CN102660924B - Steel column sectional shelf-unit construction and steel column sectional shelf-unit - Google Patents

Steel column sectional shelf-unit construction and steel column sectional shelf-unit Download PDF

Info

Publication number
CN102660924B
CN102660924B CN201210168850.3A CN201210168850A CN102660924B CN 102660924 B CN102660924 B CN 102660924B CN 201210168850 A CN201210168850 A CN 201210168850A CN 102660924 B CN102660924 B CN 102660924B
Authority
CN
China
Prior art keywords
steel
steel column
sectional shelf
strut
steel strut
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210168850.3A
Other languages
Chinese (zh)
Other versions
CN102660924A (en
Inventor
张素梅
翟文静
吕嘉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Xinshi Road & Bridge Construction Co ltd
Engineering Overall Contracting No 2 Department Of Beijing Municipal Road & Bridge Group Co ltd
Beijing Municipal Road and Bridge Co Ltd
Original Assignee
Beijing Municipal Administration Road And Bridge Ltd Co
Beijing Municipal Luqiao Ltd By Share Ltd General Contracting Two
Beijing Xinshi Road & Bridge Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Administration Road And Bridge Ltd Co, Beijing Municipal Luqiao Ltd By Share Ltd General Contracting Two, Beijing Xinshi Road & Bridge Construction Co Ltd filed Critical Beijing Municipal Administration Road And Bridge Ltd Co
Priority to CN201210168850.3A priority Critical patent/CN102660924B/en
Publication of CN102660924A publication Critical patent/CN102660924A/en
Application granted granted Critical
Publication of CN102660924B publication Critical patent/CN102660924B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a kind of steel column sectional shelf-unit construction, comprise bracket basis treatment step, make bracket basis meet required requirement for bearing capacity; And set up steel column sectional shelf-unit step, first steel strut is connected with bracket basis, after installing whole steel strut, connects between each steel strut, distribution beam is set on steel strut top.Distribution beam can be arranged to semi girder.This engineering method have occupation of land less, cost is low, construction is quick, safety is high feature.The present invention also provides a kind of special-purpose steel column combination support, comprise steel column support and distribution beam, steel column support is made up of multiple steel strut being vertically fixed on bracket basis, has bearing diagonal to connect between steel strut, the top of steel strut is provided with distribution beam, and distribution beam can be semi girder.

Description

Steel column sectional shelf-unit construction and steel column sectional shelf-unit
Technical field
The present invention relates to a kind of construction of bridge construction and special falsework thereof, relate in particular to a kind of steel column sectional shelf-unit construction and steel column sectional shelf-unit thereof.
Background technology
When building urban interchange or the means of transportation such as existing road, bridge crossed over by viaduct, often need the partial row track erection construction falsework taking existing road.Traditional rack form mainly contains bowl fastening type support and Bailey beam support.Bowl fastening type support element is single, and impact resistance is poor, and bracket assembly is originally higher, and due to single rack bearing limited in one's ability, thus for the bridge that weight is larger, the number of holders of needs is comparatively large, causes taking ground space comparatively large, easily affects the traffic capacity.Bailey beam rack construction situation is more complicated, and lifting component is difficult, removes not easily.Thus, above two kinds of traditional rack forms all inevitably produce the traffic of present situation road and disturb and cause traffic congestion, and then produce a series of social concern.
Summary of the invention
The object of the present invention is to provide a kind of steel column sectional shelf-unit construction, this engineering method adopts steel column sectional shelf-unit to replace traditional bowl fastening type support and Bailey beam support, can reduce and take existing path resource, effective alleviation traffic above-ground pressure, solve long-standing problem Urban Bridge problems in construction preferably, have the advantages that cost is low, construction is quick, safety is high.The present invention also provides a kind of special steel column sectional shelf-unit.
To achieve these goals, steel column sectional shelf-unit construction of the present invention comprises bracket basis treatment step, makes described bracket basis meet required requirement for bearing capacity; And set up steel column sectional shelf-unit step, steel strut is connected with described bracket basis, after installing whole steel strut, connects between steel strut described in each, distribution beam is set on described steel strut top, uses i iron multiple described distribution beam to be coupled together.
Described distribution beam can be semi girder, is made up of i iron or Bailey beam.
Described steel strut is made up of more piece steel strut component, first head is saved steel strut component and is connected to described bracket basis, then connects all the other joint steel strut components successively.
Steel column sectional shelf-unit construction of the present invention, also comprises preparation of construction step.
Steel column sectional shelf-unit construction of the present invention, also comprise and install sandbox or jack step, described sandbox or jack are placed on described distribution beam.
Steel column sectional shelf-unit construction of the present invention, also can not arrange distribution beam on the top of described steel strut, described sandbox or jack is directly placed on the top of described steel strut.
The present invention also provides a kind of steel column sectional shelf-unit, comprise steel column support and distribution beam, described steel column support is made up of multiple steel strut be vertically fixed on bracket basis, and the top of described steel strut is provided with distribution beam, uses i iron multiple described distribution beam to be coupled together.
Described distribution beam is semi girder, is made up of i iron or Bailey beam.
Because the distribution beam of construction of the present invention steel column sectional shelf-unit used is semi girder, when providing equal supporting surface, the floor space of the present invention's support used is fewer than conventional stent, thus reduce and take existing path resource, the impact of work progress on existing road traffic can be reduced.
Accompanying drawing explanation
Fig. 1 is steel column sectional shelf-unit construction of the present invention steel column sectional shelf-unit front view used;
Fig. 2 is steel column sectional shelf-unit construction of the present invention steel column sectional shelf-unit used top view;
Fig. 3 is the front view of steel column sectional shelf-unit construction cheek of the present invention when being directly placed on steel strut top.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, the invention will be further described.
Construction of the present invention steel column sectional shelf-unit used is formed primarily of steel strut 2, the bottom of every root steel strut 2 is connected with bracket basis 1 and is vertically fixed on bracket basis 1, connects the resistance to overturning ensureing steel column supporting structure between steel strut 2 by bearing diagonal 6.Steel strut 2 top can arrange distribution beam 3.Sandbox 5 or jack are directly or indirectly placed in distribution beam 3, the bridge superstructure deadweight and the working load that comprise steel girder box 7 (see Fig. 2) are delivered in distribution beam 3 by sandbox 5 or jack, then by distribution beam 3, load are distributed to each steel strut 2.
Apply steel column sectional shelf-unit construction provided by the invention when constructing, crossed over the both sides of road and/or as required in the road between set up steel column sectional shelf-unit respectively, Specific construction flow process mainly comprises: preparation of construction; Bracket basis process; Assembling steel column support; Distribution beam is set; Sandbox or jack are installed.
First, according to the establishment such as construction drawing design, site contour, pouring plan and appointed condition constructure scheme, and according to the intensity of the different construction stage support of construction stage load capacity calculation, rigidity and stability.According to working drawing, according to the strong point, measurement and positioning is carried out to the installation site of steel strut 2, guarantee the accurate of steel strut 2 position.
After preparation of construction work completes, bracket basis 1 is processed.Bracket basis 1 needs to be placed in meet on the ground of requirement for bearing capacity.In order to prevent basis in bridge construction process from occurring moderate finite deformation, can be clean by substrate eliminating impurities, substrate also can be avoided to be subject to water soaking and to endure cold.
After treating that bracket basis 1 process reaches the requirement of setting, namely can start to assemble steel column support.First, check that steel strut component used is to ensure that they do not have gross distortion and cross section to weaken.Then, accurate setting-out is carried out with the mounting plane control point of total powerstation to steel strut 2.Each steel strut 2 can be formed by connecting by multiple steel strut component.During assembling, adopt the form of merogenesis lifting steel strut component, first head is saved steel strut component to be connected with bracket basis 1 by basic built-in fitting such as pre-embedded bolt, then respectively connect with flange high-strength bolt between joint steel strut component at all the other, steel column top also can adopt flange high-strength bolt connected mode to be connected with top rail simultaneously, make the easy installation and removal of steel strut 2 quick like this, drastically increase operating efficiency.For increasing rigidity and quality of connection bottom steel strut 2, bottom steel strut 2, can be welded with triangular steel plate of putting more energy in surrounding and basic built-in fitting junction, such as, be four pieces.Remain during installation that steel strut 2 is vertical.For ensureing the stability of construction period support, bearing diagonal 6 is set between steel strut 2 in order to ensure the resistance to overturning of supporting structure.Steel strut component can adopt external diameter 609 millimeters, the pipe steel column of wall thickness 16 millimeters.
After steel column bracket assembled completes, steel strut 2 arranges distribution beam 3.First i iron can be set on every root steel strut 2 top or Bailey beam makes distribution beam 3, and distribution beam 3 is welded on steel strut 2 top.Distribution beam 3 can be arranged to semi girder.Sandbox 5 or jack are placed in distribution beam 3, as illustrated in fig. 1 and 2.Distribution beam 3 also can be arranged to simply supported beam, and now can weld spandrel girder again in distribution beam 3, sandbox 5 or jack are placed on spandrel girder.Alternatively, also distribution beam 3 can not be set, but load-bearing is carried out on top sandbox 5 or jack being directly placed on steel strut 2, as shown in Figure 3.Such as i iron can also be used multiple distribution beam 3 to be coupled together, thus formation working platform carry out load-bearing.
Structure and the making of the composite steel column support that construction of the present invention is used are simple, easy accessibility, and material can select pipe steel column and i iron, and these are all be easy to lease the material obtained, and significantly reduce use cost.
In addition, because distribution beam 3 adopts semi girder form, and by distribution fine strain of millet 3, loading is delivered to steel strut 2, quantity and the floor space of the steel strut 2 thus needed are less, also less on the impact of road.

Claims (5)

1. a steel column sectional shelf-unit construction, is characterized in that, comprising:
Bracket basis treatment step, makes described bracket basis meet required requirement for bearing capacity; And
Set up steel column sectional shelf-unit step, comprising:
Steel strut is connected with described bracket basis,
After installing whole steel strut, connect between steel strut described in each, and
On described steel strut top, distribution beam is set,
Described steel column sectional shelf-unit construction also comprises installs sandbox or jack step, described sandbox or jack are placed in described distribution beam, or distribution beam is not set on the top of described steel strut, described sandbox or jack is directly placed on the top of described steel strut
Bridge superstructure placed by described sandbox or jack.
2. steel column sectional shelf-unit construction according to claim 1, is characterized in that, described distribution fine strain of millet is semi girder.
3. steel column sectional shelf-unit construction according to claim 1, is characterized in that, described steel strut is made up of more piece steel strut component, first head is saved steel strut component and is connected to described bracket basis, then connects all the other joint steel strut components successively.
4. steel column sectional shelf-unit construction according to claim 1, is characterized in that, also comprise preparation of construction step.
5. steel column sectional shelf-unit construction according to claim 1, it is characterized in that, described distribution beam is made up of i iron or Bailey beam.
CN201210168850.3A 2012-05-28 2012-05-28 Steel column sectional shelf-unit construction and steel column sectional shelf-unit Expired - Fee Related CN102660924B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210168850.3A CN102660924B (en) 2012-05-28 2012-05-28 Steel column sectional shelf-unit construction and steel column sectional shelf-unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210168850.3A CN102660924B (en) 2012-05-28 2012-05-28 Steel column sectional shelf-unit construction and steel column sectional shelf-unit

Publications (2)

Publication Number Publication Date
CN102660924A CN102660924A (en) 2012-09-12
CN102660924B true CN102660924B (en) 2016-03-23

Family

ID=46770493

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210168850.3A Expired - Fee Related CN102660924B (en) 2012-05-28 2012-05-28 Steel column sectional shelf-unit construction and steel column sectional shelf-unit

Country Status (1)

Country Link
CN (1) CN102660924B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103321155B (en) * 2013-06-28 2015-09-09 杭州萧宏建设集团有限公司 Viaduct pier operation platform system and build this system and pour into a mould the method for bridge pier
CN105672695A (en) * 2016-01-27 2016-06-15 上海市基础工程集团有限公司 Steel structure bracket system for rapid construction of subway station
CN107841953B (en) * 2017-11-30 2024-02-27 中铁二十局集团第一工程有限公司 High-altitude oblique crossing Liang Doupo side span cast-in-situ section construction support and construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4343606B2 (en) * 2003-07-18 2009-10-14 三井住友建設株式会社 Bridge construction method
CN101736692A (en) * 2008-11-20 2010-06-16 中铁十六局集团有限公司 Construction technology for passenger railway line spanning existing railway cast-in-place box beam bracket
CN201678946U (en) * 2009-12-30 2010-12-22 中铁二局股份有限公司 Movable Bailey beam steel bracket made of cast-in-place rigid frame bridge top plate concrete
CN201943010U (en) * 2011-03-03 2011-08-24 葛洲坝集团第五工程有限公司 Overhead cast-in-situ box girder support platform

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102020204A (en) * 2010-08-06 2011-04-20 中铁八局集团第一工程有限公司 Assembly type ultrahigh heavy-load portal crane

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4343606B2 (en) * 2003-07-18 2009-10-14 三井住友建設株式会社 Bridge construction method
CN101736692A (en) * 2008-11-20 2010-06-16 中铁十六局集团有限公司 Construction technology for passenger railway line spanning existing railway cast-in-place box beam bracket
CN201678946U (en) * 2009-12-30 2010-12-22 中铁二局股份有限公司 Movable Bailey beam steel bracket made of cast-in-place rigid frame bridge top plate concrete
CN201943010U (en) * 2011-03-03 2011-08-24 葛洲坝集团第五工程有限公司 Overhead cast-in-situ box girder support platform

Also Published As

Publication number Publication date
CN102660924A (en) 2012-09-12

Similar Documents

Publication Publication Date Title
CN102733606A (en) Construction method of high large cantilever structure
CN104389419A (en) Cantilevered formwork platform installation structure and construction method
CN103266778B (en) Detachable triangular scaffold and steel truss assembly construction method
CN102660924B (en) Steel column sectional shelf-unit construction and steel column sectional shelf-unit
CN105804400A (en) Curved surface net frame lifting construction method
CN206457729U (en) A kind of supporting bracket of bridge construction
CN103469735B (en) The installation method of the formwork of the solid section of the pier top of the hollow column and slab pier with curved superelevation
CN101633483B (en) Integral lifting apparatus for steel structure net rack
CN205444975U (en) Large-scale roof steel construction braced system with view platform
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN202899639U (en) Concrete column structure
CN104961058B (en) A kind of double Z shaped support steel beam and crane supporting member and preparation method containing it
CN205741942U (en) A kind of great cantilever chooses arm pier cap beam segmental timbering
CN204780601U (en) Bed -jig is assembled to reinforcing bar festival section
CN100362200C (en) Supporting displacement method for lifting component and supporting system thereof
CN204343701U (en) A kind of special-shaped leg post supports installation structure
CN105821770A (en) Connecting and locating method for multiple tower roots and large-size concrete bearing platform foundation of steel structure main tower
CN201605528U (en) Bridge pier column for installing steel-structure bent cap
CN110331647A (en) Urban track traffic bondbeam and its construction method
CN113585097B (en) Construction process suitable for mounting bridge girder erection machine
CN209620622U (en) A kind of promotion platform
CN104278640B (en) For the steel truss girder assembling support in the construction of steel concrete composite truss beam
CN114837090A (en) A combined support system and construction method for high tower beam construction
CN202447842U (en) Electro-gas welding assembly bracket of detachable blast furnace shell
CN107237515A (en) The support meanss and its application method of circular steel truss structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160202

Address after: 102399 No. 37 Xinqiao street, Mentougou District, Beijing

Applicant after: BEIJING XINSHI ROAD & BRIDGE CONSTRUCTION Co.,Ltd.

Applicant after: BEIJING MUNICIPAL ROAD & BRIDGE GROUP Co.,Ltd.

Applicant after: ENGINEERING OVERALL CONTRACTING NO. 2 DEPARTMENT OF BEIJING MUNICIPAL ROAD & BRIDGE GROUP Co.,Ltd.

Address before: 102399 No. 37 Xinqiao street, Mentougou District, Beijing

Applicant before: BEIJING XINSHI ROAD & BRIDGE CONSTRUCTION Co.,Ltd.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160323

CF01 Termination of patent right due to non-payment of annual fee