CN102660923A - 外海潮间带预制40mT型梁安装施工工艺 - Google Patents
外海潮间带预制40mT型梁安装施工工艺 Download PDFInfo
- Publication number
- CN102660923A CN102660923A CN2012101648722A CN201210164872A CN102660923A CN 102660923 A CN102660923 A CN 102660923A CN 2012101648722 A CN2012101648722 A CN 2012101648722A CN 201210164872 A CN201210164872 A CN 201210164872A CN 102660923 A CN102660923 A CN 102660923A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- construction
- intertidal zone
- bridge formation
- formation machine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开一种外海潮间带预制40mT型梁安装施工工艺。潮间带是滨海工程的关键施工区段,是水、陆施工工艺均不适用的一个施工区域;潮间带的施工在国内外均属技术难题。本发明包括预制40m后张法预应力T梁完成后水运至施工现场,经转换平台上的跨墩龙门吊起吊至运梁小车,再由运梁小车运梁至架设现场,最后通过架桥机架设至指定位置,具体安装顺序为:由海侧向岸侧逐跨进行,每跨T梁的架设顺序为边→中→边→中。本发明成功地解决了引桥设计长度3千米以上,排架间距40m,上部结构采用预制T型梁,单片T型梁最大重量达到180吨以上、位于大潮的高、低潮位之间,随潮汐涨落而被淹没和露出的典型的潮间带施工难题。
Description
技术领域
本发明涉及一种外海潮间带预制40mT型梁安装施工工艺,属于建筑技术领域。
背景技术
典型的潮间带包括浅滩区(船无法进入),水深1.5m潮位出现小于3小时的区域;潮间区(船可赶潮进出),水深1.5m潮位出现不小于3小时,且水深2.5m潮位出现小于8小时的区域;浅水区(乘潮而进,乘潮而出),水深2.5m潮位出现不小于8小时的区域;潮间带是滨海工程的关键施工区段,是水、陆施工工艺均不适用的一个施工区域;潮间带的施工在国内外均属技术难题。目前还未见引桥设计长度3千米以上,排架间距40m,上部结构采用预制T型梁,单片T型梁最大重量达到180吨以上、位于大潮的高、低潮位之间,随潮汐涨落而被淹没和露出的典型的潮间带施工先例。
发明内容
本发明的目的是针对上述存在的问题提供一种外海潮间带预制40mT型梁安装施工工艺,解决了外海潮间带施工的难题。
上述的目的通过以下技术方案实现:
外海潮间带预制40mT型梁安装施工工艺,包括如下工艺步骤:预制40m后张法预应力T梁完成后水运至施工现场,经转换平台上的跨墩龙门吊起吊至运梁小车,再由运梁小车运梁至架设现场,最后通过架桥机架设至指定位置,具体安装顺序为:由海侧向岸侧逐跨进行,每跨T梁的架设顺序为边→中→边→中。
所述的外海潮间带预制40mT型梁安装施工工艺,所述的预制40m后张法预应力T梁完成后水运至施工现场包括如下施工步骤:选用Ф60mm的钢丝绳,同时采用两台100吨的龙门吊兜底起吊,移动T梁至预制场地边沿处,搁置在事先放好的两端钢梁上,待T梁安放后,在T梁两侧采用直径200mm的园木按5m的间隔对称加固,待需要时采用龙门吊将T梁吊运至驳船上,水上运输采用1200t的平板驳船,每船装载3-4件T梁,事先在平板驳上用槽钢及钢板制作钢框架,确定3-4件T梁各自的摆放的位置,上部采用绑带穿过吊点将3-4件T梁连接在一起,T梁与T梁之间用木楔楔牢,然后采用紧固器扎牢,同时在外侧梁的侧面用用直径不小于200mm的园木按不大于5m的间隔加固。
所述的外海潮间带预制40mT型梁安装施工工艺,所述的架桥机架设采用尾部喂梁、拖拉取梁、跨一孔架梁的施工工艺,第一片梁就位后,安设临时支撑,确认支撑稳定后,方可松开吊钩,第二片及后面各片梁均在第一片梁上方高于第一片梁顶面10cm位置低位运梁,梁体横移时梁两端支撑段在盖梁顶面10cm位置低位移动,到位后缓慢落梁就位,并与相邻已架设的梁面焊接不少于四块连结钢板后,才能松开吊钩,架设下一片梁。
所述的外海潮间带预制40mT型梁安装施工工艺,所述的经转换平台上的跨墩龙门吊起吊至运梁小车,运梁车装梁时,梁片重心应落在台车纵向中心线上,偏差不得超过20mm,梁片与台车支撑间应垫放硬杂木板或纤维层胶皮,以保护梁片砼。
所述的外海潮间带预制40mT型梁安装施工工艺,所述的架桥机采用YQ200-40架桥机。
有益效果:
本发明通过对外海T型梁运输、转换平台提梁方案、架桥机安装应用等工艺的选择,成功地解决了引桥设计长度3千米以上,排架间距40m,上部结构采用预制预应力T型梁,单片T型梁最大重量达到180吨以上、位于大潮的高、低潮位之间,随潮汐涨落而被淹没和露出的典型的潮间带施工难题。
具体实施方式
实施例1:
外海潮间带预制40mT型梁安装施工工艺,包括如下工艺步骤:预制40m后张法预应力T梁完成后水运至施工现场,经转换平台上的跨墩龙门吊起吊至运梁小车,再由运梁小车运梁至架设现场,最后通过架桥机架设至指定位置,具体安装顺序为:由海侧向岸侧逐跨进行,每跨T梁的架设顺序为边→中→边→中。
实施例2:
所述的外海潮间带预制40mT型梁安装施工工艺,所述的预制40m后张法预应力T梁完成后水运至施工现场包括如下施工步骤:选用Ф60mm的钢丝绳,同时采用两台100吨的龙门吊兜底起吊,移动T梁至预制场地边沿处,搁置在事先放好的两端钢梁上,待T梁安放后,在T梁两侧采用直径200mm的园木按5m的间隔对称加固,待需要时采用龙门吊将T梁吊运至驳船上,水上运输采用1200t的平板驳船,每船装载3-4件T梁,事先在平板驳上用槽钢及钢板制作钢框架,确定3-4件T梁各自的摆放的位置,上部采用绑带穿过吊点将3-4件T梁连接在一起,T梁与T梁之间用木楔楔牢,然后采用紧固器扎牢,同时在外侧梁的侧面用用直径不小于200mm的园木按不大于5m的间隔加固。
实施例3:
所述的外海潮间带预制40mT型梁安装施工工艺,所述的架桥机架设采用尾部喂梁、拖拉取梁、跨一孔架梁的施工工艺,第一片梁就位后,安设临时支撑,确认支撑后,方可松开吊钩,第二片及后面各片梁均在第一片梁上方高于第一片梁顶面10cm位置低位运梁,梁体横移时梁两端支撑段在盖梁顶面10cm位置低位移动,到位后缓慢落梁就位,并与相邻已架设的梁面焊接不少于四块连结钢板后,才能松开吊钩,架设下一片梁。
实施例4:
所述的外海潮间带预制40mT型梁安装施工工艺,所述的经转换平台上的跨墩龙门吊起吊至运梁小车,运梁车装梁时,梁片重心应落在台车纵向中心线上,偏差不得超过20mm,梁片与台车支撑间应垫放硬杂木板或纤维层胶皮,以保护梁片砼。
实施例5:
所述的外海潮间带预制40mT型梁安装施工工艺,所述的架桥机采用YQ200-40架桥机。
实施例6:
以南通港吕四港区东灶港作业区2万吨级通用码头工程为例,该工程引桥长约3714.18m,标准桥宽15.5m,0#~90#墩上部结构采用先简支后连续的40m后张法预应力T梁力混凝土T型梁,其中第1~5联,第7~10联,第13~16联,第19~20联采用5×40m 装配式预应力混凝土先简支后连续T梁;第11、17、21联采用4×40m装配式预应力混凝土先简支后连续T梁;第6、12、18联采用40m装配式预应力混凝土简支T梁。T梁按部分预应力混凝土A类构件设计,梁高2.5m,全桥宽15.5m,其中行车部分宽10m,由两片边梁、两片中梁组成。预留管廊带宽5m,由两块中梁组成。中梁翼板宽2.4m,边梁翼板宽2.15m,翼板外边缘厚20cm。跨中边梁与中梁腹板厚均为28cm,马蹄宽64cm,支点处边梁与中梁腹板厚均为40cm,马蹄宽76cm。该工程共预制、安装40mT梁366根,具体型号数量为:简支T梁(3跨):中梁12根、边梁6根,连续段边跨D80伸缩缝(8跨):中梁16根、边梁16根,连续段边跨D160伸缩缝(28跨):中梁56根、边梁56根,连续段边跨中梁(51跨):中梁102根、边梁102根。该工程40m后张法预应力T梁由预制厂预制,水运至施工现场,经转换平台上的两台100t跨墩龙门吊起吊至运梁小车,再由运梁小车运梁至架设现场,最后通过YQ200-40架桥机架设至指定位置。其体安装顺序为:由海侧向岸侧逐跨进行,每跨“T”梁的架设顺序为边→中→边→中。
该工程在T梁非连续端处墩顶为永久支座,连续端处墩顶设置临时支座,根据现场实际情况,考虑体系转换时临时支座拆除的便捷,采用自制卸落式钢制漏砂筒作为临时支座。架设T梁前,按测量放样给出的支座位置安放支座,先把漏砂筒(临时支座)下筒按设计临时支座位置安放在墩台帽上,把准备好的干砂装入钢筒内。按先已测试好的高度值装平,再把准备好的漏砂筒上筒盖在砂面上,调整使其顶面水平。其施工顺序为:预压→加砂→预压→加砂→调平砂面→检查活塞盖顶面标高→T梁安装就位,为防止梁底和钢板间有空隙,造成临时支座局部受压,需在卸落钢制漏砂筒上垫上5mm的橡胶垫。永久支座安装时,应防止支座出现偏压或产生过大的初始剪切变形。安装完成后,必须保证支座与上、下部结构紧密接触,不得出现脱空现象。支座安装后,应全面检查是否有支座漏放,支座安装方向、支座型式是否有错,四氟滑板支座是否注入硅脂油,一经发现,应及时调整和处理,确保支座安装后的正常工作,并记录支座安装后出现的各项偏差及异常情况。
预制梁采用1200t水上运输船运输至码头1分段前沿转换平台中,通过转换平台上的龙门吊将梁片从运输船上吊运至运梁台车上,运梁车装梁时,梁片重心应落在台车纵向中心线上,偏差不得超过20mm,梁片与台车支撑间应垫放硬杂木板或纤维层胶皮,以保护梁片砼。
架桥机拼装完成后,进行准备工作。
在架桥机过孔之前,对桥机再次进行试车,启动各控制开关,检查各控制开关正常与否,确认各控制系统和行程开关、卷扬机刹车等完好时,让架桥机再进行过孔。此事项在每跨过孔前都要执行安检。
架桥机先自平衡过孔33m,然后加配重过孔;在架桥机过孔之前将平车运梁走到架桥机两主梁之间的后支腿位置(平车前端到架桥机后端距离不宜小于50cm,且不宜大于100cm),停止并制动;对架桥机的前、后天车起重限制器和刹车进行检验,检查合格后方可进入下一个工序。
架桥机自行过孔33m后,然后用前天车提梁做配重,架桥机继续向前过孔,天车向后行走,保证天车提梁的位置不变,要求后支轮箱和中托上轮箱向前驱动,带动架桥机主梁和前支整体向前移动,直到前支系统到达前一个墩台处。从而完成架桥机配重过孔。在选择配重过孔时安全系数保证1.5以上。
架桥机完成过孔以后,调整前天车卷扬机升降高度,前后液压千斤顶及桥机的前后距离,架桥机主梁尽可能水平或前支略高,使前支腿落在前横移轨道上的适当位置,超平垫实前横移轨道且和中横移轨道平行,运梁车后退到合适位置,收起后支腿,横移试车。
前天车吊起梁体前端,将平车的控制接口和架桥机的控制接口进行连接,保证运梁车的后驮梁小车和架桥机的前吊梁小车同步、同速运行。
后吊梁小车吊起梁体后端,当前天车提梁走到跨中位置附近时,箱梁的后端部位于后天车位置,此时后天车进行提梁。
前后天车同时向前移动,运梁平车回去运梁,天车走到合适位置后,天车带重横移进行架设箱梁,该孔架设完毕后,调整前、后支液压千斤顶高度,使中托脱离主梁下弦,为中托向前移动到前支腿位置做准备。
利用天车吊起中托及中横移轨道前行移至合适位置,超平垫实中横移轨道;然后把天车开到后支上合适位置,重复上述步骤进行箱梁架设。
Claims (6)
1.一种外海潮间带预制40mT型梁安装施工工艺,其特征是:包括如下工艺步骤:预制40m后张法预应力T梁完成后水运至施工现场,经转换平台上的跨墩龙门吊起吊至运梁小车,再由运梁小车运梁至架设现场,最后通过架桥机架设至指定位置,具体安装顺序为:由海侧向岸侧逐跨进行,每跨T梁的架设顺序为边→中→边→中。
2.根据权利要求1所述的外海潮间带预制40mT型梁安装施工工艺,其特征是:所述的预制40m后张法预应力T梁完成后水运至施工现场包括如下施工步骤:选用Ф60mm的钢丝绳,同时采用两台100吨的龙门吊兜底起吊,移动T梁至预制场地边沿处,搁置在事先放好的两端钢梁上,待T梁安放后,在T梁两侧采用直径200mm的园木按5m的间隔对称加固,待需要时采用龙门吊将T梁吊运至驳船上,水上运输采用1200t的平板驳船,每船装载3-4件T梁,事先在平板驳上用槽钢及钢板制作钢框架,确定3-4件T梁各自的摆放的位置,上部采用绑带穿过吊点将3-4件T梁连接在一起,T梁与T梁之间用木楔楔牢,然后采用紧固器扎牢,同时在外侧梁的侧面用用直径不小于200mm的园木按不大于5m的间隔加固。
3.根据权利要求1或2所述的外海潮间带预制40mT型梁安装施工工艺,其特征是:所述的架桥机架设采用尾部喂梁、拖拉取梁、跨一孔架梁的施工工艺,第一片梁就位后,安设临时支撑,确认支撑后,方可松开吊钩,第二片及后面各片梁均在第一片梁上方高于第一片梁顶面10cm位置低位运梁,梁体横移时梁两端支撑段在盖梁顶面10cm位置低位移动,到位后缓慢落梁就位,并与相邻已架设的梁面焊接不少于四块连结钢板后,才能松开吊钩,架设下一片梁。
4.根据权利要求1或2所述的外海潮间带预制40mT型梁安装施工工艺,其特征是:所述的经转换平台上的跨墩龙门吊起吊至运梁小车,运梁车装梁时,梁片重心应落在台车纵向中心线上,偏差不得超过20mm,梁片与台车支撑间应垫放硬杂木板或纤维层胶皮,以保护梁片砼。
5.根据权利要求1或2所述的外海潮间带预制40mT型梁安装施工工艺,其特征是:所述的架桥机采用YQ200-40架桥机。
6.根据权利要求3所述的外海潮间带预制40mT型梁安装施工工艺,其特征是:所述的架桥机采用YQ200-40架桥机。
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2012101648722A CN102660923A (zh) | 2012-05-25 | 2012-05-25 | 外海潮间带预制40mT型梁安装施工工艺 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2012101648722A CN102660923A (zh) | 2012-05-25 | 2012-05-25 | 外海潮间带预制40mT型梁安装施工工艺 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN102660923A true CN102660923A (zh) | 2012-09-12 |
Family
ID=46770492
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2012101648722A Pending CN102660923A (zh) | 2012-05-25 | 2012-05-25 | 外海潮间带预制40mT型梁安装施工工艺 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102660923A (zh) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103061266A (zh) * | 2013-01-11 | 2013-04-24 | 武船重型工程股份有限公司 | 一种在强潮涌海域上的水路运输架设钢箱梁的方法 |
| CN103422441A (zh) * | 2013-08-13 | 2013-12-04 | 中铁六局集团有限公司 | Dj180架桥机架设大跨度公路箱梁过孔方法 |
| CN106315151A (zh) * | 2016-09-14 | 2017-01-11 | 中交第航务工程局有限公司 | 一种小尺寸预制构件单车出运施工方法 |
| CN110644380A (zh) * | 2019-09-27 | 2020-01-03 | 河南理工大学 | 一种大跨径跨线桥加宽工程狭窄空间梁板安装方法 |
| CN111395821A (zh) * | 2020-03-23 | 2020-07-10 | 中电建十一局工程有限公司 | 一种复杂地形条件40mT梁预制场地布置及安装施工方法 |
| CN111485498A (zh) * | 2020-04-22 | 2020-08-04 | 中交第三航务工程局有限公司 | 一种引桥折线段预制构件的安装工艺 |
| CN114108466A (zh) * | 2021-10-12 | 2022-03-01 | 中铁广州工程局集团有限公司 | 一种节段梁预制场地及码头运载节段梁的方法 |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| NL9301539A (nl) * | 1993-09-06 | 1995-04-03 | Seaway Heavy Lifting Engineeri | Werkwijze voor het oprichten van een tuimast op een steunpijlerconstructie bij een tuibrug. |
| CN101649603A (zh) * | 2008-08-15 | 2010-02-17 | 龙建路桥股份有限公司 | 50米t型梁预制安装工艺 |
| CN101781887A (zh) * | 2009-12-30 | 2010-07-21 | 天津市海王星海上工程技术有限公司 | 一种海上平台上部结构悬挑安装方法 |
| CN102127899A (zh) * | 2010-12-30 | 2011-07-20 | 中铁大桥局集团第二工程有限公司 | 大吨位钢箱梁在陆域及浅滩区的提升滑移系统及施工方法 |
-
2012
- 2012-05-25 CN CN2012101648722A patent/CN102660923A/zh active Pending
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| NL9301539A (nl) * | 1993-09-06 | 1995-04-03 | Seaway Heavy Lifting Engineeri | Werkwijze voor het oprichten van een tuimast op een steunpijlerconstructie bij een tuibrug. |
| CN101649603A (zh) * | 2008-08-15 | 2010-02-17 | 龙建路桥股份有限公司 | 50米t型梁预制安装工艺 |
| CN101781887A (zh) * | 2009-12-30 | 2010-07-21 | 天津市海王星海上工程技术有限公司 | 一种海上平台上部结构悬挑安装方法 |
| CN102127899A (zh) * | 2010-12-30 | 2011-07-20 | 中铁大桥局集团第二工程有限公司 | 大吨位钢箱梁在陆域及浅滩区的提升滑移系统及施工方法 |
Non-Patent Citations (4)
| Title |
|---|
| 刘勇等: "超长引桥工程的几项关键施工技术", 《中国港湾建设》, no. 5, 31 October 2007 (2007-10-31) * |
| 无: "承赤高速公路8合同T梁架设施工方案", 《HTTP://WENKU.BAIDU.COM/VIEW/23272C8683D049649B66583F.HTML》, 19 October 2011 (2011-10-19) * |
| 无: "预制梁安装专项安全技术方案", 《HTTP://WENKU.BAIDU.COM/VIEW/351322FA04A1B0717ED5DD01.HTML》, 1 December 2011 (2011-12-01) * |
| 王斌等: "预应力砼T形梁预制过程中的质量控制", 《江西建材》, no. 4, 31 December 2009 (2009-12-31) * |
Cited By (12)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103061266A (zh) * | 2013-01-11 | 2013-04-24 | 武船重型工程股份有限公司 | 一种在强潮涌海域上的水路运输架设钢箱梁的方法 |
| CN103061266B (zh) * | 2013-01-11 | 2015-01-14 | 武船重型工程股份有限公司 | 一种在强潮涌海域上的水路运输架设钢箱梁的方法 |
| CN103422441A (zh) * | 2013-08-13 | 2013-12-04 | 中铁六局集团有限公司 | Dj180架桥机架设大跨度公路箱梁过孔方法 |
| CN103422441B (zh) * | 2013-08-13 | 2015-10-28 | 中铁六局集团有限公司 | Dj180架桥机架设大跨度公路箱梁过孔方法 |
| CN106315151A (zh) * | 2016-09-14 | 2017-01-11 | 中交第航务工程局有限公司 | 一种小尺寸预制构件单车出运施工方法 |
| CN110644380A (zh) * | 2019-09-27 | 2020-01-03 | 河南理工大学 | 一种大跨径跨线桥加宽工程狭窄空间梁板安装方法 |
| CN111395821A (zh) * | 2020-03-23 | 2020-07-10 | 中电建十一局工程有限公司 | 一种复杂地形条件40mT梁预制场地布置及安装施工方法 |
| CN111395821B (zh) * | 2020-03-23 | 2021-08-24 | 中电建十一局工程有限公司 | 一种复杂地形条件40mT梁预制场地布置及安装施工方法 |
| CN111485498A (zh) * | 2020-04-22 | 2020-08-04 | 中交第三航务工程局有限公司 | 一种引桥折线段预制构件的安装工艺 |
| CN111485498B (zh) * | 2020-04-22 | 2022-03-29 | 中交三航局第二工程有限公司 | 一种引桥折线段预制构件的安装工艺 |
| CN114108466A (zh) * | 2021-10-12 | 2022-03-01 | 中铁广州工程局集团有限公司 | 一种节段梁预制场地及码头运载节段梁的方法 |
| CN114108466B (zh) * | 2021-10-12 | 2023-12-12 | 中铁广州工程局集团有限公司 | 一种节段梁预制场地及码头运载节段梁的方法 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101684639B (zh) | 钢构悬索桥施工的工艺方法及其专用轻型缆载吊机 | |
| CN102660923A (zh) | 外海潮间带预制40mT型梁安装施工工艺 | |
| CN104878693B (zh) | 桁架双梁式架桥机侧面喂梁架设结构、该架设结构的施工方法、以及基于该架设结构的侧面喂梁架设方法 | |
| CN103243663B (zh) | 利用架桥机拆除t型悬臂连续刚构箱梁的施工工艺 | |
| CN106978784B (zh) | 一种大跨径公路悬索桥拆除施工方法 | |
| CN102367650A (zh) | 一种钢管拱桥的施工方法 | |
| CN107499968A (zh) | 一种桥式起重机在浅水码头的卸船方法 | |
| CN102602712A (zh) | 一种钢箱梁节段滚装装船的方法 | |
| CN102514690B (zh) | 海上高空重载起升安装作业多功能双体风电工程船 | |
| CN105019357B (zh) | 一种拱桥敞口格构式钢梁上异形预制桥面板的安装方法 | |
| CN104828758A (zh) | 一种火电机组引风机结构支架整体移位装置及移位方法 | |
| CN102653938B (zh) | 下行式移动模架海上拆除施工工法 | |
| CN104018426A (zh) | 一种钢桁梁安装方法 | |
| CN110616638A (zh) | 悬索桥浅滩区钢箱梁无支架吊装方法 | |
| CN202557745U (zh) | 海上高空重载起升安装作业多功能双体风电工程船 | |
| CN216474531U (zh) | 一种下穿既有桥梁的水上钢箱梁提升滑移安装系统 | |
| CN208932821U (zh) | 一种架梁施工用高低腿龙门吊 | |
| CN208009277U (zh) | 一种陆域大吨位钢箱梁矮滑移安装系统 | |
| CN204919341U (zh) | 一种拱桥敞口格构式钢梁上异形预制桥面板的安装系统 | |
| CN202416191U (zh) | 下行式移动模架海上拆除主梁提升装置 | |
| CN202689016U (zh) | 深水桥墩双壁钢围堰施工用围堰拼装及提升平台 | |
| CN102381438B (zh) | 大型半潜船艏楼上建总段整体提拉安装方法 | |
| CN110540143A (zh) | 一种组合式吊臂托架装置 | |
| CN203682931U (zh) | 一种码头建设起重机 | |
| CN203947758U (zh) | 新型液压自动爬升卸料平台 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C05 | Deemed withdrawal (patent law before 1993) | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20120912 |