链条葫芦14,该链条葫芦14的下端挂在塔脚卡具7的挂环6上;
第七步,拆除主材上端8条防盗接头螺栓
拉紧链条葫芦至合适张紧度后,逐根拆除缺陷主材1最上端8条防盗接头螺栓,在拆除同时替换成普通接头螺栓并紧固好;
第八步,继续拆除主材上端其它8条防盗接头螺栓
继续拆除缺陷主材9上端剩余的8条防盗接头螺栓,同时替换成普通接头螺栓,该普通接头螺栓不紧固,此时慢慢放松已经紧固的好的8条螺栓,并随时观察上方主材的相对运动情况,防止其向上滑动,必要时调整链条葫芦;
第九步,拆除缺陷主材1的其他螺栓
待缺陷主材1上端接头螺栓全部松开后,且缺陷主材1上端的主材位置未发生变化,并观察各受力点均稳定后,开始拆除连接在缺陷主材上的其它防盗螺栓;
第十步,更换新主材
在缺陷主材1上方的合适位置悬挂起重钢绳,卸下缺陷主材后,安装新主材及斜材,并将所有螺栓紧固到扭矩标准;
第十一步,拆除更换工具
拆除主材卡具、钢绳套、链条葫芦、塔脚卡具、地锚和临时拉线。在更换缺陷主材时,不需要停电,避免了因停电对电网和用电客户生产生活造成的影响,而且减少了落线、紧线等工序,更换时间大大缩短。
如图2所示,为主材卡具的结构示意图,该主材卡具9包括前角板91和与该前角板91形状相同的后角板92,在前角板91和后角板92上带有螺孔93,在前角板91的前端设置有与前角板91垂直的挂钩板94,在挂钩板94的顶端设置有挂钩95,将前角板91和后角板92通过螺杆固定在主材上,固定更加牢固。

Claims (2)

1.电力转角塔拉腿主材更换方法,其特征在于:该方法包括下列步骤:
第一步,安装地锚和临时拉线
在缺陷主材基础周围外沿5m—7m处,对称均布埋设4个7t—8 t级地锚,在所述地锚上方要堆放300mm以上土堆并踩压实,在缺陷主材上方的主材内侧绑扎稍径不小于110mm、长度1.3—1.8m左右的杉杆,在铁塔主材的内侧设置四条临时拉线,临时拉线上端绑扎在杉杆上,操作人员必须站在铁塔主材的内侧,传递绳也从铁塔内侧上下;
第二步,拉紧临时拉线
临时拉线用6t链条葫芦调节向下施压,临时拉线的下端固定10t级卸扣,卸扣中穿过第一钢绳,该第一钢绳一端固定在地锚上,另一端连接在6t链条葫芦上;
第三步,拆除基础保护帽
去掉损伤拉腿基础保护帽;
第四步,安装塔脚卡具
拆除损伤拉腿外侧两对称地脚螺栓,并将带有挂环的塔脚卡具固定在地脚螺栓位置;
第五步,安装主材卡具
在缺陷主材上端的抱铁上部安装带有挂钩的主材卡具;
第六步,装好两套拉紧工具
在主材卡具的挂钩上穿过钢绳套,在钢绳套下方挂上链条葫芦,该链条葫芦的下端挂在塔脚卡具的挂环上;
第七步,拆除主材上端8条防盗接头螺栓
拉紧链条葫芦至合适张紧度后,逐根拆除缺陷主材最上端8条防盗接头螺栓,在拆除同时替换成普通接头螺栓并紧固好;
第八步,继续拆除主材上端其它8条防盗接头螺栓
继续拆除缺陷主材上端剩余的8条防盗接头螺栓,同时替换成普通接头螺栓,该普通接头螺栓不紧固,此时慢慢放松已经紧固的好的8条螺栓,并随时观察上方主材的相对运动情况,防止其向上滑动,必要时调整链条葫芦;
第九步,拆除缺陷主材的其他螺栓
待缺陷主材上端接头螺栓全部松开后,且缺陷主材上端的主材位置未发生变化,并观察各受力点均稳定后,开始拆除连接在缺陷主材上的其它防盗螺栓;
第十步,更换新主材
在缺陷主材上方的合适位置悬挂起重钢绳,卸下缺陷主材后,安装新主材及斜材,并将所有螺栓紧固到扭矩标准;
第十一步,拆除更换工具
拆除主材卡具、钢绳套、链条葫芦、塔脚卡具、地锚和临时拉线。
2.实现上述电力转角塔拉腿主材更换方法的主材卡具,其特征在于:包括前角板和与该前角板形状相同的后角板,在所述前角板和所述后角板上带有螺孔,在所述前角板前端设置有与所述前角板垂直的挂钩板,在所述挂钩板的顶端设置有挂钩。
CN201210173218.8A 2012-05-30 2012-05-30 电力转角塔拉腿主材更换方法以及专用主材卡具 Active CN102661057B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210173218.8A CN102661057B (zh) 2012-05-30 2012-05-30 电力转角塔拉腿主材更换方法以及专用主材卡具

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210173218.8A CN102661057B (zh) 2012-05-30 2012-05-30 电力转角塔拉腿主材更换方法以及专用主材卡具

Publications (2)

Publication Number Publication Date
CN102661057A true CN102661057A (zh) 2012-09-12
CN102661057B CN102661057B (zh) 2015-01-21

Family

ID=46770623

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210173218.8A Active CN102661057B (zh) 2012-05-30 2012-05-30 电力转角塔拉腿主材更换方法以及专用主材卡具

Country Status (1)

Country Link
CN (1) CN102661057B (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979346A (zh) * 2012-12-13 2013-03-20 辽宁省电力有限公司锦州供电公司 10kV多层架空线路杆塔原位更换钢管杆方法
CN104278874A (zh) * 2013-07-06 2015-01-14 湖北省电力公司黄冈供电公司 高压输电线路组立铁塔的方法
CN104596804A (zh) * 2015-01-29 2015-05-06 卢少勇 一种用于缓冲带内地表以下不同深度的径流收集装置
CN104831945A (zh) * 2015-05-14 2015-08-12 中国电力科学研究院 一种用于更换输电铁塔主材的装置
CN105317236A (zh) * 2015-11-25 2016-02-10 国家电网公司 一种输电线路轻便式更换铁塔主材包钢的装置
CN108843117A (zh) * 2018-09-25 2018-11-20 国网辽宁省电力有限公司锦州供电公司 输电线路铁塔主材快速更换方法及其装置

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010043505A (ja) * 2008-08-09 2010-02-25 Denro Corp 鉄塔の主柱材取替え工法
CN101806151A (zh) * 2010-03-19 2010-08-18 四川电力送变电建设公司 铁塔主材更换装置
CN101824932A (zh) * 2010-03-23 2010-09-08 宁波天弘电力器具有限公司 抢修塔的塔段
CN201635416U (zh) * 2010-03-19 2010-11-17 四川电力送变电建设公司 铁塔主材更换装置
CN201722944U (zh) * 2010-05-10 2011-01-26 中国电力科学研究院 一种输电角钢铁塔的加固构件
CN201738628U (zh) * 2010-07-21 2011-02-09 广东电网公司电力科学研究院 一种角钢与钢筋组合式铁塔
CN202090666U (zh) * 2011-06-09 2011-12-28 山东电力研究院 一种老旧线路输电塔主材加固装置
EP2444571A1 (en) * 2010-10-22 2012-04-25 Rautaruukki OYJ Lattice tower

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010043505A (ja) * 2008-08-09 2010-02-25 Denro Corp 鉄塔の主柱材取替え工法
CN101806151A (zh) * 2010-03-19 2010-08-18 四川电力送变电建设公司 铁塔主材更换装置
CN201635416U (zh) * 2010-03-19 2010-11-17 四川电力送变电建设公司 铁塔主材更换装置
CN101824932A (zh) * 2010-03-23 2010-09-08 宁波天弘电力器具有限公司 抢修塔的塔段
CN201722944U (zh) * 2010-05-10 2011-01-26 中国电力科学研究院 一种输电角钢铁塔的加固构件
CN201738628U (zh) * 2010-07-21 2011-02-09 广东电网公司电力科学研究院 一种角钢与钢筋组合式铁塔
EP2444571A1 (en) * 2010-10-22 2012-04-25 Rautaruukki OYJ Lattice tower
CN202090666U (zh) * 2011-06-09 2011-12-28 山东电力研究院 一种老旧线路输电塔主材加固装置

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979346A (zh) * 2012-12-13 2013-03-20 辽宁省电力有限公司锦州供电公司 10kV多层架空线路杆塔原位更换钢管杆方法
CN104278874A (zh) * 2013-07-06 2015-01-14 湖北省电力公司黄冈供电公司 高压输电线路组立铁塔的方法
CN104596804A (zh) * 2015-01-29 2015-05-06 卢少勇 一种用于缓冲带内地表以下不同深度的径流收集装置
CN104831945A (zh) * 2015-05-14 2015-08-12 中国电力科学研究院 一种用于更换输电铁塔主材的装置
CN104831945B (zh) * 2015-05-14 2017-09-01 中国电力科学研究院 一种用于更换输电铁塔主材的装置
CN105317236A (zh) * 2015-11-25 2016-02-10 国家电网公司 一种输电线路轻便式更换铁塔主材包钢的装置
CN105317236B (zh) * 2015-11-25 2017-07-11 国家电网公司 一种输电线路轻便式更换铁塔主材包钢的装置
CN108843117A (zh) * 2018-09-25 2018-11-20 国网辽宁省电力有限公司锦州供电公司 输电线路铁塔主材快速更换方法及其装置
CN108843117B (zh) * 2018-09-25 2024-05-17 国网辽宁省电力有限公司锦州供电公司 输电线路铁塔主材快速更换方法及其装置

Also Published As

Publication number Publication date
CN102661057B (zh) 2015-01-21

Similar Documents

Publication Publication Date Title
CN102661057B (zh) 电力转角塔拉腿主材更换方法以及专用主材卡具
CN206471747U (zh) 一种可带电更换的绝缘子装置
CN206250670U (zh) 一种便于操作且安全性高的绝缘子更换装置
CN104242153B (zh) 更换特高压直流线路耐张塔单片550kN玻璃绝缘子施工工艺
CN102664377B (zh) 双扇横担单人杆上组装器及双扇横担安装方法
CN202014055U (zh) 用于±660kV直流输电线路V型双串绝缘子的检修工具
CN202197048U (zh) 一种塔用双角钢挂点起重连接工具
CN202488034U (zh) 角铁塔输电线路起吊装置
CN106384964A (zh) 一种带电更换v型绝缘子串作业法
CN106992474A (zh) 10kV电缆头拆装辅助工具
CN201118144Y (zh) 500千伏耐张绝缘子串门型更换器
CN203813330U (zh) 带电更换500kV耐张绝缘子串工具
CN202594699U (zh) 钢管塔输电线路起吊装置
CN104253394B (zh) 一种耐张绝缘子串的更换工具
CN206685815U (zh) 10kV电缆头拆装辅助工具
CN204651778U (zh) 一种更换输电线路绝缘子的辅助装置
CN215989995U (zh) 一种特高压耐张塔端部瓷瓶更换辅助装置
CN108448488A (zh) 840kN级耐张四联横担侧绝缘子更换工具及方法
CN108847617A (zh) 特高压输电线路带电更换耐张跳线绝缘子串的装置及方法
CN202578116U (zh) 双扇横担单人杆上组装器
CN204651789U (zh) 带电更换绝缘子串的专用吊具
CN110757403B (zh) 一种高铁终端锚固线夹锥套和楔子的拆卸装置
CN202559823U (zh) 电力转角塔拉腿主材更换用主材卡具
CN209805246U (zh) 一种基于绝缘子串的起吊系统
CN202616658U (zh) 一种220kV线路的吊串绝缘子更换装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP. HEBEI ELECTRIC POWER CORP

Effective date: 20130318

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20130318

Address after: 053000 Hengshui East Road, Hebei, No. 185

Applicant after: HENGSHUI POWER SUPPLY Co.

Applicant after: State Grid Corporation of China

Applicant after: Hebei Electric Power Corp.

Address before: 053000 Hengshui East Road, Hebei, No. 185

Applicant before: HENGSHUI POWER SUPPLY Co.

C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 100031 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: STATE GRID HEBEI ELECTRIC POWER COMPANY HENGSHUI POWER SUPPLY BRANCH

Applicant after: STATE GRID HEBEI ELECTRIC POWER Co.

Address before: 053000 Hengshui province Hebei City Taocheng District People's Road No. 185

Applicant before: STATE GRID HEBEI ELECTRIC POWER COMPANY HENGSHUI POWER SUPPLY BRANCH

Applicant before: State Grid Corporation of China

Applicant before: STATE GRID HEBEI ELECTRIC POWER Co.

Address after: 053000 Hengshui province Hebei City Taocheng District People's Road No. 185

Applicant after: STATE GRID HEBEI ELECTRIC POWER COMPANY HENGSHUI POWER SUPPLY BRANCH

Applicant after: State Grid Corporation of China

Applicant after: STATE GRID HEBEI ELECTRIC POWER Co.

Address before: 053000 Hengshui East Road, Hebei, No. 185

Applicant before: HENGSHUI POWER SUPPLY Co.

Applicant before: State Grid Corporation of China

Applicant before: Hebei Electric Power Corp.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: HENGSHUI POWER SUPPLY COMPANY TO: HENGSHUI POWER SUPPLY BRANCH COMPANY, STATE GRID HEBEI ELECTRIC POWER COMPANY

Free format text: CORRECT: APPLICANT; FROM: HENGSHUI POWER SUPPLY BRANCH COMPANY, STATE GRID HEBEI ELECTRIC POWER COMPANY TO: STATE GRID CORPORATION OF CHINA

C14 Grant of patent or utility model
GR01 Patent grant