CN102635092B - 一种穿越复杂强透水层的组合式截渗墙结构的施工方法 - Google Patents

一种穿越复杂强透水层的组合式截渗墙结构的施工方法 Download PDF

Info

Publication number
CN102635092B
CN102635092B CN201210133429.9A CN201210133429A CN102635092B CN 102635092 B CN102635092 B CN 102635092B CN 201210133429 A CN201210133429 A CN 201210133429A CN 102635092 B CN102635092 B CN 102635092B
Authority
CN
China
Prior art keywords
construction
interior
axle
axle agitation
pile
Prior art date
Application number
CN201210133429.9A
Other languages
English (en)
Other versions
CN102635092A (zh
Inventor
李锐
卢永金
王路军
欧阳礼捷
Original Assignee
上海市水利工程设计研究院
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 上海市水利工程设计研究院 filed Critical 上海市水利工程设计研究院
Priority to CN201210133429.9A priority Critical patent/CN102635092B/zh
Publication of CN102635092A publication Critical patent/CN102635092A/zh
Application granted granted Critical
Publication of CN102635092B publication Critical patent/CN102635092B/zh

Links

Abstract

本发明公开的穿越复杂强透水层的组合式截渗墙结构,其特征在于,由外向内依次由内墙、中间墙和外墙组合而成,其中内墙和外墙采用三轴搅拌桩成墙,中间墙采用高压旋喷桩成墙。本发明的组合截渗墙结构:由三排桩组合成墙,该构造既解决了常规措施成墙质量差的问题,又解决了极端措施施工困难的问题,一般情况下本构造比极端渗控措施更经济,施工更安全。本发明还公开了该穿越复杂强透水层的组合式截渗墙结构的施工方法。

Description

一种穿越复杂强透水层的组合式截渗墙结构的施工方法
技术领域
[0001] 本发明涉及水利工程和土木工程的渗流控制垂直截渗墙结构和施工方法,特别涉及适用于临江(海)水域由抛石、土工织物充填管袋等复杂成分形成的强透水性、具有双向挡水要求的水库堤坝的垂直截渗防渗的穿越复杂强透水层的组合式截渗墙结构和施工方法。
背景技术
[0002] 临江(海)水域封闭构筑水库,堤(坝)往往为双向挡水,常会遇到强透水复杂夹层,在这种工况下,由于施工期存在水头差,常规的渗流控制垂直防渗墙工艺的成墙施工难度大、成墙质量差,后期在高水头差运行条件下,产生渗漏破坏的风险高、危害大,往往不得不采取一些极端的措施,造价很高。
发明内容
[0003] 本发明所要解决的技术问题之一在于针对具有复杂构造的强透水层渗流控制采用单一的防渗措施一般难以形成质量较好的封闭防渗体系而提供一种穿越复杂强透水层的组合式截渗墙结构。
[0004] 本发明所要解决的技术问题之一在于提供上述组合式截渗墙结构的施工方法。
[0005] 作为本发明第一方面的穿越复杂强透水层的组合式截渗墙结构,其由外向内依次由内墙、中间墙和外墙组合而成,其中内墙和外墙采用三轴搅拌桩成墙,中间墙采用高压旋喷桩成墙。
[0006] 在本发明的一个优选方案中,中间墙的厚度为0.5m。
[0007] 作为本发明第一方面的穿越复杂强透水层的组合式截渗墙结构施工方法,其由以下步骤组成:
[0008] I)外墙施工
[0009] 外墙采用三轴搅拌桩成墙,三轴搅拌桩采用Φ850@600πιπι布置套打并在透水夹层范围进行复搅,初步成墙阻水,改善下道工序的施工条件;
[0010] 2)内墙施工
[0011] 在外墙进行三轴搅拌桩成墙28天后,进行内墙施工,内墙施工采用施打三轴搅拌桩方法进行,三轴搅拌桩同样采用Φ850@600πιπι布置并套打成墙,施工时,内墙施工的三轴搅拌桩中心轴线与外墙施工的三轴搅拌桩中心轴线间距为1.35m,这样内墙与外墙之间形成净距为0.5m的槽体,槽体与内外水体进一步隔断,进一步改善下道工序的施工条件;
[0012] 3)中间墙施工
[0013] 在内墙进行三轴搅拌桩成墙28天后,进行中间墙施工,中间墙施工时施打高压旋喷桩,高压旋喷桩采用Φ600(Μ00πιπι布置并套打成墙,高压旋喷桩的辅助作用是对两排三轴桩墙体的粘结与补强,达到厚度要求,从而形成防渗质量好组合整体。
[0014] 由于采用了如上的技术方案,本发明的组合截渗墙结构:由三排桩组合成墙,该构造既解决了常规措施成墙质量差的问题,又解决了极端措施施工困难的问题,一般情况下本构造比极端渗控措施更经济,施工更安全。
附图说明
[0015] 图1为本发明穿越复杂强透水层的组合式截渗墙结构横剖面图。
具体实施方式
[0016] 以下结合附图和具体实施方式来进一步说明本发明。
[0017] 参见图1,图中给出的穿越复杂强透水层的组合式截渗墙结构,其由外向内依次由内墙10、中间墙20和外墙30组合而成,其中内墙10和外墙30采用三轴搅拌桩成墙,中间墙30采用高压旋喷桩成墙;中间墙的厚度为0.5m。
[0018] 该穿越复杂强透水层的组合式截渗墙结构施工方法,其由以下步骤组成:
[0019] I)外墙施工
[0020] 外墙采用三轴搅拌桩成墙,三轴搅拌桩采用Φ850@600πιπι布置套打并在透水夹层范围进行复搅,初步成墙阻水,改善下道工序的施工条件;
[0021] 2)内墙施工
[0022] 在外墙进行三轴搅拌桩成墙28天后,进行内墙施工,内墙施工采用施打三轴搅拌桩方法进行,三轴搅拌桩同样采用Φ850@600πιπι布置并套打成墙,施工时,内墙施工的三轴搅拌桩中心轴线与外墙施工的三轴搅拌桩中心轴线间距为1.35m,这样内墙与外墙之间形成净距为0.5m的槽体,槽体与内外水体进一步隔断,进一步改善下道工序的施工条件;
[0023] 3)中间墙施工
[0024] 在内墙进行三轴搅拌桩成墙28天后,进行中间墙施工,中间墙施工时施打高压旋喷桩,高压旋喷桩采用Φ600(Μ00πιπι布置并套打成墙,高压旋喷桩的辅助作用是对两排三轴桩墙体的粘结与补强,达到厚度要求,从而形成防渗质量好组合整体。

Claims (1)

1.一种穿越复杂强透水层的组合式截渗墙结构施工方法,其特征在于,由以下步骤组成: 1)外墙施工 外墙采用三轴搅拌桩成墙,三轴搅拌桩采用Φ850@600πιπι布置套打并在透水夹层范围进行复搅,初步成墙阻水,改善下道工序的施工条件; 2)内墙施工 在外墙进行三轴搅拌桩成墙28天后,进行内墙施工,内墙施工采用施打三轴搅拌桩方法进行,三轴搅拌桩同样采用Φ850@600πιπι布置并套打成墙,施工时,内墙施工的三轴搅拌桩中心轴线与外墙施工的三轴搅拌桩中心轴线间距为1.35m,这样内墙与外墙之间形成净距为0.5m的槽体,槽体与内外水体进一步隔断,进一步改善下道工序的施工条件; 3)中间墙施工 在内墙进行三轴搅拌桩成墙28天后,进行中间墙施工,中间墙施工时施打高压旋喷桩,高压旋喷桩采用Φ600(Μ00πιπι布置并套打成墙,高压旋喷桩的辅助作用是对两排三轴桩墙体的粘结与补强,达到厚度要求,从而形成防渗质量好组合整体。
CN201210133429.9A 2012-04-28 2012-04-28 一种穿越复杂强透水层的组合式截渗墙结构的施工方法 CN102635092B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210133429.9A CN102635092B (zh) 2012-04-28 2012-04-28 一种穿越复杂强透水层的组合式截渗墙结构的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210133429.9A CN102635092B (zh) 2012-04-28 2012-04-28 一种穿越复杂强透水层的组合式截渗墙结构的施工方法

Publications (2)

Publication Number Publication Date
CN102635092A CN102635092A (zh) 2012-08-15
CN102635092B true CN102635092B (zh) 2014-11-19

Family

ID=46619659

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210133429.9A CN102635092B (zh) 2012-04-28 2012-04-28 一种穿越复杂强透水层的组合式截渗墙结构的施工方法

Country Status (1)

Country Link
CN (1) CN102635092B (zh)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103850261A (zh) * 2012-12-06 2014-06-11 中国二十冶集团有限公司 入岩深基坑嵌岩止水帷幕施工方法
CN104695458A (zh) * 2013-12-04 2015-06-10 中国人民解放军总装备部特种工程技术安装总队 深搅旋喷组合桩止水帷幕施工方法
CN108005085B (zh) * 2017-12-04 2020-01-03 广东中南建设有限公司 基坑支护结构及其施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000144721A (ja) * 1998-11-05 2000-05-26 Takenaka Doboku Co Ltd 止水壁及びその施工方法
CN1342815A (zh) * 2000-09-14 2002-04-03 金怀娄 建筑工程地下基坑降水的施工方法
CN101435198A (zh) * 2008-12-23 2009-05-20 中铁二院工程集团有限责任公司 深基坑支挡加固防渗止水复合构造
KR20100123930A (ko) * 2009-05-18 2010-11-26 진혜경 에코지중파일벽
CN202627008U (zh) * 2012-04-28 2012-12-26 上海市水利工程设计研究院 一种穿越复杂强透水层的组合式截渗墙结构

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000144721A (ja) * 1998-11-05 2000-05-26 Takenaka Doboku Co Ltd 止水壁及びその施工方法
CN1342815A (zh) * 2000-09-14 2002-04-03 金怀娄 建筑工程地下基坑降水的施工方法
CN101435198A (zh) * 2008-12-23 2009-05-20 中铁二院工程集团有限责任公司 深基坑支挡加固防渗止水复合构造
KR20100123930A (ko) * 2009-05-18 2010-11-26 진혜경 에코지중파일벽
CN202627008U (zh) * 2012-04-28 2012-12-26 上海市水利工程设计研究院 一种穿越复杂强透水层的组合式截渗墙结构

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
深层搅拌桩与高压旋喷桩组合帷幕的应用;谢洋斌;《山西建筑》;20120331;第38卷(第8期);第73-74页 *
谢洋斌.深层搅拌桩与高压旋喷桩组合帷幕的应用.《山西建筑》.2012,第38卷(第8期), *

Also Published As

Publication number Publication date
CN102635092A (zh) 2012-08-15

Similar Documents

Publication Publication Date Title
CN103074898B (zh) 多排桩基坑支护结构及其施工方法
CN103410161B (zh) 斜向控制注浆钢锚管框架及其施工方法
CN105804758B (zh) 浅覆土大断面小间距的矩形顶管上跨地铁隧道施工方法
CN101666231B (zh) 一种盾构机进仓方法
CN101781889B (zh) 一种h型止水帷幕施工工艺
CN103967036A (zh) 用于海上风电的桩与套筒灌浆连接结构及其施工方法
CN103696779B (zh) 盾构压气作业用掌子面护壁泥膜施工工艺
CN102080554B (zh) 盾构进洞防水气囊
CN101845944B (zh) 一种定点密封瓦斯抽采钻孔的方法
CN100387785C (zh) 水力插板及使用方法
CN103075127A (zh) 一种柔性充填材料钻孔封孔装置及方法
CN104018471B (zh) 拦挡溢流坝结构
CN105442862B (zh) 一种混凝土裂缝渗漏水堵漏加固修复方法
CN101525881B (zh) 岩溶地层桩孔护壁构造及桩孔施工方法
CN105986836B (zh) 一种单线铁路隧道基底防排水加强系统
CN102619227B (zh) 海上风力发电机组单管桩基础灌浆装置、总成及灌浆方法
US20140079485A1 (en) Method for Preventing Shield Casing Catching Due to Too Large Frictional Resistance in Earth Pressure Balance Shield Machine
CN103924987B (zh) 一种smw工法桩盾构洞门防渗水结构及其施工方法
CN202689008U (zh) 一种双排预制高强混凝土薄壁钢管桩基坑支护结构
CN105133620B (zh) 局部流塑状淤泥质土体坑中坑支护结构及其施工方法
CN204253056U (zh) 一种盾构机进出洞洞口加固结构
CN102628352B (zh) 一种多段式定点水力压裂方法
CN203668969U (zh) 地下连续墙加固防水结构
CN103806449B (zh) 一种基坑支护结构
CN102373712A (zh) 用于离岸的风能设备的基底结构(夹层式基底结构)

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant