CN102545757A - 一种应用于供暖负载的离网型风电机组的功率控制方法 - Google Patents

一种应用于供暖负载的离网型风电机组的功率控制方法 Download PDF

Info

Publication number
CN102545757A
CN102545757A CN2011104134482A CN201110413448A CN102545757A CN 102545757 A CN102545757 A CN 102545757A CN 2011104134482 A CN2011104134482 A CN 2011104134482A CN 201110413448 A CN201110413448 A CN 201110413448A CN 102545757 A CN102545757 A CN 102545757A
Authority
CN
China
Prior art keywords
stator voltage
generator
voltage
current transformer
control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011104134482A
Other languages
English (en)
Other versions
CN102545757B (zh
Inventor
林资旭
赵栋利
李海东
谷海涛
赵斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Baoding Corona Control Equipment Co., Ltd.
Original Assignee
Beijing Corona Science and Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Corona Science and Technology Co Ltd filed Critical Beijing Corona Science and Technology Co Ltd
Priority to CN201110413448.2A priority Critical patent/CN102545757B/zh
Publication of CN102545757A publication Critical patent/CN102545757A/zh
Application granted granted Critical
Publication of CN102545757B publication Critical patent/CN102545757B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Control Of Eletrric Generators (AREA)

Abstract

一种应用于供暖负载的离网型风电机组的功率控制方法。当主控发送启动指令后,变流器采集三相定子电压,通过定子电压计算出电励磁同步发电机转速。依据风电机组最佳转速功率曲线,构造出转速一定子电压有效值曲线,根据所采用的定子电压闭环的控制策略,调节变流器输出励磁电流的大小,在一定转速下维持发电机定子电压有效值达到给定。定子电压经变流器内的二极管整流桥整流后转换为直流电压,在直流端连接固定电阻负载,通过电阻消耗功率实现加热的功能。本发明按照最佳叶尖速比控制,实现在固定负载情况下机组效率最高,将风电机组的功率控制转换为对同步发电机的励磁控制,简化了变流器的设计。

Description

一种应用于供暖负载的离网型风电机组的功率控制方法
技术领域
本发明涉及一种离网型风电机组的功率控制方法。
背景技术
大功率风力发电有并网型与离网型两种机组。并网型风电机组多采用变速恒频风电机组,这种机组发电机转速可以在一个较大范围内运行,实现风电机组的最佳叶尖速比控制。该机组通过变流器实现在变速情况下馈入电网电能的恒频。变流器主要起到变频与能量管理的功能。在离网型机组中,由于输出电能不馈入电网,其能量直接加在负载之上,如何通过变流器的控制实现风电机组的最佳叶尖速比控制,最大限度的吸收风能是设计的重点。
由于我国独特的地理条件和丰富的风能资源,因此离网型风力发电系统在我国有广阔的发展前景,这对我国的环保事业、能源结构的调整,减少对不可再生能源的依赖有很大的意义。随着风电机组制造成本的降低,发电效率的提高,离网型风力发电发展前景十分巨大,应用领域更加广大。
采用电励磁同步发电机的全功率变流器机组在目前风电机组中得到了广泛应用。电励磁同步发电机可以通过调节励磁电流来调节定子侧电压输出幅值,控制较为灵活,特别适用于为固定阻值的供暖负载。
目前的现有技术对离网型风电机组的能量管理多体现在通过蓄电池实现,所能实现的机组的功率等级较小。
发明内容
本发明的目的是克服现有技术的缺点,提出一种适用于大功率风电机组的功率控制方法。本发明不需要采用蓄电池,通过变流器对定子电压的控制,实现风电机组的最佳叶尖速比控制,保持机组以最大的效率输出功率,对于风电机组,其功率外特性与并网型风电机组一致。
本发明采用电压传感器采集风电机组电励磁同步发电机定子电压,由变流器采用软件锁相环的方法计算出定子电压频率和有效值,并根据同步发电机极对数计算出实际发电机转速;变流器控制器根据风电机组最佳转速-功率曲线,构造出发电机转速-定子电压有效值曲线。本发明控制采用定子电压闭环的控制策略,通过调节变流器输出励磁电流的大小,在转速运行范围内控制发电机定子电压依据转速-定子电压有效值曲线变化。发电机定子电压经变流器内的二极管整流后转换为直流,在变流器的直流端连接固定电阻负载,通过固定电阻负载消耗功率实现供暖加热的功能。本发明中的功率控制方法包括以下步骤:
(1)当接收到风电机组主控启动指令后,变流器控制器通过电压互感器采集发电机定子电压,由变流器控制器计算出定子电压角速度ω,定子电压有效值Um,并根据发电机极对数p,依据公式(2)计算发电机转速n;
n=60ω/2pπ   (2)
(2)根据给定的转速-功率(n-P)曲线,由发电机转速n、机组功率P、直流侧电阻R,依据式(3)构造转速-定子电压有效值曲线;依据所述的转速-定子电压有效值曲线,设定发电机定子电压有效值给定Usref;
U = P * R / 1.35 - - - ( 3 )
(3)采用定子电压闭环的控制策略,将Usref减Um,所得差值经PI调节器后输出发电机励磁电流给定;将励磁电流给定减实际励磁电流Ire,所得差值经PI调节器后输出调试电压,该调试电压与控制三角波进行比较,输出PWM调制波,控制变流器电励磁单元绝缘栅双极晶体管IGBT的导通和关断,从而控制发电机定子电压达到给定值Usref;
(4)所述的定子电压经变流器的二极管整流桥后转换为直流电压,变流器直流电压幅值为定子电压幅值的1.35倍;
(5)将变流器直流侧电压加载在直流负载上,实现功率输出。
本发明按照最佳叶尖速比控制,实现在固定直流负载情况下机组效率最高,将风电机组的功率控制转换为对同步发电机的励磁控制,简化了变流器的设计。
附图说明
图1离网型风电机组系统结构图;
图2离网型风电机组变流器拓扑图;
图3离网型风电机组变流器功率控制流程图;
图4离网型风电机组变流器软件锁相环。
具体实施方式
下面结合附图和具体实施方式进一步说明本发明。
图1所示为本发明的应用对象离网型电励磁同步风力发电机组。如图1所示,风吹动叶轮旋转,叶轮带动电励磁同步发电机旋转。当风速达到启动风速后,由主控系统006向变流器003发送启动指令,变流器控制发电机输出电能,供给用户直流负载。当风速超过额定风速后,变桨距系统005调节叶片桨距角,屏蔽掉多余的风能。
图2所示为本发明实现功率控制的变流器硬件载体。如图2所示,发电机定子输出经交流开关14后连接于变流器二极管整流桥011,在整流桥直流侧并联薄膜电容,稳定整流桥直流侧电压,整流桥直流侧输出加直流负载电阻。和整流桥连接的直流开关017作为保护使用,正常情况下闭合,当需要对直流负载进行检修时手动断开。
外部市电230V电源经UPS后,通过隔离变压器016连接于变流器电励磁单元012。
变流器控制器013采集发电机两个定子线电压,通过软件算法计算出定子电压频率及有效值,根据频率计算出发电机转速,依据转速-电压曲线得到发电机定子电压有效值给定;变流器控制器经过闭环调节算法后输出PWM脉宽波,控制变流器电励磁单元012中IGBT015的导通关断,从而调节励磁电流输出大小,进而控制发电机输出定子电压达到给定。
本发明的风电机组功率控制方法当接收到主控启动指令后执行,算法流程图如图3所示。变流器控制器基于TI公司DSP设计,具有高速运算功能。
步骤1:变流器控制器采集发电机定子电压。通过图4所示离网型风电机组变流器软件锁相环计算定子电压有效值Um及角频率ω。
步骤2:变流器根据发电机转速根据转速-电压曲线计算定子电压给定Usref。
步骤3:定子电压给定Usref与步骤1检查到的定子电压有效值Um做差,经PI调节器后输出励磁电流给定。
步骤4:励磁电流给定与实际检测到的励磁电流Ire做差,其偏差经PI调节器后输出调制电压,经三角波比较后输出PMW。
步骤5:PWM控制变流器电励磁单元IGBT斩波,控制实际励磁电流达到给定,从而调节发电机定子电压达到给定。
步骤6:定子输出能量经二极管整流桥后供给直流负载。
当风速增加,风电机组输入功率增加时,发电机转速升高,依据转速电压曲线,发电机输出定子电压有效值升高,直流侧能量增加,重新达到功率平衡。

Claims (2)

1.一种应用于供暖负载的离网型风电机组的功率控制方法,其特征在于,所述的功率控制方法为:根据定子电压传感器采集到的三相定子电压,由变流器计算出定子电压频率,根据发电机极对数计算出发电机转速;所述变流器根据风电机组最佳转速-功率曲线,构造出发电机转速-定子电压有效值曲线,然后采用定子电压闭环的控制策略,调节所述变流器输出励磁电流的大小,在转速运行范围内控制发电机定子电压依据所述的转速-定子电压有效值曲线变化;发电机定子电压经变流器内的二极管整流后转换为直流电压,在变流器的直流端连接固定电阻负载,通过固定电阻负载消耗功率实现供暖加热功能。
2.按照权利要求1所述的离网型风电机组的功率控制方法,其特征在于,所述的功率控制方法包括以下步骤:
(1)当接收到风电机组主控启动指令后,变流器控制器通过电压互感器采集发电机定子电压,由变流器控制器计算出定子电压角速度ω,定子电压有效值Um,并根据发电机极对数p,依据公式(1)计算发电机转速n;
n=60ω/2Pπ       (1)
(2)依据所述的转速-定子电压有效值曲线,设定发电机定子电压有效值给定;
(3)采用定子电压闭环控制策略;将定子电压给定减步骤(1)中的定子电压有效值Um,所得差值经PI调节器后输出发电机励磁电流给定;将励磁电流给定减实际励磁电流,所得差值经PI调节器后输出调试电压,所述的调试电压与控制三角波进行比较,输出PWM波形,控制变流器电励磁单元的绝缘栅双极晶体管IGBT的导通和关断,从而控制发电机定子电压达到给定值;
(4)所述的定子电压经变流器的二极管整流桥整流后转换为直流电压,变流器直流电压幅值为定子电压幅值的1.35倍;
(5)将变流器直流侧电压加载在所述的固定电阻负载上,实现功率输出。
CN201110413448.2A 2011-12-10 2011-12-10 一种应用于供暖负载的离网型风电机组的功率控制方法 Expired - Fee Related CN102545757B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110413448.2A CN102545757B (zh) 2011-12-10 2011-12-10 一种应用于供暖负载的离网型风电机组的功率控制方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110413448.2A CN102545757B (zh) 2011-12-10 2011-12-10 一种应用于供暖负载的离网型风电机组的功率控制方法

Publications (2)

Publication Number Publication Date
CN102545757A true CN102545757A (zh) 2012-07-04
CN102545757B CN102545757B (zh) 2014-06-18

Family

ID=46351860

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110413448.2A Expired - Fee Related CN102545757B (zh) 2011-12-10 2011-12-10 一种应用于供暖负载的离网型风电机组的功率控制方法

Country Status (1)

Country Link
CN (1) CN102545757B (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108880353A (zh) * 2018-07-05 2018-11-23 国家电网有限公司 基于电压源型静止变频器的大型同步调相机起动控制方法
CN110114970A (zh) * 2016-09-28 2019-08-09 艾能控制技术有限公司 用于对外部负载供电的离网电力产生系统
CN111066237A (zh) * 2017-08-29 2020-04-24 乌本产权有限公司 用于控制风能设施的多相他励同步发电机的方法
CN114263528A (zh) * 2021-11-25 2022-04-01 潍柴动力股份有限公司 一种去除发电机组中凝露的系统、方法及发电机组

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01174299A (ja) * 1987-12-28 1989-07-10 Mitsubishi Electric Corp 交流励磁同期機の制御方式
JPH11346499A (ja) * 1998-06-01 1999-12-14 Meidensha Corp ブラシレス同期発電設備の回転整流器の故障検出装置
CN101136582A (zh) * 2007-09-03 2008-03-05 中国科学院电工研究所 一种全功率变流器直流侧卸荷电路的控制方法
CN201039068Y (zh) * 2007-05-15 2008-03-19 天津市新源电气科技有限公司 变速恒频绕线型无刷双馈发电机控制装置
CN102255596A (zh) * 2011-07-15 2011-11-23 广东工业大学 一种离网型双馈风力发电系统及其最大风能捕获方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01174299A (ja) * 1987-12-28 1989-07-10 Mitsubishi Electric Corp 交流励磁同期機の制御方式
JPH11346499A (ja) * 1998-06-01 1999-12-14 Meidensha Corp ブラシレス同期発電設備の回転整流器の故障検出装置
CN201039068Y (zh) * 2007-05-15 2008-03-19 天津市新源电气科技有限公司 变速恒频绕线型无刷双馈发电机控制装置
CN101136582A (zh) * 2007-09-03 2008-03-05 中国科学院电工研究所 一种全功率变流器直流侧卸荷电路的控制方法
CN102255596A (zh) * 2011-07-15 2011-11-23 广东工业大学 一种离网型双馈风力发电系统及其最大风能捕获方法

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110114970A (zh) * 2016-09-28 2019-08-09 艾能控制技术有限公司 用于对外部负载供电的离网电力产生系统
CN110114970B (zh) * 2016-09-28 2023-07-14 艾能控制技术有限公司 用于对外部负载供电的离网电力产生系统
CN111066237A (zh) * 2017-08-29 2020-04-24 乌本产权有限公司 用于控制风能设施的多相他励同步发电机的方法
CN111066237B (zh) * 2017-08-29 2024-02-06 乌本产权有限公司 用于控制风能设施的多相他励同步发电机的方法
CN108880353A (zh) * 2018-07-05 2018-11-23 国家电网有限公司 基于电压源型静止变频器的大型同步调相机起动控制方法
CN114263528A (zh) * 2021-11-25 2022-04-01 潍柴动力股份有限公司 一种去除发电机组中凝露的系统、方法及发电机组
CN114263528B (zh) * 2021-11-25 2023-03-21 潍柴动力股份有限公司 一种去除发电机组中凝露的系统、方法及发电机组

Also Published As

Publication number Publication date
CN102545757B (zh) 2014-06-18

Similar Documents

Publication Publication Date Title
Nababan et al. An overview of power topologies for micro-hydro turbines
CA2858761C (en) Method for operating a wind turbine or a wind farm
CN101136582A (zh) 一种全功率变流器直流侧卸荷电路的控制方法
Liu et al. Quasi-Z-Source inverter based PMSG wind power generation system
CN102108937A (zh) 定桨距变速永磁同步风力发电机组无风速转速传感器全风速控制策略
CN104092235A (zh) 一种双馈发电机组交、直流并网系统及方法与应用
Saleh et al. Resolution-level-controlled WM inverter for PMG-based wind energy conversion system
US10910841B2 (en) Method and system for power grid voltage regulation by distributed energy resources
CN102832638A (zh) 一种基于电池储能的风电场低电压穿越控制系统
CN102545757B (zh) 一种应用于供暖负载的离网型风电机组的功率控制方法
CN201332278Y (zh) 风电场无功补偿联动控制系统
Hussein et al. Simple sensorless control technique of permanent magnet synchronous generator wind turbine
CN102097826B (zh) 电励磁双凸极风力发电系统的结构与控制方法
CN201903629U (zh) 交流变压型励磁同步风力发电实验装置
Hussein et al. Simple maximum power extraction control for permanent magnet synchronous generator based wind energy conversion system
CN103208851A (zh) 一种垂直轴风力发电变流装置
CN102185336A (zh) 风力发电设备
Singh et al. Stand alone power generation by 3φ asynchronous generator: A comprehensive survey
CN203942288U (zh) 一种双馈发电机组交、直流并网系统
Shanmugam et al. Design and implementation of power electronic converters in wind turbine system
Sharma et al. Power optimization technique for small wind turbine system using an incremental current control
Hu et al. Wind power fluctuations mitigation by DC-link voltage control of variable speed wind turbines
Pidiiti et al. Power maximization and control of PMSG wind energy system without wind speed sensors
Sinha et al. A two-stage converter based controller for a stand alone wind energy system used for remote applications
Srivastava et al. Analyses of Grid Connected Hybrid PV/Wind Renewable Power Generation System

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: BAODING CORONA CONTROL EQUIPMENT CO., LTD.

Effective date: 20120709

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20120709

Address after: 100083 Beijing city Haidian District Wangzhuang Road No. 1, Tsinghua Tongfang Technology Plaza, B block 23 layer

Applicant after: Beijing Corona Science & Technology Co., Ltd.

Co-applicant after: Baoding Corona Control Equipment Co., Ltd.

Address before: 100083 Beijing city Haidian District Wangzhuang Road No. 1, Tsinghua Tongfang Technology Plaza, B block 23 layer

Applicant before: Beijing Corona Science & Technology Co., Ltd.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 100083 Beijing city Haidian District Wangzhuang Road No. 1, Tsinghua Tongfang Technology Plaza, B block 23 layer

Applicant after: BEIJING CORONA WEIYE TECHNOLOGY CO., LTD.

Applicant after: Baoding Corona Control Equipment Co., Ltd.

Address before: 100083 Beijing city Haidian District Wangzhuang Road No. 1, Tsinghua Tongfang Technology Plaza, B block 23 layer

Applicant before: Beijing Corona Science & Technology Co., Ltd.

Applicant before: Baoding Corona Control Equipment Co., Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: BEIJING CORONA SCIENCE + TECHNOLOGY CO., LTD. TO: BEIJING KENUO WEIYE TECHNOLOGY CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140618

Termination date: 20201210

CF01 Termination of patent right due to non-payment of annual fee