CN102602794B - Special tool for lifting bushing - Google Patents

Special tool for lifting bushing Download PDF

Info

Publication number
CN102602794B
CN102602794B CN201210086593.9A CN201210086593A CN102602794B CN 102602794 B CN102602794 B CN 102602794B CN 201210086593 A CN201210086593 A CN 201210086593A CN 102602794 B CN102602794 B CN 102602794B
Authority
CN
China
Prior art keywords
casing
rubber
bushing
hoisting
special tool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210086593.9A
Other languages
Chinese (zh)
Other versions
CN102602794A (en
Inventor
叶治坤
侯向宏
张登坤
杨城
王朝阳
王建杰
于汶琦
李洪彬
吕润正
刘勇
柴金城
刘�英
沈荣顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Hebei Electric Power Co Ltd
Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd
State Grid Corp of China
Original Assignee
State Grid Hebei Electric Power Co Ltd
Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd
State Grid Corp of China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Hebei Electric Power Co Ltd, Cangzhou Power Supply Co of State Grid Hebei Electric Power Co Ltd, State Grid Corp of China filed Critical State Grid Hebei Electric Power Co Ltd
Priority to CN201210086593.9A priority Critical patent/CN102602794B/en
Publication of CN102602794A publication Critical patent/CN102602794A/en
Application granted granted Critical
Publication of CN102602794B publication Critical patent/CN102602794B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The invention relates to a special tool for lifting a bushing, which is used for realizing stable lifting of a transformer bushing or a CT (Current Transformer). The special tool comprises a tackle and a fixed plate, wherein the tackle is assembled at the bottom part of the bushing; the fixed plate is arranged at the top part of the bushing; and a lifting rope of the bushing penetrates through the fixed plate and then is connected with a flange lifting ring of the bushing. The special tool has the advantages that the structure is simple, the operation is convenient, not only can the bushing or CT be prevented from being collided and impacted in the lifting process, but also the operation time is shortened, the number of operators is reduced, and the working efficiency is improved.

Description

套管吊装专用工具Special tools for casing hoisting

技术领域 technical field

本发明涉及一种电力系统套管吊装专用工具,属起重技术领域。 The invention relates to a special tool for casing pipe hoisting in a power system, which belongs to the technical field of hoisting.

背景技术 Background technique

电力系统的变压器安装及维护时,经常会遇到变压器套管的拆装问题,一般套管的拆装是通过吊装设备的配合完成的。在油纸电容式套管由水平放置状态起吊至竖立状态过程中,位于套管底部的均压球受力很大,为了防止均压球损伤和控制套管正常吊起,需要用粗绳环绕均压球上部,人为施力使均压球脱离包装箱箱底,由于人为施力与吊车施力的配合难以默契,使得套管起吊时均压球由于受力不均而被损坏的现象时有发生,在CT的吊装过程中也存在相同的问题;另外上述吊装方法还存在着作业时间长、需要操作人员数量多等缺陷。 During the installation and maintenance of transformers in power systems, disassembly and assembly of transformer bushings are often encountered. Generally, the disassembly and assembly of bushings is completed through the cooperation of hoisting equipment. When the oil-paper capacitive bushing is hoisted from a horizontal state to an upright state, the pressure equalizing ball at the bottom of the bushing is subjected to a large force. On the upper part of the pressure ball, artificial force is applied to make the pressure equalizing ball break away from the bottom of the packing box. Since the cooperation between the artificial force and the force of the crane is difficult to tacitly cooperate, the phenomenon that the pressure equalizing ball is damaged due to uneven force when the casing is hoisted occurs from time to time. , the same problem also exists in the hoisting process of CT; in addition, the above-mentioned hoisting method also has defects such as long operation time and a large number of operators.

发明内容 Contents of the invention

本发明的目的在于针对现有技术之弊端,提供一种结构简单、操作方便、能有效避免套管吊装过程中零部件损伤现象发生的套管吊装专用工具。 The object of the present invention is to aim at the disadvantages of the prior art, and provide a special tool for casing hoisting which is simple in structure, easy to operate, and can effectively avoid damage to components during casing hoisting.

本发明所述问题是以下述技术方案实现的: Problem described in the present invention is realized with following technical scheme:

一种套管吊装专用工具,它包括滑车和固定板,所述滑车与套管底部配装,所述固定板安装在套管顶部,套管吊绳穿过固定板后与套管法兰吊环连接。 A special tool for casing hoisting, which includes a pulley and a fixing plate, the pulley is fitted with the bottom of the casing, the fixing plate is installed on the top of the casing, the casing lifting rope passes through the fixing plate and connects with the casing flange ring connect.

上述套管吊装专用工具,所述滑车由套管定位柱、支撑架和两个橡塑轮组成,所述套管定位柱一端固定在支撑架上,另一端穿入套管尾部的铜导管内,所述支撑架包括矩形结构的支撑板和固定在支撑板下面的橡塑轮安装座,在支撑板的上面设有缓冲胶皮,所述橡塑轮通过轮轴销固定在橡塑轮安装座上。 The above special tool for casing hoisting, the trolley is composed of a casing positioning column, a support frame and two rubber and plastic wheels, one end of the casing positioning column is fixed on the support frame, and the other end penetrates into the copper conduit at the tail of the casing , the support frame includes a support plate with a rectangular structure and a rubber-plastic wheel mounting seat fixed under the support plate, a buffer rubber is arranged on the support plate, and the rubber-plastic wheel is fixed on the rubber-plastic wheel mounting seat through a wheel axle pin .

上述套管吊装专用工具,所述固定板为菱形板结构,在其中心位置设有与套管顶部匹配的装配孔,在其两侧分别设置供吊绳穿过的吊装孔。 In the above-mentioned special tool for hoisting casing, the fixing plate is a diamond-shaped plate structure, and an assembly hole matching the top of the casing is provided at its center, and hoisting holes for the sling to pass are respectively arranged on both sides thereof.

本发明通过固定板上的吊装孔限定了吊绳在起吊过程中施加于套管法兰吊环上拉力的方向;通过滑车橡塑轮的滚动配合套管由水平放置状态至竖立的空间旋转动作;在滑车的支撑板上设置了缓冲胶皮,并将套管定位柱插入套管尾部的铜导管内;以上措施充分保证了套管在吊装过程中受力平稳,不发生磕碰等异常现象,使套管(或CT)安全就位。本发明结构简单,操作方便,不仅能保证套管(或CT)的平稳吊装,而且缩短了作业时间,减少了操作人员数量(只需两人即可完成套管吊装),提高了工作效率。 In the present invention, the direction of the pulling force applied by the sling to the casing flange ring during the lifting process is defined by the hoisting hole on the fixed plate; the rolling action of the rubber and plastic wheel of the pulley cooperates with the space rotation of the casing from a horizontally placed state to an upright position; The buffer rubber is set on the support plate of the block, and the casing positioning column is inserted into the copper conduit at the end of the casing; the above measures fully ensure that the casing is under stable force during hoisting, and no abnormal phenomena such as bumps occur, so that the casing Tube (or CT) securely in place. The invention is simple in structure and easy to operate, not only can ensure the stable hoisting of the casing (or CT), but also shortens the working time, reduces the number of operators (only two people can complete the casing hoisting), and improves the work efficiency.

附图说明 Description of drawings

下面结合附图对本发明作进一步说明。 The present invention will be further described below in conjunction with accompanying drawing.

图1是滑车结构图; Fig. 1 is a block diagram;

图2是图1的A向视图; Fig. 2 is the A direction view of Fig. 1;

图3是固定板结构图; Fig. 3 is a fixed plate structure diagram;

图4是套管起吊时本发明工作状态示意图; Fig. 4 is a schematic diagram of the working state of the present invention when the casing is hoisted;

图5是套管处于转动某一瞬间本发明的工作状态示意图; Fig. 5 is a schematic diagram of the working state of the present invention at a certain moment when the casing is in rotation;

图6是套管处于竖立位置时本发明工作状态示意图。 Fig. 6 is a schematic diagram of the working state of the present invention when the sleeve is in an upright position.

图中各标号为:1、滑车,1-1、套管定位柱,1-2、支撑板,1-3、橡塑轮,1-4、橡塑轮安装座,1-5、缓冲胶皮,2、固定板,2-1、装配孔,2-2、吊装孔,3、套管,3-1、套管法兰吊环,4、吊绳。 Each label in the figure is: 1, pulley, 1-1, casing positioning column, 1-2, support plate, 1-3, rubber and plastic wheel, 1-4, rubber and plastic wheel mounting seat, 1-5, buffer rubber , 2, fixed plate, 2-1, assembly hole, 2-2, hoisting hole, 3, casing, 3-1, casing flange ring, 4, lifting rope.

具体实施方式 Detailed ways

参看图 1、图 2、图3、图4,本发明构成中包括滑车1和固定板2,所述滑车1与套管3底部配装,所述固定板2安装在套管3顶部,套管吊绳4穿过固定板2后与套管法兰吊环3-1连接。 Referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, the present invention comprises a tackle 1 and a fixed plate 2, the tackle 1 is assembled with the bottom of the casing 3, the fixed plate 2 is installed on the top of the casing 3, and the sleeve The pipe lifting rope 4 passes through the fixed plate 2 and is connected with the casing flange lifting ring 3-1.

参看图 1、图2,本发明构成中的滑车1由套管定位柱1-1、支撑架和两个橡塑轮1-3组成,所述套管定位柱1-1一端固定在支撑架上,另一端穿入套管尾部的铜导管内,所述支撑架包括矩形结构的支撑板1-2和固定在支撑板1-2下面的橡塑轮安装座1-4,在支撑板1-2的上面设有缓冲胶皮1-5,所述橡塑轮1-3通过轮轴销固定在橡塑轮安装座1-4上。 Referring to Fig. 1 and Fig. 2, the tackle 1 in the composition of the present invention is composed of a casing positioning column 1-1, a support frame and two rubber and plastic wheels 1-3, and one end of the casing positioning column 1-1 is fixed on the support frame The other end penetrates into the copper conduit at the end of the casing. The support frame includes a support plate 1-2 of rectangular structure and a rubber and plastic wheel mounting seat 1-4 fixed under the support plate 1-2. On the support plate 1 -2 is provided with a buffer rubber 1-5, and the rubber and plastic wheel 1-3 is fixed on the rubber and plastic wheel mounting seat 1-4 by the axle pin.

参看图3,本发明构成中的固定板2为菱形板结构,在其中心位置设有与套管顶部匹配的装配孔2-1,在其两侧分别设置供吊绳4穿过的吊装孔2-2。 Referring to Fig. 3, the fixing plate 2 in the composition of the present invention is a diamond-shaped plate structure, and an assembly hole 2-1 matching the top of the casing is provided at its central position, and hoisting holes for the sling 4 to pass through are respectively provided on both sides thereof 2-2.

参看图 1、图 2、图3、图4、图5、图6,并结合具体实施例说明本发明的工作过程及工作原理:套管3起吊前,将固定板2通过装配孔2-1及螺纹连接组合件安装于套管顶部的接线座上,吊绳4穿过固定板两端的吊装孔2-2与套管法兰吊环3-1连接。在套管3的尾部安装滑车1,滑车由一根长度20cm,直径3吋的金属管材质的套管定位柱1-1与两个橡塑轮组成,将套管定位柱1-1插入套管尾部的铜导管内。起吊时,套管3的部分重量压在滑车1上,滑车1平稳转动防止套管3受力突变;固定板上的吊装孔2-2限定了吊绳4在起吊过程中施加于套管法兰起吊环3-1上拉力的方向;在滑车的支撑板上设置的缓冲胶皮1-5,减轻了吊装过程中套管尾部均压球受到的冲击。以上措施充分保证了套管3在吊装过程中受力平稳,不发生磕碰等异常现象,使套管(同样适用于CT)安全就位。实现了套管3平稳吊起。 Refer to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, and illustrate the working process and working principle of the present invention in conjunction with specific embodiments: before the casing 3 is hoisted, the fixing plate 2 is passed through the assembly hole 2-1 And the threaded connection assembly is installed on the wiring seat at the top of the casing, and the lifting rope 4 passes through the lifting holes 2-2 at the two ends of the fixed plate to connect with the casing flange ring 3-1. Install the block 1 at the tail of the casing 3, the block is composed of a casing positioning post 1-1 made of a metal pipe with a length of 20 cm and a diameter of 3 inches and two rubber and plastic wheels, insert the casing positioning post 1-1 into the casing Inside the copper conduit at the end of the tube. When hoisting, part of the weight of the casing 3 is pressed on the block 1, and the block 1 rotates smoothly to prevent sudden changes in force on the casing 3; the hoisting hole 2-2 on the fixed plate limits the lifting rope 4 applied to the casing during the lifting process. Lan lifts the direction of the pulling force on the lifting ring 3-1; the buffer rubber 1-5 arranged on the support plate of the tackle reduces the impact on the pressure equalizing ball at the tail of the casing during the hoisting process. The above measures fully ensure that the bushing 3 is subjected to a stable force during the hoisting process without bumping and other abnormal phenomena, so that the bushing (also applicable to CT) is safely in place. The casing pipe 3 is smoothly hoisted.

Claims (2)

1.一种套管吊装专用工具,其特征是,它包括滑车(1)和固定板(2),所述滑车(1)与套管(3)底部配装,所述固定板(2)安装在套管(3)顶部,套管吊绳(4)穿过固定板(2)后与套管法兰吊环(3-1)连接; 1. A special tool for casing hoisting, characterized in that it includes a pulley (1) and a fixed plate (2), the pulley (1) is fitted with the bottom of the casing (3), and the fixed plate (2) Installed on the top of the casing (3), the casing lifting rope (4) passes through the fixing plate (2) and connects with the casing flange lifting ring (3-1); 所述滑车(1)由套管定位柱(1-1)、支撑架和两个橡塑轮(1-3)组成,所述套管定位柱(1-1)一端固定在支撑架上,另一端穿入套管尾部的铜导管内,所述支撑架包括矩形结构的支撑板(1-2)和固定在支撑板(1-2)下面的橡塑轮安装座(1-4),在支撑板(1-2)的上面设有缓冲胶皮(1-5),所述橡塑轮(1-3)通过轮轴销固定在橡塑轮安装座(1-4)上。 The trolley (1) is composed of a casing positioning column (1-1), a support frame and two rubber and plastic wheels (1-3), and one end of the casing positioning column (1-1) is fixed on the support frame, The other end penetrates into the copper conduit at the end of the casing, and the support frame includes a support plate (1-2) with a rectangular structure and a rubber and plastic wheel mounting seat (1-4) fixed under the support plate (1-2), A buffer rubber (1-5) is arranged on the support plate (1-2), and the rubber-plastic wheel (1-3) is fixed on the rubber-plastic wheel mounting seat (1-4) through a wheel shaft pin. 2.根据权利要求1所述的一种套管吊装专用工具,其特征是,所述固定板(2)为菱形板结构,在其中心位置设有与套管顶部匹配的装配孔(2-1),在其两侧分别设置供吊绳(4)穿过的吊装孔(2-2)。 2. A special tool for casing hoisting according to claim 1, characterized in that the fixing plate (2) is a diamond-shaped plate structure, and an assembly hole (2- 1), the hoisting holes (2-2) for the slings (4) to pass through are respectively arranged on both sides thereof.
CN201210086593.9A 2012-03-29 2012-03-29 Special tool for lifting bushing Expired - Fee Related CN102602794B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210086593.9A CN102602794B (en) 2012-03-29 2012-03-29 Special tool for lifting bushing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210086593.9A CN102602794B (en) 2012-03-29 2012-03-29 Special tool for lifting bushing

Publications (2)

Publication Number Publication Date
CN102602794A CN102602794A (en) 2012-07-25
CN102602794B true CN102602794B (en) 2014-02-12

Family

ID=46520673

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210086593.9A Expired - Fee Related CN102602794B (en) 2012-03-29 2012-03-29 Special tool for lifting bushing

Country Status (1)

Country Link
CN (1) CN102602794B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103072893B (en) * 2013-01-17 2015-03-18 中国核工业二三建设有限公司 Tool and method for overturning vertical equipment in nuclear power plant
CN103287977B (en) * 2013-06-04 2015-12-23 国家电网公司 A kind of capacitance graded bushing tail defense device
CN103303794A (en) * 2013-06-24 2013-09-18 保定天威保变电气股份有限公司 Auxiliary standing tool and standing method for cable-through bushing
CN104961044B (en) * 2015-05-29 2017-01-18 云南省送变电工程公司 Method for installing or removing high voltage bushing by using C-shaped hoseclamp cross binding strap

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60122682A (en) * 1983-12-08 1985-07-01 三菱電機株式会社 Hanger for bushing for electrical apparatus
DE29921479U1 (en) * 1999-09-15 2001-02-08 August Steingass & Sohn GmbH & Co, 42653 Solingen Electromagnetic hoist with an electromagnet
JP2001187684A (en) * 1999-12-28 2001-07-10 Hitachi Plant Eng & Constr Co Ltd Suspension method and hanging bracket for long objects
JP2007276975A (en) * 2006-04-10 2007-10-25 Chugoku Electric Power Co Inc:The Suspension assisting tool
CN202138946U (en) * 2011-03-23 2012-02-08 青海送变电工程公司 Special hoisting tool for transformer sleeves
CN202594599U (en) * 2012-03-29 2012-12-12 沧州供电公司 Tool special for hoisting casing

Also Published As

Publication number Publication date
CN102602794A (en) 2012-07-25

Similar Documents

Publication Publication Date Title
CN203201216U (en) Vertical rod centralizer
CN103009174B (en) The axial slip of large-sized rotor tipping arrangement, radially location and clamping device
CN103730231B (en) A kind of head cover of transformer lowering or hoisting gear
CN205159901U (en) Special dolly is installed and removed to high -order earth connection
CN102992203B (en) Simple hoisting device for steel structure bridge installation
CN203998580U (en) Indoor GIS equipment transport carriage
CN202429945U (en) Hoisting device for power supply facility
CN104129730B (en) A kind of transformer and JP cabinet dismounting suspender
CN206051382U (en) A kind of electric power facility hanging apparatus
CN204549923U (en) The mobile mast-up of a kind of chemical equipment overhaul
CN204111235U (en) A kind of voltage transformer and JP cabinet dismounting special purpose device
CN102602794A (en) Special tool for lifting bushing
CN205543906U (en) Cubical switchboard hoisting accessory
CN202594599U (en) Tool special for hoisting casing
CN103556837B (en) A kind of method realizing steel column at annex place and install
CN106429869A (en) Horizontal heavy equipment aerial mounting device and mounting method
CN106081901A (en) A kind of novel SMD hoisting trolley
CN207345848U (en) A kind of more changing device and replacement system
CN105366559A (en) Small hoisting machine fixed on channel steel framework
CN105827071B (en) The method for dismounting of magnet pole of rotor of hydraulic generator key and provision for disengagement
CN202131996U (en) Steel wire rope traction device of rotary drilling machine
CN203284092U (en) Transformer substation insulator lifting frame
CN205016899U (en) Unsettled transformer mounting bracket
CN203939815U (en) Be used in the suspension centre fixing device on emergency first-aid repair tower
CN103738860A (en) Small interval dual-purpose hoisting device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP. HEBEI ELECTRIC POWER CORP

Effective date: 20121008

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121008

Address after: 061001 No. 21 West Yongji Road, Hebei, Cangzhou

Applicant after: Cangzhou Power Supply Co.

Applicant after: State Grid Corporation of China

Applicant after: Hebei Electric Power Corp.

Address before: 061001 No. 21 West Yongji Road, Hebei, Cangzhou

Applicant before: Cangzhou Power Supply Co.

C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA

Free format text: FORMER OWNER: CANGZHOU POWER SUPPLY CO., LTD.

Effective date: 20140326

Owner name: CANGZHOU POWER SUPPLY BRANCH COMPANY, STATE GRID H

Free format text: FORMER OWNER: STATE GRID CORPORATION OF CHINA HEBEI ELECTRIC POWER CORPORATION

Effective date: 20140326

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 061001 CANGZHOU, HEBEI PROVINCE TO: 100031 DONGCHENG, BEIJING

TR01 Transfer of patent right

Effective date of registration: 20140326

Address after: 100031 West Chang'an Avenue, Beijing, No. 86

Patentee after: State Grid Corporation of China

Patentee after: STATE GRID HEBEI ELECTRIC POWER COMPANY, CANGZHOU BRANCH

Patentee after: STATE GRID HEBEI ELECTRIC POWER Co.

Address before: 061001 No. 21 West Yongji Road, Hebei, Cangzhou

Patentee before: Cangzhou Power Supply Co.

Patentee before: State Grid Corporation of China

Patentee before: Hebei Electric Power Corp.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140212

CF01 Termination of patent right due to non-payment of annual fee